TFDM Section C.docx

DOCX document 321 KB Posted

Attached to
Request for Information - Brand New Air Traffic Control System
Solicitation number
693KA7BNATCS
Issued by

About this file

This document is a Statement of Work (SOW) for the Terminal Flight Data Manager (TFDM) system, a NextGen air traffic control technology being developed by the Federal Aviation Administration (FAA). The TFDM is designed to improve airport surface management and terminal airspace operations by providing integrated electronic flight data, surface collaborative decision-making tools, and enhanced traffic flow management capabilities. The system aims to save time and fuel, reduce emissions, and improve efficiency by enabling real-time data sharing among controllers, aircraft operators, and airports.

The SOW comprehensively details the contractor's responsibilities across multiple domains, including system engineering, design, production, site implementation, logistics, training, and test and evaluation. Key requirements include developing and delivering a fully integrated system with hardware and software components, conducting extensive testing, creating technical documentation and training materials, and supporting the transition from legacy systems. The contractor must develop multiple training courses for air traffic controllers and technical operations personnel, conduct detailed system and user testing, and provide ongoing maintenance and support services. The contract involves multiple system builds and deployments across various FAA facilities, with a focus on incremental implementation and continuous system improvement.

View the file

Other files

File Type Posted
Notice 6.18.25.pdf PDF
BNATCS Industry Day Attendees.docx DOCX document
BNATCS Industry Day videos.docx DOCX document
Industry Day 2 Briefings.pdf PDF
Industry Day 1 Briefings.pdf PDF
RFI System Providers 1.docx DOCX document
Question for one on ones 6.6.2025.docx DOCX document
2025.06.05 Industry Day Agendas.docx DOCX document
STARS Section C.docx DOCX document
RFI Brand New ATC System A1.docx DOCX document
ETR Section C.pdf PDF
TBFM Section C.pdf PDF
ILS-420 Section C.pdf PDF
ALSF -2 SLEP SOW 5-28-25.pdf PDF
DNTS Section C.pdf PDF
IVSR Section C.pdf PDF
VSBP Section C.pdf PDF
DME Contract Section C_P18 Final.pdf PDF
CTD Section C_AMEND 0001.docx DOCX document
MEVA 3 NetworkSection C.pdf PDF
TFM2 Section C.pdf PDF
ETVS RDVS STVS Section C.pdf PDF
SMR4 Section C ASDE-3 SMR Replacement.pdf PDF
CSS-Wx Section C.docx DOCX document
STARS Section C.docx DOCX document
APCS Section C.docx DOCX document
ASSC Section C.pdf PDF
DCIS Section C Award Mod 0143.docx DOCX document
NEXCOM Section C.docx DOCX document
RFI Brand New ATC System.docx DOCX document
WSIC Section C.pdf PDF
E-IDS Section C.docx DOCX document
EIS Section C.pdf PDF
MSBRS Section C.pdf PDF
CCS-W Bridge Section C.pdf PDF
MCT SECTION C.pdf PDF
NWP Section C.docx DOCX document
NVR Section C.pdf PDF
FENS Section C.docx DOCX document
AIMMS2 Section C.pdf PDF
WMSS3 Section C.docx DOCX document
NEXCOM V2 Section C.pdf PDF
RVR Section C.pdf PDF
ERAM Section C.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table of Contents

C.1TERMINAL FLIGHT DATA MANAGER (TFDM) OVERVIEW7
C.1.1Introduction7
C.1.2Background7
C.1.3Purpose8
C.1.4Scope8
C.1.5Benefits8
C.2APPLICABLE DOCUMENTS9
C.2.1Military Standards and Specifications9
C.2.2FAA/DOT Specifications, Standards, and Orders10
C.2.3Other Publications and Specifications12
C.3PROGRAM MANAGEMENT16
C.3.1Meetings, Reviews, Conferences, and Evaluations16
C.3.1.1Post Award Conference17
C.3.1.2Program Management Reviews18
C.3.1.3Integrated Baseline Review19
C.3.1.4System Requirements Review20
C.3.1.4.1System Requirements Review Acceptance Criteria…………………………………………….20
C.3.1.5Preliminary Design Review………………………………………………………………………..21
C.3.1.5.1Preliminary Design Review Acceptance Criteria……………………………………………….22
C.3.1.6Critical Design Review…………………………………………………………………………….22
C.3.1.6.1Critical Design Review Acceptance Criteria……………………………………………………23
C.3.1.7Logistics Product Data23
C.3.1.7.1Logistics Guidance Conference…………………………………………………………………23
C.3.1.7.1.1Provisioning Guidance Conference24
C.3.1.7.2Provisioning Conference………………………………………………………………………...24
C.3.1.8Training Guidance Conference25
C.3.1.8.1Training in Process Review……………………………………………………………………..26
C.3.1.9Technical Interchange Meetings and Working Groups26
C.3.2Program Control26
C.3.2.1Work Breakdown Structure27
C.3.2.2Integrated Master Schedule27
C.3.2.3Earned Value Management27
C.3.3Performance Reporting28
C.3.3.1Metrics28
C.3.3.2Technical Performance Parameters Plan29
C.3.4Data Management29
C.3.4.1Data Items30
C.3.5Risk, Issue, Opportunity Management30
C.3.5.1Systems Engineering Risk Reduction Activities31
C.3.6Configuration Management Program32
C.3.6.1Configuration Management Plan32
C.3.6.2Configuration Identification32
C.3.6.3Configuration Baselines33
C.3.6.4Configuration Control33
C.3.6.4.1Configuration Control Board……………………………………………………………………33

C.3.6.4.2 Engineering Change Proposal………………………………...………………………………...34

C.3.6.4.3Request for Deviation…………………………………………………………………………...35
C.3.6.4.3.1Restrictions on Deviations35
C.3.6.4.4Request for Waiver……………………………………………………………………………...36
C.3.6.4.5Parts Substitution………………………………………………………………………………..36
C.3.6.4.6Notice of Revision………………………………………………………………………………36
C.3.6.5Configuration Audits36
C.3.6.5.1Functional Configuration Audit…………………………………………………………………37
C.3.6.5.2Physical Configuration Audit……………………………...……………………………………38
C.3.6.6Configuration Status Accounting39
C.3.7Program Trouble Reports39
C.3.8Configuration Control Working Groups39
C.3.9Quality Assurance40
C.3.9.1Quality Assurance Program40
C.3.9.2Quality Assurance Management Responsibility41
C.3.9.3Software Conformity Review41
C.3.10Phase-Out Period42
C.4SYSTEMS ENGINEERING AND DESIGN42
C.4.1Systems Engineering Management42
C.4.1.1Systems Engineering Management Plan42
C.4.1.2Access to System Development Environment42
C.4.1.3System Engineering Requirements43
C.4.1.3.1Interim Design Checkpoint……………………………………………………………………...43
C.4.1.3.2Requirements Management……………………………...……………………………………...44
C.4.1.4Software Engineering Management44
C.4.2Human Engineering45
C.4.2.1Human Engineering Program and Planning45
C.4.2.2Human Engineering Design46

C.4.2.2.1 RESERVED………………………………………………………………………………………47

C.4.2.3Human Engineering Analysis47
C.4.2.3.1Human Engineering Review Support…………………………………………………………...47
C.4.2.3.2Early User Involvement Events…………………………………………………………………48
C.4.2.3.2.1Air Traffic EUIE48
C.4.2.3.2.2Technical Operations EUIE………………………………………………………………….49
C.4.3Safety Program49
C.4.3.1Hazard Assessments50
C.4.3.2System Safety Assessment51
C.4.3.3Hazard Tracking/Safety Control Verification Tracking51
C.4.3.4Safety Program Schedule51
C.4.4Security Engineering47
C.4.4.1Security System Authorization Support51

C.4.4.1.1 Security Characterization Document………………………………………………………….. 52 C.4.4.1.2 System Security Plan…………………………………………………………………………...52 C.4.4.1.3 NAS Contingency Plan…………………………………………………………………………53 C.4.4.1.4 Security Standard Operating Procedures……………………………………………………….53 C.4.4.1.5 Privacy Threshold Assessment (PTA)………………………………………………………….54 C.4.4.1.6 Plan of Action and Milestone (POAM) Status Report………………………………………….54 C.4.4.2 Security Engineering Support ……………………………………………………………………..54 C.4.4.3 Security Measures ………………55 C.4.4.4 Software Vulnerability Assessment and Patching……………………………………… .………51 C.4.4.4.1 Software Security Patch Program………………………………………………………………...51

C.4.4.4.2Software Vulnerability Assessment……………………………………..………………………..51
C.4.5System Design55
C.4.5.1System Architecture55
C.4.5.1.1Functional Block Diagrams System…………………………………………………………….56
C.4.5.1.2Additional Functionally Significant Item (AFSI) Selection…………………………………….56
C.4.5.2Interface Development56
C.4.5.3Software57
C.4.5.3.1Software Documentation…………………………………………..……………………………58
C.4.5.3.1.1Software Requirements Specification…………………………………………………… 58

C.4.5.3.1.2 Software Design Description……………………………………………………………...58

C.4.5.3.1.3Version Description Document…………………………………………………………....59
C.4.5.3.1.4Interface Design Document………………………………………………………………..59

C.4.5.3.1.5 Software Configuration Management Plan………………………………………………..59 C.4.4.3.1.6 Software Quality Assurance Plan………………………………………………………….59 C.4.5.3.1.7 Software Standards………………………………………………………………………...60

C.4.5.3.2Software Development Tools…………………………………………………………………...60
C.4.5.3.3Software Programs………………………………………………………………………………60
C.4.5.3.4Software Engineering Practice…………………………………………………………………..60
C.4.5.3.5Programming Languages……………………………………………………………………..…61
C.4.5.3.6Development of Support Software61
C.4.5.3.7System Wide Information Management61
C.4.5.3.8Software Assurance Audits61
C.4.5.3.9Software Accomplishment Summary61
C.4.5.4Hardware61
C.4.5.4.1Hardware Manufacture, Assembly and Test61
C.4.5.4.2Hardware Identification and Selection61
C.4.5.4.3Hazardous Materials63
C.4.5.4.4Thermal Analysis64
C.4.5.4.5Electromagnetic Interference and Susceptibility64
C.4.5.4.6Interchangeability64
C.4.5.5System Firmware64
C.4.5.6Reliability and Maintainability Analysis and Predictions64
C.4.5.6.1Design Analysis65
C.4.5.6.2Fault Tree Analysis65
C.4.5.6.3Failure Duration Analysis65
C.4.5.6.4Failure Management Analysis65
C.4.5.6.5Availability Analysis66
C.4.5.6.6Reliability Centered Maintenance66
C.4.5.6.7Functional Failure Analysis66
C.4.5.6.8Reliability Program66
C.4.5.6.9Maintainability Program67
C.5PRODUCTION67C.5.1 System Production67
C.5.1.1System Definition68
C.5.1.1.1Developmental Test System68
C.5.1.1.2First Article System68
C.5.1.1.3Production System68
C.5.2TFDM Internet Protocol Network Addressing69
C.5.3Parameter Adaptation69
C.6SITE PLANNING AND IMPLEMENTATION70
C.6.1Generic Implementation Tasks70
C.6.1.1Environment, Occupational Safety and Health70
C.6.1.1.1Training71

C.6.1.1.2 Program Dcoumentation……………………………………...…………………………………72 C.6.1.1.3 Site Surveys……………………………………………………………………………………..72 C.6.1.1.4 Environmental Compliance……………………………………………………………………..72 C.6.1.1.5 Site Preparation and Installation………………………………………………………………...72 C.6.1.1.6 Hazardous Materials……………………………………………………………………….……74 C.6.1.1.7 System Test and Evaluation………………………………………………………………...… 75 C.6.1.1.8 Implementation…………………………………………………………………...……………..75 C.6.1.1.9 Legacy Hardware Disposition………………………………………………………….……….75 C.6.1.1.10 Maintenance……………………………………………………………………………………..76

C.6.1.2Implementation Management76
C.6.1.3Site Implementation Management Plan76
C.6.2Site Specific Implementation Tasks76
C.6.2.1Pre Site Survey76
C.6.2.2Site Survey77
C.6.2.2.1Site Survey Report77
C.6.2.3Site Preparation and Design78
C.6.2.3.1Site Installation Plan78
C.6.2.4Hardware and Software Delivery and Installation78
C.6.2.5Software Optimization & Customization79
C.6.2.6Contractor Acceptance Inspection79
C.6.2.6.1Site Configuration Document80
C.6.3Post Installation Activities80
C.6.3.1Legacy System Hardware Removal and Disposal80
C.6.3.2In Service Support80
C.6.3.3Transition Planning80
C.7REMOTE MONITORING AND LOGGING SYSTEM81
C.8TEST AND EVALUATION PROGRAM81
C.8.1Test Program Description82
C.8.1.1Developmental Test Program Description82
C.8.1.2Other DT Special Test Program Description83
C.8.1.3Production Acceptance Test Program Description84
C.8.1.4Site Acceptance Test Program Description84
C.8.2Test Plans and Procedures84
C.8.3Test and Evaluation Management85
C.8.3.1Program Trouble Reporting85
C.8.4Formal Test85
C.8.4.1General Requirements for Formal Test85
C.8.4.1.1System Checkout87
C.8.4.2Test Readiness Review88
C.8.4.3Developmental Tests89
C.8.4.3.1Other DT Special Tests91
C.8.4.3.1.1Reliability and Stability Demonstration91
C.8.4.3.1.2Human Factors Test92
C.8.4.3.1.3Maintainability Demonstration92
C.8.4.3.1.4Accreditation Testing93
C.8.4.3.1.5TFDM DT Regression Testing94
C.8.4.4Acceptance Tests94
C.8.4.4.1Production Acceptance Tests94
C.8.4.4.2Site Acceptance Tests95
C.8.4.5TFDM Test Support96
C.8.4.5.1TFDM Test Capabilities96
C.8.5Faulted Modules96
C.8.6TFDM Testbed(s)97
C.8.7TFDM Operational Testing and Independent Operational Assessment Support97
C.8.8Post DT Test and Evaluation Program…………………………………………………………………...97

C.8.8.1 Post DT Test and Evaluation Management…………………………………………………..…… C.8.8.2 Post DT Test Procedures……………………………………………………………..………...…….97 C.8.8.3 Formal Test Conduct………………………………………………………………………………....98 C.8.8.4 Test Readines Review………………………………………………………………………….……….99 C.8.8.5 Regression Tetsing……………………………………………………………………………..… .100

C.8.8.5.1 Stability Tesing……………………………………………………………………………….
C.8.8.5.2 Reliability Testing……………………………………………………………………………

C.8.8.6 Program Trouble Reporting………………………………………………………………….......…100 C.8.8.6.1 PTR Verification (PTR-V)…………………………………………………………………… C.8.8.7 Test Report…………………………………………………………………………..………..…….100 C.8.8.8 Maintenance of Temporary Build 1.x/2.x Test Labs………………………………………………101 C.8.8.9 Maintain the XL Gen10 Mimic lab for SIG50 RedHat Enterprise Linux 8.2 and associated new COTS integration and test for Build 2.X………………………………………….………… …...101

C.9LOGISTICS101
C.9.1Integrated Logistics Management………………………………………………………………………101
C.9.2Integrated Logistics Management Team………………………………………………………………..102
C.9.3System Supply Support Catalog Instruction102
C.9.4System Contractor Support Services103
C.9.4.1System On-Site Contractor Maintenance Support103
C.9.4.2Terminal Second Level Engineering (TSLE) Support `103
C.9.4.3System Toll-free Telephone Assistance104
C.9.4.4System Contractor Software Support Services104
C.9.4.5Reserved105
C.9.4.6CDLS Tasks………………………………………………………………………………… …..105
C.9.4.7Surge Training System……………………………………………………………………. …….107
C.9.4.8Air Trafiic Training Systems Support……………………………………………………….…...108
C.9.4.9Technical Documentation Support……………………………………………………………......108
C.9.5Logistics Requirements…………………………………………………………………………………108
C.9.5.1Logistics Product Data………………………………………………………………………...….108
C.9.5.1.1Reserved109
C.9.5.1.2Repair Level and Spares Analysis Summary…………………………………………………..109
C.9.5.2Asset Identification109

C.9.5.2.1 Barcode Symbology Standard………………………………………………………………….109 C.9.5.2.2 System Level Data……………………………………………………………………….…….110 C.9.5.2.3 Examples of Equipment Types…………………………………………………………...……110 C.9.5.2.4 Asset Management Systems……………………………………………………….…………..110 C.9.5.2.5 Barcoded Asset Listing……………………………………………………………….………..110 C.9.5.2.6 Asset Identification Report…………………………………………………………………….110

C.9.5.3Tools and Test Equipment110
C.9.5.4Contractor Engineering/Technical/Maintenance Support Services111
C.9.5.5TFDM Lifecycle Support111
C.9.5.6TFDM Warranty111
C.9.5.7Delivery Procedures111
C.9.5.7.1Delivery Schedule (Repair or Replace)111
C.9.5.8Diminishing Manufacturing Sources Material Shortages Program112
C.9.5.8.1Replacements When Identical Parts Become Unavailable112
C.9.5.9Maintenance Support Transition113
C.9.5.9.1First Level Maintenance Support Transition Planning113
C.9.5.9.2Second Level Engineering Support Transition Planning113
C.9.5.9.3Depot Support Transition113
C.9.5.9.4Technical Manuals114
C.9.5.9.4.1Technical Manuals Conference116
C.9.5.9.4.2Operator Manual116
C.9.5.9.4.3Reserved116
C.9.5.9.4.4Technical Instruction Book (TIB)………116
C.9.5.9.4.5 Monitor and Control User’s Manual117
C.9.5.9.4.6Software Programmer Manual117

C.5.9.5 Quick Reference Guides and Cards..…………………………………………………...…….. 117

C.9.5.9.6Software Transition…………………………………………………………………………….117
C.9.5.9.7System Adaptation Manual…………………………………………………………………….118
C.9.5.9.8System Security and Network Configuration Manual…………………………………………108
C.9.5.9.9Audit of the Inventory of Government Property………………………………………………118

C.9.5.9.10 Contractor Requesst for Government Property……………...…………………………… . …118

C.9.6Automation Issues Management System (AIMS) Program118
C.9.6.1Reserved118
C.9.7Technical Data119
C.9.7.1Technical Data Package119
C.9.8Failure Reporting, Analysis, and Corrective Action System ILS119
C.9.9Support and Test Equipment Logistics120
C.9.10Site and Depot Repair Logistics120
C.10SUPPORT SYSTEMS120
C.10.1TFDM Test and Support Systems120
C.10.2TFDM Training Systems121
C.10.2.1Technical Operations Training Systems121
C.10.2.2Air Traffic Control Training Systems121
C.11TFDM TRAINING122
C.11.1Contractor Provided Training122
C.11.2Scope of Training Development123
C.11.3Contract Data Requirements List124
C.11.4RESERVED125
C.11.5RESERVED125
C.11.6Air Traffic Control Specialist Training Program125
C.11.6.1Air Traffic Specialist Control Training Course125
C.11.6.2Air Traffic Control Specialist Cadre Training Course125
C.11.6.3Operations Specialist (OS) Controller-In-Charge / Traffic Management Coordinator (TMC) Training Course Build 1126
C.11.6.4Traffic Manager Coordinator (TMC) Advanced Training Course Build 2………………………126
C.11.6.5Air Traffic Controller Specialist (ATCS) Course, The Air Traffic Controller Specialist (ATCS) Cadre Course, and the Operations Supervisor/Controller-In-Charge/Traffic Management Coordinator (OS/CIC/TMC) Course Re-baselining and Revalidation……………...……………114

C.11.6.6 Training Course Reformatting Requirements…………………………………………………….129

C.11.7Technical Operations Training Program126
C.11.7.1First Level System Maintenance and Technical Operations Training Course126
C.11.7.2Control Center Briefing Operations Control Center Training Course126
C.11.7.3Service Operations Center Training Course127
C.11.8Second Level Engineering Training Course127
C.11.9RESERVED127
C.11.10 RESERVED127
C.11.11Training Development and Delivery Specifications127
C.11.11.1Specifications for Training Deliverables127
C.11.11.2Specifications for Training Delivery128
C.11.11.3Separately Orderable Training Materials128
C.11.12Training Program Deliverables129
C.11.12.1Personnel Qualification Report129
C.11.12.2Analysis Plan129
C.11.12.3Analysis Report129
C.11.12.4Course Design Guide130
C.11.12.5Training Course Materials130
C.11.12.6Course Walk-through Presentation/Alpha Test for eLearning……………………………………130
C.11.12.7Operational Tryout/Beta Test for eLearning130
C.11.12.8First Course Conduct131
C.11.12.9RESERVED131
C.11.12.10 Project Status Report131
C.11.12.11 In-Process Reviews131
C.11.12.12 Transition Plan131

C.11.12.13 Site Training Scenario…………………………………………………………………………... 132 C.11.12.14 Web-Based Training……………………………………………………………………………..132 C.11.12.15 Build 1.4 to Build 1.5 Training “Delta Pack”……………………………………………………132 C.11.12.16 TTS-1 Site Specific Scenarios Maintenance …………………………………………………….132 C.11.13 Training Course Maintenance Support…………………………………………………………………132 C.11.13.1 Training Course Re-baselining……………………………………………………………………132 C.11.13.2 Training Course Validation………………………………………………………...…………….132 C.11.14 Air Traffic Training and First Level System Maintenance and Technical Operations Course Printing Suppport………………………………………………………………...…………………….127 C.11.15 Technical Operations Training Delta Packs………………………………………………………… 127

C.12GENERAL ENGINEERING/TECHNICAL SERVICES133
C.12.1Change Request Control Process for TFDM Build/Release Content133
C.13AIMS PTR SUPPORT…...…………………………………………………………………………….133
C.13.1 AIMS Board Support ……..……………………………… ………………………………..………….128
C.13.2Operational Build Release Letter……..……...…………………………………………………………128

Appendix 1: Terms of Reference & Acronyms List 134

TABLES

TABLE 1: MILITARY STANDARDS AND SPECIFICATIONS10
TABLE 2: FAA/DOT SPECIFICATIONS, STANDARDS, AND ORDERS11
TABLE 3: OTHER PUBLICATIONS AND SPECIFICATIONS13

Section C

Terminal Flight Data Manager (TFDM) DTFAWA-16-C-00021 Mod 155 i i Terminal Flight Data Manager (TFDM) DTFAWA-16-C-00021 Mod 155 C.1 Flight Data Manager (TFDM) Overview

C.1.1 Introduction As demand for our National Air Space System (NAS) grows, smarter Next Generation (NextGen) technologies are making air travel more efficient, safer, and environmentally friendly. The Federal Aviation Administration (FAA) is committed to update terminal automation systems and implement NextGen Air Traffic Control (ATC) capabilities that will improve air traffic operations in the National Airspace System (NAS). The implementation of NextGen technologies is a continuous effort to align airplanes’, airlines’, and airports’ technical capabilities. This alignment affects pilots, controllers, airport operators, airlines operators, and the flying public. One such system that the Federal Aviation Administration (FAA) is developing is called Terminal Flight Data Manager (TFDM). Terminal Flight Data Manager (TFDM) is an FAA NextGen program based on airport surface management concepts developed under NextGen direction. The TFDM concepts have been validated with operational users through FAA funded concept engineering and prototype development activities. TFDM will help save time and fuel, reduce emissions, and improve the experience for the flying public.

The FAA Air Traffic Organization (ATO), Decision Support Systems Organization with the Program Management Office (PMO) is the agency sponsor for this acquisition. TFDM capabilities will be incrementally deployed to provide efficiencies in the airport surface and terminal airspace by providing new integrated surface traffic control and management capabilities. TFDM functions include: Surface Collaborative Decision Making (S-CDM), including departure scheduler and other airport decision tools; Electronic Flight Data (EFD); Enhanced Air Traffic Control Tower (ATCT) Traffic Flow Management System (TFMS); and Replacement or integration of multiple systems in the National Airspace System (NAS). TFDM will share data among controllers, aircraft operators, and airports so they can better stage arrivals and departures and manage traffic flow within terminal airspace for greater efficiency. Stakeholders will have a shared awareness of flights on the ground and in the air; the ability to exchange

C.1.2 Background Currently, at most airports, paper flight strips are being used to monitor and share flight plans, requiring controllers to handle and communicate safety-critical data manually. Traffic predictions and decisions are tied to flight plan data that is often untimely and unable to be shared between stakeholders. Flight plans are used to estimate arrivals, gate push-backs, routings, and departures. Their use in the tactical decisions made in handling the more than 40,000 flights daily can lead to inefficiencies across the national airspace system. In addition, aircraft operators currently board passengers and push back from the gates before flights are given slots in line for departure. This can lead to tarmac congestion and wasted fuel with aircraft idling as they wait to join the departure queue.

The imbalance between capacity and demand causes significant growth of delays and severely disrupts the movement of passengers and goods. The implementation of TFDM will result in improved collaboration with users, enhanced accuracy of demand and capacity predictions, and improvements in system modeling and measurement will lead to a better understanding of alternative strategies, enabling more informed decisions.

C.1.3 Purpose

The purpose of this Statement of Work (SOW) is to define the effort required to design, develop, test, implement and support the TFDM System that meets all requirements in the FAA TFDM System Specification Document (SSD), provided in Section J (Attachment J-6) of this contract. This SOW also includes provisions for Program Management (PM), System Engineering (SE), System Design, System Development, System Test and Evaluation, Training, Implementation, Integrated Logistic Support, Engineering Services, and General Engineering/Technical Services. The Contract Data Requirements List (CDRL) contained in Section J of this contract defines the products to be delivered to the Government resulting from the effort defined in this SOW.

C.1.4 Scope

The scope of this contract includes the following major components:

1. Establish and maintain a Program Management Office and perform Program Management to support and coordinate the work performed under this contract to ensure compliance with all terms and conditions

2. Design, development and test of TFDM requirements in accordance with the FAA TFDM System Specification Document (SSD) (Attachment J-6).

3. Development of training for FAA TFDM operators and maintainers

4. Implementation including replacement or integration of multiple systems in the National Airspace System (NAS) and Logistical Support

5. Engineering Services and System/Site Support C.1.5 Benefits TFDM will provide automated data available to stakeholders in real-time to facilitate faster and higher quality decision-making and reduce errors. It will accomplish this through providing the following benefits:

· Real-time Accuracy. Accurate data from surface and terminal surveillance in continuously updated capacity-and-demand predictions will decrease time aircraft spend waiting to taxi, improve the traffic flow, and help prevent missed connections.

· Collaborative Decisions. By connecting aircraft operators, controllers, and airports with digital flight plans, shared surveillance data, and collaborative decision-support tools, TFDM will help stakeholders work together to optimize flights. This will save time and fuel, reduce emissions, and improve the experience for passengers.

· Connected Stakeholders. TFDM lets stakeholders exchange data electronically to make more informed tactical decisions and better handle changing traffic volume, weather, and other evolving situations.

· Better Predictive Tools. TFDM uses surface and terminal surveillance and flow-management capabilities in its predictive modeling for improved departure management, ground movement, and flight coordination.

· Taxpayer Savings. Multiple costly legacy systems will be replaced with a single, easily maintained state-of-the-art TFDM platform.

· Environmentally Friendly. Reduced taxi times, fewer delays and missed connections, and greater predictability with TFDM will save fuel and reduce emissions.

C.2 Applicable Documents The following specifications, handbooks, orders, standards, and drawings form a part of this contract and are applicable to the extent specified herein Tables 1: Military Standards and Specifications, Table 2: FAA/Department of Transportation (DOT) Specifications, Standards, and Orders, and Table 3: Other Publications and Specifications. In the event of conflict between this contract and any of the applicable documents cited below, the provisions of this SOW must apply.

a. Copies of Federal Aviation Administration (FAA) specifications and interface documents may be obtained from the Federal Aviation Administration, Headquarters Public Inquiry Center APA-230, 800 Independence Avenue SW, Washington, DC 20591, 202-267-3484. Requests should fully identify material desired and cite the solicitation or contract number.

The FAA Test and Evaluation Handbook, VVSPT-A2-PDD-013_TnE_Handbook_v3.0, may be obtained at the following website: http://www.faa.gov/about/office_org/headquarters_offices/ang/offices/tc/initiatives/vnv/documents/publications/VVSPT-A2-PDD-013_TnE_Handbook_v3.0.pdf

The FAA Work Breakdown Structure (WBS) Version 5.1 may be obtained at the following website: http://fast.faa.gov/docs/wbs.doc

b. Requests for copies of documents not covered in the preceding paragraph should be addressed to the Contracting Officer (CO). Requests should fully identify material desired and cite the solicitation or contract number.

c. Military Standards and Specifications can be ordered from the Department of Defense Single Stock Point (DODSSP), Building 4/Section D, 700 Robbins Avenue, Philadelphia, PA 19111-5098. Information is available at their website, http://dodssp.daps.dla.mil.

d. Copies of ANSI/ASQC-Q9001-2008 and ISO 9000-3:2004 can be obtained from the following source: American Society for Quality Control P.O. Box 3005, Milwaukee, WI 53201-3005 or 600 North Plankinton Avenue, Milwaukee, WI 53203 Phones: (414) 272-8575 or (800) 248-1946. The Fax is: (414) 272- 1247.

e. Copies of RTCA Documents can be ordered from the RTCA website: http://www.rtca.org C.2.1 Military Standards and Specifications Table 1: Military Standards and Specifications

Standards and Specifications
Description
MIL-HDBK-470A
Designing And Developing Maintainable

Products And Systems Volume I

MIL-HDBK-781A
Reliability Test Methods, Plans, and Environments for Engineering Development, Qualification, and Production
MIL-HDBK-217F
Reliability Prediction of Electronic Equipment
MIL-HDBK-502A
Product Support Analysis
GEIA-STD-0007B
Logistics Product Data
MIL-DTL-31000C
Technical Data Packages
MIL-STD-129P Change 4
Military Marking for Shipment and Storage
MIL-STD-961E
Defense and Program-Unique Specifications Format and Content
MIL-STD-2073-1D
Application of Packaging Requirements with Standard Practice for Military Packaging
MIL-STD-3034A
Reliability Centered Maintenance (RCM) Process

C.2.2 FAA/DOT Specifications, Standards, and Orders Table 2: FAA/DOT Specifications, Standards, and Orders

FAA/DOT Specifications, Standards, and Orders
Description
FAA Acquisition Management System (AMS)
FAA Acquisition Management System (AMS)
FAA-STD-028C
Contract Training Program
FAA-STD-021A
Configuration Management (Contractor Requirements)
FAA-STD-025F
Preparation of Interface Control Documentation
FAA-STD-026A
NAS Software Development, June 1, 2001
FAA-STD-019E
Lightning and Surge Protection, Grounding, Bonding and Shielding Requirements for Facilities and Equipment
FAA HF-STD-001
Human Factors Design Standard
FAA HF-STD-002
Baseline Requirements For Color Use In Air Traffic Control Displays
FAA HF-STD-003
Alarms and Alerts in the Technical Operations Environment
FAA HF-STD-004
Requirements for a Human Factors Program
JO 3900.57A
Environmental and Occupational Safety and Health (EOSH) Requirements In The Planning And Execution Of Construction And Maintenance Activities At National Airspace System (NAS) Facilities
FAA Order 1050.10C
Prevention, Control and Abatement of FAA Environmental Pollution
FAA Order 1050.20A
Airway Facilities Asbestos Control Program
FAA Order 1050.14B
Polychlorinated Biphenyls (PCBs) in the National Airspace System (NAS)
FAA Order 4600.27B Change 1
Personal Property Management
FAA Order 1050.19B
Environmental Due Diligence Audits in the Conduct of FAA Real Property Transactions
FAA Order 1800.66 Change 3
Configuration Management Policy
FAA Order 6000.15G
General Maintenance Handbook for National Airspace Systems (NAS) Facilities
FAA-C-1217F
Electrical Work, Interior
FAA-D-2494B
Technical Instruction Book Manuscript: Electronic, Electrical, & Mechanical Equipment Requirements for Preparation of Manuscript & Production of Books
FAA-G-2100H
Electronic Equipment, General Requirements
FAA Order 1370.82A
Information Systems Security Program
FAA Order 8000.360CA
FAA Safety Management System
SRMGSA
FAA Safety Risk Management Guidance for System Acquisitions October 2022 Version 2
FAA-HDBK-006A
Reliability, Maintainability, and Availability (RMA) Handbook
Supply Support Catalog Instructions (SSCI)
Standard Subject Identification Code (SSIC) Manual
FAA Order 6010.7B
Joint Acceptance Inspection
ASD-100-SSE-1 Rev 10
NAS Modernization System Safety Management Program (SSMP)
FAA Air Traffic Organization (ATO) Security Authorization Handbook Version 1, Dated October 2016
FAA Air Traffic Organization (ATO) Security Authorization Handbook
FAA Order 1810.8
FAA William J. Hughes Technical Center's Test and Evaluation Policy
JO 1050.17A
Environmental Compliance at Air Traffic Control Towers
JO 6980.25D
Maintenance of Batteries for Standby Power
TFDM Test and Evaluation Master Plan (TEMP) Version 2.6
TFDM Test and Evaluation Master Plan
FAA-STD-065A
Preparation of Web Service Description Documents (WSDDs)
FAA-STD-070
Preparation of Web Service Requirements Documents
FAA-STD-073
Preparation of JAVA Message Service Description Documents
FAA Section 508
Section 508 of the Rehabilitation Act (29 U.S.C. 794d
FAA System Wide Information Management (SWIM) Governance Policies Version 2.0
FAA System Wide Information Management (SWIM) Governance Policies
FAA Work Breakdown Structure (WBS) Version 5.1
FAA Work Breakdown Structure (WBS)
Electronic Learning Management System (eLMS) Content Integration Guide
Electronic Learning Management System (eLMS) Content Integration Guide
eLearning Design and Systems Requirements Style Guide
eLearning Design and Systems Requirements Style Guide
AJI DEVELOPMENT GUIDE FOR INSTRUCTOR-LED TRAINING MATERIALS – SINGLE COLUMN, Version V.2020.09
Instructor Led Training Development Guide

C.2.3 Other Publications and Specifications Table 3: Other Publications and Specifications

Other Publications and Specifications
Description
ANSI/ASQC-Q9001-2008
American National Standard, Quality System-Model for Quality Assurance in Design, Development, Production, Installation, and Servicing
ISO 9000-3:2004
International Standard, Quality Management and Quality Assurance Standards – Part 3: Application of International Standards Organization (ISO) 9001 to the Development, Supply and Maintenance of Software
ISO/IEC 12207-2008
Systems and Software Engineering - Software Life Cycle Processes
SP-800-18 Rev.1
Guide for Developing Security Plans for Federal Information Systems
SP-800-34 Rev.1
Contingency Planning Guide for Federal Information Systems
SP 800-53 Rev.4
Security Controls for Federal Information Systems and Organizations
SP-800-60 Volumes 1 & 2
Volume 1: Guide for Mapping Types of Information and Information Systems to Security Categories.

Volume II: Appendices to Guide for Mapping Types of Information and Information Systems to Security Categories

ANSI/EIA-748C
Earned Value Management System
GEIA-HB-649
Configuration Management Package
IEEE-STD-200
Institute of Electrical and Electronics Equipment (IEEE) Standard Reference Designations for Electrical and Electronics Parts and Equipment
IEEE-STD-315
Graphic Symbols for Electrical and Electronics Diagrams (Including Reference Designation Letters)
IEEE Standard 830-1998
IEEE Recommended Practice for Software Requirements Specifications
IEEE Standard 1016-2009
IEEE Standard For Information Technology–Systems Design–Software Design Descriptions
IEEE/EIA 12207-2008
Standard for Information Technology—Software Life Cycle Processes
29 CFR 1910.1001
Asbestos
29 CFR 1910.1025
OSHA Toxic and Hazardous Substances
29 CFR 1910.145
Accident Prevention Tags
29 CFR 1910.146
Permit-Required Confined Spaces
29 CFR 1910.147
OSHA Control Of Hazardous Energy (Lockout/Tagout)
29 CFR 1910.242
Hand and Portable Powered Tools and Other Hand-Held Equipment
29 CFR 1910.1200
Hazard Communications
29 CFR 1910.1926
Occupational Safety and Health Standards
29 CFR 1926.62
OSHA Lead Exposure In Construction
29 CFR 1960.20
Alternate Standard for Fire Safety in Air Traffic Control Towers
40 CFR
Protection of Environment
40 CFR Chapter 1 Sub-Chapter I
Solid Waste
40 CFR Part 82
Protection of Stratospheric Zone
40 CFR 260-280
Hazardous Waste Management System
49 CFR 170-180
Federal Hazardous Materials Regulations
National Defense Industrial Organization (NDIA) Integrated Baseline Review (IBR) Guide : September 2010
Integrated Baseline Review Guide
National Environmental Policy Act (NEPA)-80
Fire Doors and Other Opening Protectives
National Fire Protection Association Code 70. Current edition: 2014
National Electrical Code
National Fire Protection Association (NFPA) 70E, Current edition: 2015
Standard for Electrical Safety in the Workplace
29 CFR 1910
Occupational Safety and Health Standards
Resource Conservation and Recovery Act (RCRA) of 1976
Controls hazardous wastes from generation through disposal.
IEEE 1517:1999
IEEE Standard for Information Technology – Software Life Cycle Processes – Reuse Processes
ASTM-D5077-90 (2009)
Standard Terminology Relating to Electrostatic Discharge (ESD) Packaging
ASTM-D3951
Standard Practices for Best Commercial Packaging
FIPS 199
Standards for Security Categorization of Federal Information and Information Systems
FIPS 200
Minimum Security Requirements for Federal Information and Information Systems
RTCA/DO-278A
Software Integrity Assurance Considerations for Communication, Navigation, Surveillance and Air Traffic Management (CNS/ATM) Systems
RTCA/DO-330
Software Tool Qualification Considerations

C.3 Program Management The Contractor must establish and maintain a Program Management Office (PMO) and perform Program Management to support and coordinate the work performed under this contract to ensure compliance with all terms and conditions set forth in this contract. The Contractor must establish clear and effective lines of authority, coordination, communication, and accountability between the Contractor’s PMO and the Government to ensure sufficient and timely resources are given to the resolution of any problems that may arise.

The Contractor must assign a Program Manager (PM) who will ensure performance under this contract and will be the primary point of contact for the work to be performed under this contract. The PM must keep the FAA informed of any potential problems and make recommendations for resolution. The PM must ensure that all necessary management, business, contracts, engineering, implementation, and maintenance resources are available and sufficient, both in terms of the quantity of resources and their qualifications to successfully perform all the tasks required in this contract. The Contractor is responsible for management and control of all subcontractors/team members to ensure compliance with all requirements of this contract.

The Contractor must include, but not be limited to, program management activities such as contract administration, finance, obtaining and retaining qualified personnel, as well as technical support across all phases of the program. The PM must have sufficient corporate resources and authority to direct, execute, and control all elements of the program to ensure efficient and timely program execution. The PM must be the focal point within the Contractor's activities for all required program tasks. The PM must be prepared at all times to present and discuss the current program status as well as forecasts related to contract activities with the Government Contracting Officer (CO), the Contracting Officer's Representative (COR), and/or the Government PM. The Contractor must support the Contract/Finance Working Group, Working Group and TIMs Listing (Attachment J-7), to address relevant contract activities including, but not be limited to, resource loading, work breakdown structure, schedules, deliverables, Earned Value (EV) analysis, program tracking, contract modifications, and funds expenditure tracking and status.

The Contractor must provide management oversight of all contract activities to ensure high quality of work effort and deliverables that demonstrate traceability to all program requirements. The Contractor must identify and remedy potential technical cost and schedule risks and issues. The tasks described herein must be fully integrated to ensure their efficient and timely execution.

The Contractor must develop and implement and update every 24 months an integrated Program Management Plan (PMP) in accordance with (CDRL M01). The PMP must integrate all functional areas and must articulate the specific objectives to be accomplished at an overview level. The PMP must also identify the staffing and other resources required to meet contract requirements.

M01 Program Management Plan (PMP)

C.3.1 Meetings, Reviews, Conferences, and Evaluations The Contractor must support recurring meetings such as status meetings, Technical Interchange Meetings (TIMs), Program Management Reviews (PMRs), Formal Design Reviews (i.e. System Requirements Review (SRR), Preliminary Design Review (PDR), Critical Design Review (CDR), and evaluations with the Government to discuss program progress, and identify potential problems and resolve identified issues.

The Contractor must prepare Agendas, Meeting Minutes, Action Item Lists, and Presentation Materials for each meeting, conference review and/or evaluation. The Contractor must provide an agenda and notify the CO of its readiness five business days prior to the start of each meeting, conference, review or evaluation. All CDRL items required for a meeting, conference, review or evaluation, are to be delivered in accordance with the (CDRL M03) requirements.

The following instructions are applicable to all meetings, reviews, conferences, and/or evaluations:

1. All Program Management Reviews will be held at a Contractor provided facility within the fifty (50) mile radius local commuting area of Washington, DC unless otherwise directed by or approved by the government. All other meetings, conferences and/or evaluations will be held at the Contractor’s facility unless otherwise directed by or approved by the Government. The Contractor must provide teleconferencing capability, internet access, and facility location(s) to accommodate necessary participation as requested by the Government. The Contractor must propose a date for the meeting, review, conference, and/or evaluation for the COR's approval.

2. For all presentations and agendas, the Government reserves the right to revise the agenda and/or presentation material. The Contractor must provide appropriate Contractor personnel to respond to Government questions. The Contractor must prepare and deliver a summary of open, pending, and closed action items and presentation materials prior to the start of each scheduled meeting, conference, review or evaluation. The Government will revise the delivery times when necessary.

3. The Contractor must record and submit minutes. The Contractor must track action items. Each assigned action item must have a due date and responsible person(s) assigned, who must provide the status of the action at agreed upon intervals until the action is closed. Unless otherwise specified by the Government, the Contractor must respond to all action items with a written closure statement. In the event that an action item cannot be closed promptly a plan of action must be developed for closure.

M03 Agenda, Presentation Materials, Action Item List and Meeting Minutes

C.3.1.1 Post Award Conference The Contractor must plan for, host, support, and participate in a Post Award Conference (PAC) to be held at the Contractor's site within twenty-one (21) calendar days after contract award and document the conference in accordance with (CDRL M03). At this conference, the Contractor must address the plans and schedules for the TFDM work efforts. The Contractor must demonstrate adequacy of proposed efforts to meet all contractual requirements.

The conference is intended to:

1. Establish a liaison between the Contractor, FAA Contracting Officer, FAA Contracting Officer Representative (COR), FAA Technical Training Advisor (TTA), and other FAA personnel specified in the contract and charged with the responsibility for contract administration.

2. Permit inspection of the Contractor’s facility and establish a working relationship with contractor personnel.

M03 Agenda, Presentation Materials, Action Item List and Meeting Minutes

C.3.1.2 Program Management Reviews The Contractor must conduct and support Program Management Reviews (PMRs) in accordance with (CDRL M03) to provide a status and review of work and efforts being conducted under this contract. The Contractor must be prepared to support monthly PMRs but the Government reserves the right to decrease the frequency in accordance with the program needs. For all PMRs, the Government PM may modify the meeting schedule and/or PMR agenda topics to accommodate special program needs. At PMRs, the Contractor must provide, at a minimum, program's management, technical, cost and schedule status. The age of financial data presented at the PMR will be clearly indicated to support the goal that it should be as current as possible. The PMR must be accomplished nominally within one working day.

The Government reserves the right to conduct Executive PMR(s) as part of the PMR agenda(s).

The Contractor must use PMRs to provide program insight to Government representatives on the topics including, but not limited to:

1. Major accomplishments since the last PMR and expected major accomplishments prior to the next PMR;

2. Anticipated differences between contract milestones, schedules, technical performance, cost, Estimate at Completion (EAC) and performance status including identification of major drivers behind cost/schedule variances and the action plans to resolve these variances;

3. Changes in organizational chart and planned versus actual staffing by functional discipline;

4. Review of actions from previous PMR, future required actions, and continual funding status;

5. Integrated Master Schedule (IMS) identifying schedule changes from previous PMR, completed and upcoming milestones, critical path status, all critical path changes, critical path issues and impacts, and a preview of all activities for the next ninety (90) calendar days;

6. Contractor deliverables to be delivered within the following ninety (90) calendar days, the status of CDRL reviews from the Government and status of changes from the previous PMR;

7. Status of open program trouble reports (PTRs), and/or discrepancy reports (DRs) and change requests (CRs) since the last PMR;

8. Status of testing including testing metrics;

9. Status of program risks and their mitigation plan;

10. Program management action item status;

11. Notification of any deviations/waivers from the requirements and the associated justification;

12. Commercial product obsolescence and supportability issues and recommended actions;

13. (Reserved as of BCD RFO) Status of Engineering Change Proposals (ECPs);

14. Implementation and site activation/deployment status; and

15. Status of production readiness to include:

a. Procurement/integration and production schedules for system components; and

b. System integration schedules that demonstrate compatibility with the site deployment schedule.

16. Reporting of metrics specified in SOW Section C.3.3.1.

M03 Agenda, Presentation Materials, Action Item List and Meeting Minutes

C.3.1.3 Integrated Baseline Review The Government will conduct an Integrated Baseline Review (IBR) no later than 120 days after contract award. The contractor will host the event and is to play an active role in planning and providing all requested data in preparation for the event. The purpose of the IBR is to:

· Evaluate the Contractor’s implementation of the performance measurement baseline;

· Ensure that the Government and Contractor mutually understand program scope, schedule, resources, inherent risk, and management approach;

· Review contractor’s planning and execution efforts to meet contractual requirements in areas including but not limited to complete coverage of the SOW, logical scheduling of work activities and adequate allocation of resources;

· Ensure early and adequate planning;

· Identify risks to be tracked; and

· Ensure appropriate reporting levels have been identified and variance thresholds are agreed to by the Government and Contractor.

The Contractor must provide the Government with requested information to include, but not be limited to, data and documents in accordance with IPMR Material (CDRL M08). The contractor must refer to Section H and the National Defense Industrial Association (NDIA) IBR Guide dated September 2010 as guidance for the IBR. The Government may conduct additional IBRs within six months after major modifications to the contract, through mutual agreement between the Government and the Contractor. The Contractor must submit meeting minutes in accordance with (CDRL M03) following each IBR.

M03Agenda, Presentation Materials, Action Item List and Meeting Minutes
M08Integrated Baseline Review Material

C.3.1.4 System Requirements Review The Contractor must plan for, participate in, and conduct a System Requirements Review (SRR) in accordance with (CDRL E07 and M03). The objective of this review is to ascertain the adequacy of the Contractor’s efforts in defining the complete set of system requirements specified in the TFDM System Specification Document (SSD) (Attachment J-6), and TFDM Deployment Build Release Plan (Attachment J-10) as specified in this contract. A single, comprehensive SRR must be conducted to address the requirements outlined above. Incremental or “delta” SRRs may be conducted, subject to Government approval, to address those TFDM functional requirements addressed in the SRR which have been impacted from the development and implementation of segregated TFDM Software Builds.

The SRR must be conducted when the Government determines through the Requirements Identification and Development Working Group (RIDWG) that a significant portion of the system functional requirements have been established.

E03System/Subsystem Specification
E06Software Development Plan
E07System Requirements Review Materials
M03Agenda, Presentation Materials, Action Item List and Meeting Minutes
T01Contractor Master Test Plan

C.3.1.4.1 System Requirements Review Acceptance Criteria To successfully complete the SRR, the Contractor must meet the following acceptance criteria:

· Obtain Government acceptance of all SRR-associated CDRLs;

· Analyze requirements in the FAA TFDM System Specification Document (SSD) (Attachment J-6) and demonstrate a thorough understanding of these requirements;

· Identify any derived requirements; and

· Establish a requirements baseline consisting of the requirements in, FAA TFDM System Specification Document (SSD) (Attachment J-6), and any derived requirements.

C.3.1.5 Preliminary Design Review The Contractor must conduct a Preliminary Design Review (PDR) in accordance with (CDRLs E04 andM03). Subject to Government approval the Contractor may conduct incremental, or “delta” PDRs. All PDRs must address:

1. Allocation of TFDM functional requirements to individual TFDM Software Builds, specified in Deployment Build Release Plan (Attachment J-10) of the contract, and/or

2. PDR topics that have been impacted from the development and implementation of segregated TFDM Software Builds, specified in Deployment Build Release Plan (Attachment J-10) This review must be conducted for each configuration item or aggregate of configuration items to:

1. Evaluate the progress, technical adequacy, and risk resolution (on a technical, cost, and schedule basis) of the selected design approach.

2. Evaluate the degree of definition and assess the technical risk associated with the selected manufacturing methods/processes.

3. Establish the existence and compatibility of the physical and functional interfaces among the configuration items and other items of equipment, facilities, computer software, and personnel.

For Computer Software Configuration Items (CSCIs), this review must focus on:

1. The evaluation of the progress, consistency, and technical adequacy of the selected top-level design and test approach.

2. Compatibility between software requirements and preliminary design.

3. The preliminary version of the operation and support approach.

The SRR must be approved by the Government before a PDR may be conducted, and all SRR action items must be closed prior to conducting the PDR, unless the Government has given permission to proceed. The PDR must cover the preliminary design of all Contractor-developed hardware and software configuration items. For items that are not Contractor-developed, the Contractor must provide a functional/physical description of the item, the results of the analysis that verifies the item will meet the associated technical requirements, and a description of the interfaces with other configuration items.

At the PDR, the Contractor must describe the products, processes, methodologies, milestones, and measurements to be used in conducting software development activities. The Contractor must describe its plans for acquiring and developing the required hardware and software to meet contract requirements. The Contractor must describe a process and products similar to those in IEEE/EIA 12207-2008. Overall technical program risks must be reviewed on a technical, cost, and schedule basis.

M03Meeting Agenda, Meeting Minutes, and Presentation Materials
E04Preliminary Design Review Materials

C.3.1.5.1 Preliminary Design Review Acceptance Criteria To successfully complete the PDR, the Contractor must meet the following acceptance criteria:

· Allocate all the requirements in the requirements baseline to Hardware Configuration Items (HWCIs) and Computer Software Configuration Item (CSCIs);

· Provide a traceability of the requirements baseline to the HWCIs and CSCIs;

· For each HWCI and CSCI, identify which requirements are satisfied by Commercial Off The Shelf (COTS), which requirements are already implemented, but require modification, and which requirements require development; and

· Present a preliminary design in accordance with (CDRL E04) that shows how COTS, modified COTS, and new…