Biloxi Building 1 Renovation - Biloxi, MS -- Y1DA
Solicitation number
QSE--36C10F24R50025
Issued by

About this file

This document is a solicitation for the renovation of Building 1 at the Biloxi VA Medical Center in Biloxi, Mississippi. The project includes exterior building envelope alterations and approximately 54,370 gross square feet of renovation on the third, fourth and fifth floors of the building. The work also includes replacement of HVAC, plumbing, electrical, and chilled water systems.

The project magnitude is between $50M and $100M. The period of performance is 912 calendar days from receipt of the Notice to Proceed. This is an unrestricted procurement, but offerors must be registered and certified in the SBA VetCert system if submitting as an SDVOSB or VOSB entity. All offerors must be registered in the System for Award Management (SAM) prior to submitting a proposal. The Construction Wage Rate Requirements apply to this procurement. The solicitation contains detailed evaluation factors for award including project experience, key personnel, past performance, small business participation, and occupational safety and health performance.

View the file

Other files

File Type Posted
S02_Solicitation Amendment 0003.pdf PDF
C28_02821319 TILE AND MASTIC AND BRICK COATING ABATEMENT.pdf PDF
C28_02833313 LEAD PAINT REMOVAL.pdf PDF
P12_AE Addendum Two.pdf PDF
SolicitationAmendment0004.pdf PDF
P03_Justification and Approval - TekTone Nurse Call System - revised 05.24.24.pdf PDF
P12_Asbestos Report - 01.03.2022.pdf PDF
SolicitationAmendment0003.pdf PDF
52.219-28 Post-Award Small Business Program Rerepresentation.pdf PDF
Wage Determination - Harrison County MS.pdf PDF
QSE 36C10F24R50025.pdf PDF
P12_Asbestos Report - 07.06.2017.pdf PDF
S05_RFI Questions and Answers.pdf PDF
P12_Lead Based Paint Analysis - Bldg 1 - 01.11.2017.pdf PDF
S02_117300 CEILING MOUNTED PATIENT LIFTS - Revised.pdf PDF
P12_Asbestos Report - 05.06.2008.pdf PDF
P12_Addendum 1 - 05.14.2024.pdf PDF
S04_Biloxi Bldg 1 Reno - Pre-Proposal Conference Attendees.pdf PDF
SolicitationAmendment0002.pdf PDF
SolicitationAmendment0001.pdf PDF
QSE 36C10F24R50025.pdf PDF
Wage Determination - Harrison County MS.pdf PDF
52.219-28 Post-Award Small Business Program Rerepresentation.pdf PDF
Drawings - Architectural - 3.pdf PDF
General Contractor Reference Form.docx DOCX document
Drawings - Telecommunication.pdf PDF
Drawings - Architectural - 4.pdf PDF
Drawings - Reference.pdf PDF
VA Biloxi 4th Floor Footwall.pdf PDF
Drawings - Architectural - 1.pdf PDF
Building 1 Inventory - d.pdf PDF
Adec Submittal - VA Biloxi.pdf PDF
Drawings - Electrical - 2.pdf PDF
LOCQ7780-03-SWS-Biloxi VA Dental Lab.pdf PDF
Justification and Approval - Siemens Security and Video Surveillance System.pdf PDF
Past Performance Questionnaire.docx DOCX document
A-dec Floor Plan - VA Biloxi - Elevations.pdf PDF
Drawings - Structural - 2.pdf PDF
Specifications Volume II.pdf PDF
Biloxi VA Reno B1 - Set H.pdf PDF
Drawings - Plumbing - 1.pdf PDF
Drawings - Structural - 1.pdf PDF
VA Biloxi Patient Room Footwall Typical Elevation.pdf PDF
Justification and Approval - Herman Miller Compass Patient Care Modular System.pdf PDF
000000 Cover Page Appendix.pdf PDF
Justification and Approval - ESTIII Fire Alarm System.pdf PDF
Drawings - General.pdf PDF
A-dec Floor Plan - VA Biloxi - Preliminary.pdf PDF
Drawings - Mechanical - 2.pdf PDF
Drawings - Plumbing - 2.pdf PDF
Show 40 more

Latest 50 of 64 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Document Number: 36C10F24R50025 PROCESSED Page 1 of 59

SOLICITATION,OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

36C10F24R50025 SEALED BID (IFB)

X NEGOTIATED (RFP)

2. TYPE OF SOLICITATION 3. DATE ISSUED

04/09/2024

PAGE OF PAGES

1 59

IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

F365203-24-2000011

6. PROJECT NO.

520-317X

CODE 36C10F

Department of Veterans Affairs Office of Construction and Facilities Management (CFM) Central Region 1425 Tri-State Parkway, Suite 140 Gurnee, IL 60031

7. ISSUED BY

Department of Veterans Affairs Office of Construction and Facilities Management (CFM) Central Region 1425 Tri-State Parkway, Suite 140 Gurnee, IL 60031

8. ADDRESS OFFER TO

9. FOR INFORMATION

CALL:

a. NAME Jason W Hardy

b. TELEPHONE NO. (Include area code)(NO COLLECT CALLS)

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Renovate Building 1 - Biloxi VAMC The contractor shall provide all qualified supervision, labor, materials, transportation, and equipment necessary to complete the renovation of Building 1 - Biloxi VAMC in accordance with the drawings, specifications, and all other terms and conditions of the contract. The project magnitude is between $50M and $100M. NAICS Code: 236220 (Commercial and Industrial Building Construction) Size Standard: $45.0 Million This procurement is NOT set-aside and is unrestricted. If submitting as an SDVOSB or VOSB entity, your firm must be registered and certified in the SBA VetCert system prior to submitting a proposal and remain active through contract award. All offerors shall be registered in the System for Award Management (SAM) before submitting an offer and remain active through contract award and administration. Award cannot be made until the contractor is registered. Offerors are encouraged to ensure that they are registered and up-to-date in SAM.gov prior to submitting their proposal. All RFI questions are due to the Contracting Officer, Jason Hardy by May 3, 2024 at 3:00pm CST (Local Time). Offerors are encouraged to track this solicitation via the Contract Opportunities section of SAM.gov for updates including any amendments issued. Please note: failure to acknowledge any amendments will result in the proposal being considered ineligible for award. Please note the following and attached Justification for Other than Full and Open Competition memos for proprietary items: A Dec Dental Suite; Herman Miller Patient Care Modular System; Siemens Building Automation; Siemens Security System; TekTone Nurse Call System; and ESTIII Fire Alarm System. Please note that FAR clause 52.222-34 ALT I: Project Labor Agreement (Jan 2024) is applicable to this procurement. Please reference applicable provision and clause and additional instructions contained within the solicitation for further details.

11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving10 912

52.211-10award, X notice to proceed. This performance period is X mandatory negotiable. (See __________________________.)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).

X YES NO

12b. CALENDAR DAYS

Sealed offers in original and copies to perform the work required are due at the place specified in item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

0 15:00a.

05/24/2024

b. An offer guarantee X is, is not required.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.

120d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

13. ADDITIONAL SOLICITATION REQUIREMENTS:

NSN 7540-01-155-3212 STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d)

Document Number: 36C10F24R50025 PROCESSED Page 2 of 59

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CODE FACILITY CODE

The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ___________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

17.

AMOUNTS

CLIN 0001

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

Jason W Hardy

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

STANDARD FORM 1442 (REV. 8/2014)BACK

Document Number: 36C10F24R50025 PROCESSED Page 3 of 59

Table of Contents

Section Description Page Number

B Supplies or Services and Prices/Costs C Descriptions/Specifications/Statement of Work E Inspection and Acceptance

52.246-12 Inspection of Construction (Aug 1996) F Deliveries or Performance

52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) 52.211-12 Liquidated Damages-Construction (Sept 2000) 52.211-13 Time Extensions (Sept 2000) 52.236-15 Schedules for Construction Contracts (Apr 1984) 52.242-14 Suspension of Work (Apr 1984)

I Contract Clauses 52.252-2 Clauses Incorporated by Reference (Feb 1998) 52.202-1 Definitions (Jun 2020) 52.203-3 Gratuities (Apr 1984) 52.203-5 Covenant Against Contingent Fees (May 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) 52.203-7 Anti-Kickback Procedures (Jun 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014) 52.203-12 Limitation On Payments to Influence Certain Federal Transactions (Jun 2020) 52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021) 52.203-14 Display of Hotline Poster(s) (Nov 2021) 52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May 2011) 52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) 52.204-13 System for Award Management Maintenance (Oct 2018) 52.204-14 Service Contract Reporting Requirements (Oct 2016) 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023) 52.208-9 Contractor Use of Mandatory Sources of Supply or Services (May 2014) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Nov 2021) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) 52.210-1 Market Research (Nov 2021) 52.215-2 Audit and Records-Negotiation (Jun 2020) 52.215-10 Price Reduction for Defective Certified Cost or Pricing Data (Aug 2011) 52.215-12 Subcontractor Certified Cost or Pricing Data (Jun 2020) 52.215-15 Pension Adjustments and Asset Reversions (Oct 2010) 52.215-17 Waiver of Facilities Capital Cost of Money (Oct 1997) 52.215-18 Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other than Pensions (July 2005) 52.215-19 Notification of Ownership Changes (Oct 1997) 52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data-Modifications (Nov 2021) 52.219-8 Utilization of Small Business Concerns (Feb 2024)

Document Number: 36C10F24R50025 PROCESSED Page 4 of 59

52.219-9 Alt II Small Business Subcontracting Plan (Sep 2023) - Alternate II (Nov 2016) 52.219-16 Liquidated Damages-Subcontracting Plan (Sep 2021) 52.222-3 Convict Labor (June 2003) 52.222-4 Contract Work Hours and Safety Standards--Overtime Compensation (May 2018) 52.222-6 Construction Wage Rate Requirements (Aug 2018) 52.222-7 Withholding of Funds (May 2014) 52.222-8 Payrolls and Basic Records (Jul 2021) 52.222-9 Apprentices and Trainees (July 2005) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) 52.222-11 Subcontracts (Labor Standards) (May 2014) 52.222-12 Contract Termination - Debarment (May 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988) 52.222-15 Certification of Eligibility (May 2014) 52.222-21 Prohibition of Segregated Facilities (Apr 2015) 52.222-26 Equal Opportunity (Sept 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-33 Alt II Notice of Requirement for Project Labor Agreement (Jan 2024) - Alternate II (Jan 2024) 52.222-35 Equal Opportunity for Veterans (Jun 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (Jun 2020) 52.222-37 Employment Reports on Veterans (Jun 2020) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) 52.222-41 Service Contract Labor Standards (Aug 2018) 52.222-44 Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (May 2014) 52.222-50 Combating Trafficking in Persons (Nov 2021) 52.222-54 Employment Eligibility Verification (May 2022) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) 52.223-5 Pollution Prevention and Right-to-Know Information (May 2011) 52.223-6 Drug-Free Workplace (May 2001) 52.223-15 Energy Efficiency in Energy-Consuming Products (May 2020) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts (Aug 2018) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (Jun 2020) 52.225-13 Restrictions on Certain Foreign Purchases (Feb 2021) 52.227-1 Authorization and Consent (Jun 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020) 52.227-4 Patent Indemnity-Construction Contracts (Dec 2007) 52.228-2 Additional Bond Security (Oct 1997) 52.228-5 Insurance-Work on a Government Installation (Jan 1997) 52.228-11 Individual Surety-Pledge of Assets (Feb 2021) 52.228-12 Prospective Subcontractor Requests for Bonds (Dec 2022) 52.228-14 Irrevocable Letter of Credit (Nov 2014) 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) 52.229-3 Federal, State and Local Taxes (Feb 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-17 Interest (May 2014) 52.232-23 Assignment of Claims (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer-System for Award Management (Oct 2018) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-1 Alt I Disputes (May 2014) - Alternate I (Dec 1991) 52.233-3 Protest after Award (Aug 1996) 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) 52.236-1 Performance of Work by the Contractor (Apr 1984) 52.236-2 Differing Site Conditions (Apr 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984)

Document Number: 36C10F24R50025 PROCESSED Page 5 of 59

52.236-5 Material and Workmanship (Apr 1984) 52.236-6 Superintendence by the Contractor (Apr 1984) 52.236-7 Permits and Responsibilities (Nov 1991) 52.236-8 Other Contracts (Apr 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) 52.236-10 Operations and Storage Areas (Apr 1984) 52.236-11 Use and Possession Prior to Completion (Apr 1984) 52.236-12 Cleaning Up (Apr 1984) 52.236-13 Accident Prevention (Nov 1991) 52.236-14 Availability and Use of Utility Services (Apr 1984) 52.236-21 Alt I Specifications and Drawings for Construction (Feb 1997) - Alternate I (Apr 1984) 52.236-26 Preconstruction Conference (Feb 1995) 52.242-5 Payments to Small Business Subcontractors (Jan 2017) 52.242-13 Bankruptcy (July 1995) 52.243-4 Changes (June 2007) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Feb 2024) 52.245-1 Alt I Government Property (Sep 2021) - Alternate I (Apr 2012) 52.245-9 Use and Charges (Apr 2012) 52.246-21 Alt I Warranty of Construction (Mar 1994) - Alternate I (Apr 1984) 52.248-3 Value Engineering-Construction (Oct 2020) 52.249-2 Alt I Termination for Convenience of the Government (Fixed-Price) (Apr 2012) - Alternate I (Sept 1996) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.253-1 Computer Generated Forms (Jan 1991) 52.204-21 Basic Safeguarding of Covered Contractor Information Systems (Nov 2021) 52.219-28 Post-Award Small Business Program Rerepresentation (Feb 2024) 52.222-34 Alt I Project Labor Agreement (Jan 2024) - Alternate I (Jan 2024) 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008) 52.223-21 Foams (Jun 2016) 52.225-11 Buy American-Construction Materials under Trade Agreements (Nov 2023) 52.225-12 Notice of Buy American Requirement--Construction Materials Under Trade Agreements (May 2014) 52.236-4 Physical Data (Apr 1984) 52.245-2 Government Property Installation Operation Services (Apr 2012)

852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)

852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY

2020)

852.204-71 INFORMATION AND INFORMATION SYSTEMS SECURITY (FEB 2023)

852.219-70 VA SMALL BUSINESS SUBCONTRACTING PLAN MINIMUM REQUIREMENTS

(NOV 2022)

852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)

852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (INCLUDING

NAS-CPM) (NOV 2018)

852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)

852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)

852.236-72 Alt I PERFORMANCE OF WORK BY THE CONTRACTOR (APR 2019) - Alternate I

(APR 2019)

852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)

852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)

852.236-90 RESTRICTION ON SUBMISSION AND USE OF EQUAL PRODUCTS (APR

2019)

852.237-75 KEY PERSONNEL (OCT 2019)

852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)

852.243-70 CONSTRUCTION CONTRACT CHANGES-SUPPLEMENT (SEP 2019)

J List of Attachments K Representations, Certifications and Other Statements of Offerors or Respondents

Document Number: 36C10F24R50025 PROCESSED Page 6 of 59

52.223-4 Recovered Material Certification (May 2008) 52.236-28 Preparation of Proposals-Construction (Oct 1997) 52.204-8 Annual Representations and Certifications (Feb 2024) 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.209-7 Information Regarding Responsibility Matters (Oct 2018) 52.209-13 Violation of Arms Control Treaties or Agreements-Certification (Nov 2021)

L Instructions, Conditions and Notices to Offerors or Respondents 52.252-1 Solicitation Provisions Incorporated by Reference (Feb 1998) 52.204-7 System for Award Management (Oct 2018) 52.204-16 Commercial and Government Entity Code Reporting (Aug 2020) 52.204-22 Alternative Line Item Proposal (Jan 2017) 52.215-1 Alt I Instructions to Offerors-Competitive Acquisition (Nov 2021) - Alternate I (Oct 1997) 52.215-16 Facilities Capital Cost of Money (June 2003) 52.215-20 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data (Nov 2021) 52.216-1 Type of Contract (Apr 1984) 52.228-1 Bid Guarantee (Sept 1996) 52.228-17 Individual Surety-Pledge of Assets (Bid Guarantee) (Feb 2021) 52.222-5 Construction Wage Rate Requirements - Secondary Site of the Work (May 2014) 52.233-2 Service of Protest (Sept 2006) 52.236-27 Alt I Site Visit (Construction) (Feb 1995) - Alternate I (Feb 1995)

852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED

SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)

852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)

M Evaluation Factors for Award

- Basis of Award and Evaluation Factors Evaluation Factor 1 Project Experience Evaluation Factor 2 Key Personnel Evaluation Factor 3 Past Performance Evaluation Factor 4 Small Business Participation / Subcontracting Plan Evaluation Factor 5 Occupational Safety and Health Performance Evaluation Factor 6 Price Proposal

Document Number: 36C10F24R50025 PROCESSED Page 7 of 59

Section B - Supplies or Services and Prices/Costs

Number Supplies or Services Qty Unit Unit Price Total (Inc. disc., tax, and fees)

0001 See Description Below

PSC: Y1DA

CONSTRUCTION

OF HOSPITALS AND

INFIRMARIES

1.000000 JA

Description: The project includes exterior building envelope alterations and approximately 54,370 gross square feet of renovation on the third, fourth and fifth floors of Building 1. It also includes replacement of HVAC, plumbing, electrical, and chilled water systems

Reference Line: F365203-24-2000011 - 0001

Section C - Descriptions/Specifications/Statement of Work

. The scope of work is described in the drawings and specifications as listed in Section J which are attachments to the solicitation.

Section E - Inspection and Acceptance

52.246-12 Inspection of Construction (Aug 1996)

(a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not--

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this- section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and

Document Number: 36C10F24R50025 PROCESSED Page 8 of 59 tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may--

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor's right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately.

Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.

(End of clause)

Section F - Deliveries or Performance

52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to (a) commence work under this contract within 10 Calendar Days [Contracting Officer insert number] calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 912 Calendar Days after Notice to Proceed.* The time stated for completion shall include final cleanup of the premises.

* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

(End of clause)

52.211-12 Liquidated Damages-Construction (Sept 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,000.00 [Contracting Officer insert amount] for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

52.211-13 Time Extensions (Sept 2000)

Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other

Document Number: 36C10F24R50025 PROCESSED Page 9 of 59 portions of the work will not be altered. The change order also may provide an equitable readjustment of liquidated damages under the new completion schedule.

(End of clause)

52.236-15 Schedules for Construction Contracts (Apr 1984)

(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.

(End of clause)

52.242-14 Suspension of Work (Apr 1984)

(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.

(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer's failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.

(c) A claim under this clause shall not be allowed--

(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and

(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.

(End of clause)

Section I - Contract Clauses

52.252-2 Clauses Incorporated by Reference (Feb 1998)

Document Number: 36C10F24R50025 PROCESSED Page 10 of 59

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/ these address(es):

www.acquisition.gov/browse/index/far (FAR) www.va.gov/oal/library/vaar/index.asp (VAAR) [Insert one or more Internet addresses]

(End of clause) Clause Title Fill-ins

52.202-1 Definitions (Jun 2020)

52.203-3 Gratuities (Apr 1984)

52.203-5 Covenant Against Contingent Fees (May 2014)

52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020)

52.203-7 Anti-Kickback Procedures (Jun 2020)

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper

Activity (May 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014)

52.203-12 Limitation On Payments to Influence Certain Federal Transactions (Jun 2020)

52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021)

52.203-14 Display of Hotline Poster(s) (Nov 2021) Posters 1: "VA OIG Hotline

Poster"

Obtain from 1: "https:// www.vaoig.gov/hotline/online-forms"

Posters 2: "DHS OIG Hotline

Poster"

Obtain from 2: "https:// www.oig.dhs.gov/hotline"

52.203-17 Contractor Employee Whistleblower Rights (Nov 2023)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (Jan 2017)

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May

2011)

52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011)

Document Number: 36C10F24R50025 PROCESSED Page 11 of 59

Clause Title Fill-ins

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Jun

2020)

52.204-13 System for Award Management Maintenance (Oct 2018)

52.204-14 Service Contract Reporting Requirements (Oct 2016)

52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020)

52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014)

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023)

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video

Surveillance Services or Equipment (Nov 2021)

52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023)

52.208-9 Contractor Use of Mandatory Sources of Supply or Services (May 2014)

52.209-6 Protecting the Government's Interest When Subcontracting with Contractors

Debarred, Suspended, or Proposed for Debarment (Nov 2021)

52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters

(Oct 2018)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015)

52.210-1 Market Research (Nov 2021)

52.215-2 Audit and Records-Negotiation (Jun 2020)

52.215-10 Price Reduction for Defective Certified Cost or Pricing Data (Aug 2011)

52.215-12 Subcontractor Certified Cost or Pricing Data (Jun 2020)

52.215-15 Pension Adjustments and Asset Reversions (Oct 2010)

52.215-17 Waiver of Facilities Capital Cost of Money (Oct 1997)

52.215-18 Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other than Pensions (July 2005)

52.215-19 Notification of Ownership Changes (Oct 1997)

52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than

Certified Cost or Pricing Data-Modifications (Nov 2021)

52.219-8 Utilization of Small Business Concerns (Feb 2024)

52.219-9 Alt II Small Business Subcontracting Plan (Sep 2023) - Alternate II (Nov 2016)

Document Number: 36C10F24R50025 PROCESSED Page 12 of 59

52.219-16 Liquidated Damages-Subcontracting Plan (Sep 2021)

52.222-3 Convict Labor (June 2003)

52.222-4 Contract Work Hours and Safety Standards--Overtime Compensation (May

2018)

52.222-6 Construction Wage Rate Requirements (Aug 2018)

52.222-7 Withholding of Funds (May 2014)

52.222-8 Payrolls and Basic Records (Jul 2021)

52.222-9 Apprentices and Trainees (July 2005)

52.222-10 Compliance with Copeland Act Requirements (Feb 1988)

52.222-11 Subcontracts (Labor Standards) (May 2014)

52.222-12 Contract Termination - Debarment (May 2014)

52.222-13 Compliance with Construction Wage Rate Requirements and Related

Regulations (May 2014)

52.222-14 Disputes Concerning Labor Standards (Feb 1988)

52.222-15 Certification of Eligibility (May 2014)

52.222-21 Prohibition of Segregated Facilities (Apr 2015)

52.222-26 Equal Opportunity (Sept 2016)

52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015)

52.222-33 Alt II Notice of Requirement for Project Labor Agreement (Jan 2024) - Alternate II

(Jan 2024)

52.222-35 Equal Opportunity for Veterans (Jun 2020)

52.222-36 Equal Opportunity for Workers with Disabilities (Jun 2020)

52.222-37 Employment Reports on Veterans (Jun 2020)

52.222-40 Notification of Employee Rights Under the National Labor Relations Act

(Dec 2010)

52.222-41 Service Contract Labor Standards (Aug 2018)

52.222-44 Fair Labor Standards Act and Service Contract Labor Standards-Price

Adjustment (May 2014)

52.222-50 Combating Trafficking in Persons (Nov 2021)

52.222-54 Employment Eligibility Verification (May 2022)

Document Number: 36C10F24R50025 PROCESSED Page 13 of 59

52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022)

52.223-5 Pollution Prevention and Right-to-Know Information (May 2011)

52.223-6 Drug-Free Workplace (May 2001)

52.223-15 Energy Efficiency in Energy-Consuming Products (May 2020)

52.223-17 Affirmative Procurement of EPA-designated Items in Service and

Construction Contracts (Aug 2018)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (Jun

2020)

52.225-13 Restrictions on Certain Foreign Purchases (Feb 2021)

52.227-1 Authorization and Consent (Jun 2020)

52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun

2020)

52.227-4 Patent Indemnity-Construction Contracts (Dec 2007)

52.228-2 Additional Bond Security (Oct 1997)

52.228-5 Insurance-Work on a Government Installation (Jan 1997)

52.228-11 Individual Surety-Pledge of Assets (Feb 2021)

52.228-12 Prospective Subcontractor Requests for Bonds (Dec 2022)

52.228-14 Irrevocable Letter of Credit (Nov 2014)

52.228-15 Performance and Payment Bonds-Construction (Jun 2020)

52.229-3 Federal, State and Local Taxes (Feb 2013)

52.232-5 Payments under Fixed-Price Construction Contracts (May 2014)

52.232-17 Interest (May 2014)

52.232-23 Assignment of Claims (May 2014)

52.232-27 Prompt Payment for Construction Contracts (Jan 2017)

52.232-33 Payment by Electronic Funds Transfer-System for Award Management (Oct

2018)

52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar

2023)

52.233-1 Alt I Disputes (May 2014) - Alternate I (Dec 1991)

Document Number: 36C10F24R50025 PROCESSED Page 14 of 59

52.233-3 Protest after Award (Aug 1996)

52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004)

52.236-1 Performance of Work by the Contractor (Apr 1984) PercentofWork: "15"

52.236-2 Differing Site Conditions (Apr 1984)

52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984)

52.236-5 Material and Workmanship (Apr 1984)

52.236-6 Superintendence by the Contractor (Apr 1984)

52.236-7 Permits and Responsibilities (Nov 1991)

52.236-8 Other Contracts (Apr 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (Apr 1984)

52.236-10 Operations and Storage Areas (Apr 1984)

52.236-11 Use and Possession Prior to Completion (Apr 1984)

52.236-12 Cleaning Up (Apr 1984)

52.236-13 Accident Prevention (Nov 1991)

52.236-14 Availability and Use of Utility Services (Apr 1984)

52.236-21 Alt I Specifications and Drawings for Construction (Feb 1997) - Alternate I (Apr

1984)

52.236-26 Preconstruction Conference (Feb 1995)

52.242-5 Payments to Small Business Subcontractors (Jan 2017)

52.242-13 Bankruptcy (July 1995)

52.243-4 Changes (June 2007)

52.244-6 Subcontracts for Commercial Products and Commercial Services (Feb 2024)

52.245-1 Alt I Government Property (Sep 2021) - Alternate I (Apr 2012)

52.245-9 Use and Charges (Apr 2012)

52.246-21 Alt I Warranty of Construction (Mar 1994) - Alternate I (Apr 1984)

52.248-3 Value Engineering-Construction (Oct 2020)

52.249-2 Alt I Termination for Convenience of the Government (Fixed-Price) (Apr 2012) -

Alternate I (Sept 1996)

52.249-10 Default (Fixed-Price Construction) (Apr 1984)

Document Number: 36C10F24R50025 PROCESSED Page 15 of 59

52.253-1 Computer Generated Forms (Jan 1991)

52.204-21 Basic Safeguarding of Covered Contractor Information Systems (Nov 2021)

(a) Definitions. As used in this clause--

"Covered contractor information system" means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.

"Federal contract information" means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public Web sites) or simple transactional information, such as necessary to process payments.

"Information" means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction

(CNSSI) 4009).

"Information system" means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).

"Safeguarding" means measures or controls that are prescribed to protect information systems.

(b) Safeguarding requirements and procedures.

(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:

(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).

(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.

(iii) Verify and control/limit connections to and use of external information systems.

(iv) Control information posted or processed on publicly accessible information systems.

(v) Identify information system users, processes acting on behalf of users, or devices.

(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.

(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.

(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.

(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.

(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.

(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.

Document Number: 36C10F24R50025 PROCESSED Page 16 of 59

(xii) Identify, report, and correct information and information system flaws in a timely manner.

(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.

(xiv) Update malicious code protection mechanisms when new releases are available.

(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.

(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.

(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial products or commercial services, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.

(End of clause)

52.219-28 Post-Award Small Business Program Rerepresentation (Feb 2024)

<SPAN style="font-family: Times New Roman; color:#000000; font-size:small"><AMSCLAUSEEDITOR><P>(a) <EM>Definitions</EM>. As used in this clause--</P> <P> </P> <P><EM>Long-term contract</EM> means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.</P> <P> </P> <P><EM>Small business concern</EM>--</P> <P> </P> <P>(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (d) of this clause.</P> <P> </ P> <P>(2) <EM>Affiliates</EM>, as used in this definition, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.</P> <P> </P> <P>(b) If the Contractor represented that it was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (f) of this clause or, if applicable, paragraph (h) of this clause, upon occurrence of any of the following:</P> <P> </P> <P>(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.</P> <P> </P> <P>(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.</P> <P> </P> <P>(3) For long-term contracts--</P> <P> </P> <P>(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and</P> <P> </P> <P>(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.</P> <P> </P> <P>(c) If the Contractor represented that it was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph

(f) of this clause or, if applicable, paragraph (h) of this clause, when the Contracting Officer explicitly requires it for an order issued under a multiple-award contract.</P> <P> </P> <P>(d) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at <EM>https:// www.sba.gov/document/support--table-size-standards</EM>.</P> <P> </P> <P>(e) The small business size standard for a Contractor providing an end item that it does not manufacture, process, or produce itself, for a contract other than a construction or service contract, is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition--</P> <P> </P> <P>(1) Was set aside for small business and has a value above the simplified acquisition threshold;</P> <P> </P> <P>(2) Used the HUBZone price evaluation preference regardless of dollar value, unless the Contractor waived the price evaluation preference; or</P> <P> </P> <P>(3) Was an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.</P> <P> </P> <P>(f) Except as provided in paragraph (h) of this clause, the Contractor shall make the representation(s) required by paragraph (b) and

(c) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause, or with its offer for an order (see paragraph (c) of this clause), that the data have been validated or updated, and provide the date of the validation

Document Number: 36C10F24R50025 PROCESSED Page 17 of 59 or update.</P> <P> </P> <P>(g) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (f) or (h) of this clause.</P> <P> </P> <P>(h) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:</P> <P> </P> <P>(1) The Contractor represents that it <SPAN class="contractingOfficer-Fillin"><INPUT id="(h)(1) is" size="" maxlength="2147483647" description="" compareval="" fillintype="field" usertype="2" value="" mandatory="true" type="checkbox" manualupdate="F"></ SPAN> is, <SPAN class="contractingOfficer-Fillin"><INPUT id="(h)(1) is not" size="" maxlength="2147483647" description="" compareval="" fillintype="field" usertype="2" value="" mandatory="true" type="checkbox" manualupdate="F"></SPAN> is not a small business concern under NAICS Code <SPAN class="contractingOfficer-Fillin"><INPUT id="(h)(1) NAICS Code" size="12" maxlength="2147483647" description="" compareval="" fillintype="field" usertype="2" value="236220" mandatory="true" type="text" manualupdate="F"></SPAN> assigned to contract number <SPAN class="contractingOfficer-Fillin"><INPUT id="(h)

(1) Contract Number" size="20" maxlength="2147483647" description="" fillintype="field" usertype="2" value="" mandatory="true" type="text" manualupdate="F">. (2) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that it is, is not, a small disadvantaged business concern as defined in 13 CFR 124.1001. (3) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that it is, is not a women-owned small business concern. (4) Women-owned small business (WOSB) joint venture eligible under the WOSB Program. The Contractor represents that it is, is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [The Contractor shall enter the name and unique entity identifier of each party to the joint venture: .] (5) Economically…