This document contains a pre-construction checklist and federal contract opportunity notice. The pre-construction checklist outlines requirements for a construction project, including submitting a schedule of costs within 10 days of notice to proceed, providing daily logs to the VA project manager, and complying with safety, change order, subcontractor, payroll, and correspondence standards. The related federal contract opportunity is a pre-solicitation notice for project 578-17-027 to replace steam pipes at the Edward Hines, Jr. VA Hospital. The 100% small business set-aside opportunity has an estimated value between $10-20 million and requires replacing steam pipes and constructing pipe racks and tunnels by a deadline of 730 calendar days from notice to proceed. Interested vendors must be registered in the System for Award Management and certified as an SBA-verified service-disabled veteran-owned small business.

View the file

Other files

File Type Posted
36C25223R0026 0007.docx DOCX document
36C25223R0026 0006.docx DOCX document
S02 SOL 0026 AttG Wage Rate.Rev2 IL20230009_mod7 2023.06.30 current as of 2023.07.13.pdf PDF
S06 36C25223R0026 0005 Att OFFER SCHEDULE.Rev1 578-17-027 2023.07.11.pdf PDF
36C25223R0026 0005.docx DOCX document
S06 36C25223R0026 0004 Att Q6.12.b Spec 028213.13 Glovebag Abatement.pdf PDF
36C25223R0026 0004.docx DOCX document
S06 36C25223R0026 0004 Att Q6.12.a Spec 028211 Asbestos Abatement.pdf PDF
S06 36C25223R0026 0004 Att SOW.R2 578-17-027 2023.07.07.pdf PDF
S06 36C25223R0026 0004 Att OFFER SCHEDULE.Rev1 578-17-027 2023.07.11.pdf PDF
S06 36C25223R0026 0004 Att Q6.10 Photo Stockpile_Trailer.pdf PDF
S06 36C25223R0026 0004 Att Q5.5 Photos.pdf PDF
S06 36C25223R0026 0004 Att Q7.3 Spec 014500 Quality Control.pdf PDF
S06 36C25223R0026 0003.pdf PDF
S06 0003_Att1 36C25223R0026_SOL AttG.R1 Wage Rate Update IL20230009_06.09.2023.pdf PDF
36C25223R0026 0002.docx DOCX document
S06 001 Att1_2 S04 Site Visits Sign-In Sheets 578-17-027 Steam Line-South Leg.pdf PDF
36C25223R0026 0001.docx DOCX document
S02 SOL 0026 AttA-SOW.12) Contractor Parking.pdf PDF
S02 SOL 0026 AttF Seasonal Influenza Vaccination Program 2020.08.10.pdf PDF
S02 SOL 0026 AttA.0 SOW 2023. 578-17-027 2023.04.26.kk.docx DOCX document
S02 SOL 0026 AttA-SOW.19.2) 578-17-027 Replace Steam Pipe South Leg SPECS Volume 2 of 2 Div 22_33 2023.04.21.pdf PDF
S02 SOL 0026 AttA-SOW.18.1b) 578-17-027 Replace Steam Pipe South Leg DWGS Vol 1Bof2 2023.04.21.pdf PDF
S02 SOL 0026 AttA-SOW.13) OIT Horizontal Cable Requirements.pdf PDF
S02 SOL 0026 AttA-SOW.02) Hines Underground Utility Plan.pdf PDF
S02 SOL 0026 AttA-SOW.20) 578-17-027 Replace Steam Pipe South Leg UNCONTAMINATED SOIL REPORT.pdf PDF
S02 SOL 0026 AttA-SOW.17) NOT APPLICABLE.docx DOCX document
S02 SOL 0026 AttB VAAR 852.219-75 Certification 578-17-027.docx DOCX document
36C25223R0026_1.docx DOCX document
S02 SOL 0026 AttA-SOW.16) Hines COVID-19 Guidelines.pdf PDF
S02 SOL 0026 AttA-SOW.01b) Hines VA Campus Site Plan-Building Directory.pdf PDF
S02 SOL 0026 AttD Contractor EMR Safety Info 578-17-027.docx DOCX document
S02 SOL 0026 AttA-SOW.04) Safety and Health During Construction Activities.pdf PDF
S02 SOL 0026 AttC Contractor Info 578-17-027.docx DOCX document
S02 SOL 0026 AttG Wage Rates IL20230009 2023.04.07 current as of 2023.04.25.pdf PDF
S02 SOL 0026 AttA-SOW.18.1a) 578-17-027 Replace Steam Pipe South Leg DWGS Vol 1Aof2 2023.04.21.pdf PDF
S02 SOL 0026 AttA-SOW.05) Cutting Welding and Other Hot Work.pdf PDF
S02 SOL 0026 AttA-SOW.18.2) 578-17-027 Replace Steam Pipe South Leg DWGS Vol2of2 2023.04.21.pdf PDF
S02 SOL 0026 AttA-SOW.08) Pre-Construction Risk Assessment (PCRA).pdf PDF
S02 SOL 0026 AttA-SOW.06) Dig Permit SOP Form.pdf PDF
S02 SOL 0026 AttA-SOW.15) Infection Control Barrier Sample.pdf PDF
S02 SOL 0026 AttA-SOW.10) Interim Life Safety Measures (ILSM).pdf PDF
S02 SOL 0026 AttA-SOW.07) Above Ceiling Entry and Wall Construction Permits.pdf PDF
S02 SOL 0026 AttA-SOW.14) No Smoking Policy 10-1-19.pdf PDF
S02 SOL 0026 AttA-SOW.11) Contractor PIV Instructions and Form.pdf PDF
S02 SOL 0026 Att.A-SOW.01a) Hines VA Campus Site Plan.pdf PDF
S02 SOL 0026 AttE Financial Disclosure 578-17-027.docx DOCX document
S02 SOL 0026 AttA-SOW.19.1) 578-17-027 Replace Steam Pipe South Leg SPECS Volume 1 of 2 Div 00_21 2023.04.21.pdf PDF
S02 SOL 0026 AttA-SOW.09) Infection Control Risk Assessment (ICRA).pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-CONSTRUCTION CHECKLIST

PROJECT: __________________________________________________

DATE: ____________________ CONTRACT: _____________________

1. AUTHORITY OF GOVERNMENT PERSONNEL.

☐ a. The Contracting Officer is the only person authorized to bind the U.S.

Government, and then only to the extent of the authority invested in him/her by the appointment.

☐ b. The VA Project Manager is designated as the Contracting Officer's representative for the purpose of technical supervision and acceptance. The VA Project Manager is responsible for the inspection of the work called for in the contract schedules, including related specifications and contract terms regarding on-site work requirements. Pursuant to the delegation of authority (attached), the Project Manager does not have the authority to make changes to the contract in amount or time.

☐ c. The VA Project Manager for this project is _________________

☐ d. No other office or individual has the authority to act in any manner on behalf of the U.S. Government in the performance of this contract. The VA Project Manager will refer any changes or questions regarding this contract to the Contracting Officer.

2. CONTRACT PROGRESS SCHEDULES AND REPORTS:

☐ a. The Contractor shall submit a schedule of cost to the Contracting Officer within 10 calendar days after date of receipt of the Notice to Proceed.

The approved cost schedule will be one of the bases for determining progress payments for work completed. In accordance with FAR 52.236-1, Performance of Work by the Contractor, the schedule must indicate what portion(s) of the work the contractor intends to perform with his/her own workforce to meet the 15% requirement.

☐ b. The Contractor shall submit a progress chart, with in l O calendar days after issuance of a Notice to Proceed, which indicates the anticipated installation of work versus the elapsed contract time, which shall be represented in the form of a bar graph. The starting date of the schedule shall be the date of the Notice to Proceed and the ending date shall be the original contract completion date.

☐ c. Submittals, samples, and shop drawings. Project Engineer will explain distribution procedures

3. PAYMENT REQUESTS:

☐ a. Payments shall be made monthly by the VA according to the value of completed work from the Contractor's approved Schedule of Costs. All invoices should be submitted to Austin Texas as outlined in the contract. In accordance with the Prompt Payment Act, the fourteen (14) day timeframe for payment shall commence on the date a proper invoice is received by the CO. Included with the pay request shall be the payroll sheets for the Contractor and Subcontractors.

4. PROTECTION OF SURROUNDING AREA:

☐ a. In performing this contract, the Contractor shall provide for protecting the lives and health of employees and other persons, preventing damage to property, materials, supplies, equipment and avoiding work interruptions.

☐ b. Any damage caused by the Contractor or his personnel will be restored and repaired at the expense of the Contractor.

5. DAILY LOGS:

☐ a. The Contractor shall provide the VA Project Manager with daily logs.

Project Engineer will explain frequency. The daily log shall identify the number of laborers, supervisors and each branch of work and will be used to verify payrolls submitted.

6. SAFETY:

☐ a. The VA Safety Officer has the authority to stop work if a serious safety violation is being committed.

7. CHANGES:

☐ a. The Contracting Officer (CO), from information furnished by the COTR may, by a written order, make changes to the drawings and/or specifications that are within the general scope of the contract. No other person is authorized to make revisions, changes, or deletions from the contract.

☐ b. Proposals for changes in work shall be submitted to the Contracting Officer according to the requirements contained in Clauses 52.243-4 and 852.236-88 of the General Conditions. Proposals more than $1,000 must include:

1. Itemized breakdown of labor and material costs.

2. List of subcontractors performing the work.

3. Overhead & Profit percentages.

☐ c. Change Orders (Proceed Orders): There may be some instances (as described in Clause 52.343-4 of the General Conditions) where the need to proceed with a change in work is necessary. In these cases, written authorization will be issued by the Contracting Officer (CO) to proceed with the work. An equitable adjustment will be negotiated within 30 calendar days.

8. SUBCONTRACTORS:

☐ a. The Contractor shall submit a list of subcontractors which will include names and addresses and the nature of work involved (SF 1413). The Contracting Officer reserves the right to disapprove any proposed Subcontractor who has had prior record of unsatisfactory work at this site, or any Federal or non-Federal Agency.

9. LABOR STANDARDS PROVISONS AND PAYROLLS:

☐ a. A copy of the rates and wages shall be posted by the Contractor in a prominent place at the work site.

☐ b. Apprentices will be permitted to work only under a Bona Fide apprenticeship program. Concurrent with or prior to the first payroll listing, certificates of apprenticeship from a recognized council shall be submitted to the Contracting Officer.

10. CORRESPONDENCE:

a. All correspondence from the Contractor shall bear:

☐ (1) Contract Number

☐ (2) Project Title

☐ (3) Project Name

11. OTHER TOPICS SPECIFIC TO THIS PROJECT:

{Signature of Contracting Officer, (CO) Date

Signature of Project Manager, (COR) Date

Signature of Contractor Date:

PROJECT:
DATE:
CONTRACT:
c The VA Project Manager for this project is:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 1:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 2:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 3:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 4:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 5:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 6:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 7:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 8:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 9:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 10:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 11:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 12:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 13:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 14:
Check Box1: Off
Check Box2: Off
Check Box3: Off
Check Box4: Off
Check Box5: Off
Check Box6: Off
Check Box7: Off
Check Box8: Off
Check Box9: Off
Check Box10: Off
Check Box11: Off
Check Box12: Off
Check Box13: Off
Check Box14: Off
Check Box15: Off
Check Box16: Off
Check Box17: Off
Check Box18: Off
Check Box19: Off
Check Box20: Off
Check Box21: Off

File details come from the government source that posted it. Updated .