This is a WebAIM Short Form Task Group Instruction (TGI) document for ship maintenance work on the USS RAFAEL PERALTA (DDG-115). The document provides instructions for the installation and removal of scaffolding at two locations: the Freeboard Weather area (Frames 308-338, Port side) and the Torpedo Missile and Rocket Magazine (1-304-2-M) on the Main Deck (Frames 308-338). The work is being performed in support of the Ship Repair Facility and Japan Regional Maintenance Center (SRF-JRMC), which will conduct maintenance and preservation work on blowout hatches.

The contractor work period extends from July 22, 2026, to September 11, 2026. The primary tasks are to erect and hang scaffolding assemblies (two separate lots) in accordance with 29 CFR Part 1915.71 (Scaffolding or Staging standards) and to remove the scaffolding upon completion when requested by SRF-JRMC via Code 333. No Government Furnished Material is required. SRF-JRMC will provide supporting services including crane and crane rigging services, safety inspections for SRF-JRMC employees, and Quality Assurance inspections for marked items. The document was prepared by T. Ando (Code 231B) on November 17, 2025, and approved by T. Takeishi on the same date. The Work Integration Manager is T. Yaginuma (Code 333).

View the file

Other files

File Type Posted
TGI_38K6113702A01_c0v0_REV2.pdf PDF
TGI_38K6144104A01_c0v0_REV2.pdf PDF
TGI_38K6112318A01_c2v2_REV2.pdf PDF
TGI_38K6171101A01_c0v0_REV2.pdf PDF
TGI_38K6113601A01_c0v0_REV2.pdf PDF
TGI_38K6112321A01_c0v0_REV2.pdf PDF
Solicitation Amendment N6264926RA0360005 SF 30.pdf PDF
TGI_38K6186301A01_c0v0_rev2.pdf PDF
TGI_38K6113801A01_c1v0_REV2.pdf PDF
TGI 38K6112318A01_c2v2_REV2.pdf PDF
TGI_38K6113701A01_c0v0_REV1.pdf PDF
TGI_38K6113801A01_c1v0_REV1.pdf PDF
TGI_38K6152101A02_c0v0_REV1.pdf PDF
TGI_38K6145601A01_c0v0_REV1.pdf PDF
TGI_38K6164401A01_c1v2_REV1.pdf PDF
Solicitation Amendment N6264926RA0360002 SF 30.pdf PDF
TGI_38K6113702A01_c0v0_REV1.pdf PDF
TGI_38K6112303A01_c0v0_REV1.pdf PDF
TGI_38K6113601A01_c0v0_REV1.pdf PDF
TGI_38K6113602A01_c0v0_REV1.pdf PDF
TGI_38K6112325A01_c0v0_REV1.pdf PDF
TGI_38K6154103A02_c0v0_REV1.pdf PDF
TGI_38K6144104A01_c0v0_REV1.pdf PDF
TGI_38K6151101A01_c0v0_REV1.pdf PDF
material info.pdf PDF
6220213_53711_-_0001_ R_-_0001.pdf PDF
38K6112318A01-Engrg Inst.pdf PDF
Attachment IV Request for Information Form.docx DOCX document
Attachment II Proposal Sheet Generator v1.2.xlsx XLSX spreadsheet
TGI_38K6113801A01_c1v0.pdf PDF
TGI_38K6145601A01_c0v0.pdf PDF
TGI_38K6112318A01_c0v0.pdf PDF
TGI 38K6186301A01_c0v0.pdf PDF
TGI_38K6112320A01_c1v1.pdf PDF
TGI_38K6112305A01_c1v0.pdf PDF
TGI 38K6144104A01_c0v0.pdf PDF
Attachment III Request for Information Sheet (Fillable).pdf PDF
TGI_38K6154103A02_c0v0.pdf PDF
TGI_38K6112301A01_c0v0.pdf PDF
TGI 38K6158301A01_c0v0.pdf PDF
TGI_38K6112317A01_c0v0.pdf PDF
TGI_38K6112304A01_c0v0.pdf PDF
TGI 38K6152101A02_c0v0.pdf PDF
TGI 38K6154101A01_c1v1.pdf PDF
TGI 38K6165401A01_c0v0.pdf PDF
TGI 38K6164401A01_c1v2.pdf PDF
TGI 38K6154101T02_c0v0.pdf PDF
Attachment IV DDG-115_BUNDLE1_GFP_List.xlsx XLSX spreadsheet
Attachment VIII Contract data.pdf PDF
Solicitation - N6264926RA036.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

29-JAN-2026 0905

20.14.15.2.9333 (September 2024) ICN: 38K6112001 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY STAGING SY TST A 1 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61 86511

CU PHASE TITLE: *F/O - INSTL & RMV SCAFFOLDING TO/FROM FREEBD WEA & 1-304-2-M FOR SRF-JRMC WORK

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 3

CG030737

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

ANDO, TOMOHIKO 231B 3152434372 17-NOV-2025

APPROVED BY: CODE: PHONE: DATE:

TAKEISHI, TAKAYUKI 231B 3152436704 17-NOV-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

CG03-0737

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

SAITO, KAZUNOBU VARIOUS U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

120A0001

1. SCOPE/PURPOSE:

1.1 Title: Scaffolding for Ship Repair Facility and Japan Regional Maintenance Center (SRF-JRMC) Work; install and remove

1.2 Location of Work:

1.2.1 Freeboard Weather, Frames between 308 and 338, Port

1.2.2 Torpedo Missile and Rocket Magazine (1-304-2-M)

1.3 Identification:

1.3.1 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.1 Remarks: Maintenance / Preservation work of blowout hatch will be accomplished by SRF-JRMC.

TGI Short Form

29-JAN-2026 0905

20.14.15.2.9333 (September 2024) (Continued) ICN: 38K6112001 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY STAGING SY TST A 1 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61 86511

CU PHASE TITLE: *F/O - INSTL & RMV SCAFFOLDING TO/FROM FREEBD WEA & 1-304-2-M FOR SRF-JRMC WORK

FOUO Pg 2 of 3

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1.3.2 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.2, Main Deck Frames between 308 and 338 Remarks: Maintenance / Preservation work of blowout hatch will be accomplished by SRF-JRMC.

1.4 Security Classification: None.

1.5 Initial Condition: None.

1.6 Contractor work start date:

1.7 Contractor work completion date:

2. PROCEDURE:

2.1 Erect/hang scaffolding listed in 1.3.1 and 1.3.2 in accordance with Ref. No. 3.

2.2 Remove scaffolding listed in 1.3.1 and 1.3.2 upon completion of the work in accordance with Ref. Ref. No. 3 when requested by SRF-JRMC via Code 333.

2.3 Notes:

2.3.1 Planner: Code 231B T. Ando, 243-4372

2.3.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560

2.3.3 JCN CG03-0737 is related to this TGI.

2.4 Government Furnished Material (GFM): None.

2.5 SRF-JRMC will provide the following service work: (TGI No. 38K6112001S02)

2.5.1 [C740] Crane and crane rigging service.

2.5.2 [C106.1] Safety inspection for SRF-JRMC employees.

2.5.3 [C133] QA inspection for (G) symbol(s).

Kouichi.Yoshida.ja Typewritten Text 7/22/2026

Kouichi.Yoshida.ja Typewritten Text 9/11/2026

29-JAN-2026 0905

20.14.15.2.9333 (September 2024) (Continued) ICN: 38K6112001 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY STAGING SY TST A 1 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61 86511

CU PHASE TITLE: *F/O - INSTL & RMV SCAFFOLDING TO/FROM FREEBD WEA & 1-304-2-M FOR SRF-JRMC WORK

FOUO Pg 3 of 3

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N

3 TM 29 CFR PART

1915.71 Scaffolding or Staging - N

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 38K6112001 KEY OP: A01