CSS-Wx Section C.docx

DOCX document 225 KB Posted

Attached to
Request for Information - Brand New Air Traffic Control System
Solicitation number
693KA7BNATCS
Issued by

About this file

This document is a Statement of Work (SOW) for the Common Support Services - Weather (CSS-Wx) contract with the Federal Aviation Administration (FAA). The contract aims to address challenges in aviation weather data management by developing a system that acquires weather information from various sources, standardizes data formats, and publishes weather products through the System Wide Information Management (SWIM) system. Key capabilities include standardizing weather information in Open Geospatial Consortium formats, filtering weather information geospatially and temporally, disseminating information via SWIM, performing weather data management, and storing and retrieving weather information.

The base contract period is 4 years with potential for four 1-year options. The contractor will be responsible for system design, hardware selection, software development, integration, testing, deployment, help desk support, operational support, and maintenance. Specific requirements include developing a configuration management plan, implementing an information systems security program, conducting human factors engineering, providing training for FAA personnel, performing hardware and software maintenance, and supporting system transitions. The contract also includes provisions for potential additional work such as cloud migration services, system extensions, equipment relocations, and implementing enhanced system capabilities like additional web services and hosted algorithms.

View the file

Other files

File Type Posted
Notice 6.18.25.pdf PDF
BNATCS Industry Day Attendees.docx DOCX document
BNATCS Industry Day videos.docx DOCX document
Industry Day 2 Briefings.pdf PDF
Industry Day 1 Briefings.pdf PDF
RFI System Providers 1.docx DOCX document
Question for one on ones 6.6.2025.docx DOCX document
2025.06.05 Industry Day Agendas.docx DOCX document
STARS Section C.docx DOCX document
RFI Brand New ATC System A1.docx DOCX document
TFDM Section C.docx DOCX document
ETR Section C.pdf PDF
TBFM Section C.pdf PDF
ILS-420 Section C.pdf PDF
ALSF -2 SLEP SOW 5-28-25.pdf PDF
DNTS Section C.pdf PDF
IVSR Section C.pdf PDF
VSBP Section C.pdf PDF
DME Contract Section C_P18 Final.pdf PDF
CTD Section C_AMEND 0001.docx DOCX document
MEVA 3 NetworkSection C.pdf PDF
TFM2 Section C.pdf PDF
ETVS RDVS STVS Section C.pdf PDF
SMR4 Section C ASDE-3 SMR Replacement.pdf PDF
STARS Section C.docx DOCX document
APCS Section C.docx DOCX document
ASSC Section C.pdf PDF
DCIS Section C Award Mod 0143.docx DOCX document
NEXCOM Section C.docx DOCX document
RFI Brand New ATC System.docx DOCX document
WSIC Section C.pdf PDF
E-IDS Section C.docx DOCX document
EIS Section C.pdf PDF
MSBRS Section C.pdf PDF
CCS-W Bridge Section C.pdf PDF
MCT SECTION C.pdf PDF
NWP Section C.docx DOCX document
NVR Section C.pdf PDF
FENS Section C.docx DOCX document
AIMMS2 Section C.pdf PDF
WMSS3 Section C.docx DOCX document
NEXCOM V2 Section C.pdf PDF
RVR Section C.pdf PDF
ERAM Section C.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTFAWA-15-D-00003

CSS-Wx Option Year 3+ 5/10/2021

PART I - SECTION C

STATEMENT OF WORK

Table of Contents

C.1Introduction9
C.1.1Purpose9
C.1.2Background9
C.1.3Mission Need9
C.1.4Common Support Services – Weather9
C.2Applicable Documents10
C.2.1FAA Specifications and Standards10
C.2.2FAA Orders11
C.2.3Other FAA Documents12
C.2.4Other Government Documents12
C.2.5Industry Standards13
C.2.6Availability of Documents13
C.3Government-Furnished Information, Data, and Services14
C.3.1Software14
C.3.2RESERVED14
C.4Scope of Work14
C.5Task Orders14
C.6Period of Performance15
C.7Place of Performance15
C.8Requirements15
C.8.1Program Management15
C.8.1.1Program Management Organization and Coordination15
C.8.1.2Quality Management16
C.8.1.3Earned Value Management System16
C.8.1.4Monitoring and Reporting16
C.8.1.5Program Reviews and Conferences16
C.8.1.6Post-Award Conference16
C.8.1.6.1Integrated Baseline Review17
C.8.1.6.2Program Management Review17
C.8.1.7Proposal Preparation18
C.8.2System Engineering and Design18
C.8.2.1System Engineering Management18
C.8.2.2System Requirements Analysis18
C.8.2.3Interface Requirements Analysis and Design18
C.8.2.4System Architecture Definition19
C.8.2.5Software Design and Development19
C.8.2.5.1Software Development Plan20
C.8.2.5.2Software Design20
C.8.2.5.3Open Source Software Verification20
C.8.2.5.4Software Testing20
C.8.2.5.4.1Software Development Testing20
C.8.2.5.4.2RESERVED21
C.8.2.5.4.3Software Increment Testing21
C.8.2.5.5Software Quality Measurement21
C.8.2.5.6Software Products and Deliverables21
C.8.2.6NAS Service Registry/Repository Support21
C.8.2.7Hardware Selection22
C.8.2.8NDIs and COTS Hardware and Software22
C.8.2.9Technical Reviews22
C.8.2.9.1Combined Review23
C.8.2.9.2Preliminary Design Review23
C.8.2.9.3Critical Design Review24
C.8.3Test and Evaluation24
C.8.3.1Test Process24
C.8.3.2Formal Test Activities26
C.8.3.2.1Formal Test Entrance Criteria26
C.8.3.2.2Formal Test Exit Criteria27
C.8.3.3Contractor Master Test Plan27
C.8.3.4Test Plans and Procedures28
C.8.3.5Reserved28
C.8.3.6Pre-Test Briefing28
C.8.3.7Test Execution29
C.8.3.8Test Reports29
C.8.3.9Post-Test Briefing29
C.8.3.10Program Trouble Reports30
C.8.3.11Test Bed Development31
C.8.3.11.1Factory Development Test System31
C.8.3.11.2WJHTC Test System31
C.8.3.11.2.1Contractor Acceptance Inspection (CAI) for WJHTC Systems31
C.8.3.11.3Test Tool Accreditation32
C.8.3.12Contractor-Supported Tests33
C.8.3.13In-Service Management/Maintenance Release Testing36
C.8.3.13.1ISM Test Plans and Test Procedures38
C.8.3.13.2ISM Pre-Test Briefing38
C.8.3.13.3ISM Test Execution38
C.8.3.13.4ISM Test Reports39
C.8.3.13.5ISM Post-Test Briefing39
C.8.3.14Formal Retest39
C.8.3.15Government Test Meetings39
C.8.4Implementation39
C.8.4.1Implementation Planning39
C.8.4.1.1Site Surveys40
C.8.4.2Equipment Delivery41
C.8.4.3Installation41
C.8.4.3.1Installation Activities in Operational Facilities41
C.8.4.3.2Lead Paint Protection41
C.8.4.3.3Hazard Prevention and Warning42
C.8.4.3.4Site Clean-up42
C.8.4.3.5Damages to Facilities42
C.8.4.3.6Auxiliary Equipment42
C.8.4.3.6.1Reserved42
C.8.4.3.6.2Reserved42
C.8.4.4Site Documentation42
C.8.4.5Hardware Disposal43
C.8.5Technical Interchange Meetings43
C.8.6Configuration Management43
C.8.6.1Configuration Management Planning43
C.8.6.2Configuration Status Accounting System43
C.8.6.3System Documentation44
C.8.6.4Configuration Audits44
C.8.6.5Configuration Change Control44
C.8.6.5.1Change Proposals and Notices44
C.8.6.5.1.1Engineering Change Proposals45
C.8.6.5.1.2Requests for Deviation45
C.8.6.5.1.3Request for Waiver45
C.8.6.5.1.4Specification Change Notice45
C.8.6.5.2Configuration Control Board45
C.8.7Security46
C.8.7.1Information Systems Security46
C.8.7.1.1Access Control46
C.8.7.1.2Audit47
C.8.7.1.3Security Configuration Management47
C.8.7.1.4Identity Management48
C.8.7.1.5Media Protection48
C.8.7.1.6System and Communication Protection49
C.8.7.1.7System and Information Integrity49
C.8.7.2Security Authorization Program50
C.8.7.3Security Training51
C.8.8Human Factors Engineering51
C.8.8.1HFE Program51
C.8.8.2HFE Design Approach Documents52
C.8.8.3HFE Reviews52
C.8.9Environmental and Occupational Safety and Health52
C.8.9.1EOSH Program Plan53
C.8.9.2EOSH Training53
C.8.9.3Use of Protective Equipment53
C.8.9.4Program Documentation53
C.8.9.5Hazardous Materials53
C.8.9.6Identification of Hazards53
C.8.10Safety Risk Management54
C.8.11Integrated Logistics Support54
C.8.11.1ILS Planning54
C.8.11.2Training and Training Support54
C.8.11.3Technical Documentation57
C.8.11.4Reliability, Maintainability, and Availability58
C.8.11.4.1Service Report58
C.8.11.5System Monitoring Service (Option)59
C.8.11.6Help Desk59
C.8.11.7Maintenance60
C.8.11.7.1Maintenance Response Time61
C.8.11.7.2Software Maintenance61
C.8.11.7.3Hardware Maintenance62
C.8.11.7.3.1Preventive Maintenance62
C.8.11.7.3.2Corrective Maintenance63
C.8.11.7.3.3Replacement Procedures63
C.8.11.7.3.4Technician Qualifications64
C.8.11.7.4Maintenance Reporting64
C.8.11.7.5Supply Support64
C.8.11.7.6Depot-Level Maintenance64
C.8.11.7.7Bar Code Asset Tracking System64
C.8.11.7.8On-Site Contractor Support65
C.8.11.8Depot Support Transition Plan65
C.8.11.9Software Transition Plan65
C.8.11.10ILS Transition Activities65
C.8.11.10.1Transition Technical Documentation65
C.8.11.10.2Logistics Management Information66
C.8.11.10.3Transition of Supply Support66
C.8.11.10.3.1Interim Contractor Depot Logistics Support (ICDLS) (Optional)66
C.8.11.10.3.2Web-based Requisition Interface Procedures67
C.8.11.10.3.3ICDLS Repair Decisions67
C.8.11.10.3.4ICDLS Repair and Test Procedures68
C.8.11.10.3.5Expendable LRUs68
C.8.11.10.3.6Reporting Requirements68
C.8.11.10.3.7Repair Service Priorities69
C.8.11.10.4Logistics and Provisioning Guidance Conference69
C.8.11.10.5Provisioning Conference69
C.8.11.10.6Transition Training70
C.8.11.10.7Transition Training Delivery Support73
C.8.11.10.8Maintenance Transition Timeframe74
C.8.11.10.9Second Level Engineering Support74
C.8.12Operations74
C.8.12.1System Access Management75
C.8.12.2Management of User Requirements75
C.8.12.3New User Support75
C.8.12.4Delivery of Archived Data75
C.8.13NOAAPORT75
C.8.13.1NOAAPORT Receiver System75
C.8.13.2NOAAPORT Integration76
C.8.14Cloud Migration Services76
C.8.15Engineering Support Services76
C.8.15.1Additional Systems77
C.8.15.1.1Extend the System77
C.8.15.1.2Additional CSS-Wx Support System77
C.8.15.2Equipment Relocation77
C.8.15.2.1Relocation of Equipment within the Same Facility77
C.8.15.2.2Relocation of Equipment to Other Facilities77
C.8.15.3Service Adaptors78
C.8.15.4Common Services Interface78
C.8.15.5Mobile Devices78
C.8.16Work Package 278
C.8.16.1Additional System Interfaces78
C.8.16.1.1Radar79
C.8.16.1.2Aviation Weather Sensors79
C.8.16.1.3Commercial Lightning Data Provider79
C.8.16.2Enhanced System Capabilities79
C.8.16.2.1Additional Web Services79
C.8.16.2.2Additional Hosted Algorithms79
C.8.16.2.3Additional Filtering Capabilities80
C.8.16.2.4Name Subscriptions or Queries80
C.9Acronyms81

This page intentionally left blank.

DTFAWA-15-D-00003

CSS-Wx Option Year 3+ 5/10/2021

PART I - SECTION C

STATEMENT OF WORK

C-i Introduction Purpose This statement of work (SOW) sets forth the requirements for the Common Support Services – Weather (CSS-Wx) contract.

Background The operation of today's National Airspace System (NAS) is supported by a variety of weather sensing and processing systems maintained by Federal agencies and private entities. These disparate sources of aviation weather data sometimes conflict with one another, creating challenges for efficient operational planning and decision-making. Furthermore, consistent NAS-wide weather information is rarely available for use in any one location. As a result, NAS-wide operational coordination requires excessive, ad hoc discussion among stakeholders, which is time-consuming and inefficient.

The realization of the Next Generation Air Transportation System (NextGen) will require changes to the FAA’s weather architecture. The integration of weather information into air traffic management decision support tools, which will require an increased use of gridded weather data with high spatial and temporal resolutions, and the increase in the number of weather data users will impose significant demands on the capacity of the FAA Telecommunications Infrastructure (FTI) Operations Internet Protocol network. The addition of new types of data sources and new users could also require costly, purpose-built connections and service adaptors to translate among data formats.

Mission Need The FAA has identified a need for a solution that will address the inconsistency of weather data and the limitations in network coverage and scalability. Through data filtering and standardization of data formats, the CSS-Wx solution will enable the efficient publication of high-resolution aviation weather data from the variety of producing systems to weather information users throughout the NAS. The solution will provide users with access to the NAS-wide weather information required for operational planning. It will also institute standard protocols for NAS systems and will be scalable to facilitate the addition of new systems, thereby minimizing the need for service adaptors.

Common Support Services – Weather The CSS-Wx System will acquire weather information from FAA and other sources and provide these data to systems that consume weather data. It will publish weather information in standardized formats for use by the FAA’s Air Traffic Organization (ATO), commercial aviation, general aviation, and other Federal agencies. The CSS-Wx System will publish aviation weather products provided by the NextGen Weather Processor (NWP), National Oceanic and Atmospheric Administration's (NOAA) NextGen Web Services, other FAA weather data sources, and non-FAA weather data sources for aviation users. The CSS-Wx System will ultimately provide the following high-level capabilities:

Standardize weather information in common formats identified by the Open Geospatial Consortium (OGC);

Filter weather information geospatially and temporally based on a user’s requirements;

Disseminate weather information via the System Wide Information Management (SWIM) system;

Perform weather data management; and Store, archive, and retrieve weather information.

Applicable Documents The documents listed in this section are referenced in this SOW. When a referenced document is in conflict with the requirements in this SOW, this SOW takes precedence. If two or more referenced documents are in conflict or two or more sections of this SOW are in conflict, the Contractor must notify the Contracting Officer (CO) to resolve the conflict.

Referenced documents are applicable to the extent specified herein. If applicability is not further specified in the text of the requirement, then the entire document is applicable.

FAA Specifications and Standards

Document Identifier
Document Title
FAA-D-2494B
Technical Instruction Book Manuscript: Electronic, Electrical, and Mechanical Equipment, Requirements for Preparation of Manuscript and Production of Books
FAA-G-2100H
Electronic Equipment, General Requirements
FAA-STD-002F
Standard Engineering Drawing Preparation and Support
FAA-STD-019E
Lightning and Surge Protection, Grounding, Bonding and Shielding Requirements for Facilities and Electronic Equipment
FAA-STD-021A
Configuration Management (Contractor Requirements)
FAA-STD-025F
Preparation of Interface Documentation
FAA-STD-026A
Software Development for the NAS
FAA-STD-028C
Contract Training Programs
FAA-STD-065A
Preparation of Web Service Description Documents (WSDD)
FAA-STD-070
Preparation of Web Service Requirements Documents
FAA-STD-073
Preparation of Java Messaging Service Description Documents
HF-STD-001
Human Factors Design Standard for Acquisition of COTS Subsystems, NDIs, and Developmental Systems
HF-STD-004
Requirements for a Human Factors Program

FAA Orders

Document Identifier
Document Title
Order 1050.10C
Prevention, Control, and Abatement of FAA Environmental Pollution
Order 1370.82A
Information Systems Security Program
JO 1370.96
ATO System Access Control
Order JO 1370.101
ATO Information Security Incident Detection, Reporting, and Response Policy
Order 1370.100
Media Sanitizing and Destruction Policy
Order 1370.103
Encryption Policy
Order 1370.106
Information Systems Security Awareness and Training Policy
Order 1370.111
Removable Media Security Policy
JO 1370.114
Implementation of FTI Services and Information Security Requirements in the NAS
Order 1600.75
Protecting Sensitive Unclassified Information (SUI)
Order 1800.66 CHG 3
Configuration Management Policy
Order 3000.57A
ATO Technical Operations Training and Personnel Certification, Appendix 14 Section 5 Guidelines for Training Development, Revision, and Implementation and Section 6. Review of D&R Efforts
Order 3000.22B
Air Traffic Organization Outcome – Based Technical Training
Order 3900.19B
FAA Occupational Safety and Health Program
JO 3900.57A
Environmental and Occupational Safety and Health (EOSH) Requirements in the Planning and Execution of Construction and Maintenance Activities at NAS Facilities
JO 3900.63
ATO Fall Protection Program
Order 4600.27B CHG 1
Personal Property Management
Order 6000.15H
General Maintenance Handbook for NAS Facilities

Other FAA Documents

Document Identifier
Document Title
N/A
ATO Safety Management System (SMS) Manual, April 2019
N/A
Fiscal Year 2020 (FY20) Security Authorization Handbook
N/A
NAS External Boundary Protection Guidelines
N/A
Safety Risk Management Guidance for System Acquisitions (SRMGSA), March 2020
N/A
Technical Operations Safety Risk Management Policy Memorandum,

March 2008

N/A
FY20 ATO ISS Procedures Guidance v1.0_19-1028
N/A
FY20 ATO System Security Plan Moderate Workbook v1.0_19-1028
N/A
Air Traffic Organization The Technical Training Directorate/Analysis Guide (AJI-2)
N/A
Air Traffic Organization The Technical Training Directorate/Design Guide (AJI-2)
N/A
eLearning Design and Style Guide
N/A
FAA eLMS Content Integration Guide
N/A
Written Test Blueprint_Final
N/A
Performance Test Blueprint_Final
N/A
Nat’l Air Traffic Training Program/Analysis Report
N/A
Nat’l Air Traffic Training Program/Course Design Guide (CDG)

Other Government Documents

Document Identifier
Document Title
29 CFR 1910
Occupational Safety and Health Standards
FIPS Pub. 200
Minimum Security Requirements for Federal Information and Information Systems
NIST SP 800-53, Revision 4
Security and Privacy Controls for Federal Information Systems and Organizations
Title III, Pub. L. No. 107-347
Federal Information Security Management Act (FISMA) of 2002

Industry Standards

Document Identifier
Document Title
ANSI/International Organization for Standardization (ISO)/American Society for Quality (ASQ) Q9001-2008
Quality Management Systems – Requirements
Institute of Electrical and Electronics Engineers (IEEE) Standard 1003.1, 2004 Edition
Standard for Information Technology - Portable Operating System Interface (POSIX)
National Fire Protection Association (NFPA) 70
National Electrical Code
NFPA 70E
Standard for Electrical Safety in the Workplace
NFPA 101
Life Safety Code

Availability of Documents

Document Name
Access to Document Information
FAA Documents
Copies of FAA specifications, standards, and publications may be obtained from the Contracting Officer noted in Section G. Requests should clearly identify the desired material by name and number (when applicable) and state the intended use of the material. Requested copies will be provided in digital format.
Federal Documents
Copies of federal publications may be obtained from the U.S. Government Printing Office, 710 North Capitol Street, Washington DC, 20401, by calling (202) 512-0132, or through the Web site, http://bookstore.gpo.gov/.
National Institute of Standards and Technology (NIST) Documents
Copies of National Institute of Standards and Technology documents may be obtained through the Web site, http://csrc.nist.gov/publications/PubsSPs.html.
ANSI Documents
Copies of ANSI documents may be obtained through the Web site, http://webstore.ansi.org/.

Government-Furnished Information, Data, and Services The Government will furnish the information, software code, and software documentation listed in Section J to the CSS-Wx Contractor. The Government will provide telecommunications services to support the operation of the CSS-Wx System.

Software The Government will make software executables available to offerors with the release of the CSS-Wx solicitation package and will make software source code available to the Contractor after contract award. Use of this software does not relieve the Contractor of responsibility for meeting the requirements in this SOW or in the Attachment J-01, CSS-Wx System Specification Document (CSS-Wx SSD).

RESERVED

Scope of Work The scope of work of the CSS-Wx procurement consists of the design of the CSS-Wx System in accordance with Attachment J-01, CSS-Wx SSD, the selection of hardware, the development of system and client software, integration, testing, deployment, help desk and operational support, and maintenance of the system hardware and software. The scope of work also includes the acquisition, implementation, and integration of a NOAAPORT receiver system output into the CSS-Wx System. Lastly, the scope of work includes additional engineering services as required by the Government.

Task Orders Some work performed under this contract will be authorized by task order. Task orders will be allocated into two work packages. Attachment J-02, CSS-Wx System Requirements Allocation Matrix shows the allocation of requirements to both work packages; Work Package 2 requirements are in C.8.16.

Period of Performance The base period of the CSS-Wx contract is 4 years. The base period may be followed by four 1-year options, if exercised.

Place of Performance The Contractor is responsible for providing facilities for the development of the CSS-Wx System.

The Contractor must implement the CSS-Wx System at the FAA facilities listed in Table B-4 of Attachment J-07, NextGen Weather Systems Description Document. The Government reserves the right to change the selection of these locations as late as the Preliminary Design Review (PDR).

Requirements This section contains the requirements for the services performed by the CSS-Wx Contractor. Attachment J-03, Contract Data Requirements List (CDRL) contains additional requirements with respect to required deliverables.

Program Management The Contractor must manage the activities, personnel, resources, and subcontracts involved in the performance of the CSS-Wx contract so as to mitigate risk, meet requirements, and achieve the program’s schedule milestones. The Contractor must monitor and control the effort in accordance with approved work plans and schedules. The Contractor must also provide the FAA with clear, timely, and proactive communication on the status of planned and completed activities. The Contractor must describe their approach to managing the effort, mitigating risk, and delivering high-quality products and services that meet requirements in a Program Management Plan (CDRL PM01).

Program Management Organization and Coordination The Contractor must establish a business model that fosters collaborative relationships with the FAA and with other FAA contractors. In particular, the interdependencies of the CSS-Wx and NWP Systems, combined with similar implementation schedules, require close coordination between the program vendors from architecture to deployment to increase innovation, optimization, and performance; minimize costs and risks; and integrate and deliver both systems efficiently.

The Contractor must designate a program manager to manage, coordinate, and communicate with the Government and other FAA contractors. The program manager must have sufficient corporate authority to direct, execute, and control all elements of the program.

Quality Management The Contractor must develop and implement a plan for managing the quality of the CSS-Wx System hardware, software, systems, data items, and services required under this contract in accordance with ANSI/ISO/ASQ Q9001-2008, Quality Management Systems – Requirements. The Contractor must also ensure the quality of the products and services provided by subcontractors and third party contractors. The Contractor must submit a Quality Management Plan (CDRL PM02) that describes the Contractor’s plan for managing quality.

Earned Value Management System The Contractor must utilize an earned value management system (EVMS) that complies with ANSI/EIA-748-C, Earned Value Management Systems, to plan, control, and report the status of the effort. The Contractor must develop a Contractor Work Breakdown Structure (CDRL PM03) for approval by the Government. The Contractor must submit an Integrated Program Management Report (CDRL PM04) to provide earned value information.

Monitoring and Reporting The Contractor must continuously monitor performance under this contract and all subcontracts. The Contractor must develop and maintain a risk database to manage the categorization, reporting, tracking, and resolution of risks identified and documented. The Contractor must provide read only access to the risk database to the Government, thereby allowing the Government to maintain awareness of and generate reports of risks as needed. The Contractor must provide the FAA with an assessment of project progress, risks, issues, and proposed resolutions in a Project Status Report (CDRL PM05).

Program Reviews and Conferences The Contractor must plan, host, conduct, and attend meetings and conferences to discuss topics and communicate issues related to this effort as requested by the Government. The Contractor may be required to prepare materials for presentation and distribution prior to meetings and conferences. The Contractor must prepare and submit Meeting Minutes (CDRL PM07) for Government approval following each meeting, conference, or technical review.

Post-Award Conference The Contractor must plan, host, and participate in a post-award conference at the Contractor's facility. The Government will determine the actual date of the post-award conference within 30 business days after the contract start date. The purpose of the post-award conference is for the Contractor and the Government to:

Reach a mutual understanding of the contract requirements; and Review the integrated baseline review (IBR) preparations and EVMS tailoring.

Integrated Baseline Review The Contractor must plan, host, and participate in an IBR within 6 months of contract award. The purpose of the IBR is to:

Evaluate the Contractor’s implementation of the performance measurement baseline;

Ensure that the Government and the Contractor mutually understand program scope, schedule, resources, inherent risk, and program management processes;

Establish a schedule for program management reviews (PMRs);

Ensure early and adequate planning;

Identify risks to be tracked; and Ensure appropriate reporting levels have been identified and variance thresholds are agreed to by the Government and the Contractor.

The Contractor must provide access to the records and data that support the cost and schedule data reported. The Contractor must conduct the IBR as a separate review until such time as the Government determines that it can be integrated into PMRs. The Contractor may also be required to participate in an IBR within six months of a major design or requirements change that dictates a re-baselining of the program or after major modifications to the contract or after the Government exercises a new contract option.

Program Management Review The Contractor must convene PMRs at least monthly for the first year of the contract to update the Government on the status of the Contractor’s efforts and project milestones. At each PMR, the Contractor must review the monthly project status report with the Government. The Contractor must propose the dates of the PMRs for Government approval. The PMRs will normally be conducted at the Contractor's facility; however, the location of a PMR may be changed through mutual agreement between the Government and the Contractor. PMRs may also be held virtually, through mutual agreement between the Government and the Contractor.

Proposal Preparation The contractor may be asked by the Contracting Officer to submit proposals for new work within the scope of this contract. The Contracting Officer will provide the contractor a not to exceed amount for the contractor’s proposal effort. Providing a ROM, an alternate design material, or investigations of already in-scope tasks may not constitute a proposal for new work funded under Proposal Prep. If the contractor anticipates needing additional funding for the proposal generation, the contractor must receive approval from the Contracting Officer prior to exceeding the not to exceed amount. The contractor will be reimbursed for their costs of the proposal. There will be no fee provided for proposal preparation work.

System Engineering and Design The Contractor must design, develop, and integrate all components of the CSS-Wx System to meet the requirements contained in the CSS-Wx SSD. The Contractor must integrate the NOAAPORT receiver system output into the CSS-Wx System. The Contractor must also develop and integrate hosted algorithms as specified in Attachment J-04, CSS-Wx Hosted Algorithm Description ATC-413 and the CSS-Wx SSD.

System Engineering Management The Contractor must develop and implement a System Engineering Management Plan (SEMP) (CDRL SE01) that describes the Contractor’s plan for the definition, design, development, verification, integration, and testing of the CSS-Wx System requirements. The Contractor’s SEMP must address all aspects of performance, quality, life-cycle cost, maintainability, reliability, schedule, risk, data processing reserves, and future growth requirements.

System Requirements Analysis The Contractor must assess and refine the A-level requirements in the CSS-Wx SSD and submit a revised CSS-Wx System Specification Document (Revision) (CDRL SE02) to the Government. The Contractor must decompose the requirements in the revised SSD to define the lower-level (B-level) requirements of the CSS-Wx System, define the functional subsystems and components of the CSS-Wx System, and allocate the B-level requirements to the subsystems and components. The Contractor must develop a System/Subsystem Specification (SSS) (CDRL SE03) that documents the allocation of B-level requirements to subsystems and components and demonstrates the traceability of the B-level requirements to the A-level requirements in the CSS-Wx SSD.

Interface Requirements Analysis and Design The Contractor must develop the interface design documents listed in Attachment J-05, CSS-Wx System Interface Deliverables. The Contractor must develop each CSS-Wx System Interface Design Description (IDD) (CDRL SE04) in accordance with the Interface Design Description data item description (DID) in FAA-STD-026A, Software Development for the NAS. The Contractor must develop WSDDs (CDRL SE05) in accordance with FAA-STD-065A, Preparation of WSDDs. The Contractor must develop each CSS-Wx System Interface Control Document (ICD) (CDRL SE06) in accordance with the referenced attachment and with FAA-STD-025F, Preparation of Interface Documentation. The Contractor must develop Product Description Documents (PDDs) (CDRL SE07) for new weather products derived from the Attachment J-07, NextGen Weather Systems Description Document (e.g., new weather products that are re-organization, quantization and/or graphical representations of binary or ASCII Producer data) that are the output of the CSS-Wx System’s Web or Java Message Service (JMS)-based services and made available to consumers other than CSS-Wx itself PDD requirements must be traceable to the requirements contained in the Government-provided Web Service Requirements Documents (WSRDs). The Contractor must develop a Java Messaging Service Description Document (JMSDD) (CDRL SE21) in accordance with FAA-STD-073, Preparation of Java Messaging Service Description Documents.

The Contractor must explain to the Government how the design of the CSS-Wx System incorporates SWIM Messaging Services. The Contractor must be prepared to present analyses to justify the design.

System Architecture Definition The Contractor must define and develop the CSS-Wx System architecture baseline and allocated baseline. The Contractor must develop a Software Requirements Specification (CDRL SE08), Interface Requirements Specification (CDRL SE09), and System/Subsystem Design Description (CDRL SE10) that describe the allocated subsystems and segments. The Contractor must document the relationships between the system, subsystems, and equipment drawings in an Engineering Drawing Tree (CDRL SE11).

The Contractor must propose a failover procedure, for government approval, that will function with the redundant component concept described in Attachment J-7 NextGen Weather Systems Description Document, Section 2.2 Systems and Operations. The failover procedure may be automated with manual initiation.

Software Design and Development The Contractor must design, code, integrate, install, test, and deliver the CSS-Wx System software to meet the requirements in the CSS-Wx SSD in accordance with FAA-STD-026A. The Government will monitor software design and development. The Government will monitor software sprint demonstrations. The Contractor must provide online access to software artifacts (e.g., design and development source code, scripts, procedures, source code configuration management information) to the Government. The Government reserves the right to audit the software artifacts at any time.

Software Development Plan The Contractor must develop a Software Development Plan (CDRL SE12) that describes the Contractor’s plan for designing and developing the CSS-Wx System software.

Software Design The Contractor must design, develop, integrate, and document new and modified software in accordance with the Government-approved Software Development Plan. The Contractor must submit a Software Design Description (CDRL SE13) for Government approval. The Contractor must prepare or update all software documentation for developmental and modified software to show how the developmental software is integrated with the non-developmental software in accordance with the Software Development Plan. If any commercial software is used to satisfy requirements, the Contractor must submit corresponding commercial documentation, licensing agreements, and usage limitations to the Government for approval. The Contractor must ensure that the Government has unrestricted access to additional copies of commercial software documentation.

The Contractor must design the CSS-Wx System software to be hardware-platform independent and compatible with the IEEE Standard 1003.1, 2004 Edition, Standard for Information Technology - Portable Operating System Interface (POSIX). The Contractor must develop software that can operate on virtualized hardware using a hypervisor that has been approved by the Government.

Open Source Software Verification The Contractor must identify open source software (OSS) used in the development of the CSS-Wx System. The Contractor is responsible for resolving any OSS issues that affect the performance of the CSS-Wx System.

Software Testing Software Development Testing The purpose of software development testing is to verify specifications at the B-level. The Contractor must conduct software testing on software decomposed into computer software configuration items (CSCIs), computer software components, and functional design components (i.e., unit testing, user story testing, sprint testing, epic testing, regression testing, and software integration testing). The Contractor must conduct software testing at the Contractor’s site or at the William J. Hughes Technical Center (WJHTC) in accordance with the Government-approved Contractor Master Test Plan (CMTP) (Section C.8.3.3). The Government reserves the right to monitor all software testing activities.

RESERVED

Software Increment Testing The purpose of software increment testing is to verify execution of the system through multiple computer software components during agile software development activities. Software increment testing verifies specifications at the B level. Software increment testing is conducted at the Contractor’s facility. The Government will monitor the Contractor software increment testing. The Government will monitor agile increment demonstrations.

Software Quality Measurement The Contractor must measure the quality of CSS-Wx System software at the method (function), class, and file levels, including shared library routines and weather library routines. The Contractor must evaluate each individual software module and submit a Software Quality Report (CDRL SE14) to the Government. The Government will review and approve the Software Quality Report based on an independent verification of the metrics utilizing the Contractor’s baselined source code. Any code designated as “undesirable” will require inspection by the Government. After inspection of the code, the Government will determine if corrective action will need to be taken.

Software Products and Deliverables The Contractor must develop the following products and deliverables:

Software Product Specification (CDRL SE15) that contains or references the executable software, source files, and software support information, including "as built" design information and compilation, build, and modification procedures, for a CSCI;

Software User Manual (CDRL SE16) that describes how to install and use a CSCI, a group of related CSCIs, or a software system or subsystem. It may also cover a particular aspect of software operation, such as instructions for a particular administrative task; and Software Version Description (CDRL SE17) that identifies and describes a software version consisting of one or more CSCIs. It is used to release, track, and control software versions.

NAS Service Registry/Repository Support The Contractor must support the registering of CSS-Wx services in the NAS Service Registry Repository. The Contractor must provide the metadata for CSS-Wx services to the Government in accordance with FAA-STD-070, Preparation of Web Service Requirements Documents, FAA-STD-065A, Preparation of WSDDs, and FAA-STD-073, Preparation of Java Messaging Service Description Documents.

Hardware Selection The Contractor must select the hardware to be used in the system design to meet the requirements in the CSS-Wx SSD. The Contractor must conduct analysis to justify the proposed hardware approach to the Government. The Government will provide power constraints and weight limitations of the hardware to the Contractor prior to PDR. The Contractor must submit the hardware listing for Government approval.

NDIs and COTS Hardware and Software The Contractor must identify NDIs and COTS hardware and software used in the development of the CSS-Wx System. The Contractor is responsible for resolving any issues associated with the NDIs and COTS items that affect the performance of the CSS-Wx System. The Contractor must provide the Government with all applicable licenses and agreements.

Technical Reviews The Contractor must plan and participate in technical reviews to obtain approval for CSS-Wx System specifications and designs and to provide the FAA with insight into the Contractor’s progress. The Contractor must notify the CO of readiness for a technical review at least 20 business days (i.e., Monday-Friday, excluding Federal holidays) in advance of the planned start date. The Contractor must submit all deliverables required for the review at least 10 business days in advance of the planned start date. At each review, the Contractor must be prepared to present and discuss the content of required data items, the assumptions made, and the methodologies used to arrive at specific designs, plans, recommendations, and conclusions. The Contractor must make qualified personnel available to respond to Government questions.

The Contractor must obtain Government permission to proceed before conducting a technical review. The Contractor must close all action items or obtain Government approval for any open action items prior to conducting a technical review. If the Contractor has not submitted all required documents or if the preceding technical review has not been approved by the Government, the Government can postpone a technical review without prejudice to other contractual requirements. The Contractor must not consider formal reviews complete until the Government has granted approval in writing.

Combined Review The Contractor must conduct a System Requirements Review (SRR), System Design Review (SDR), and System Specification Review (SSR) as a single, combined review. The purpose of this combined review is for the Government to:

Determine whether the system requirements are consistent, achievable, testable, and complete, and whether the Government and the Contractor have a clear, mutual understanding of the system requirements;

Evaluate the status and maturity of the system design; and Evaluate the Software Requirements Specification.

The Contractor must submit an SRR/SDR/SSR Data Package (CDRL SE18) prior to the combined review. During the combined review, the Contractor must be prepared to present and discuss:

The revised SSD, and the allocation and traceability of requirements from the revised SSD to the preliminary System/Subsystem Specification, Web service requirements, interface requirements, and configuration items;

Draft Web services description documents;

The results of functional analyses, syntheses, and trade studies;

The Software Requirements Specification;

The final System/Subsystem Specification;

The System/Subsystem Design Description; and The Software Development Plan;

Preliminary Design Review The purpose of the PDR is for the Government to evaluate the Contractor’s system architecture and design approach to determine whether the Contractor is prepared to begin detailed design. Prior to the PDR, the Contractor must submit a PDR Data Package (CDRL SE19). During the PDR, the Contractor must demonstrate how the process used to arrive at the design meets the functional and performance requirements for each configuration item. The Contractor must also demonstrate that the requirements in the functional baseline are traceable to the requirements in the revised SSD, IRDs, WSRDs, and PDDs. The Contractor must be prepared to present and discuss the preliminary system design, software design, hardware design, human factors, telecommunications, interface design, and approach to testing. At the PDR, the Contractor must also provide the Government with the Contractor Master Test Plan (CMTP), Verification Requirements Traceability Matrix (VRTM), and estimated telecommunication requirements for the proposed solution in accordance with Attachment J-06, FTI Operational Network IP Users' Guide.

Critical Design Review The purpose of the Critical Design Review (CDR) is for the Government to determine whether the Contractor’s detailed design meets the requirements specified in the CSS-Wx SSD and whether the design is complete and ready to be implemented. Prior to the CDR, the Contractor must submit a CDR Data Package (CDRL SE20). During the CDR, the Contractor must be prepared to present and discuss the final system design, software design, hardware design, human factors, telecommunications, interface design, and test plans. During software development, the Contractor must update the CDR Data Package prior to development of each agile software increment. The Contractor must conduct a review of the revised CDR Data Package prior to development of each agile software increment. In addition, the Contractor must demonstrate that:

All software requirements are allocated and traceable to the computer software unit level;

The detailed designs reflect an architecture that satisfactorily meets the IRDs, WSRDs, PDDs, and minimizes risk;

The database design is complete and meets all requirements; and The Contractor has analyzed the impact of changes to requirements on the detailed software design, including interfaces.

Test and Evaluation The Contractor must establish a test and evaluation program consistent with the Government’s CSS-Wx Test and Evaluation Master Plan (TEMP) to verify that the CSS-Wx System and its components meet the physical, functional, interface, and performance requirements contained in the CSS-Wx SSD, referenced interface requirements documents, and referenced Web service requirements documents prior to putting the system in service.

Test Process The Contractor’s test and evaluation program must include the development testing (DT) activities described in Table 1. The Contractor must perform DT activities as indicated in the table below to demonstrate that all specified technical and performance requirements have been met. These activities will be considered Run-For-Record (RFR).

Table 1: Development Testing Activities

DT Activity
Description
Factory Acceptance Testing (FAT)
The purpose of FAT is to verify that CSS-Wx System meets the CSS-Wx System’s A-level and B-level requirements including hardware, firmware, COTS items, and non-developmental subsystem components. FAT may be conducted at the Contractor’s facility or at the WJHTC. FAT must include a 48-hour stability test period with the system running with an operational load. The FAA will witness FAT. This work was completed in 2018.
Candidate Release Test (CRT)
The purpose of CRT is to verify that CSS-Wx System meets CSS-Wx’s A-level and B-level requirements including hardware, firmware, COTS items, and non-developmental subsystem components. CRT may take part in increments to verify all requirements. Preplanned software baseline updates that has been scheduled in the Integrated Master Schedule (IMS) may be implemented onto the Factory Development Test System during the CRT test period. All hardware and unplanned software baseline changes will require approval by the FAA prior to any test activities. CRT will be conducted at the Contractor’s facility. CRT must include a 48-hour stability test period with the system running with an operational load. CRT will occur before the corresponding Integration Testing and System Testing of the applicable requirements. The FAA will witness CRT.
Integration Testing
The purpose of integration testing is to verify the proper installation and functioning of the complete CSS-Wx System in a testing environment, including the verification of system interfaces with other NAS and Government-furnished equipment (GFE). The FAA will witness integration testing conducted by the Contractor.
System Testing
The purpose of system testing is to verify that the CSS-Wx System’s integrated software and hardware components meet A-level requirements under conditions that emulate projected operational conditions. System testing must include a 48-hour stability test period with the system running with an operational load. System testing must be conducted at the WJHTC. The Government will witness system testing conducted by the Contractor.
Production Acceptance Testing (PAT)
The purpose of PAT is to verify that production line units of hardware and software (e.g., software version, firmware, BIOS, etc.) conform to applicable specifications. This testing also verifies that the production unit is free from manufacturing defects and is substantially identical to qualified hardware. . PAT must be conducted at the Contractor’s facility prior to installation at field sites. The Government will witness PAT.
Site Acceptance Testing (SAT)
The purpose of SAT is to verify that the fully integrated software and hardware components of the CSS-Wx System meet A-level specification items that could not be sufficiently tested during system testing. SAT also enables the Government to verify that the CSS-Wx System installed at each operational site still meets the requirements that were verified through system testing. The Government will witness SAT.

Formal Test Activities FAT and all test activities conducted after FAT are designated as formal test activities. The Contractor must meet the entrance and exit criteria for formal test activities described in this section.

Formal Test Entrance Criteria The Contractor must complete the following actions prior to the start of each formal test activity:

Submit and obtain Government approval for test procedures;

Baseline the test system;

Document the test configuration;

Complete test tool/capability accreditation and baseline the test tools and capabilities;

Complete all dry-run testing and incorporate redline changes into final test procedures;

Confirm all formal dry-run testing was conducted on the same software baseline as the formal CRT event;

Verify that there are no open program trouble reports (PTRs) that affect the configuration under test;

Analyze, document, submit, and obtain Government approval for test configuration deficiencies;

Coordinate test activities with affected users (e.g., internal and external users, NAS and non-NAS weather interface users, and WJHTC test bed users);

In lieu of the Test Readiness Review (TRR), complete the Pre-test Briefing;

Notify the Government of the Contractor’s intent to conduct tests at least 20 business days prior to beginning testing;

Train contractor personnel in accordance with the Contractor Master Test Plan (CMTP);

Identify and make required contractor personnel available to support test activities;

Familiarize Government personnel with the system being tested; and Identify and request that Government personnel required to support testing activities be available.

Formal Test Exit Criteria The Contractor must complete the following actions prior to the completion of each formal test activity:

Complete all test activities in accordance with the approved test plan and test procedure;

Complete the post-test briefing;

Verify that all requirements are completed;

Submit and receive Government acceptance of the test results;

Document, assess, and indicate the disposition of all PTRs;

Update all required documentation to reflect changes made during testing;

Log all pertinent test data in accordance with approved quality assurance processes;

Update the VRTM master database;

Document updates to test tools/capabilities identified during testing; and Document and implement required updates to the system test configuration.

Contractor Master Test Plan The Contractor must develop a CMTP (CDRL TE01) that describes, at a high level, the complete test approach for the tests listed in Table 1. The CMTP must include the following:

Test management approach;

Identification and description of the major test areas, test tools, test environment, and test schedule;

Configuration management and quality assurance approach;

Methods for tracking requirements, including safety requirements and the VRTM (CDRL TE02);

An approach for integration testing;

A test strategy for NDIs and COTS products, interfaces to the NAS, and security;

A process for submitting PTRs and taking corrective action;

Required initial system certifications (e.g., certification for NextGen Weather Radar (NEXRAD) connectivity); and The requirements for access to Government facilities for testing.

Test Plans and Procedures The Contractor must submit a Test Plan (CDRL TE03) and Test Procedures (CDRL TE04) for approval by the Government for all formal test activities listed in Table 1. The Contractor must follow the Government-approved test and evaluation plans and procedures for each formal test. A test procedure may be individually developed for a formal test activity or may be a component of an overall plan implemented repeatedly as the articles under evaluation dictate. The Government will approve deviations from approved plans or procedures.

Reserved Pre-Test Briefing Prior to each individual formal test, the Contractor must conduct an informal pre-test briefing. The purpose of this briefing is to ensure that the objectives and requirements for the test will be verified during the test and post-test activities. During the pre-test briefing, the Contractor must:

Overview of testing to be performed Status of all applicable test documentation, (for example: plans, procedures, test tool certification results, test bed configuration diagrams, test tool accreditation results) Identification of required Government and contractor resources and personnel Configuration control and accreditation of test tools and test items (both hardware and software) and any other items necessary for the successful conduct of testing, including Data Reduction and Analysis (DR&A) tools and equipment Prior test results, including those from any dry runs of tests List of recommended test plan or test procedure changes, for FAA review Summary of all PTRs, including status of relevant hardware, firmware, and software problems Review of test baseline, configuration, and environment System CM status GFE, GFI, and GFP status (if applicable) Traceability between requirements and their associated tests using the DT VRTM Test schedules Identify test limitations, deviations, and workarounds that apply to the test Test Execution The Contractor must execute testing in accordance with the Contractor’s testing approach as documented in the CMTP, applicable test plans, and applicable test procedures. The Contractor must collect all applicable test output during execution of each test procedure. Through the execution of a test procedure, the Contractor must verify assigned system requirements by demonstration, test, or analysis, or through a combination of all three methods.