TFDM Section C.docx
DOCX document 321 KB Posted
- Solicitation number
- 693KA7BNATCS
About this file
This document is a Statement of Work (SOW) for the Terminal Flight Data Manager (TFDM) system, a NextGen air traffic control technology being developed by the Federal Aviation Administration (FAA). The TFDM is designed to improve airport surface management and terminal airspace operations by providing integrated electronic flight data, surface collaborative decision-making tools, and enhanced traffic flow management capabilities. The system aims to save time and fuel, reduce emissions, and improve efficiency by enabling real-time data sharing among controllers, aircraft operators, and airports.
The SOW comprehensively details the contractor's responsibilities across multiple domains, including system engineering, design, production, site implementation, logistics, training, and test and evaluation. Key requirements include developing and delivering a fully integrated system with hardware and software components, conducting extensive testing, creating technical documentation and training materials, and supporting the transition from legacy systems. The contractor must develop multiple training courses for air traffic controllers and technical operations personnel, conduct detailed system and user testing, and provide ongoing maintenance and support services. The contract involves multiple system builds and deployments across various FAA facilities, with a focus on incremental implementation and continuous system improvement.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents
| C.1 | TERMINAL FLIGHT DATA MANAGER (TFDM) OVERVIEW | 7 |
| C.1.1 | Introduction | 7 |
| C.1.2 | Background | 7 |
| C.1.3 | Purpose | 8 |
| C.1.4 | Scope | 8 |
| C.1.5 | Benefits | 8 |
| C.2 | APPLICABLE DOCUMENTS | 9 |
| C.2.1 | Military Standards and Specifications | 9 |
| C.2.2 | FAA/DOT Specifications, Standards, and Orders | 10 |
| C.2.3 | Other Publications and Specifications | 12 |
| C.3 | PROGRAM MANAGEMENT | 16 |
| C.3.1 | Meetings, Reviews, Conferences, and Evaluations | 16 |
| C.3.1.1 | Post Award Conference | 17 |
| C.3.1.2 | Program Management Reviews | 18 |
| C.3.1.3 | Integrated Baseline Review | 19 |
| C.3.1.4 | System Requirements Review | 20 |
| C.3.1.4.1 | System Requirements Review Acceptance Criteria…………………………………………….20 | |
| C.3.1.5 | Preliminary Design Review………………………………………………………………………..21 | |
| C.3.1.5.1 | Preliminary Design Review Acceptance Criteria……………………………………………….22 | |
| C.3.1.6 | Critical Design Review…………………………………………………………………………….22 | |
| C.3.1.6.1 | Critical Design Review Acceptance Criteria……………………………………………………23 | |
| C.3.1.7 | Logistics Product Data | 23 |
| C.3.1.7.1 | Logistics Guidance Conference…………………………………………………………………23 | |
| C.3.1.7.1.1 | Provisioning Guidance Conference | 24 |
| C.3.1.7.2 | Provisioning Conference………………………………………………………………………...24 | |
| C.3.1.8 | Training Guidance Conference | 25 |
| C.3.1.8.1 | Training in Process Review……………………………………………………………………..26 | |
| C.3.1.9 | Technical Interchange Meetings and Working Groups | 26 |
| C.3.2 | Program Control | 26 |
| C.3.2.1 | Work Breakdown Structure | 27 |
| C.3.2.2 | Integrated Master Schedule | 27 |
| C.3.2.3 | Earned Value Management | 27 |
| C.3.3 | Performance Reporting | 28 |
| C.3.3.1 | Metrics | 28 |
| C.3.3.2 | Technical Performance Parameters Plan | 29 |
| C.3.4 | Data Management | 29 |
| C.3.4.1 | Data Items | 30 |
| C.3.5 | Risk, Issue, Opportunity Management | 30 |
| C.3.5.1 | Systems Engineering Risk Reduction Activities | 31 |
| C.3.6 | Configuration Management Program | 32 |
| C.3.6.1 | Configuration Management Plan | 32 |
| C.3.6.2 | Configuration Identification | 32 |
| C.3.6.3 | Configuration Baselines | 33 |
| C.3.6.4 | Configuration Control | 33 |
| C.3.6.4.1 | Configuration Control Board……………………………………………………………………33 |
C.3.6.4.2 Engineering Change Proposal………………………………...………………………………...34
| C.3.6.4.3 | Request for Deviation…………………………………………………………………………...35 | |
| C.3.6.4.3.1 | Restrictions on Deviations | 35 |
| C.3.6.4.4 | Request for Waiver……………………………………………………………………………...36 | |
| C.3.6.4.5 | Parts Substitution………………………………………………………………………………..36 | |
| C.3.6.4.6 | Notice of Revision………………………………………………………………………………36 | |
| C.3.6.5 | Configuration Audits | 36 |
| C.3.6.5.1 | Functional Configuration Audit…………………………………………………………………37 | |
| C.3.6.5.2 | Physical Configuration Audit……………………………...……………………………………38 | |
| C.3.6.6 | Configuration Status Accounting | 39 |
| C.3.7 | Program Trouble Reports | 39 |
| C.3.8 | Configuration Control Working Groups | 39 |
| C.3.9 | Quality Assurance | 40 |
| C.3.9.1 | Quality Assurance Program | 40 |
| C.3.9.2 | Quality Assurance Management Responsibility | 41 |
| C.3.9.3 | Software Conformity Review | 41 |
| C.3.10 | Phase-Out Period | 42 |
| C.4 | SYSTEMS ENGINEERING AND DESIGN | 42 |
| C.4.1 | Systems Engineering Management | 42 |
| C.4.1.1 | Systems Engineering Management Plan | 42 |
| C.4.1.2 | Access to System Development Environment | 42 |
| C.4.1.3 | System Engineering Requirements | 43 |
| C.4.1.3.1 | Interim Design Checkpoint……………………………………………………………………...43 | |
| C.4.1.3.2 | Requirements Management……………………………...……………………………………...44 | |
| C.4.1.4 | Software Engineering Management | 44 |
| C.4.2 | Human Engineering | 45 |
| C.4.2.1 | Human Engineering Program and Planning | 45 |
| C.4.2.2 | Human Engineering Design | 46 |
C.4.2.2.1 RESERVED………………………………………………………………………………………47
| C.4.2.3 | Human Engineering Analysis | 47 |
| C.4.2.3.1 | Human Engineering Review Support…………………………………………………………...47 | |
| C.4.2.3.2 | Early User Involvement Events…………………………………………………………………48 | |
| C.4.2.3.2.1 | Air Traffic EUIE | 48 |
| C.4.2.3.2.2 | Technical Operations EUIE………………………………………………………………….49 | |
| C.4.3 | Safety Program | 49 |
| C.4.3.1 | Hazard Assessments | 50 |
| C.4.3.2 | System Safety Assessment | 51 |
| C.4.3.3 | Hazard Tracking/Safety Control Verification Tracking | 51 |
| C.4.3.4 | Safety Program Schedule | 51 |
| C.4.4 | Security Engineering | 47 |
| C.4.4.1 | Security System Authorization Support | 51 |
C.4.4.1.1 Security Characterization Document………………………………………………………….. 52 C.4.4.1.2 System Security Plan…………………………………………………………………………...52 C.4.4.1.3 NAS Contingency Plan…………………………………………………………………………53 C.4.4.1.4 Security Standard Operating Procedures……………………………………………………….53 C.4.4.1.5 Privacy Threshold Assessment (PTA)………………………………………………………….54 C.4.4.1.6 Plan of Action and Milestone (POAM) Status Report………………………………………….54 C.4.4.2 Security Engineering Support ……………………………………………………………………..54 C.4.4.3 Security Measures ………………55 C.4.4.4 Software Vulnerability Assessment and Patching……………………………………… .………51 C.4.4.4.1 Software Security Patch Program………………………………………………………………...51
| C.4.4.4.2 | Software Vulnerability Assessment……………………………………..………………………..51 | |
| C.4.5 | System Design | 55 |
| C.4.5.1 | System Architecture | 55 |
| C.4.5.1.1 | Functional Block Diagrams System…………………………………………………………….56 | |
| C.4.5.1.2 | Additional Functionally Significant Item (AFSI) Selection…………………………………….56 | |
| C.4.5.2 | Interface Development | 56 |
| C.4.5.3 | Software | 57 |
| C.4.5.3.1 | Software Documentation…………………………………………..……………………………58 | |
| C.4.5.3.1.1 | Software Requirements Specification…………………………………………………… 58 |
C.4.5.3.1.2 Software Design Description……………………………………………………………...58
| C.4.5.3.1.3 | Version Description Document…………………………………………………………....59 |
| C.4.5.3.1.4 | Interface Design Document………………………………………………………………..59 |
C.4.5.3.1.5 Software Configuration Management Plan………………………………………………..59 C.4.4.3.1.6 Software Quality Assurance Plan………………………………………………………….59 C.4.5.3.1.7 Software Standards………………………………………………………………………...60
| C.4.5.3.2 | Software Development Tools…………………………………………………………………...60 | |||
| C.4.5.3.3 | Software Programs………………………………………………………………………………60 | |||
| C.4.5.3.4 | Software Engineering Practice…………………………………………………………………..60 | |||
| C.4.5.3.5 | Programming Languages……………………………………………………………………..…61 | |||
| C.4.5.3.6 | Development of Support Software | 61 | ||
| C.4.5.3.7 | System Wide Information Management | 61 | ||
| C.4.5.3.8 | Software Assurance Audits | 61 | ||
| C.4.5.3.9 | Software Accomplishment Summary | 61 | ||
| C.4.5.4 | Hardware | 61 | ||
| C.4.5.4.1 | Hardware Manufacture, Assembly and Test | 61 | ||
| C.4.5.4.2 | Hardware Identification and Selection | 61 | ||
| C.4.5.4.3 | Hazardous Materials | 63 | ||
| C.4.5.4.4 | Thermal Analysis | 64 | ||
| C.4.5.4.5 | Electromagnetic Interference and Susceptibility | 64 | ||
| C.4.5.4.6 | Interchangeability | 64 | ||
| C.4.5.5 | System Firmware | 64 | ||
| C.4.5.6 | Reliability and Maintainability Analysis and Predictions | 64 | ||
| C.4.5.6.1 | Design Analysis | 65 | ||
| C.4.5.6.2 | Fault Tree Analysis | 65 | ||
| C.4.5.6.3 | Failure Duration Analysis | 65 | ||
| C.4.5.6.4 | Failure Management Analysis | 65 | ||
| C.4.5.6.5 | Availability Analysis | 66 | ||
| C.4.5.6.6 | Reliability Centered Maintenance | 66 | ||
| C.4.5.6.7 | Functional Failure Analysis | 66 | ||
| C.4.5.6.8 | Reliability Program | 66 | ||
| C.4.5.6.9 | Maintainability Program | 67 | ||
| C.5 | PRODUCTION | 67 | C.5.1 System Production | 67 |
| C.5.1.1 | System Definition | 68 | ||
| C.5.1.1.1 | Developmental Test System | 68 | ||
| C.5.1.1.2 | First Article System | 68 | ||
| C.5.1.1.3 | Production System | 68 | ||
| C.5.2 | TFDM Internet Protocol Network Addressing | 69 | ||
| C.5.3 | Parameter Adaptation | 69 | ||
| C.6 | SITE PLANNING AND IMPLEMENTATION | 70 | ||
| C.6.1 | Generic Implementation Tasks | 70 | ||
| C.6.1.1 | Environment, Occupational Safety and Health | 70 | ||
| C.6.1.1.1 | Training | 71 |
C.6.1.1.2 Program Dcoumentation……………………………………...…………………………………72 C.6.1.1.3 Site Surveys……………………………………………………………………………………..72 C.6.1.1.4 Environmental Compliance……………………………………………………………………..72 C.6.1.1.5 Site Preparation and Installation………………………………………………………………...72 C.6.1.1.6 Hazardous Materials……………………………………………………………………….……74 C.6.1.1.7 System Test and Evaluation………………………………………………………………...… 75 C.6.1.1.8 Implementation…………………………………………………………………...……………..75 C.6.1.1.9 Legacy Hardware Disposition………………………………………………………….……….75 C.6.1.1.10 Maintenance……………………………………………………………………………………..76
| C.6.1.2 | Implementation Management | 76 |
| C.6.1.3 | Site Implementation Management Plan | 76 |
| C.6.2 | Site Specific Implementation Tasks | 76 |
| C.6.2.1 | Pre Site Survey | 76 |
| C.6.2.2 | Site Survey | 77 |
| C.6.2.2.1 | Site Survey Report | 77 |
| C.6.2.3 | Site Preparation and Design | 78 |
| C.6.2.3.1 | Site Installation Plan | 78 |
| C.6.2.4 | Hardware and Software Delivery and Installation | 78 |
| C.6.2.5 | Software Optimization & Customization | 79 |
| C.6.2.6 | Contractor Acceptance Inspection | 79 |
| C.6.2.6.1 | Site Configuration Document | 80 |
| C.6.3 | Post Installation Activities | 80 |
| C.6.3.1 | Legacy System Hardware Removal and Disposal | 80 |
| C.6.3.2 | In Service Support | 80 |
| C.6.3.3 | Transition Planning | 80 |
| C.7 | REMOTE MONITORING AND LOGGING SYSTEM | 81 |
| C.8 | TEST AND EVALUATION PROGRAM | 81 |
| C.8.1 | Test Program Description | 82 |
| C.8.1.1 | Developmental Test Program Description | 82 |
| C.8.1.2 | Other DT Special Test Program Description | 83 |
| C.8.1.3 | Production Acceptance Test Program Description | 84 |
| C.8.1.4 | Site Acceptance Test Program Description | 84 |
| C.8.2 | Test Plans and Procedures | 84 |
| C.8.3 | Test and Evaluation Management | 85 |
| C.8.3.1 | Program Trouble Reporting | 85 |
| C.8.4 | Formal Test | 85 |
| C.8.4.1 | General Requirements for Formal Test | 85 |
| C.8.4.1.1 | System Checkout | 87 |
| C.8.4.2 | Test Readiness Review | 88 |
| C.8.4.3 | Developmental Tests | 89 |
| C.8.4.3.1 | Other DT Special Tests | 91 |
| C.8.4.3.1.1 | Reliability and Stability Demonstration | 91 |
| C.8.4.3.1.2 | Human Factors Test | 92 |
| C.8.4.3.1.3 | Maintainability Demonstration | 92 |
| C.8.4.3.1.4 | Accreditation Testing | 93 |
| C.8.4.3.1.5 | TFDM DT Regression Testing | 94 |
| C.8.4.4 | Acceptance Tests | 94 |
| C.8.4.4.1 | Production Acceptance Tests | 94 |
| C.8.4.4.2 | Site Acceptance Tests | 95 |
| C.8.4.5 | TFDM Test Support | 96 |
| C.8.4.5.1 | TFDM Test Capabilities | 96 |
| C.8.5 | Faulted Modules | 96 |
| C.8.6 | TFDM Testbed(s) | 97 |
| C.8.7 | TFDM Operational Testing and Independent Operational Assessment Support | 97 |
| C.8.8 | Post DT Test and Evaluation Program…………………………………………………………………...97 |
C.8.8.1 Post DT Test and Evaluation Management…………………………………………………..…… C.8.8.2 Post DT Test Procedures……………………………………………………………..………...…….97 C.8.8.3 Formal Test Conduct………………………………………………………………………………....98 C.8.8.4 Test Readines Review………………………………………………………………………….……….99 C.8.8.5 Regression Tetsing……………………………………………………………………………..… .100
| C.8.8.5.1 Stability Tesing………………………………………………………………………………. |
| C.8.8.5.2 Reliability Testing…………………………………………………………………………… |
C.8.8.6 Program Trouble Reporting………………………………………………………………….......…100 C.8.8.6.1 PTR Verification (PTR-V)…………………………………………………………………… C.8.8.7 Test Report…………………………………………………………………………..………..…….100 C.8.8.8 Maintenance of Temporary Build 1.x/2.x Test Labs………………………………………………101 C.8.8.9 Maintain the XL Gen10 Mimic lab for SIG50 RedHat Enterprise Linux 8.2 and associated new COTS integration and test for Build 2.X………………………………………….………… …...101
| C.9 | LOGISTICS | 101 |
| C.9.1 | Integrated Logistics Management………………………………………………………………………101 | |
| C.9.2 | Integrated Logistics Management Team………………………………………………………………..102 | |
| C.9.3 | System Supply Support Catalog Instruction | 102 |
| C.9.4 | System Contractor Support Services | 103 |
| C.9.4.1 | System On-Site Contractor Maintenance Support | 103 |
| C.9.4.2 | Terminal Second Level Engineering (TSLE) Support ` | 103 |
| C.9.4.3 | System Toll-free Telephone Assistance | 104 |
| C.9.4.4 | System Contractor Software Support Services | 104 |
| C.9.4.5 | Reserved | 105 |
| C.9.4.6 | CDLS Tasks………………………………………………………………………………… …..105 | |
| C.9.4.7 | Surge Training System……………………………………………………………………. …….107 | |
| C.9.4.8 | Air Trafiic Training Systems Support……………………………………………………….…...108 | |
| C.9.4.9 | Technical Documentation Support……………………………………………………………......108 | |
| C.9.5 | Logistics Requirements…………………………………………………………………………………108 | |
| C.9.5.1 | Logistics Product Data………………………………………………………………………...….108 | |
| C.9.5.1.1 | Reserved | 109 |
| C.9.5.1.2 | Repair Level and Spares Analysis Summary…………………………………………………..109 | |
| C.9.5.2 | Asset Identification | 109 |
C.9.5.2.1 Barcode Symbology Standard………………………………………………………………….109 C.9.5.2.2 System Level Data……………………………………………………………………….…….110 C.9.5.2.3 Examples of Equipment Types…………………………………………………………...……110 C.9.5.2.4 Asset Management Systems……………………………………………………….…………..110 C.9.5.2.5 Barcoded Asset Listing……………………………………………………………….………..110 C.9.5.2.6 Asset Identification Report…………………………………………………………………….110
| C.9.5.3 | Tools and Test Equipment | 110 |
| C.9.5.4 | Contractor Engineering/Technical/Maintenance Support Services | 111 |
| C.9.5.5 | TFDM Lifecycle Support | 111 |
| C.9.5.6 | TFDM Warranty | 111 |
| C.9.5.7 | Delivery Procedures | 111 |
| C.9.5.7.1 | Delivery Schedule (Repair or Replace) | 111 |
| C.9.5.8 | Diminishing Manufacturing Sources Material Shortages Program | 112 |
| C.9.5.8.1 | Replacements When Identical Parts Become Unavailable | 112 |
| C.9.5.9 | Maintenance Support Transition | 113 |
| C.9.5.9.1 | First Level Maintenance Support Transition Planning | 113 |
| C.9.5.9.2 | Second Level Engineering Support Transition Planning | 113 |
| C.9.5.9.3 | Depot Support Transition | 113 |
| C.9.5.9.4 | Technical Manuals | 114 |
| C.9.5.9.4.1 | Technical Manuals Conference | 116 |
| C.9.5.9.4.2 | Operator Manual | 116 |
| C.9.5.9.4.3 | Reserved | 116 |
| C.9.5.9.4.4 | Technical Instruction Book (TIB)……… | 116 |
| C.9.5.9.4.5 Monitor and Control User’s Manual | 117 | |
| C.9.5.9.4.6 | Software Programmer Manual | 117 |
C.5.9.5 Quick Reference Guides and Cards..…………………………………………………...…….. 117
| C.9.5.9.6 | Software Transition…………………………………………………………………………….117 |
| C.9.5.9.7 | System Adaptation Manual…………………………………………………………………….118 |
| C.9.5.9.8 | System Security and Network Configuration Manual…………………………………………108 |
| C.9.5.9.9 | Audit of the Inventory of Government Property………………………………………………118 |
C.9.5.9.10 Contractor Requesst for Government Property……………...…………………………… . …118
| C.9.6 | Automation Issues Management System (AIMS) Program | 118 |
| C.9.6.1 | Reserved | 118 |
| C.9.7 | Technical Data | 119 |
| C.9.7.1 | Technical Data Package | 119 |
| C.9.8 | Failure Reporting, Analysis, and Corrective Action System ILS | 119 |
| C.9.9 | Support and Test Equipment Logistics | 120 |
| C.9.10 | Site and Depot Repair Logistics | 120 |
| C.10 | SUPPORT SYSTEMS | 120 |
| C.10.1 | TFDM Test and Support Systems | 120 |
| C.10.2 | TFDM Training Systems | 121 |
| C.10.2.1 | Technical Operations Training Systems | 121 |
| C.10.2.2 | Air Traffic Control Training Systems | 121 |
| C.11 | TFDM TRAINING | 122 |
| C.11.1 | Contractor Provided Training | 122 |
| C.11.2 | Scope of Training Development | 123 |
| C.11.3 | Contract Data Requirements List | 124 |
| C.11.4 | RESERVED | 125 |
| C.11.5 | RESERVED | 125 |
| C.11.6 | Air Traffic Control Specialist Training Program | 125 |
| C.11.6.1 | Air Traffic Specialist Control Training Course | 125 |
| C.11.6.2 | Air Traffic Control Specialist Cadre Training Course | 125 |
| C.11.6.3 | Operations Specialist (OS) Controller-In-Charge / Traffic Management Coordinator (TMC) Training Course Build 1 | 126 |
| C.11.6.4 | Traffic Manager Coordinator (TMC) Advanced Training Course Build 2………………………126 | |
| C.11.6.5 | Air Traffic Controller Specialist (ATCS) Course, The Air Traffic Controller Specialist (ATCS) Cadre Course, and the Operations Supervisor/Controller-In-Charge/Traffic Management Coordinator (OS/CIC/TMC) Course Re-baselining and Revalidation……………...……………114 |
C.11.6.6 Training Course Reformatting Requirements…………………………………………………….129
| C.11.7 | Technical Operations Training Program | 126 |
| C.11.7.1 | First Level System Maintenance and Technical Operations Training Course | 126 |
| C.11.7.2 | Control Center Briefing Operations Control Center Training Course | 126 |
| C.11.7.3 | Service Operations Center Training Course | 127 |
| C.11.8 | Second Level Engineering Training Course | 127 |
| C.11.9 | RESERVED | 127 |
| C.11.10 RESERVED | 127 | |
| C.11.11 | Training Development and Delivery Specifications | 127 |
| C.11.11.1 | Specifications for Training Deliverables | 127 |
| C.11.11.2 | Specifications for Training Delivery | 128 |
| C.11.11.3 | Separately Orderable Training Materials | 128 |
| C.11.12 | Training Program Deliverables | 129 |
| C.11.12.1 | Personnel Qualification Report | 129 |
| C.11.12.2 | Analysis Plan | 129 |
| C.11.12.3 | Analysis Report | 129 |
| C.11.12.4 | Course Design Guide | 130 |
| C.11.12.5 | Training Course Materials | 130 |
| C.11.12.6 | Course Walk-through Presentation/Alpha Test for eLearning……………………………………130 | |
| C.11.12.7 | Operational Tryout/Beta Test for eLearning | 130 |
| C.11.12.8 | First Course Conduct | 131 |
| C.11.12.9 | RESERVED | 131 |
| C.11.12.10 Project Status Report | 131 | |
| C.11.12.11 In-Process Reviews | 131 | |
| C.11.12.12 Transition Plan | 131 |
C.11.12.13 Site Training Scenario…………………………………………………………………………... 132 C.11.12.14 Web-Based Training……………………………………………………………………………..132 C.11.12.15 Build 1.4 to Build 1.5 Training “Delta Pack”……………………………………………………132 C.11.12.16 TTS-1 Site Specific Scenarios Maintenance …………………………………………………….132 C.11.13 Training Course Maintenance Support…………………………………………………………………132 C.11.13.1 Training Course Re-baselining……………………………………………………………………132 C.11.13.2 Training Course Validation………………………………………………………...…………….132 C.11.14 Air Traffic Training and First Level System Maintenance and Technical Operations Course Printing Suppport………………………………………………………………...…………………….127 C.11.15 Technical Operations Training Delta Packs………………………………………………………… 127
| C.12 | GENERAL ENGINEERING/TECHNICAL SERVICES | 133 |
| C.12.1 | Change Request Control Process for TFDM Build/Release Content | 133 |
| C.13 | AIMS PTR SUPPORT…...…………………………………………………………………………….133 | |
| C.13.1 AIMS Board Support ……..……………………………… ………………………………..………….128 | ||
| C.13.2 | Operational Build Release Letter……..……...…………………………………………………………128 |
Appendix 1: Terms of Reference & Acronyms List 134
TABLES
| TABLE 1: MILITARY STANDARDS AND SPECIFICATIONS | 10 |
| TABLE 2: FAA/DOT SPECIFICATIONS, STANDARDS, AND ORDERS | 11 |
| TABLE 3: OTHER PUBLICATIONS AND SPECIFICATIONS | 13 |
Section C
Terminal Flight Data Manager (TFDM) DTFAWA-16-C-00021 Mod 155 i i Terminal Flight Data Manager (TFDM) DTFAWA-16-C-00021 Mod 155 C.1 Flight Data Manager (TFDM) Overview
C.1.1 Introduction As demand for our National Air Space System (NAS) grows, smarter Next Generation (NextGen) technologies are making air travel more efficient, safer, and environmentally friendly. The Federal Aviation Administration (FAA) is committed to update terminal automation systems and implement NextGen Air Traffic Control (ATC) capabilities that will improve air traffic operations in the National Airspace System (NAS). The implementation of NextGen technologies is a continuous effort to align airplanes’, airlines’, and airports’ technical capabilities. This alignment affects pilots, controllers, airport operators, airlines operators, and the flying public. One such system that the Federal Aviation Administration (FAA) is developing is called Terminal Flight Data Manager (TFDM). Terminal Flight Data Manager (TFDM) is an FAA NextGen program based on airport surface management concepts developed under NextGen direction. The TFDM concepts have been validated with operational users through FAA funded concept engineering and prototype development activities. TFDM will help save time and fuel, reduce emissions, and improve the experience for the flying public.
The FAA Air Traffic Organization (ATO), Decision Support Systems Organization with the Program Management Office (PMO) is the agency sponsor for this acquisition. TFDM capabilities will be incrementally deployed to provide efficiencies in the airport surface and terminal airspace by providing new integrated surface traffic control and management capabilities. TFDM functions include: Surface Collaborative Decision Making (S-CDM), including departure scheduler and other airport decision tools; Electronic Flight Data (EFD); Enhanced Air Traffic Control Tower (ATCT) Traffic Flow Management System (TFMS); and Replacement or integration of multiple systems in the National Airspace System (NAS). TFDM will share data among controllers, aircraft operators, and airports so they can better stage arrivals and departures and manage traffic flow within terminal airspace for greater efficiency. Stakeholders will have a shared awareness of flights on the ground and in the air; the ability to exchange
C.1.2 Background Currently, at most airports, paper flight strips are being used to monitor and share flight plans, requiring controllers to handle and communicate safety-critical data manually. Traffic predictions and decisions are tied to flight plan data that is often untimely and unable to be shared between stakeholders. Flight plans are used to estimate arrivals, gate push-backs, routings, and departures. Their use in the tactical decisions made in handling the more than 40,000 flights daily can lead to inefficiencies across the national airspace system. In addition, aircraft operators currently board passengers and push back from the gates before flights are given slots in line for departure. This can lead to tarmac congestion and wasted fuel with aircraft idling as they wait to join the departure queue.
The imbalance between capacity and demand causes significant growth of delays and severely disrupts the movement of passengers and goods. The implementation of TFDM will result in improved collaboration with users, enhanced accuracy of demand and capacity predictions, and improvements in system modeling and measurement will lead to a better understanding of alternative strategies, enabling more informed decisions.
C.1.3 Purpose
The purpose of this Statement of Work (SOW) is to define the effort required to design, develop, test, implement and support the TFDM System that meets all requirements in the FAA TFDM System Specification Document (SSD), provided in Section J (Attachment J-6) of this contract. This SOW also includes provisions for Program Management (PM), System Engineering (SE), System Design, System Development, System Test and Evaluation, Training, Implementation, Integrated Logistic Support, Engineering Services, and General Engineering/Technical Services. The Contract Data Requirements List (CDRL) contained in Section J of this contract defines the products to be delivered to the Government resulting from the effort defined in this SOW.
C.1.4 Scope
The scope of this contract includes the following major components:
1. Establish and maintain a Program Management Office and perform Program Management to support and coordinate the work performed under this contract to ensure compliance with all terms and conditions
2. Design, development and test of TFDM requirements in accordance with the FAA TFDM System Specification Document (SSD) (Attachment J-6).
3. Development of training for FAA TFDM operators and maintainers
4. Implementation including replacement or integration of multiple systems in the National Airspace System (NAS) and Logistical Support
5. Engineering Services and System/Site Support C.1.5 Benefits TFDM will provide automated data available to stakeholders in real-time to facilitate faster and higher quality decision-making and reduce errors. It will accomplish this through providing the following benefits:
· Real-time Accuracy. Accurate data from surface and terminal surveillance in continuously updated capacity-and-demand predictions will decrease time aircraft spend waiting to taxi, improve the traffic flow, and help prevent missed connections.
· Collaborative Decisions. By connecting aircraft operators, controllers, and airports with digital flight plans, shared surveillance data, and collaborative decision-support tools, TFDM will help stakeholders work together to optimize flights. This will save time and fuel, reduce emissions, and improve the experience for passengers.
· Connected Stakeholders. TFDM lets stakeholders exchange data electronically to make more informed tactical decisions and better handle changing traffic volume, weather, and other evolving situations.
· Better Predictive Tools. TFDM uses surface and terminal surveillance and flow-management capabilities in its predictive modeling for improved departure management, ground movement, and flight coordination.
· Taxpayer Savings. Multiple costly legacy systems will be replaced with a single, easily maintained state-of-the-art TFDM platform.
· Environmentally Friendly. Reduced taxi times, fewer delays and missed connections, and greater predictability with TFDM will save fuel and reduce emissions.
C.2 Applicable Documents The following specifications, handbooks, orders, standards, and drawings form a part of this contract and are applicable to the extent specified herein Tables 1: Military Standards and Specifications, Table 2: FAA/Department of Transportation (DOT) Specifications, Standards, and Orders, and Table 3: Other Publications and Specifications. In the event of conflict between this contract and any of the applicable documents cited below, the provisions of this SOW must apply.
a. Copies of Federal Aviation Administration (FAA) specifications and interface documents may be obtained from the Federal Aviation Administration, Headquarters Public Inquiry Center APA-230, 800 Independence Avenue SW, Washington, DC 20591, 202-267-3484. Requests should fully identify material desired and cite the solicitation or contract number.
The FAA Test and Evaluation Handbook, VVSPT-A2-PDD-013_TnE_Handbook_v3.0, may be obtained at the following website: http://www.faa.gov/about/office_org/headquarters_offices/ang/offices/tc/initiatives/vnv/documents/publications/VVSPT-A2-PDD-013_TnE_Handbook_v3.0.pdf
The FAA Work Breakdown Structure (WBS) Version 5.1 may be obtained at the following website: http://fast.faa.gov/docs/wbs.doc
b. Requests for copies of documents not covered in the preceding paragraph should be addressed to the Contracting Officer (CO). Requests should fully identify material desired and cite the solicitation or contract number.
c. Military Standards and Specifications can be ordered from the Department of Defense Single Stock Point (DODSSP), Building 4/Section D, 700 Robbins Avenue, Philadelphia, PA 19111-5098. Information is available at their website, http://dodssp.daps.dla.mil.
d. Copies of ANSI/ASQC-Q9001-2008 and ISO 9000-3:2004 can be obtained from the following source: American Society for Quality Control P.O. Box 3005, Milwaukee, WI 53201-3005 or 600 North Plankinton Avenue, Milwaukee, WI 53203 Phones: (414) 272-8575 or (800) 248-1946. The Fax is: (414) 272- 1247.
e. Copies of RTCA Documents can be ordered from the RTCA website: http://www.rtca.org C.2.1 Military Standards and Specifications Table 1: Military Standards and Specifications
| Standards and Specifications |
| Description |
| MIL-HDBK-470A |
| Designing And Developing Maintainable |
Products And Systems Volume I
| MIL-HDBK-781A |
| Reliability Test Methods, Plans, and Environments for Engineering Development, Qualification, and Production |
| MIL-HDBK-217F |
| Reliability Prediction of Electronic Equipment |
| MIL-HDBK-502A |
| Product Support Analysis |
| GEIA-STD-0007B |
| Logistics Product Data |
| MIL-DTL-31000C |
| Technical Data Packages |
| MIL-STD-129P Change 4 |
| Military Marking for Shipment and Storage |
| MIL-STD-961E |
| Defense and Program-Unique Specifications Format and Content |
| MIL-STD-2073-1D |
| Application of Packaging Requirements with Standard Practice for Military Packaging |
| MIL-STD-3034A |
| Reliability Centered Maintenance (RCM) Process |
C.2.2 FAA/DOT Specifications, Standards, and Orders Table 2: FAA/DOT Specifications, Standards, and Orders
| FAA/DOT Specifications, Standards, and Orders |
| Description |
| FAA Acquisition Management System (AMS) |
| FAA Acquisition Management System (AMS) |
| FAA-STD-028C |
| Contract Training Program |
| FAA-STD-021A |
| Configuration Management (Contractor Requirements) |
| FAA-STD-025F |
| Preparation of Interface Control Documentation |
| FAA-STD-026A |
| NAS Software Development, June 1, 2001 |
| FAA-STD-019E |
| Lightning and Surge Protection, Grounding, Bonding and Shielding Requirements for Facilities and Equipment |
| FAA HF-STD-001 |
| Human Factors Design Standard |
| FAA HF-STD-002 |
| Baseline Requirements For Color Use In Air Traffic Control Displays |
| FAA HF-STD-003 |
| Alarms and Alerts in the Technical Operations Environment |
| FAA HF-STD-004 |
| Requirements for a Human Factors Program |
| JO 3900.57A |
| Environmental and Occupational Safety and Health (EOSH) Requirements In The Planning And Execution Of Construction And Maintenance Activities At National Airspace System (NAS) Facilities |
| FAA Order 1050.10C |
| Prevention, Control and Abatement of FAA Environmental Pollution |
| FAA Order 1050.20A |
| Airway Facilities Asbestos Control Program |
| FAA Order 1050.14B |
| Polychlorinated Biphenyls (PCBs) in the National Airspace System (NAS) |
| FAA Order 4600.27B Change 1 |
| Personal Property Management |
| FAA Order 1050.19B |
| Environmental Due Diligence Audits in the Conduct of FAA Real Property Transactions |
| FAA Order 1800.66 Change 3 |
| Configuration Management Policy |
| FAA Order 6000.15G |
| General Maintenance Handbook for National Airspace Systems (NAS) Facilities |
| FAA-C-1217F |
| Electrical Work, Interior |
| FAA-D-2494B |
| Technical Instruction Book Manuscript: Electronic, Electrical, & Mechanical Equipment Requirements for Preparation of Manuscript & Production of Books |
| FAA-G-2100H |
| Electronic Equipment, General Requirements |
| FAA Order 1370.82A |
| Information Systems Security Program |
| FAA Order 8000.360CA |
| FAA Safety Management System |
| SRMGSA |
| FAA Safety Risk Management Guidance for System Acquisitions October 2022 Version 2 |
| FAA-HDBK-006A |
| Reliability, Maintainability, and Availability (RMA) Handbook |
| Supply Support Catalog Instructions (SSCI) |
| Standard Subject Identification Code (SSIC) Manual |
| FAA Order 6010.7B |
| Joint Acceptance Inspection |
| ASD-100-SSE-1 Rev 10 |
| NAS Modernization System Safety Management Program (SSMP) |
| FAA Air Traffic Organization (ATO) Security Authorization Handbook Version 1, Dated October 2016 |
| FAA Air Traffic Organization (ATO) Security Authorization Handbook |
| FAA Order 1810.8 |
| FAA William J. Hughes Technical Center's Test and Evaluation Policy |
| JO 1050.17A |
| Environmental Compliance at Air Traffic Control Towers |
| JO 6980.25D |
| Maintenance of Batteries for Standby Power |
| TFDM Test and Evaluation Master Plan (TEMP) Version 2.6 |
| TFDM Test and Evaluation Master Plan |
| FAA-STD-065A |
| Preparation of Web Service Description Documents (WSDDs) |
| FAA-STD-070 |
| Preparation of Web Service Requirements Documents |
| FAA-STD-073 |
| Preparation of JAVA Message Service Description Documents |
| FAA Section 508 |
| Section 508 of the Rehabilitation Act (29 U.S.C. 794d |
| FAA System Wide Information Management (SWIM) Governance Policies Version 2.0 |
| FAA System Wide Information Management (SWIM) Governance Policies |
| FAA Work Breakdown Structure (WBS) Version 5.1 |
| FAA Work Breakdown Structure (WBS) |
| Electronic Learning Management System (eLMS) Content Integration Guide |
| Electronic Learning Management System (eLMS) Content Integration Guide |
| eLearning Design and Systems Requirements Style Guide |
| eLearning Design and Systems Requirements Style Guide |
| AJI DEVELOPMENT GUIDE FOR INSTRUCTOR-LED TRAINING MATERIALS – SINGLE COLUMN, Version V.2020.09 |
| Instructor Led Training Development Guide |
C.2.3 Other Publications and Specifications Table 3: Other Publications and Specifications
| Other Publications and Specifications |
| Description |
| ANSI/ASQC-Q9001-2008 |
| American National Standard, Quality System-Model for Quality Assurance in Design, Development, Production, Installation, and Servicing |
| ISO 9000-3:2004 |
| International Standard, Quality Management and Quality Assurance Standards – Part 3: Application of International Standards Organization (ISO) 9001 to the Development, Supply and Maintenance of Software |
| ISO/IEC 12207-2008 |
| Systems and Software Engineering - Software Life Cycle Processes |
| SP-800-18 Rev.1 |
| Guide for Developing Security Plans for Federal Information Systems |
| SP-800-34 Rev.1 |
| Contingency Planning Guide for Federal Information Systems |
| SP 800-53 Rev.4 |
| Security Controls for Federal Information Systems and Organizations |
| SP-800-60 Volumes 1 & 2 |
| Volume 1: Guide for Mapping Types of Information and Information Systems to Security Categories. |
Volume II: Appendices to Guide for Mapping Types of Information and Information Systems to Security Categories
| ANSI/EIA-748C |
| Earned Value Management System |
| GEIA-HB-649 |
| Configuration Management Package |
| IEEE-STD-200 |
| Institute of Electrical and Electronics Equipment (IEEE) Standard Reference Designations for Electrical and Electronics Parts and Equipment |
| IEEE-STD-315 |
| Graphic Symbols for Electrical and Electronics Diagrams (Including Reference Designation Letters) |
| IEEE Standard 830-1998 |
| IEEE Recommended Practice for Software Requirements Specifications |
| IEEE Standard 1016-2009 |
| IEEE Standard For Information Technology–Systems Design–Software Design Descriptions |
| IEEE/EIA 12207-2008 |
| Standard for Information Technology—Software Life Cycle Processes |
| 29 CFR 1910.1001 |
| Asbestos |
| 29 CFR 1910.1025 |
| OSHA Toxic and Hazardous Substances |
| 29 CFR 1910.145 |
| Accident Prevention Tags |
| 29 CFR 1910.146 |
| Permit-Required Confined Spaces |
| 29 CFR 1910.147 |
| OSHA Control Of Hazardous Energy (Lockout/Tagout) |
| 29 CFR 1910.242 |
| Hand and Portable Powered Tools and Other Hand-Held Equipment |
| 29 CFR 1910.1200 |
| Hazard Communications |
| 29 CFR 1910.1926 |
| Occupational Safety and Health Standards |
| 29 CFR 1926.62 |
| OSHA Lead Exposure In Construction |
| 29 CFR 1960.20 |
| Alternate Standard for Fire Safety in Air Traffic Control Towers |
| 40 CFR |
| Protection of Environment |
| 40 CFR Chapter 1 Sub-Chapter I |
| Solid Waste |
| 40 CFR Part 82 |
| Protection of Stratospheric Zone |
| 40 CFR 260-280 |
| Hazardous Waste Management System |
| 49 CFR 170-180 |
| Federal Hazardous Materials Regulations |
| National Defense Industrial Organization (NDIA) Integrated Baseline Review (IBR) Guide : September 2010 |
| Integrated Baseline Review Guide |
| National Environmental Policy Act (NEPA)-80 |
| Fire Doors and Other Opening Protectives |
| National Fire Protection Association Code 70. Current edition: 2014 |
| National Electrical Code |
| National Fire Protection Association (NFPA) 70E, Current edition: 2015 |
| Standard for Electrical Safety in the Workplace |
| 29 CFR 1910 |
| Occupational Safety and Health Standards |
| Resource Conservation and Recovery Act (RCRA) of 1976 |
| Controls hazardous wastes from generation through disposal. |
| IEEE 1517:1999 |
| IEEE Standard for Information Technology – Software Life Cycle Processes – Reuse Processes |
| ASTM-D5077-90 (2009) |
| Standard Terminology Relating to Electrostatic Discharge (ESD) Packaging |
| ASTM-D3951 |
| Standard Practices for Best Commercial Packaging |
| FIPS 199 |
| Standards for Security Categorization of Federal Information and Information Systems |
| FIPS 200 |
| Minimum Security Requirements for Federal Information and Information Systems |
| RTCA/DO-278A |
| Software Integrity Assurance Considerations for Communication, Navigation, Surveillance and Air Traffic Management (CNS/ATM) Systems |
| RTCA/DO-330 |
| Software Tool Qualification Considerations |
C.3 Program Management The Contractor must establish and maintain a Program Management Office (PMO) and perform Program Management to support and coordinate the work performed under this contract to ensure compliance with all terms and conditions set forth in this contract. The Contractor must establish clear and effective lines of authority, coordination, communication, and accountability between the Contractor’s PMO and the Government to ensure sufficient and timely resources are given to the resolution of any problems that may arise.
The Contractor must assign a Program Manager (PM) who will ensure performance under this contract and will be the primary point of contact for the work to be performed under this contract. The PM must keep the FAA informed of any potential problems and make recommendations for resolution. The PM must ensure that all necessary management, business, contracts, engineering, implementation, and maintenance resources are available and sufficient, both in terms of the quantity of resources and their qualifications to successfully perform all the tasks required in this contract. The Contractor is responsible for management and control of all subcontractors/team members to ensure compliance with all requirements of this contract.
The Contractor must include, but not be limited to, program management activities such as contract administration, finance, obtaining and retaining qualified personnel, as well as technical support across all phases of the program. The PM must have sufficient corporate resources and authority to direct, execute, and control all elements of the program to ensure efficient and timely program execution. The PM must be the focal point within the Contractor's activities for all required program tasks. The PM must be prepared at all times to present and discuss the current program status as well as forecasts related to contract activities with the Government Contracting Officer (CO), the Contracting Officer's Representative (COR), and/or the Government PM. The Contractor must support the Contract/Finance Working Group, Working Group and TIMs Listing (Attachment J-7), to address relevant contract activities including, but not be limited to, resource loading, work breakdown structure, schedules, deliverables, Earned Value (EV) analysis, program tracking, contract modifications, and funds expenditure tracking and status.
The Contractor must provide management oversight of all contract activities to ensure high quality of work effort and deliverables that demonstrate traceability to all program requirements. The Contractor must identify and remedy potential technical cost and schedule risks and issues. The tasks described herein must be fully integrated to ensure their efficient and timely execution.
The Contractor must develop and implement and update every 24 months an integrated Program Management Plan (PMP) in accordance with (CDRL M01). The PMP must integrate all functional areas and must articulate the specific objectives to be accomplished at an overview level. The PMP must also identify the staffing and other resources required to meet contract requirements.
M01 Program Management Plan (PMP)
C.3.1 Meetings, Reviews, Conferences, and Evaluations The Contractor must support recurring meetings such as status meetings, Technical Interchange Meetings (TIMs), Program Management Reviews (PMRs), Formal Design Reviews (i.e. System Requirements Review (SRR), Preliminary Design Review (PDR), Critical Design Review (CDR), and evaluations with the Government to discuss program progress, and identify potential problems and resolve identified issues.
The Contractor must prepare Agendas, Meeting Minutes, Action Item Lists, and Presentation Materials for each meeting, conference review and/or evaluation. The Contractor must provide an agenda and notify the CO of its readiness five business days prior to the start of each meeting, conference, review or evaluation. All CDRL items required for a meeting, conference, review or evaluation, are to be delivered in accordance with the (CDRL M03) requirements.
The following instructions are applicable to all meetings, reviews, conferences, and/or evaluations:
1. All Program Management Reviews will be held at a Contractor provided facility within the fifty (50) mile radius local commuting area of Washington, DC unless otherwise directed by or approved by the government. All other meetings, conferences and/or evaluations will be held at the Contractor’s facility unless otherwise directed by or approved by the Government. The Contractor must provide teleconferencing capability, internet access, and facility location(s) to accommodate necessary participation as requested by the Government. The Contractor must propose a date for the meeting, review, conference, and/or evaluation for the COR's approval.
2. For all presentations and agendas, the Government reserves the right to revise the agenda and/or presentation material. The Contractor must provide appropriate Contractor personnel to respond to Government questions. The Contractor must prepare and deliver a summary of open, pending, and closed action items and presentation materials prior to the start of each scheduled meeting, conference, review or evaluation. The Government will revise the delivery times when necessary.
3. The Contractor must record and submit minutes. The Contractor must track action items. Each assigned action item must have a due date and responsible person(s) assigned, who must provide the status of the action at agreed upon intervals until the action is closed. Unless otherwise specified by the Government, the Contractor must respond to all action items with a written closure statement. In the event that an action item cannot be closed promptly a plan of action must be developed for closure.
M03 Agenda, Presentation Materials, Action Item List and Meeting Minutes
C.3.1.1 Post Award Conference The Contractor must plan for, host, support, and participate in a Post Award Conference (PAC) to be held at the Contractor's site within twenty-one (21) calendar days after contract award and document the conference in accordance with (CDRL M03). At this conference, the Contractor must address the plans and schedules for the TFDM work efforts. The Contractor must demonstrate adequacy of proposed efforts to meet all contractual requirements.
The conference is intended to:
1. Establish a liaison between the Contractor, FAA Contracting Officer, FAA Contracting Officer Representative (COR), FAA Technical Training Advisor (TTA), and other FAA personnel specified in the contract and charged with the responsibility for contract administration.
2. Permit inspection of the Contractor’s facility and establish a working relationship with contractor personnel.
M03 Agenda, Presentation Materials, Action Item List and Meeting Minutes
C.3.1.2 Program Management Reviews The Contractor must conduct and support Program Management Reviews (PMRs) in accordance with (CDRL M03) to provide a status and review of work and efforts being conducted under this contract. The Contractor must be prepared to support monthly PMRs but the Government reserves the right to decrease the frequency in accordance with the program needs. For all PMRs, the Government PM may modify the meeting schedule and/or PMR agenda topics to accommodate special program needs. At PMRs, the Contractor must provide, at a minimum, program's management, technical, cost and schedule status. The age of financial data presented at the PMR will be clearly indicated to support the goal that it should be as current as possible. The PMR must be accomplished nominally within one working day.
The Government reserves the right to conduct Executive PMR(s) as part of the PMR agenda(s).
The Contractor must use PMRs to provide program insight to Government representatives on the topics including, but not limited to:
1. Major accomplishments since the last PMR and expected major accomplishments prior to the next PMR;
2. Anticipated differences between contract milestones, schedules, technical performance, cost, Estimate at Completion (EAC) and performance status including identification of major drivers behind cost/schedule variances and the action plans to resolve these variances;
3. Changes in organizational chart and planned versus actual staffing by functional discipline;
4. Review of actions from previous PMR, future required actions, and continual funding status;
5. Integrated Master Schedule (IMS) identifying schedule changes from previous PMR, completed and upcoming milestones, critical path status, all critical path changes, critical path issues and impacts, and a preview of all activities for the next ninety (90) calendar days;
6. Contractor deliverables to be delivered within the following ninety (90) calendar days, the status of CDRL reviews from the Government and status of changes from the previous PMR;
7. Status of open program trouble reports (PTRs), and/or discrepancy reports (DRs) and change requests (CRs) since the last PMR;
8. Status of testing including testing metrics;
9. Status of program risks and their mitigation plan;
10. Program management action item status;
11. Notification of any deviations/waivers from the requirements and the associated justification;
12. Commercial product obsolescence and supportability issues and recommended actions;
13. (Reserved as of BCD RFO) Status of Engineering Change Proposals (ECPs);
14. Implementation and site activation/deployment status; and
15. Status of production readiness to include:
a. Procurement/integration and production schedules for system components; and
b. System integration schedules that demonstrate compatibility with the site deployment schedule.
16. Reporting of metrics specified in SOW Section C.3.3.1.
M03 Agenda, Presentation Materials, Action Item List and Meeting Minutes
C.3.1.3 Integrated Baseline Review The Government will conduct an Integrated Baseline Review (IBR) no later than 120 days after contract award. The contractor will host the event and is to play an active role in planning and providing all requested data in preparation for the event. The purpose of the IBR is to:
· Evaluate the Contractor’s implementation of the performance measurement baseline;
· Ensure that the Government and Contractor mutually understand program scope, schedule, resources, inherent risk, and management approach;
· Review contractor’s planning and execution efforts to meet contractual requirements in areas including but not limited to complete coverage of the SOW, logical scheduling of work activities and adequate allocation of resources;
· Ensure early and adequate planning;
· Identify risks to be tracked; and
· Ensure appropriate reporting levels have been identified and variance thresholds are agreed to by the Government and Contractor.
The Contractor must provide the Government with requested information to include, but not be limited to, data and documents in accordance with IPMR Material (CDRL M08). The contractor must refer to Section H and the National Defense Industrial Association (NDIA) IBR Guide dated September 2010 as guidance for the IBR. The Government may conduct additional IBRs within six months after major modifications to the contract, through mutual agreement between the Government and the Contractor. The Contractor must submit meeting minutes in accordance with (CDRL M03) following each IBR.
| M03 | Agenda, Presentation Materials, Action Item List and Meeting Minutes |
| M08 | Integrated Baseline Review Material |
C.3.1.4 System Requirements Review The Contractor must plan for, participate in, and conduct a System Requirements Review (SRR) in accordance with (CDRL E07 and M03). The objective of this review is to ascertain the adequacy of the Contractor’s efforts in defining the complete set of system requirements specified in the TFDM System Specification Document (SSD) (Attachment J-6), and TFDM Deployment Build Release Plan (Attachment J-10) as specified in this contract. A single, comprehensive SRR must be conducted to address the requirements outlined above. Incremental or “delta” SRRs may be conducted, subject to Government approval, to address those TFDM functional requirements addressed in the SRR which have been impacted from the development and implementation of segregated TFDM Software Builds.
The SRR must be conducted when the Government determines through the Requirements Identification and Development Working Group (RIDWG) that a significant portion of the system functional requirements have been established.
| E03 | System/Subsystem Specification |
| E06 | Software Development Plan |
| E07 | System Requirements Review Materials |
| M03 | Agenda, Presentation Materials, Action Item List and Meeting Minutes |
| T01 | Contractor Master Test Plan |
C.3.1.4.1 System Requirements Review Acceptance Criteria To successfully complete the SRR, the Contractor must meet the following acceptance criteria:
· Obtain Government acceptance of all SRR-associated CDRLs;
· Analyze requirements in the FAA TFDM System Specification Document (SSD) (Attachment J-6) and demonstrate a thorough understanding of these requirements;
· Identify any derived requirements; and
· Establish a requirements baseline consisting of the requirements in, FAA TFDM System Specification Document (SSD) (Attachment J-6), and any derived requirements.
C.3.1.5 Preliminary Design Review The Contractor must conduct a Preliminary Design Review (PDR) in accordance with (CDRLs E04 andM03). Subject to Government approval the Contractor may conduct incremental, or “delta” PDRs. All PDRs must address:
1. Allocation of TFDM functional requirements to individual TFDM Software Builds, specified in Deployment Build Release Plan (Attachment J-10) of the contract, and/or
2. PDR topics that have been impacted from the development and implementation of segregated TFDM Software Builds, specified in Deployment Build Release Plan (Attachment J-10) This review must be conducted for each configuration item or aggregate of configuration items to:
1. Evaluate the progress, technical adequacy, and risk resolution (on a technical, cost, and schedule basis) of the selected design approach.
2. Evaluate the degree of definition and assess the technical risk associated with the selected manufacturing methods/processes.
3. Establish the existence and compatibility of the physical and functional interfaces among the configuration items and other items of equipment, facilities, computer software, and personnel.
For Computer Software Configuration Items (CSCIs), this review must focus on:
1. The evaluation of the progress, consistency, and technical adequacy of the selected top-level design and test approach.
2. Compatibility between software requirements and preliminary design.
3. The preliminary version of the operation and support approach.
The SRR must be approved by the Government before a PDR may be conducted, and all SRR action items must be closed prior to conducting the PDR, unless the Government has given permission to proceed. The PDR must cover the preliminary design of all Contractor-developed hardware and software configuration items. For items that are not Contractor-developed, the Contractor must provide a functional/physical description of the item, the results of the analysis that verifies the item will meet the associated technical requirements, and a description of the interfaces with other configuration items.
At the PDR, the Contractor must describe the products, processes, methodologies, milestones, and measurements to be used in conducting software development activities. The Contractor must describe its plans for acquiring and developing the required hardware and software to meet contract requirements. The Contractor must describe a process and products similar to those in IEEE/EIA 12207-2008. Overall technical program risks must be reviewed on a technical, cost, and schedule basis.
| M03 | Meeting Agenda, Meeting Minutes, and Presentation Materials |
| E04 | Preliminary Design Review Materials |
C.3.1.5.1 Preliminary Design Review Acceptance Criteria To successfully complete the PDR, the Contractor must meet the following acceptance criteria:
· Allocate all the requirements in the requirements baseline to Hardware Configuration Items (HWCIs) and Computer Software Configuration Item (CSCIs);
· Provide a traceability of the requirements baseline to the HWCIs and CSCIs;
· For each HWCI and CSCI, identify which requirements are satisfied by Commercial Off The Shelf (COTS), which requirements are already implemented, but require modification, and which requirements require development; and
· Present a preliminary design in accordance with (CDRL E04) that shows how COTS, modified COTS, and new…