Base_Specific_Q&As_AFGOCO_Northwest_Region-HIll_AFB.pdf

PDF 184 KB Posted

Attached to
Operation and Maintenance of Fuel Facilities - SPE603-18-R-0507
Solicitation number
SPE603-18-R-0507
Issued by

About this file

Questions & Answers Hill AFB

View the file

Other files

File Type Posted
Hill_AFB_WD_2015-5483_Rev_5.pdf PDF
Mtn_Home_WD_2015-5513_Rev_5.pdf PDF
Ellsworth_AFB_WD_2015-5367_Rev_8.pdf PDF
Minot_AFB_WD_2015-5383_Rev_5.pdf PDF
Grand_Forks_AFB_WD_2015-4973_Rev_8.pdf PDF
Nellis_AFB_WD_2015-5593_Rev_8.pdf PDF
SF30_SPE60318R05070004.pdf PDF
Final_Conformed_Solicitation_SPE603-18-R-0507_JUL_24,_2018.pdf PDF
Q&A_Attachment_IV_Grand_Forks_AFB_Appendix_AF_01_May_18.pdf PDF
Base_Specific_Q&As_AFGOCO_Northwest_Region-Minot_AFB.pdf PDF
Base_Specific_Q&As_AFGOCO_Northwest_Region-Grand_Forks_AFB.pdf PDF
Q&A_Attachment_I_General_Contracting_Q&As_-_AFGOCO_Northwest_Region.pdf PDF
Q&A_Attachment_III_Ellsworth_AFB_Appendix_AF_01_May_18.pdf PDF
AFGOCO_Consolidated_PWS_(dated_12_Feb_2018).pdf PDF
Q&A_Attachment_IX_Mountain_Home_AFB_Appendix_AF__01_May_18.pdf PDF
Minot_AFB_-_MAF_413_Runs_(FY_16).xlsx XLSX spreadsheet
Q&A_Attachment_X_Nellis_AFB_Appendix_AF_01_May_18.pdf PDF
Q&A_Attachment_V_Hill_AFB_Appendix_AF__01_May_18.pdf PDF
Base_Specific_Q&As_AFGOCO_Northwest_Region-Nellis_AFB.pdf PDF
Q&A_Attachment_II_General_Technical_Q&As_-_AFGOCO_Northwest_Region.pdf PDF
Base_Specific_Q&As_AFGOCO_Northwest_Region-Mountain_Home_AFB.pdf PDF
Minot_AFB_-_MAF_413_Runs_(FY_17).xlsx XLSX spreadsheet
Final_Solicitation_SPE603-18-R-0507_5MAY2018.pdf PDF
Q&A_Attachment_VI_Minot_AFB_Appendix_AF_01_May_18.pdf PDF
SF30_SPE60318R05070003.pdf PDF
ATTACHMENT_II_-__OFFEROR_SUBMISSION_PACKAGE_AFGOCO_Northwest.pdf PDF
Base_Specific_Q&As_AFGOCO_Northwest_Region-Ellsworth_AFB.pdf PDF
Final_Solicitation_SPE603-18-R-0507_25APR2018.pdf PDF
Amendment_0002.pdf PDF
ATTACHMENT_II_-__OFFEROR_SUBMISSION_PACKAGE_AFGOCO_Northwest.pdf PDF
Mountain_Home_AFB_PWS_Appendix.pdf PDF
AF_GOCO_Preproposal_Conference_Presentation.pdf PDF
SF1449_SPE60318R0507.pdf PDF
Minot_AFB_PWS_Appendix.pdf PDF
AF_GOCO_Northwest_Region_Site_visit_2017_Attendance_sheets.pdf PDF
SF30_SPE60318R05070001.pdf PDF
Nellis_AFB_PWS_Appendix.pdf PDF
Grand_Forks_AFB_PWS_Appendix.pdf PDF
Hill_AFB_PWS_Appendix.pdf PDF
AF_GOCO_Pre-Proposal_Conference_Attendance_Sheet.pdf PDF
Ellsworth_AFB_PWS_Appendix.pdf PDF
Attachment_1_-_AF_GOCO_Consolidated_PWS_(dated_12_Feb_2018).pdf PDF
ATTACHMENT_III_-_Past_Performance_Questionaire_-_AFGOCO_Northwest.pdf PDF
GF_AFB_WD_2015-4973.pdf PDF
Nellis_AFB_Appendix.pdf PDF
ATTACHMENT_II_-__OFFEROR_SUBMISSION_PACKAGE_AFGOCO_Northwest.pdf PDF
Hill_AFB_Appendix.pdf PDF
Grand_Forks_AFB_Appendix.pdf PDF
Mtn_Home_AFB_WD_2015-5513.pdf PDF
ATTACHMENT_IV_-_JOINT_VENTURE_CONSENT_FORM.pdf PDF
Show 40 more

Latest 50 of 59 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOURCE SELECTION INFORMATION. SEE FAR 2.101 AND 3.104 1 of 4

SOLICITATION SPE603-18-R-0507 – AF GOCO NORTHWEST REGION

BASE SPECIFIC QUESTIONS: HILL AFB, SD

1. The Appendix AF for Hill AFB states “The PWS indicates that after hours (outside

M-F 0600-1900) will be provided by “Standby” personnel…with no indication as to where these Standby personnel come from: flight or contractor. Blackson Arrow personnel will adjust schedule to meet mission demands such as pipeline receipts.”

What are the responsibilities of Blackson Arrow contractors? How do their responsibilities impact the responsibilities of the awarded contractor?

Answer: Refer to PWS Appendix AF para II.A. (3).

2. Reference PWS Appendix AF – Hill: The workload information states there are 2 transfers performed on average per week. What is the duration of a transfer?

3. Reference PWS Appendix AF – Hill: The workload information references one emergency generator being in the Contractor’s AOR, and that it is inspected daily.

Who is to perform this daily inspection, the Government or the Contractor?

4. Reference PWS Appendix AF – Hill: The workload information references one emergency generator being in the Contractor’s AOR. Please confirm that a

Government entity is responsible for conducting the periodic generator testing.

5. Reference PWS Appendix AF – Hill: The workload information references one emergency generator being in the Contractor’s AOR. Please confirm that the

Government provides the fuel for this generator in the event that the Contractor is responsible for testing.

6. Reference PWS Appendix AF – Hill: The workload information states there are confined spaces. Do Contractor personnel have to enter any of the confined spaces to perform work tasks?

Answer: Refer to PWS paragraph C-5.3.2.2, Appendix C.I.5, and AF para II.A. (3).

SOURCE SELECTION INFORMATION. SEE FAR 2.101 AND 3.104 2 of 4

7. Reference PWS Appendix AF – Hill: The base specific requirements provide a listing of Government-furnished facilities to be used by the Contractor. Are initial and replacement spill kits to be provided by the Government?

Answer: Refer to PWS para C-5.8.2 and Appendix F

8. Reference PWS Appendix AF – Hill: There is no listing of furniture included for the Government furnished facilities. Does the Government provide furniture for the

Contractor’s use?

Answer: Refer to PWS Appendix AF para II.A. (9).

9. Please confirm that the government is responsible for all PM’s at this location.

Answer: Refer to PWS paragraph C-5.3.2.2 and Appendix AF para I.

10. Reference Appendix AF - Average number of receipts per month: “Pipeline receipts take 10-11 hours for 10MBBL barrel receipt. We are at the mercy of the cross country pipeline schedule.”

With a storage capacity of about 6.4M gallons, where would they put a 10MBBL pipeline receipt (420M Gallons)?

11. How many pipeline receipts are received per month? What is the actual duration of the pipeline receipts?

12. Can government please provide more information regarding Note 1 of Hours of

Operation in Appendix AF. Can workload data be provided for weekend pipeline receipts?

13. Does the contractor have to enter confined spaces?

Answer: Refer to PWS paragraph C-5.3.2.2, Appendix C.I.5, and AF para II.A. (3).

SOURCE SELECTION INFORMATION. SEE FAR 2.101 AND 3.104 3 of 4

14. Does the Fuels Management Flight designate the number of fuels personnel who must be present when off-loading multiple tank trucks simultaneously in their Fuels

Operating Instructions? And if so, what does it stipulate?

Answer: Refer to PWS Appendix D and Appendix AF.

15. Please confirm whether or not there are any low point drains within the system that the Contractor is responsible for maintaining. Is the Contractor required to drive on the airfield to access pits, low points etc.?

Answer: Refer to PWS Appendix AF para II.A. (4).

16. Please provide the average number of pipeline receipts per month. Appendix AF

Workload Information shows the average number of tank trucks received but not the average number of pipeline receipt per month.

17. What is the average duration for the fuel transfers to the government facilities?

18. Please confirm that the level of DLA Energy/USACE RM provided maintenance

(Appendix AF displays N/A).

19. Reference Appendix AF (4) Base Specific Requirements, please provide historical workload factors for DFSP out-load operations.

20. Reference Appendix AF, (5) Facilities, installed equipment description shows 2 FSII tanks and 1 Hammonds injector. Additionally, table (6) Petroleum Storage Tanks reflects two FSII tanks. What is the Contractors role with injection of additives?

Does the Contractor only inject FSII or are there other additives? How are additives received? Who places the order for additives? Does the Contractor need to provide any equipment to support additive injection, such as storage shed etc.?

SOURCE SELECTION INFORMATION. SEE FAR 2.101 AND 3.104 4 of 4

21. Reference (9) Equipment (NON-EAID), please confirm the statement “Fuels

Management Flight takes care of all maintenance on equipment such as snow blowers and lawnmowers” is correct. Does this mean the Government provides snow blowers and lawnmowers and maintains them or do they provide maintenance for Contractor provided equipment? There is no equipment listed in the table so the assumption is that the equipment is Contractor furnished.

Answer: Refer to PWS Appendix AF para II.A. (8) and (9).

22. Please confirm the Contractor does not use the DLA Energy computer as specified in Appendix AF (11) ITEC (DLA Energy).

Answer: Refer to PWS Appendix AF para II.A. (11).