This document is a Statement of Work (SOW) for the Emergency Transceiver Replacement (ETR) contract, detailing requirements for delivering emergency communication equipment for the Federal Aviation Administration (FAA). The contract aims to provide emergency air/ground communication capability during catastrophic failures of normal radio communication systems, such as power loss, facility abandonment, or connectivity issues. The SOW covers comprehensive requirements including equipment delivery, configuration management, integrated logistics support, bar code and asset tracking, testing protocols, technical support services, and telephonic support.

Key contract requirements include developing and delivering emergency transceivers that meet specific FAA product specifications, conducting multiple test phases (Factory Acceptance Test, Operational Test, Production Acceptance Test, Production Unit Test), maintaining configuration control, providing detailed logistics management documentation, implementing a bar code tracking system, and offering technical support services. The contractor must also establish a toll-free dedicated telephone support line operating seven days a week from 8:00 AM to 8:00 PM Central Time to provide guidance on equipment engineering, maintenance, operation, and training problems for the duration of the contract and warranty period.

View the file

Other files

File Type Posted
Notice 6.18.25.pdf PDF
BNATCS Industry Day videos.docx DOCX document
BNATCS Industry Day Attendees.docx DOCX document
Industry Day 1 Briefings.pdf PDF
Industry Day 2 Briefings.pdf PDF
RFI System Providers 1.docx DOCX document
Question for one on ones 6.6.2025.docx DOCX document
2025.06.05 Industry Day Agendas.docx DOCX document
STARS Section C.docx DOCX document
RFI Brand New ATC System A1.docx DOCX document
RFI Brand New ATC System.docx DOCX document
EIS Section C.pdf PDF
MSBRS Section C.pdf PDF
SMR4 Section C ASDE-3 SMR Replacement.pdf PDF
CCS-W Bridge Section C.pdf PDF
TFDM Section C.docx DOCX document
ETVS RDVS STVS Section C.pdf PDF
APCS Section C.docx DOCX document
MEVA 3 NetworkSection C.pdf PDF
TFM2 Section C.pdf PDF
STARS Section C.docx DOCX document
E-IDS Section C.docx DOCX document
CSS-Wx Section C.docx DOCX document
MCT SECTION C.pdf PDF
VSBP Section C.pdf PDF
NWP Section C.docx DOCX document
CTD Section C_AMEND 0001.docx DOCX document
TBFM Section C.pdf PDF
NEXCOM V2 Section C.pdf PDF
DNTS Section C.pdf PDF
AIMMS2 Section C.pdf PDF
ALSF -2 SLEP SOW 5-28-25.pdf PDF
NVR Section C.pdf PDF
ILS-420 Section C.pdf PDF
IVSR Section C.pdf PDF
ERAM Section C.docx DOCX document
RVR Section C.pdf PDF
FENS Section C.docx DOCX document
WMSS3 Section C.docx DOCX document
ASSC Section C.pdf PDF
DME Contract Section C_P18 Final.pdf PDF
NEXCOM Section C.docx DOCX document
WSIC Section C.pdf PDF
DCIS Section C Award Mod 0143.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

693KA8-21-D-00002

Page C-1

Modification P00014

PART I – SECTION C

STATEMENT OF WORK

TABLE OF CONTENTS

C.1. INTRODUCTION

C.1.1 Purpose C.1.2 Scope

C.2. APPLICABLE DOCUMENTS

C.2.1 SPECIFICATIONS

C.2.2 STANDARDS AND ORDERS

C.3. REQUIREMENTS

C.3.1 EQUIPMENT & ASSOCIATED EQUIPMENT/DOCUMENTATION/SOFTWARE

C.3.1.1 Optional Maintenance Data Terminal Software Enterprise License (MDTSEL)

C.3.2 CONTRACT MANAGEMENT

C.3.2.1 Program Management C.3.2.2 Integrated Master Schedule C.3.2.3 Quality System Plan

C.3.3 CONFIGURATION MANAGEMENT

C.3.3.1 Configuration Identification C.3.3.2 Documentation Management C.3.3.3 Product Baseline C.3.3.4 Configuration Control C.3.3.5 Configuration Status Accounting C.3.3.6 Configuration Audits

C.3.4 MEETINGS

C.3.5 PROGRAM REPORTING

C.3.5.1 Monthly Progress Status Report (MPSR) C.3.5.2 Quarterly Financial Progress Status Report (QFPSR) C.3.5.3 Performance Report (PR)

C.3.6 INTEGRATED LOGISTICS SUPPORT (ILS)

C.3.6.1 Point of Contact C.3.6.2 National Airspace Integrated Logistics Support (NAILS) Program C.3.6.3 Integrated Support Plan (ISP) C.3.6.4 Logistics Guidance Conference (LGC) C.3.6.5 Logistics Management Information C.3.6.6 Final Breakdown Structure C.3.6.7 Tools and Test Equipment List (T&TEL) C.3.6.8 Repairs C.3.6.9 Technical Instruction Books (TIBs) C.3.6.10 Training

Page C-2

Modification P00014

C.3.6.11 Long Term Supportability Data Package (LTSDP)

C.3.7 BAR CODE AND ASSET TRACKING SYSTEM

C.3.7.1 Identification Markings C.3.7.2 Applying Identification Bar Codes on Containers C.3.7.3 Production, Warranty, and Repair Data Requirements C.3.7.4 FAA Scanning Process C.3.7.5 FAA Scanning Process Pilot Run

C.3.8 TEST

C.3.8.1 Point of Contact C.3.8.2 Contractor Master Test Plan (CMTP) C.3.8.3 Factory Acceptance Test C.3.8.4 FAA Operational Test (OT) C.3.8.5 Production Acceptance Test C.3.8.6 Production Unit Test (PUT)

C.3.9 TECHNICAL SUPPORT SERVICES

C.3.10 TELEPHONIC SUPPORT

Page C-3

Modification P00014

C.1. INTRODUCTION

C.1.1 Purpose This Statement of Work (SOW) defines the requirements for the Contractor to deliver Emergency Transceiver (ET) equipment in accordance with (IAW) Federal Aviation Administration (FAA) ET Product Specification (FAA-E-7868) in Section J01.

The purpose of the Emergency Transceiver Replacement (ETR) contract is to provide emergency air/ground communication capability for air traffic control (ATC) operations during catastrophic failure of the normal radio communication system. Communication failure might be experienced during loss of ATC facility power, or the failure of the inter/intra facility connectivity to the air/ground radio communications equipment. ET also provides emergency radio communication when a facility must be abandoned, e.g., in the event of facility fire, bomb threat, or severe weather.

The ET provides the air/ground communication capability during the first critical 60 minutes after these events occur. The ET will replace the existing grab-n-go Transceiver Communications Equipment (TCE) at all Air Traffic Control Towers (ATCTs), Terminal Radar Approach Control (TRACONs), and Alaskan Flight Service Stations (FSSs).

C.1.2 Scope The ETR contract scope encompasses all necessary equipment, software, documentation, and Contractor services required to replace existing emergency transceivers. Contractor services include warranty and repair, contract and program management, configuration management, integrated logistics support, bar code and asset tracking, support of Government testing activities, development of maintenance/operator training, support of Government spares provisioning and maintenance program, Quick Reference Guide installation into all ETR kits, and other required services necessary for the implementation, maintenance, and operation of the emergency transceivers.

The scope of the Indefinite Delivery/Indefinite Quantity (IDIQ) contract encompasses acquisition of future emergency communications equipment and services required during catastrophic failure of the normal radio communications systems or during emergency facility abandonment. Such additional equipment/services and their associated performance specifications would be determined as these requirements are identified. In addition, the ET equipment, software, and services may be ordered to support Department of Transportation (DOT) requirements, other FAA Program Offices, and other Government agencies, as needed.

C.2. APPLICABLE DOCUMENTS

The versions of the following documents in effect at Contract award are included in this SOW.

C.2.1 SPECIFICATIONS

FAA:

Page C-4

Modification P00014

FAA-E-7868 NEXCOM II Emergency Transceiver Product Description

FAA-D-2494 Technical Instruction Book Manuscript: Electronic, Electrical, and Mechanical Equipment, Requirements for Preparation of Manuscript and Production of Books

C.2.2 STANDARDS AND ORDERS

FAA:

FAA-Order 6000.15 General Maintenance Handbook for National Airspace System

(NAS) Facilities

FAA-STD-021 Configuration Management

FAA Order 3000.22 Air Traffic Organization Outcomes-Based Technical Training

FAA Order 3000.57 Air Traffic Organization Technical Operations Training and

Personnel Certification Programs

Publication FAA Asset Identification Process and Procedure Guide

Version 3.2

General Services Administration (GSA):

FED-STD-5 Standard Guides for Preparation of Proposed Item Logistics Data Records

Government Electronics Industry Association (GEIA)-STD-0007-A Logistics Product

Data Handbook (SAE)

Categories of eLearning Technology and their Impact on Performance and Proficiency, November 2008

FAA eLMS Content Integration Guide, December 2017

In the event of conflict between the documents referenced herein and this SOW, the contents of this SOW take precedence.

Page C-5

Modification P00014

C.3. REQUIREMENTS

The Contractor must fully manage all work to ensure its efficient and timely execution. The requirements include the specifications and standards set forth in SOW Section C.2. The data to be delivered by the Contractor, as a result of performing the tasks prescribed by this SOW, are specified in the Contract Data Requirement Lists (CDRLs) and Data Item Descriptions (DIDs) in Attachment J02 of this contract.

C.3.1 EQUIPMENT & ASSOCIATED EQUIPMENT/DOCUMENTATION/SOFTWARE

The Contractor must have control over all aspects of this contract process. The Contractor must provide equipment, firmware, and software that meet the contract’s requirements. The equipment, firmware, and software provided under this contract must be supported by the Contractor for the life of this contract including exercised options and warranty period. The equipment includes the associated components, firmware, and software.

C.3.1.1 Optional Maintenance Data Terminal Software Enterprise License (MDTSEL)

The Contractor must provide an enterprise license for the MDTS IAW CDRL-S003. This license will allow FAA and its support contractors to distribute the MDTS freely without restriction.

C.3.2 CONTRACT MANAGEMENT

The Contractor must provide the required personnel and facilities to manage and administer the work required under this contract. This contract requires program management, planning, testing, and testing management, configuration management, logistics planning and logistics management, quality assurance, scheduling, and coordination activities. These activities include the internal and external management activities necessary for basic contract performance, reporting progress, demonstrating results, and coordinating technical activities with the FAA.

C.3.2.1 Program Management

The Contractor must maintain programmatic control over the work performed under this contract, including subcontractors and vendors. The Contractor must provide and maintain a Program Management Plan (PMP) as specified by CDRL-A001 and manage the contract in compliance with the approved PMP. The PMP must include the Quality System Plan (QSP), defined in section C.3.2.3 and the Configuration Management Plan (CMP) (CDRL-A006), defined in section C.3.3, as they are integral to the successful execution of this contract. The Contractor must provide an Integrated Master Schedule (IMS) (CDRL-A004), defined in section C.3.2.2, as part of the PMP.

The Contractor must specify an individual who serves as the Program Manager and will manage this contract using the PMP.

C.3.2.1.1 Performance Based Management System (PBMS) The PBMS is an internal management system which provides for reporting contract performance information to the Government. The Contractor must plan, schedule, budget, monitor, manage, and report performance applicable to this contract. The Contractor's PBMS must be the single point of integrated formal reporting for the Government. This reporting system must meet both

Page C-6

Modification P00014 the Contractor's internal management requirements and the requirements of the FAA for timely, reliable performance reporting information.

C.3.2.1.2 Contract Work Breakdown Structure (CWBS) The FAA will provide the Contractor a high-level framework for developing a complete CWBS.

The Contractor must generate and maintain a CWBS Dictionary for this effort based upon the standard FAA Work Breakdown Structure (WBS) defined in the FAA Acquisition Standard Toolset (FAST – http://fast.faa.gov) and IAW CDRL-A002 and CDRL-A003. The CWBS framework provided by the FAA will serve as the basis for further extension by the Contractor to lower levels during the performance of this contract.

The Contractor must extend the CWBS down to the appropriate level required to provide adequate internal management, surveillance, and performance measurement, regardless of the reporting level stipulated in this contract for FAA visibility. The CWBS must identify the Government program or project by utilizing a prefix code specified by the FAA.

Contract modifications that modify, add, or delete work scope under this contract must be incorporated into appropriate CWBS elements for work effort identification, definition, and procurement request relationships, as in the basic contract. The FAA will approve the CWBS.

The Contractor must not change the approved CWBS, associated definitions, or any of the reporting elements without prior written approval from the CO during the performance of this contract.

C.3.2.2 Integrated Master Schedule

The Contractor must provide an IMS (CDRL-A004), as part of the PMP, which must be consistent with the CWBS. A field may be set aside to record the CWBS number if using the CWBS as part of the Activity Identification (ID) proves restrictive. The Contractor must utilize the IMS as the day-to-day planning and execution tool to both manage the execution of this contract, and to assess program progress in meeting program requirements. The Contractor must report on program progress consistent with the IMS at each program management review, at selected technical reviews, and at other times at the Government’s request. The Contractor must revise the IMS, when necessary; to reflect current and changing contract milestones and deliverables. The IMS must include all activities and dependencies of the Contractor, subcontractors, vendors and interrelated Government activities (e.g., Operational Test). All Contractor schedule information delivered to the Government or presented at program reviews must originate from the IMS. The Contractor must perform appropriate analyses of the IMS tasks and report potential or existing problem areas and recommend corrective actions to eliminate or reduce schedule impact to the program.

Page C-7

Modification P00014

C.3.2.3 Quality System Plan The Contractor must have quality control over all aspects of this contract, including the production process. The Contractor must maintain and update a QSP IAW Section E, Quality Assurance Requirements of this contract. The QSP that complies with Section E of this contract must be attached to the PMP (CDRL-A001) as an appendix and integrated into the overall program. The Contractor must operate under the approved PMP and its integrated QSP. The PMP must outline how the QSP will be applied for this contract. The Contractor must maintain quality control over work performed by subcontractors and vendors.

C.3.3 CONFIGURATION MANAGEMENT

The Contractor must have configuration management control over all contract deliverables including the production process. The Contractor must maintain and update a CMP (CDRL- A006) that is integrated into the PMP (CDRL-A001). The Contractor must maintain configuration management on all Configuration Items and Documentation, described in sections C.3.3.1 and C.3.3.2 respectively, IAW the approved CMP. The Contractor must specify an individual who serves as a point of contact for all configuration management related issues. The Contractor must maintain configuration control over work performed by subcontractors and vendors to include, but not limited to, configuration identification (hardware, software, and documentation), establishment and control of configuration baselines (FCA and PCA), configuration status accounting, and audits.

C.3.3.1 Configuration Identification

The Contractor must maintain a system to identify, bar code, label, serialize, and mark Hardware Configuration Items (HWCI) and Software Configuration Items (SWCI) to provide traceability from delivery of the first FAA production unit to the final unit delivered under this contract. The identification process of HWCI and SWCI must be detailed in the CMP.

C.3.3.2 Documentation Management

The Contractor must deliver documents under this contract that adhere to configuration management practices as identified in section C.3.3. The Contractor must identify by titling, labeling, numbering, identifying date of publication, identifying originator of the documentation, and cataloging all documentation.

The procedures used must accomplish the following:

1. Identify specific versions of each element, HWCI, and/or SWCI to which a document applies; and,

2. Uniquely identify the document number, edition, change status, and other identification details of each document.

Page C-8

Modification P00014

C.3.3.3 Product Baseline

The Contractor must establish the Product Baseline after successful completion of the Factory Acceptance Test (FAT), described in section C.3.8.3, FCA, described in section C.3.3.6.1, and the PCA, defined in section C.3.3.6.2. The Product Baseline must occur prior to PAT, described in section C.3.8.5. The software versions and components comprising the Lowest Replaceable Unit (LRU) must form the basis of the Product Baseline identified in the Final Breakdown Structure, described in section C.3.6.6. An LRU is the lowest level subassembly that can be replaced during site level maintenance activities. The Government will review for approval the results of FAT, FCA, and the PCA for the establishment of the Product Baseline. The Product Baseline results in the identification of an established Government accepted baseline of hardware and software versions. The CSAR (CDRL-A008), described in section C.3.3.5, must be part of the Product Baseline documents submitted for review and is the mechanism for tracking changes to the Product Baseline.

C.3.3.4 Configuration Control

The Contractor must extend configuration control to include hardware, software, and documentation. The Contractor must maintain a Configuration Control Board (CCB) to support baseline management of the Product Baseline. The Contractor must maintain traceability, currency of the baselines, and consistency among all project documentation, hardware, and software. Changes generated by the Contractor after the Product Baseline has been established, which provide the same form, fit and function will not require formal approval by the Government.

This type of change, known as a Class II change, must be determined in concert with the Government. All changes that affect any of the Product Baseline documents or the Logistics Management Information (LMI) will require Government approval. Class II changes must be reviewed by the Quality Reliability Officer (QRO) for determination of these changes.

Any such changes, known as Class I changes, must be submitted to the Contracting Officer (CO) as Engineering Change Proposals (ECPs) (CDRL-A007). An accepted Class I change may require successful re-performance of FAT as described in section C.3.8.3.

Class I and Class II changes are defined in FAA-STD-021A paragraphs 80.4.1 and 80.4.2. The Contractor must submit the proposed changes prior to implementing any changes into the system design. FAA configuration control over system functional performance will be in effect from formal approval of the FCA. FAA configuration control over the physical form, fit, and function will be in effect from the formal PCA approval until the warranty expiration of the ultimate units delivered IAW this contract.

Page C-9

Modification P00014

C.3.3.5 Configuration Status Accounting

The Contractor must generate CSARs (CDRL-A008) to document changes to the Product Baseline. The CSAR identifies the configuration items, status of changes, and provides the supporting documentation reflecting these changes. The CSAR must provide traceability of any change through the change control process. The first submission of the CSAR must be generated for the Product Baseline as part of establishing the baseline.

C.3.3.6 Configuration Audits

The Contractor must host Functional and Physical Configuration Audits at the Contractor's facility. These audits must include all hardware, software, and documentation. The Contractor must submit the PCA Report, describing conduct and results of the audit as an attachment to the meeting minutes (CDRL-A006) for the Physical Configuration Audit. The report must catalog any discovered deficiencies and provide conclusions and recommendations as well as planned corrective actions. The Government will disapprove the audit if identification of major discrepancies such as unbaselined (missed requirement traceability) specifications, invalid or unverified requirements and uncorrected test failures are found. The Government will indicate whether the audit is approved without conditions, approved with contingencies, or disapproved.

Production orders will not be placed until all deficiencies are resolved and the audits are approved by the Government. The Government will not schedule audits until the prerequisite material or contract requirement is successfully completed.

C.3.3.6.1 Functional Configuration Audit The purpose of the FCA is to ensure that the system meets the functional performance requirements defined in the Product Specification (FAA-E-7868). The Government will review the FAT results prior to conducting the FCA. FCA must be conducted within 60 calendar days after the successful completion of the FAT and acceptance of the FAT Report, described in section C.3.8.3.4. The FCA is one of several meeting types outlined in section C.3.4.c). Production orders will not be placed until the Government has approved the Contractor’s proposed corrective actions for any unresolved FCA deficiencies.

C.3.3.6.2 Physical Configuration Audit The purpose of the PCA is: 1) to review top level design documentation for each LRU to validate that the Contractor has adequate engineering drawings to continue production of the hardware, software, and documentation; and 2) to identify the baselined physical characteristics of the various devices and control changes (for FAA support purposes). The PCA must be conducted no more than 60 days after the successful completion of FCA, described in section C.3.3.6.1, on the equipment that passed the FAT. The Contractor must provide technically competent personnel to disassemble the equipment as necessary, and to respond to Government queries during the PCA.

Prior to conducting the PCA, the Contractor must resolve all action items assigned at FCA and provide documentary evidence of the resolution. The Government will not place production orders until all proposed corrective actions are approved. The PCA is one of several meeting types outlined in section C.3.4.d).

Page C-10

Modification P00014

C.3.3.6.2.1 PCA Conduct The PCA baseline is established at the external perimeter of the primary LRUs, and includes all appurtenances, appliances, ancillary equipment, etc. that are part of the delivered device and/or that may be replaced for support purposes. The purpose of this baselining is to permit reliable configuration control by the FAA over the deployed equipment while avoiding unnecessary government involvement in internal system design.

C.3.4 MEETINGS

The Contractor must prepare and deliver to the Government an agenda, as specified by CDRL- A009, prior to each conference and meeting. The Contractor must record and prepare minutes, as specified by CDRL-A010, for each scheduled conference and meeting. Contractor administrative support must be provided only when meetings or conferences are held at a contractor facility.

Such support may consist of providing facilities, office equipment, and clerical support. The Contractor must provide facilities with adequate accommodation to house a government team that will generally consist of no more than twenty-five (25) representatives. The Government will not pay the direct costs for the meetings listed below, other than the price of the CLINs associated with CDRLs A009 and A010.

Meetings will be coordinated with the Contracting Officer’s Representative (COR) and approved by the CO (contractor’s facility agreed to by Contractor and FAA).

The Contractor must participate in the following meetings IAW contract requirements.

a) Post Award Conference (PAC). The Contractor must plan, host, provide administrative support, and participate in a PAC to be held at the Contractor’s facility, within the 48 contiguous states following contract award. The Government will determine the actual date of the PAC, which will occur no later than 60 calendar days after the contract award date. The PAC is held to provide detailed clarifications of the Government’s expectations under the contract. The PAC agenda is set by the Contactor but approved by the FAA. During the PAC, the Contractor must brief the plans and schedule for satisfying each SOW requirement and provide a list of all the COTS documentation that will be delivered with the software and equipment. The Contractor must include the finalized list of the COTS documentation as part of the PAC meeting minutes.

b) Logistics Guidance Conference (LGC), described in section C.3.6.4, and the Training

Guidance Conference described in Section C.3.6.10.1 must be at the Contractor’s facility, within the 48 contiguous states.

c) FCA, described in section C.3.3.6.1, must be at the Contractor's facility within the 48 contiguous states.

Page C-11

Modification P00014

d) PCA, described in section C.3.3.6.2 , must be at the Contractor's facility within the 48 contiguous states.

e) Provisioning Conference, described in section C.3.6.5.3, must be at the Contractor’s facility within the 48 contiguous states.

f) Four Program Management Reviews (PMRs) will be held annually through the first 24 months of this contract. Two PMRs will be held annually through the remaining term of this contract. The Government anticipates that all PMRs will be held at the Contractor's facility within the 48 contiguous states.

Technical Interchange Meetings (TIMs). The Contractor must support and participate in TIMs. The purpose of these meetings is to promote a free exchange of ideas between the Contractor and the Government in order to identify and resolve technical problems. The Contractor must provide the appropriate subject matter experts in order to respond to Government questions. The Contractor and FAA will coordinate the best location for the meetings. The Contractor must provide the appropriate subject matter experts in order to respond to Government questions. The Contractor and FAA will coordinate the best location for the meetings. TIMs will be done via Task Orders utilizing the Technical Support Services CLIN(s)

Teleconference meetings may be held in lieu of travel. The CO will notify the Contractor of the Government's readiness at least 15 working days in advance of each teleconference.

C.3.5 PROGRAM REPORTING

C.3.5.1 Monthly Progress Status Report (MPSR)

The Contractor must track and report the identification and status of new and existing risks, action items, and problems as identified in the PMP. This data must be maintained for the life of this contract and no entry will be deleted without Government approval. The report must comply with CDRL-A011, the Monthly Program Status Report (MPSR).

C.3.5.2 Quarterly Financial Progress Status Report (QFPSR)

The Contractor must furnish QFPSRs (CDRL-A012) that state the financial status of this contract.

C.3.5.3 Performance Report (PR)

The Contractor must submit a monthly Performance Report prepared IAW CDRL-A013. The Contractor must report summarized performance information at each Program Management Review, at selected technical reviews, and at other times at the Government's request.

Performance information should be reported by CLIN. The reported budget and actual cost values are FAA prices and not internal Contractor costs.

Page C-12

Modification P00014

C.3.6 INTEGRATED LOGISTICS SUPPORT (ILS)

C.3.6.1 Point of Contact

The Contractor must specify an individual who serves as a point of contact for all logistics issues.

C.3.6.2 National Airspace Integrated Logistics Support (NAILS) Program The Contractor must establish and maintain a NAILS Program IAW the logistics requirements contained in Section 3.6. The Contractor must participate as a member of the NAILS Management Team (NAILSMT) for the life of this contract. Participation must consist of attending NAILSMT meetings and resolving problems identified by the NAILSMT. Meeting support must include formulation/submission of agenda items, reports of the Contractor’s Integrated Logistics Support work, administrative support, and attendance by Contractor personnel considered necessary by the Contractor. The Government will determine whether the Contractor’s subcontractor participation in scheduled meetings is required.

Unless otherwise agreed to by the Government, NAILSMT meetings must be held at the Contractor’s facility. NAILSMT meetings should be combined with or included as part of other programmatic meetings (i.e., PMRs).

The Contractor must support the NAILSMT by submitting agenda items and ensuring participation (e.g., status briefings) of the Contractor/subcontractor personnel responsible for preparing the ILS deliverables identified in the NAILSMT meeting agenda. The Government will determine whether the Contractor’s subcontractor participation in scheduled meetings is required.

C.3.6.3 Integrated Support Plan (ISP)

The Contractor must deliver an ISP (CDRL-L001). The ISP must detail the Contractor’s plan for managing the ILS program for the program life cycle. The ISP will include the Contractor’s Logistics Management Information Plan. The Contractor is responsible for ensuring that all subcontractors and vendors comply with the ISP requirements.

C.3.6.4 Logistics Guidance Conference (LGC)

As part of the Post Award Conference described in section C.3.4.a), the Contractor must host an LGC. The purpose of the LGC is to ensure the Contractor understands all Integrated Logistics Support tasks. Included in the LGC will be a Provisioning Guidance Conference (PGC). The purpose of the PGC is to ensure contractor’s understanding of the provisioning requirements. The purpose of the TGC is to ensure contractors’ understanding of the training requirements. The Contractor must ensure the participation of appropriate Contractor/subcontractor personnel responsible for preparing the logistics deliverables specified in this contract. The Government will prepare the agenda for the LGC.

C.3.6.5 Logistics Management Information

The Contractor must deliver to the Government the LMI Data Products (CDRL-L002). The LMI data products must represent the physical top-down breakdown system design configuration

Page C-13

Modification P00014 including systems, subsystems, components, assemblies, subassemblies, cables and cable assemblies, support and test equipment, and training equipment required by the ET. Data submitted must be to the component level for all developmental items and to the LRU level for all COTS and non-developmental items. Any modification to a COTS item may disqualify it as COTS and may require LMI data to the component level. The Government will determine the level of LMI data required for COTS modified items. The Contractor must identify system LRUs (e.g., printed circuit boards, modules, disk drives, cables and cable assemblies, power supplies, etc.) during the LMI/Provisioning process. All items must be listed in the LMI submissions in the proper top-down break down format. The Contractor must update the breakdown structure during the Government’s FCA/PCA and during the Provisioning Conference (PC) as required. After the PC the Contractor must deliver the final breakdown structure to the Government for approval IAW the CDRL-L003. During the PC, the Government has the right to determine final system LRUs. Additionally, the Government reserves the right to add items it considers to be an LRU that are not considered an LRU by the Contractor. Data for temporary items is not required. The Contractor must adhere to the data definitions, edits, and data formats as described in Appendix B of GEIA-STD-0007-A. The Contractor must make maximum use of previously collected and analyzed data, and documentation prepared for COTS hardware and software components whenever possible. Modified COTS items must be explicitly identified as modified COTS. Items identified as proprietary must be clearly marked and identified as PROPRIETARY, marked in accordance with Clause 3.2.2.3-16, Restricting, Disclosing and Using Data (July 2004).

C.3.6.5.1 LMI Data Acceptance Criteria

The Contractor must adhere to the data definitions, edits, and formats as described in LMI Data Products (CDRL-L002).

C.3.6.5.2 LMI Data Reviews

The Contractor must present LMI Data Products for review at TIMs, program reviews, logistics reviews/meetings or via electronic means.

C.3.6.5.3 Provisioning Conference

The Contractor must host and support PCs, as outlined in section C.3.4 e). The PC must be held at the Contractor’s facility unless otherwise specified by the Government. The Contractor must ensure the participation of ET knowledgeable contractor/subcontractor personnel. A PC must be held no later than 60 calendar days after Government receipt of the initial LMI data.

During the PC, the Contractor:

a) must make all ET Government approved drawings (e.g., approved during a PCA), proprietary and non-proprietary, available for Government to use as references. The Government will not copy or remove any proprietary data from the Contractor’s facility unless the Contractor is required to submit such data as part of other submissions.

Page C-14

Modification P00014

b) must have copies of the Government approved FCA/PCA documentation available for use as a reference.

c) must make samples of systems, assemblies, and parts listed in the approved Product Baseline available for examination for the duration of the conference.

d) must furnish technically knowledgeable personnel and the tools required to disassemble the equipment, to the extent required by the Government.

e) must provide facilities (e.g., office space, conference room, access to telephone/facsimile/internet), for the Government provisioning team and contractor personnel. The number of Government participants in the PC will be provided to the Contractor prior to the conference.

f) must ensure the participation of contractor personnel with detailed knowledge of the subject matter they represent (e.g., provisioning, provisioning and technical documentation, hardware/software maintenance, engineering and system design).

At any time during the term of this contract or any extension thereof, the Government reserves the right to order additional provisioning conferences and updates to LMI data that may be required to support the PC.

C.3.6.6 Final Breakdown Structure

The Contractor must provide a top-down Final Breakdown Structure to the LRU level on all hardware, IAW CDRL-L003, after successful completion of FAT. The Final Breakdown Structure is developed by sequencing all parts comprising the end item in a lateral and descending family tree/generation breakdown. This breakdown must consist of the end item, including all components, listing every assembly, subassembly, and parts, which can be disassembled, reassembled/replaced. All parts are listed in their relation to the end item, component, assembly, or installation system in which they are contained and to their own further sub-subassemblies and parts. This relationship is shown by means of an indenture code. The Final Breakdown Structure shows the relationship of all items to one another. The Contractor must update the breakdown structure during the Government’s audits (FCA and combined PCA/PC). After the PCA, the Contractor must deliver the Final Breakdown Structure (CDRL-L003) to the Government for approval.

C.3.6.7 Tools and Test Equipment List (T&TEL)

The Contractor must prepare and deliver to the Government a list of all the tools and test equipment (CDRL-L004), both common and special, that are not an integral part of the ET but are required to inspect, test, calibrate, service, and repair them. This list must include only the tools and test equipment required to perform authorized site maintenance tasks (e.g., fault isolation and replacement to the LRU level). The Contractor must ensure that the T&TEL data on the list agrees with the T&TEL information contained in ETR technical documentation, e.g., the technical instruction book.

Page C-15

Modification P00014

C.3.6.8 Repairs

The Contractor must furnish repair services IAW the provisions of this section for all repairable items and/or LRU(s). The Contractor must have the capability and expertise necessary to repair all repairable items and components. Under this concept, the FAA Logistics Center (FAALC) will manage and store exchange and repair (E&R) spares to support sites. The Contractor must furnish all qualified labor, supervision, materials, equipment, tools, appliances, and services to repair components of the equipment. The turn-around-time (TAT) for all repairs must be within 45 calendar days from the receipt of the item for repair unless otherwise specified by the CO.

Repairable items and components will be shipped to the Contractor facility for repair directly from the FAALC. The FAALC Item Manager will furnish shipping instructions for repaired items. The shipment will be at the FAA expense to and from the Contractor facility. The Contractor must follow the repair requirements identified herein.

Unless otherwise directed by the Government, the Contractor must ship the repaired LRU to the FAALC in Oklahoma City, OK.

a) Contractor repair procedures must include the following:

1) Cleaning, visual inspection, bench tests, and fault isolation;

2) Disassembly as necessary to identify and accomplish required repairs or to establish the item as serviceable;

3) Reassembly, calibration, functionality testing, acceptance inspection, and preparation for shipment.

4) All repaired LRUs must successfully pass Production Unit Testing (PUT), as described in C.3.8.6, prior to being returned to the Government.

5) The Contractor must integrate repair process activity into the bar code scanning activities IAW C.3.7 and must include such data IAW the bar code scanning reporting requirements in C.3.7.4 for the life of this contract.

b) The Contractor must conduct all repairs IAW the Contractor’s established shop methods and procedures developed for the equipment.

c) When the Contractor determines that an item is beyond the Contractor’s ability to repair or the cost to replace the item is less than the repair cost, the Contractor must promptly notify the FAA CO and submit rationale for that determination. If the FAA CO agrees that an item cannot be repaired, since the non-repairable item is Government Furnished Equipment (GFE), the FAA CO will provide disposition instructions for the item to the Contractor and may request a replacement in lieu of repair.

d) The Contractor must complete any Government approved modification to items required by this contract and not previously accomplished at the time of repair. Each modified item or LRU must meet form, fit, and function of the item that it replaces and be two-way interchangeable, i.e., unmodified items must operate in place of modified items and modified

Page C-16

Modification P00014 items must operate in place of unmodified items.

e) The Contractor must be responsible for the initial lay-in of piece parts and for obtaining replenishment units and spare piece parts required for use in the repair of failed items. These parts must remain the property of the Contractor until incorporated into the repaired items at which time they become Government property. All parts removed during repair become the property of the Contractor.

f) Upon receipt of a failed LRU from the Government, the Contractor must document the receipt and the initial determination of the LRU for warranty or non-warranty repair using the Monthly Repair Status Report (MRSR) described in section C.3.6.8.3 (CDRL-L005).

g) The Contractor must maintain the Government provided FAA Form 4650-12 that accompanies the failed LRU and report the information in the MRSR described in section C.3.6.8.3.

h) The Contractor must prepare the Packing List/Shipping Report/Invoice to include the following information: -Contract Number, Report Control Number, Part Number, Serial Number, Item Description, and National Stock Number for the FAALC receipt of a repaired

LRU.

i) After inspection by the Quality Reliability Officer (QRO), the Contractor must ship the repaired LRU to the FAALC with a completed copy of the FAA Form 4650-12, Fed Express shipping label, and instructions inside the container within this contractual TAT.

C.3.6.8.1 Warranty Repairs or Replacements With the exception of batteries, items which fail while under warranty must follow the instructions in section 3.6.8 above.

In the case of batteries which fail while under warranty, the FAALC will notify the contractor of the failure and the contractor will direct ship a replacement battery to the FAA site that experienced the battery failure.

C.3.6.8.2 Cannot Duplicate/No Fault Found (CND/NFF)

The Contractor must follow the repair requirements in Section C.3.6.8. If the Contractor’s repair procedures IAW C.3.6.8 a) do not isolate any fault in the returned item, the return is a CND/NFF.

C.3.6.8.3 Non-Warranty Repair

The Contractor must follow the repair requirements identified in section C.3.6.8. Non-warranty repairs must apply to each unit that is determined not to be under warranty. This determination must be made IAW Section H.3.j of this contract.

a) The Contractor must fax (or otherwise electronically send) a copy of the FAA Form 4650-

Page C-17

Modification P00014

12 and provide supporting information in sufficient detail to demonstrate that the cause of the failure was outside the warranty, to the FAA CO based on section H.3.j of this contract.

b) When items with failures determined to be outside of the warranty are returned to the

Contractor in accordance with this clause, the Contractor must pay the transportation costs and bear the risk of loss or damage from the Contractor’s repair location to the Government’s designated supply depot, as per the Non-warranty Repair CLIN.

c) The TAT for repair of the non-warranty repairs must be the same time as warranty repairs

(refer to Section H.3.g) after receipt of a response from the FAA CO.

d) In the event a repair is required to return a defective LRU back into warranty status, the

Contractor must bill the Non-warranty Repair for the repair costs.

C.3.6.8.4 Monthly Repair Status Reports

The Contractor must develop a MRSRs, as specified by CDRL-L005 and must contain the repair information for warranty and non-warranty repair actions.

C.3.6.9 Technical Instruction Books (TIBs)

The Contractor must develop and provide technical instruction books meeting the requirements of FAA-D-2494, Appendix I, as a minimum. The Contractor must deliver copies of the TIB (CDRL-L008). There must be no restriction on reproduction or use of the TIB. The Contractor must specify an individual who will serve as a point of contact for all TIB issues. The Contractor must grant the Government unlimited rights to the TIB data, which includes the right to use, disclose, reproduce, prepare derivative works, distribute copies to the public, and perform publicly and display publicly, in any manner and for any purpose, and to have or permit others to do so.

C.3.6.10 Training

The Contractor must develop and deliver training materials for FAA personnel responsible for operating and maintaining of the ET equipment. The Contractor must deliver training for an eLearning environment in the format compatible with the FAA eLMS platform. Training must be developed using Instructional Systems Development methodologies described in FAA Order

3000.22 and FAA Order 3000.57 and operations and maintenance requirements of the Technical Instruction Book. The Contractor must ensure that training materials comply with the copyright and Section 508 of the Rehabilitation Act of 1973 as amended (29 U.S.C 794) and requirements of JO3000.22. Details for these requirements will be answered during the Contractor hosted Training Guidance Conference (TGC). Templates for Contractor use will be provided by the FAA via the FAA AJI “Huddle” web page. The delivery of the CDRLs will be agreed upon by the Contractor and the Government.

The learning level for the E-Learning Operations and Maintenance Course must be Level 2 IAW

Page C-18

Modification P00014

Categories of eLearning Technology and their Impact on Performance and Proficiency.

The integration of the E-Learning Operations and Maintenance Course and Operator Briefing into the eLMS must be in accordance with FAA eLMS Content Integration Guide.

C.3.6.10.1 Training Guidance Conference

As part of the Post Award Conference described in section C.3.4.a, the Contractor must host a TGC. The purpose of the TGC is to ensure the Contractor understands all training requirements.

The Contractor must ensure the participation of appropriate Contractor/subcontractor personnel responsible for preparing the training deliverables specified in this contract. The Contractor must submit agendas IAW CDRL-A009 and minutes IAW CDRL-A010.

C.3.6.10.2 Environmental Occupational Safety and Health (EOSH)

All training developed or revised by a Contractor must meet or exceed the appropriate Environmental Occupational Safety and Health Administration (EOSHA) regulations (see Occupational Safety and Health Administration (OSHA) 29 CFR 1910). OSHA safety regulations must be integrated into course content, as appropriate. All instruction must emphasize each person’s accident prevention responsibilities, both as an individual and as a representative of the Government. Safety precautions related to training on the operations, maintenance, and/or troubleshooting of the equipment must be a prominent part of the training.

C.3.6.10.3 Personnel Qualification Report (PQR)

The Contractor must submit for Government review and approval, a PQR (CDRL-L011).

C.3.6.10.4 Training Development Plan (TDP)

The Contractor must develop and deliver for Government review and approval, a TDP (CDRL- L012).

C.3.6.10.5 Analysis Report (AR)

The Contractor must develop and submit for Government review and approval, a AR IAW

(CDRL-L013).

C.3.6.10.6 Course Design Guides (CDGs)

The Contractor must develop and deliver for Government review and approval, a CDG (CDRL- L014). Two separate CDGs are required: one (1) for the Operator Briefing and one (1) for the Operations and Maintenance Training.

C.3.6.10.7 Student Achievement Tests (SAT) If ordered by the Government, the Contractor must prepare and deliver for Government review and approval, a SAT (CDRL-L015). The Contractor must develop a minimum of three examination items for each cognitive objective identified in the CDGs. In accordance with the design requirements one SAT is required for the Operations and Maintenance Training course.

Page C-19

Modification P00014

C.3.6.10.8 Operations and Maintenance (O&M) Course and Operator Briefing If ordered by the Government, the Contractor must develop and deliver for Government review and approval, an E-Learning OMC and Operator Briefing (CDRL-L016). In accordance with the design requirements of the two separate CDGs, two separate courses are required: one (1) which covers the Operations and Maintenance Training and one (1) which covers the Operator Briefing.

C.3.6.10.9 Course Walk-Through (CWT) – Contractor’s Presentation

The Contractor must present the examination questions, and O&M Course and Operator Briefing.

The Contractor must correct deficiencies identified during the course walk-through. The Contractor must submit corrected course materials for review and approval. This will be conducted virtually. It is anticipated to be a two-day event.

C.3.6.10.10 First Course Conduct (FCC) The Contractor must support the FCC O&M Course and Operator Briefing. The Contractor must correct deficiencies identified during the FCC. The Contractor must submit corrected course materials for review and approval.

C.3.6.10.11 On-the-Job Training (OJT) Package

The Contractor must provide an OJT package IAW CDRL-L017.

C.3.6.10.12 OJT Course Performance Examination

The Contractor must provide a performance examination in IAW CDRL-L018.

C.3.6.11 Long Term Supportability Data Package (LTSDP)

The Contractor must assemble and submit for review and inspection by the Government, an LTSDP (CDRL-L006). The LTSDP must be placed in a Contractor established account and held in escrow by a third party, mutually agreed upon by the Government and Contractor. The intent of the LTSDP is to ensure that in the event the Contractor refuses to continue support of the equipment or cessation of logistics support by the Contractor or Contractor bankruptcy, the Government is not left without logistic support for the total system. This package must include production drawings, associated lists and corresponding circuit descriptions supplementing the production drawings, and master patterns to support follow-up sparing, equipment procurement, quality control, production and repair test procedures, and tolerances for each replaceable component. Production drawings, for each replaceable component, must be provided to a level of definition sufficiently complete to enable a competent manufacturer to produce and maintain quality control of items to the degree that physical and performance characteristics interchangeable with those of the original design are obtained, without resorting to additional product design effort, additional design data, or recourse to the original design activity. Fabrication drawings of all production and depot level test beds and fixtures must be provided. Source code for all associated software and firmware must be included within the LTSDP.

Page C-20

Modification P00014

C.3.6.11.1 Escrow Account Index (EAI)

The Contractor must deliver an EAI (CDRL-L007) of all the technical data contained in the escrow account. The Contractor must maintain the index and deliver an updated index to the Government as required.. The Contractor must establish and maintain (including bear the cost of) a third-party escrow account containing a complete set of the technical documentation, including proprietary information, for the portable transceiver system. Changes approved under the Contractor's configuration management program must be applied to the data in escrow.

The escrow account must include the following data:

a. Product drawings and associated lists at least equivalent to MIL-T-31000A (i.e., commercial drawings and associated lists for Non-Developmental Items (NDIs) and production drawings for developmental equipment);

b. Special inspection equipment drawings and associated lists;

c. Special inspection equipment operating instructions;

d. Special inspection equipment calibration procedures;

e. Special tooling drawings and associated lists; and

f. Software procedures and products (includes source codes).

Additionally, the escrow account must contain all software products necessary to view all file types that populate the LTSDP. The Contractor must assure and document in an escrow account data index package that the data in the escrow account and elements thereof conform to these contractual requirements and accurately depict the hardware developed, produced and modified under this contract. Contractor’s use of the data in the escrow account to produce, inspect, and test the system hardware is considered acceptable evidence that the validation requirement has been met. The Contractor must identify, in the escrow account, sources for the repair, service, and replacement of the hardware and components used in the system, for the duration of this contract, including all options and the warranty obligations.

C.3.6.11.2 LTSDP Inspection

The Contractor must support an LTSDP inspection. The Government will inspect the LTSDP prior to its placement in escrow. Initial inspection of the LTSDP must be performed concurrently with the PCA. The Contractor must provide support to the Government, as required, during the inspection. The Contractor must manage the LTSDP configuration and must process documentation control numbers as changes occur to the system configuration.

C.3.6.11.3 LTSDP Procurement

The Government must have, but is not limited to, the option to purchase the LTSDP in the event that:

a. the Contractor enters bankruptcy or

b. the Contractor fails to perform under the requirements of this contract.

Page C-21

Modification P00014

The Contractor must deliver IAW CDRL-L006:

a. the LTSDP, including any…