The document is a Statement of Work (SOW) Attachment C - 15% Concept Demolition Plan for a mechanical room renovation project. The plan details comprehensive demolition requirements for existing mechanical systems, including:

Specific demolition tasks include removing abandoned steam piping, steam accessories, domestic cold water (DCW), domestic hot water (DHW), and related infrastructure. The plan involves removing existing boilers, gas piping, water heaters, circulation pumps, and associated electrical services. The scope requires complete removal of glycol feeder tank systems, gas meters, and various piping systems back to specified points of connection. The demolition is part of a broader mechanical room upgrade, with provisions for potential reuse of some existing components like water heater flue exhaust pipes, contingent on their condition. The document is part of the FY25 Multiple Award Construction Contract (MACC) for Fairchild Air Force Base in Washington, covering facility maintenance and renovation work.

View the file

Other files for this federal contract opportunity

Other files attached to FY25 Multiple Award Construction Contract (MACC), newest first.
File Type Posted
25R0001_Amend0006-SF30-20250509.pdf PDF
SOWAtchF_Amend0005ExistingB2256Drwgs.pdf PDF
25R0001_Amend0005-SF30-20250508.pdf PDF
25R0001_Amend0004-SF30-20250508.pdf PDF
25R0001_Amend0003-SF30-20250501.pdf PDF
25R0001_PreProposalSiteVisitSignIn-20250428.pdf PDF
25R0001_Amend0002-SF30-20250428.pdf PDF
25R0001_Amend0001-SF30-20250417.pdf PDF
25R0001_Atch7D-WA20250095-Residential20250207.pdf PDF
25R0001_Atch11_FOPR_GJKZ1149058.pdf PDF
SOWAtchD1-15PcntConceptPlan.pdf PDF
SOWAtchE-BasisofDesignEqpmnt.pdf PDF
SOWAtchF-ExistingB2256Drwgs.pdf PDF
25R0001_Atch3-2025BDGDataSheets.pdf PDF
25R0001_Atch5-FAFBClimateWeatherData.pdf PDF
25R0001_Atch6-RealIDActPamphlet.pdf PDF
25R0001_Atch7A-WA20250114-Building20250214.pdf PDF
SOWAtchA-SiteHaulRoute.pdf PDF
25R0001_Atch1-FY25MACCSpecs12FEB2025.pdf PDF
25R0001_SF1442-20250414.pdf PDF
25R0001_Atch7B-WA20250130-Heavy20250207.pdf PDF
25R0001_Atch7C-WA20250001-Highway20250321.pdf PDF
25R0001_Atch8-PastPerfCvrLtrQuestionnaire.pdf PDF
25R0001_Atch9-PastPerformanceInfo.pdf PDF
25R0001_Atch10-SubKTRTeamingArrngmntRelease.pdf PDF
25R0001_Atch11A_FOPR_GJKZ1149058-Atch1-PriceSchedule.pdf PDF
25R0001_Atch11B_FOPR_GJKZ1149058-Atch2-SOW20DEC2024.pdf PDF
SOWAtchB-PhotosB2256_2257_2258_2259.pdf PDF
SOWAtchD2-15PcntConcept Plan.pdf PDF
25R0001_Atch2-2025BDGSpecs11MAR2025.pdf PDF
25R0001_Atch4-2018FAFBIFS26JUN2018.pdf PDF
25R0001_Atch12-OrientationSmnrSOW.pdf PDF
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

This drawing does not represent the current as-built status of the MER. Steam heating system has been replaced by boiler and hydronic heating accessories and water heater has been replaced. Many steam components have been abandoned in place to make space for the existing boiler, which replaced the steam heating system.

MAU is not shown but has been approximated for location. Field measurements will be required for ROM piping calculations (demo and new). Only ROM concept plan has been shown and not piping length approximations.

Area well approximately 15 feet below grade -existing boiler and water heater combustion air, and boiler and water heater flue exhaust located here

Remove all leftover abandoned steam piping and steam accessories - see SOW for approximate quantities, but KTR is responsible to bid based on their observations / measurements

Completely remove DCW, DHW, DRHW piping systems, including water heaters, storage tanks, circulation pumps, mixing valves, expansion tanks, combustion air piping, gas piping, gas regulators, gas regulator vents, etc., back to MER entrance near interior door. This includes recirculation piping back to the MER interior door. Electrical service to domestic service equipment shall be removed and new service re-installed to new equipment (water heater, circulation pumps, disconnects, etc.).

DCW

Remove existing boiler, gas piping back to gas meter (outside), HWS piping back to air separator, HWR piping to location shown, combustion air and flue exhaust piping, muffler

(DEMO - 15% CONCEPT)

Make-Up Air unit (remains) -approximate location. Removal of fan motor may be necessary to bring new equipment into MER.

DCW service entry

Remove (E) 2-inch gas line serving boiler from meter outside - see Page 2

Cap this gas line at wall/ceiling

Existing electrical Panel M to remain

Water heater flue exhaust pipe (metal) - Design team may re-use if functional and uncompromised; otherwise, remove water heater flue exhaust and route new water heater flue exhaust through mechanical area well. If cannot re-use, cap at mechanical room ceiling and at exterior termination.

(ABANDONED)

Existing switchboard

Remove glycol feeder tank system, including all piping back to POC on HWR and CHWR pipe

FA462025R0001

FOPR_GJKZ1149058

SOW Attachment C - 15% Concept Demo Plan

Remove (E) gas meter and 2" gas pipe to (E) boiler in mechanical room. This meter and gas pipe is currently dedicated to only the boiler. Remove existing gas energy meter and replace with new.