36C25223R0026 0004.docx

DOCX document 64 KB Posted

Attached to
Z2NZ--578-17-027 Replace Steam Pipe South Leg at Hines
Solicitation number
36C25223R0026
Issued by

About this file

This pre-solicitation notice provides details for an upcoming construction Request for Proposal for Project 578-17-027 Replace Steam Pipe - South Leg at the Edward Hines, Jr. VA Hospital in Hines, Illinois. The project scope includes replacing existing steam pipe between Vault 9 and Vault 7, and between Vault 9 and Pit 5. It is set aside 100% for verified Service-Disabled Veteran-Owned Small Businesses. The estimated value is between $10-20 million. The contract term is a single phase to be completed within 730 calendar days of the notice to proceed. A pre-bid site visit will be held after the RFP is posted to SAM.gov on May 22, 2023. The solicitation will include specifications and drawings. Interested parties should monitor SAM.gov and register in SAM to receive the RFP and any amendments. The Department of Veterans Affairs Veterans Health Administration VISN 12 is the agency overseeing this upcoming construction opportunity.

View the file

Other files

File Type Posted
36C25223R0026 0007.docx DOCX document
36C25223R0026 0006.docx DOCX document
S02 SOL 0026 AttG Wage Rate.Rev2 IL20230009_mod7 2023.06.30 current as of 2023.07.13.pdf PDF
S06 36C25223R0026 0005 Att OFFER SCHEDULE.Rev1 578-17-027 2023.07.11.pdf PDF
36C25223R0026 0005.docx DOCX document
S06 36C25223R0026 0004 Att Q6.12.b Spec 028213.13 Glovebag Abatement.pdf PDF
S06 36C25223R0026 0004 Att Q6.12.a Spec 028211 Asbestos Abatement.pdf PDF
S06 36C25223R0026 0004 Att SOW.R2 578-17-027 2023.07.07.pdf PDF
S06 36C25223R0026 0004 Att OFFER SCHEDULE.Rev1 578-17-027 2023.07.11.pdf PDF
S06 36C25223R0026 0004 Att Q6.10 Photo Stockpile_Trailer.pdf PDF
S06 36C25223R0026 0004 Att Q5.5 Photos.pdf PDF
S06 36C25223R0026 0004 Att Q7.3 Spec 014500 Quality Control.pdf PDF
S06 36C25223R0026 0003.pdf PDF
S06 0003_Att1 36C25223R0026_SOL AttG.R1 Wage Rate Update IL20230009_06.09.2023.pdf PDF
36C25223R0026 0002.docx DOCX document
S06 001 Att1_2 S04 Site Visits Sign-In Sheets 578-17-027 Steam Line-South Leg.pdf PDF
36C25223R0026 0001.docx DOCX document
S02 SOL 0026 AttA-SOW.12) Contractor Parking.pdf PDF
S02 SOL 0026 AttF Seasonal Influenza Vaccination Program 2020.08.10.pdf PDF
S02 SOL 0026 AttA.0 SOW 2023. 578-17-027 2023.04.26.kk.docx DOCX document
S02 SOL 0026 AttA-SOW.19.2) 578-17-027 Replace Steam Pipe South Leg SPECS Volume 2 of 2 Div 22_33 2023.04.21.pdf PDF
S02 SOL 0026 AttA-SOW.18.1b) 578-17-027 Replace Steam Pipe South Leg DWGS Vol 1Bof2 2023.04.21.pdf PDF
S02 SOL 0026 AttA-SOW.13) OIT Horizontal Cable Requirements.pdf PDF
S02 SOL 0026 AttA-SOW.03) Pre-Construction Checklist Rev 07.27.2021.pdf PDF
S02 SOL 0026 AttA-SOW.02) Hines Underground Utility Plan.pdf PDF
S02 SOL 0026 AttA-SOW.20) 578-17-027 Replace Steam Pipe South Leg UNCONTAMINATED SOIL REPORT.pdf PDF
S02 SOL 0026 AttA-SOW.17) NOT APPLICABLE.docx DOCX document
S02 SOL 0026 AttB VAAR 852.219-75 Certification 578-17-027.docx DOCX document
36C25223R0026_1.docx DOCX document
S02 SOL 0026 AttA-SOW.16) Hines COVID-19 Guidelines.pdf PDF
S02 SOL 0026 AttA-SOW.01b) Hines VA Campus Site Plan-Building Directory.pdf PDF
S02 SOL 0026 AttD Contractor EMR Safety Info 578-17-027.docx DOCX document
S02 SOL 0026 AttA-SOW.04) Safety and Health During Construction Activities.pdf PDF
S02 SOL 0026 AttC Contractor Info 578-17-027.docx DOCX document
S02 SOL 0026 AttG Wage Rates IL20230009 2023.04.07 current as of 2023.04.25.pdf PDF
S02 SOL 0026 AttA-SOW.18.1a) 578-17-027 Replace Steam Pipe South Leg DWGS Vol 1Aof2 2023.04.21.pdf PDF
S02 SOL 0026 AttA-SOW.05) Cutting Welding and Other Hot Work.pdf PDF
S02 SOL 0026 AttA-SOW.18.2) 578-17-027 Replace Steam Pipe South Leg DWGS Vol2of2 2023.04.21.pdf PDF
S02 SOL 0026 AttA-SOW.08) Pre-Construction Risk Assessment (PCRA).pdf PDF
S02 SOL 0026 AttA-SOW.06) Dig Permit SOP Form.pdf PDF
S02 SOL 0026 AttA-SOW.15) Infection Control Barrier Sample.pdf PDF
S02 SOL 0026 AttA-SOW.10) Interim Life Safety Measures (ILSM).pdf PDF
S02 SOL 0026 AttA-SOW.07) Above Ceiling Entry and Wall Construction Permits.pdf PDF
S02 SOL 0026 AttA-SOW.14) No Smoking Policy 10-1-19.pdf PDF
S02 SOL 0026 AttA-SOW.11) Contractor PIV Instructions and Form.pdf PDF
S02 SOL 0026 Att.A-SOW.01a) Hines VA Campus Site Plan.pdf PDF
S02 SOL 0026 AttE Financial Disclosure 578-17-027.docx DOCX document
S02 SOL 0026 AttA-SOW.19.1) 578-17-027 Replace Steam Pipe South Leg SPECS Volume 1 of 2 Div 00_21 2023.04.21.pdf PDF
S02 SOL 0026 AttA-SOW.09) Infection Control Risk Assessment (ICRA).pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

07/11/2023 578-23-2-6907-0002 578-23-2-6907-0003 578-17-027 Department of Veterans Affairs

GLAC (69D)

115 South 84th Street, Suite 101 Milwaukee WI 53214-1476 Department of Veterans Affairs

GLAC-MILWAUKEE (69D)

Great Lakes Acquisition Center - HC 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476 To all Offerors/Bidders

36C25223R0026 05-18-2023

X X 23:45 CST, Wednesday, July 19, 2023 X Project 578-17-027 REPLACE STEAM LINE - SOUTH LEG at the Hines VA Hospital in Hines, IL

Amendment 0004 hereby incorporates the attached questions & answers, clarifications, photos, added specifications and revised scope of work details into the solicitation requirements.

Proposal due date has been extended to July 19, 2023 at 23:45 CST (via email) to Kristi.Kluck3@va.gov.

Kristi Kluck Contracting Officer

VA-VHA-2020-8B1E7283

SOLICITATION 36C25223R0026

AMENDMENT 0004

July 11, 2023

Project:578-17-027 Replace Steam Pipe - South Leg
Location:Hines VA Hospital in Hines, IL

AMENDMENT 0004 hereby incorporates the following clarifications/change(s) into the solicitation package:

A. QUESTION 3.0 (Contractor question received 6/6/2023):

3.0
QUESTION: I am submitting Alfrex FR Metal Composite Material for consideration as an acceptable equal to the specified products. We are equal to the other domestic MCM manufacturers, Alucobond, Alpolic, Reynobond, and Alucoil since:

· We use the same aluminum alloy, PPG paints, fire-resistant core type, and manufacturing process.

· We manufacture the same standard product thicknesses, widths, and lengths

· We provide the same finish warranties and product performance warranties

· We are fully tested and product compliant to the same North American building code requirements.

· We have passed the same required fire performance tests for the USA and Canada.

· We all only manufacture MCM panels and supply those panels to the same customer base. It is that customer base which supplies their own proprietary installation systems and final fabricated panel assembly.

· Our manufacturing plant and global headquarters is located in Buford, Georgia USA.

For review I have attached a digital submittal package containing a request for substitution form and supporting documentation, including our ICC-ESR report and project references. Please note that we are typically more price competitive since we manufacture our fire-resistant core material in house, and extremely competitive on custom colors. For additional information, please visit our website at www.alfrexusa.com

VA REPLY:

The User/Engineers have reviewed the samples and noted the following:

The product alternate appears to have functional equivalence with respect to fire resistance, strength, and suitability for outside use. The functional equivalence is based on the contractor providing and implementing design details suitable for outside intended use. For aesthetics equivalence, we had requested samples of the product be reviewed by the concerned VA staff as stated in 07 40 00 - 1.2 and 1.5.

Hines received the seven Alfrex FR samples. None of the samples received match the color of the mansard coping which is a dark brown. Therefore, all seven of these samples would be rejected if submitted based upon the color, even though the composition is an acceptable alternative. Final approval will be subject to color match and composition based upon a post-award, pre-order submittal.

The exact color isn’t specified but Spec 07 40 00 - 1.2.B indicates the following: 1.2.B. Color and texture of finish: Aluminum Composite Material Product Stock, Color Library, Alabaster PVD 2 or Approved Equal.

As long as you can match any of the standard colors of this brand, the Alfrex product would be acceptable. If manufacturer submitted color fails to comply with specified requirement contractor would need to submit a different product the does fulfill contract requirements.

B. QUESTIONS 4.1 & 4.2 - (Contractor question received 6/8/2023):

4.1. Rebar Mftr RFI’s:

Item
Question
Reply
4.1.1
Section 11/SB5.03 cut at the new vaults. It reads that the walls below are existing when they are new. If the construction joint and couplers are required as currently shown, indicate if (a) form saver couplers at the joint with a threaded hook bar or (b) have vertical extend past joint (provide length) and use a mechanical coupler. (c) or we can disregard detail and provide verticals with standard hook (similar to 3/SB503).

They are NEW and not As-Builts. Details 11 and 12 are not applicable- follow Detail 3.

4.1.2
Can we assume the new pier per AA/SB504 and Sheet SB508 is at every new HSS Column on SS104?

This is correct.

4.1.3
Do the Footing and Pier schedules on sheet S001 apply to this project?

No, these are no longer applicable. Footers and piers called out on SB504 and Detail 1 SB508.

4.1.4
Should section callout 1/SB501 on sheet SS100 be 1/SS120? If not, please provide sheet SB501.
Yes, it should be 1/SS120. SB501 does not exist.

4.2 Soils/Utilities

Item
Question
Reply
4.2.1
Request a copy of environmental soil testing reports along the underground piping route

Testing information is shown in spec 33 63 00 Appendix A. Environmental soil testing is performed on a limited segment of steam pipe. UNIT-rate pricing shall be negotiated, post-award.

4.2.2
Soil Spoils that are to be hauled off site are to be assumed clean or is a Subtitle D?
Reference Q&A 4.1.1
4.2.3
Provide instruction at utilities crossing. Are we to assume that we are going under or over existing utilities?

See Profiles on the CU-series drawings.

4.2.4
Request Depth of existing site utilities along steam tunnel route.
See Profiles on the CU-series drawings.

C. QUESTIONS 5.1 – 5.16 (Contractor questions received 6/9/2023):

Item
Question
Reply
5.1
Will the Owner mitigate the extreme heat conditions within the existing structures where the contractor personnel will need to enter for construction purposes? During our site visit it was witnessed that the existing conditions at vault 9 are not compatible with human occupancy.

Vault 9 can be shut down between May and October as long as the west side section of steam line is operational and buildings 217 and 221 receive steam.

5.2
Is the existing underground water main located at new vault 9.2 supplied by multiple directions?

Yes.

5.3
What size are all three legs of this water main that needs to be relocated?

12-inch.

5.4
Can the contractor reutilize the existing pipe, valves, and fittings for the relocation of this water main?
The water main is to be protected as noted on the drawings and remain in place and operational during construction.
5.5
Can the water main be shut down for any length of time? How long of an outage is acceptable?
No. It shall be the contractor’s own means and methods for engineered beams/ saddles/ supports, etc. to span trenches to construct steam tunnel below existing utilities.

See Amendment 0004 “Att Q5.5 photos” of what Hines will accept as an adequate level of support.

5.6
Are there any restrictions for work on the roof of the existing buildings that would affect construction activities such as occupancy below construction?
Follow standard safety precautions for crane lifts, etc. to protect occupants. Quiet hours will be established for noise producing work such as hammer drills, etc.
5.7
Are there any restrictions for opening the roof for penetrations and connecting of new pipe supports or steel?
Do not work in the rain or when inclement weather is forecasted. All roofs must be watertight at the end of each workday.
5.8
Can Earth Retention Systems – Drilled beams and wood lagging – installed for the Vaults construction, remain in place?
Yes, but must be cut and removed 4 feet below finished grade and details added to as-built drawings where they are abandoned.
5.9
Will a water supply be available for Hydro-Vacuum Excavation Trucks? Will contractor be charged for water? If so – what rate will be charged?

Yes. There is no charge to the contractor.

5.10
What is the bottom elevation of the proposed Box Conduits on the north and south sides of Vault 5.3?

See profile on sheet CU-200.

5.11
Existing storm sewers that need to be removed and replaced:

· Drawing CU-100 – 30” S.S / 12” S.S. / 2 each 6” S.S. – what is type of pipe material?

· Drawing CU-200 – 24” S.S. / Unknown S.S. - what is type of pipe material?

· Drawing CU-201 – 30” S.S. – what is type of pipe material?

The existing underground utilities are to be protected as noted on the drawings and remain in place and operational during construction. Refer to the profiles for depths and materials, in general storm sewers are concrete, although there are clay pipes near the older buildings. It shall be the contractor’s own means and methods for engineered beams/saddles/supports, etc. to span trenches to construct steam tunnel below them.

5.12
Please provide voltage of existing electrical lines and what they service? Can any be temporarily put out of service?
Voltages range from 120 VAC to 4160 VAC and shall remain in service at all times.
5.13
Existing Communication – Fiber Optic – CATV lines. Can any be temporarily put out of service?

Communication lines shall remain in service at all times.

5.14
Due to the extent and in some cases - unknown location and/or type of utilities, would the VA consider a Contract Allowance for the protection/relocation of the existing Electrical – Communications – Fiber Optic – CATV lines?
No relocation is required. It shall be the contractor’s own means and methods for engineered beams / saddles / supports, etc. to span trenches to construct steam tunnel below them.
5.15
The existing Natural Gas Line at Station 9+37.73 – shown on Drawing CU-201 – is less than 2’ above the proposed Box Conduit. Please advise as to how this line can be relocated? Will NICOR have to perform the relocation?
No relocation is required. It shall be the contractor’s own means and methods for engineered beams / saddles / supports, etc. to span trenches to construct steam tunnel below the line.
5.16
What CLIN Item on the Offer Schedule should be used for the Steam Pipe installation over the roof and into Vault 7?

CLIN 0005

D. QUESTIONS 6.1 – 6.37 (Contractor questions received 6/9/2023):

Item
Question
Reply
6.1
Please confirm personnel requirements for this project. Can (1) superintendent fulfill SSHO requirements? Or does (1) superintendent and (1) SSHO need to be on site full-time?
Superintendent and (1) SSHO need to be on site full-time while work is being performed. The same person cannot provide both duties and must be provided by the prime contractor.
6.2
23 09 23 Controls Integrator: Please confirm, does the prime contractor have to directly hire the controls integrator, or can the controls integrator be carried by a subcontractor?
It is a single contract where the general contractor shall hire and engage all their subcontractors including a controls integrator.
6.3
Work Hours: Please confirm the work hours for this project. Are there any specific tasks or trade divisions that must be on overtime? Are there any specific areas of work that must be on overtime?

See 5.6 above response

6.4
07 51 13.11 Roofing Warranty: Who holds the current roof warranty? Is there a proprietary roofing contractor required or requested to perform roof work in order to uphold the current warranty?
Building 217 is a Hydrotech roof. Building 221 is a TPO roof. The Outer Corridor Roofs are a combination of both TPO and built-up roof.

Hines holds the warranties for both Buildings 217 and 221. All roof repairs shall be performed by a certified, qualified installer for each roof type.

6.5
Submittal Exchange: Is the contractor responsible for costs associated with submittal exchange platform?
Contractor to provide any construction management software it intends to use on the project. Hines is familiar with Submittal Exchange, Newforma and Procore.
6.6
07 13 54 EVFM Testing: Is the EVFM waterproof testing contractor required to be 3rd-party hired directly by the prime contractor? Or can this be carried out by the waterproofing subcontractor?
Waterproof testing contractor is required to be a 3rd-party entity hired directly by the prime contractor.
6.7
07 84 00 Firestopping Inspector: Is the firestopping inspector referenced in spec section 07 84 00 to be hired directly by the

prime contractor as a 3rd party independent inspector, or can the inspector be a second-tier subcontractor carried by the firestopping contractor?

Firestopping inspector referenced in spec section 07 84 00 is.to be hired directly by the prime contractor as a 3rd party independent inspector.

6.8
Contaminated Soil: Is soil within work area anticipated to be contaminated?

see 4.2 response above

6.9
Contaminated Soil: If encountered, can contaminated soil be used as backfill?

see 4.2 response above

6.10
Stockpiling: Is there a designated location for stockpiling on-site?
See attached images with suggested locations for the stockpile and trailer. The contractor is to protect stockpile site with silt fence. The contractor is to restore stockpile site with clean topsoil and hydroseed.

Electrical service is available in the suggested trailer location. The contractor is responsible for making the electrical connection to their trailer.

The contractor is to include security fencing to protect trailer and laydown area.

The contractor to repair and restore both the stockpile site and the trailer site per specifications and contract drawings.

See Amendment 0004 “Att Q6.10 photos” of what Hines will accept as an adequate level of support.

6.11
Fireproofing: Is fireproofing referenced on page MS104 to be 1-hour or 2-hour rated? Please provide a fireproofing specification section for.

See Details 1 and 2- M502 Schedule; Spec 07 84 00 included.

6.12
Dwg MS104 Asbestos Abatement: Is there asbestos anticipated to be disturbed during construction? If so, please provide an

asbestos report with quantities to be assumed for bidding purposes.

Any asbestos found would be considered an unforeseen condition. Any suspected asbestos should be tested by a qualified testing service as part of the contractor's base scope of work. If the tests come back positive for asbestos, the contractor should notify the COR and CO immediately upon discovery for a potential change order.

Abatement should be addressed per specification 028211 Traditional Asbestos Abatement and/or 028213.13 Glovebag Asbestos Abatement.

Monitoring will be conducted by a 3rd party contractor by the government.

See Amendment 0004 “Att Q6.12a” and “Att Q6.12.b” for new specifications.

6.13
Dwg A100-A500: Option Pricing: Option pricing shown on drawing pages A100-A500 does not match the CLIN Schedule. Please

clarify how pricing is to be submitted No option pricing is required.

Option 1 shall be included in the base proposal as a part of CLIN 0001.

Disregard Options 2 and 3 as they are NOT a part of this solicitation.

6.14
Stair Tower: Will a stair tower be required on Building 217 where piping goes up the exterior wall based on the interior being a high traffic patient area?
Hines does not want the contractor entering the building's patient care areas. In the case of Building 217, the adjacent areas are occupied by patients 24/7/365. Temporary means of accessing Building 217's roof should be provided by the contractor during the construction phase. Whether this is a stair tower or something else is the contractor's means and methods.
6.15
CIH: Will a Certified Industrial Hygenist be required to oversee abatement? Will this cost be the responsibility of the contractor?

See 6.12 response above

6.16
Spec 01 00 00 SIOR: Will the contractor be responsible for costs associated with hiring a Special Inspector of Record?
Specification 01 00 00 makes no mention of a Special Inspector of Record.
6.17
Spec 01 00 00 Commissioning Agent: Will the contractor be responsible for hiring a Commissioning agent?

Specification 01 00 00 makes no mention of Commissioning Agent.

6.18
Cool Suits: Will cool suits be required for personnel protection in hot areas of tunnels?
The safety of the construction personnel is a responsibility of contractor according to their means and methods intended.
6.19
Work Restrictions: Is there any work duration restrictions in tunnels due to high temperatures?
The safety of the construction personnel is a responsibility of contractor according to their means and methods intended.
6.20
Winter Conditions: Should contractor include cost for winter conditions in their proposal?
This project shall be completed within Seven Hundred Thirty (730) calendar days once NTP is issued. It is the contractor's responsibility to complete the work within this timeframe without any adverse impacts to patients, staff, or visitors. The contractor shall include all factors into their cost based upon their planned timeline of events.
6.21
Infection Controls: What level infection control is required for interior work?

Refer to the ICRA attached to the SOW.

6.22
Is the existing underground water main located at new vault 9.2 supplied by multiple directions?

See 5.2 above response

6.23
What size are all three legs of this water main that needs to be relocated?

See 5.3 above response

6.24
Can the contractor reutilize the existing pipe, valves, and fittings for the relocation of this water main?

See 5.4 above response

6.25
Can the water main be shut down for any length of time? How long of an outage is acceptable?

See 5.5 above response

6.26
Are there any restrictions for work on the roof of the existing buildings that would affect construction activities such as occupancy below construction?

See 5.6 above response

6.27
Are there any restrictions for opening the roof for penetration and connecting of new pipe supports or steel?

See 5.7 above response

6.28
Can Earth Retention Systems – Drilled beams and wood lagging – installed for the Vaults construction, remain in place?

See 5.8 above response

6.29
Will a water supply be available for Hydro-Vacuum Excavation Trucks? Will the contractor be charged for water? If so – what rate will be charged?

See 5.9 above response

6.30
What is the bottom elevation of the proposed Box Conduits on the north and south sides of Vault 5.3?

See 5.10 above response

6.31
Existing storm sewers that need to be removed and replaced:

Drawing CU-100 – 30” S.S / 12” S.S. / 2 each 6” S.S. – what is type of pipe material?

Drawing CU-200 – 24” S.S. / Unknown S.S. - what is type of pipe material?

Drawing CU-201 – 30” S.S. – what is type of pipe material?

See 5.11 above response

6.32
Please provide voltage of existing electrical lines and what they service? Can any be temporarily put out of service?

See 5.12 above response

6.37
Existing Communication – Fiber Optic – CATV lines. Can any be temporarily put out of service?

See 5.13 above response

6.33
Due to the extent and in some cases - unknown location and/or type of utilities, would the VA consider a Contract Allowance for the protection/relocation of the existing Electrical – Communications – Fiber Optic – CATV lines?

See 5.14 above responses

6.34
The existing Natural Gas Line at Station 9+37.73 – shown on Drawing CU-201 – is less than 2’ above the proposed Box Conduit. Please advise as to how this line can be relocated. Will NICOR have to perform the relocation?

See 5.15 above responses

6.35
What CLIN Item on the Offer Schedule should be used for the Steam Pipe installation over the roof and into Vault 7?

See 5.16 above responses

6.36
Will the Owner mitigate the extreme heat conditions in the existing structures where the contractor personnel will need to enter for construction purposes? During our site visit it was witnessed that the existing conditions at vault 9 are not compatible with human occupancy.

See 5.1 above response

E. QUESTIONS 7.1 – 7.45 (Contractor questions received 6/9/2023):

Item
Question
Reply
7.1
Please confirm that all the interior work areas are considered ICRA level III, per the issued ICRA report.

Confirmed.

7.2
Is it anticipated that this project will be taken as a single project incorporating all CLINS? Or is there a potential that there will be CLIN/Tasks will be taken separately? The question determines proper application of General Conditions/Overhead/Profit/etc.

At this time, the VA plans to award all CLINs.

7.3
Please provide a Quality Control specification for this project.
See Amendment 0004 “Att Q7.3” for new Specification 014500 Quality Control.
7.4
How many full-time individuals will GC be required to have onsite during performance of work? Do SSHO and QC need to be separate individuals? Or can SSHO & QC be same person?
See 6.1 above responses
7.5
QUESTION: Will contractors be able to be paid for material stored offsite? Given the procurement time periods and environment, it will be important to procure materials as soon as possible in order to meet the project schedule?

ANSWER: The Contracting Officer will consider for monthly progress payments material and/or equipment procured by the Contractor and stored on the construction site, as space is available, or at a local approved location off the site, under such terms and conditions as the Contracting Officer approves, including but not limited to the following—

(1) The materials or equipment are in accordance with the contract requirements and/or approved samples and shop drawings;

(2) The materials and/or equipment are approved by the resident engineer;

(3) The materials and/or equipment are stored separately and are readily available for inspection and inventory by the resident engineer;

(4) The materials and/or equipment are protected against weather, theft and other hazards and are not subjected to deterioration; and

(5) The Contractor obtains the concurrence of its surety for off-site storage.

Additional requirements:

1. Contractor shall provide complete listing of equipment/materials that contractor is requesting payment and date/timeframe when equipment/materials will be delivered/installed at worksite.

2. COR (or other VA official) or AE verify/inspect the equipment/materials and storage area – recommended to take photographic evidence.

3. Contractor provide a Certificate of Insurance listing VA as “ third party Interest” or “Additional Insured” and consent from contractor’s surety for off-site storage.

4. Supplemental Agreement (SA) will be executed between Government & the contractor which includes the off-site storage agreement and signed consent of the contractor’s surety for off-site storage.

NOTE:

1. VA will not pay for off-site storage fees.

2. Upon execution of the supplemental agreement, the contractor may invoice up to (50-80% CO/COR will discuss appropriate %) of the value of the equipment. The balance will be paid after installation and acceptance.

3. Upon payment to the subcontractors for equipment in storage a copy of “Proof of Title”, shall be submitted to the VA. {The contractor, prior to receiving a progress or final payment under this contract, shall submit to the contracting officer a certification that the contractor has made payment from proceeds of prior payments, or that timely payment will be made from the proceeds of the progress or final payment then due, to subcontractors and suppliers in accordance with the contractual arrangements with them.

7.6
Are lifting plans required for setting pipe?
Not for tunnels or trenches as there is no occupied space below them.

Lifting plans are required for work over occupied buildings and spaces.

7.7
Has the proposed piping path been radar scanned for interferences?
No, however surveys (potholing and daylighting) were performed during design.
7.8
What are the construction hours? Are we able to start as early as 6:00 am? Are there any areas that require off-hour work?
At Bldgs 217 and 221, there are established quiet hours. Quiet hours for Building 217 are daily from 11:00 PM to 8:00 AM, but a 10:00 AM start time is preferred.

Quiet hours for Building 221 are daily from 9:00 PM to 7:00 AM. Quiet hours include work no less than 100 feet from the buildings. These restrictions also apply to weekends.

7.9
Can existing pipe be abandoned in place if it does not interfere with new route?
Piping to be removed or abandon in place are indicated as such in Demo drawings.
7.10
Does the VA have a quantity of the amount of pipe that requires flowable fill?
No. The drawings indicated where existing pipes are located and take-offs can be developed from this information.

Post-award change order pricing will be established for the following:

1) Soil disposal - per cubic yard.

2) Asbestos removal of pipe insulation and fittings (traditional) - per linear foot of pipe.

3) Asbestos removal of pipe insulation and fittings (Glovebag) - per linear foot of pipe.

4) Flowable fill for abandoned pipes - per cubic yard.

7.11
Are contractors required to provide trailers and/or storage boxes?
It is not required but the VA will not be providing office or storage space.
7.12
Is the proposed routing located on a flood plain?
See Soil Report analysis- 33 63 00-A.
7.13
Who will be the engineer of record? What are the limits of their responsibility?
Drawings and specs are prepared by USFIN as engineer of record. As needed, the contractor shall supplement or complement the drawings to account for the field conditions; and for temporary shoring and field engineering purposes under the supervision of contractor's professional engineer. Such supplementary information shall be presented for approval by the VA/USFIN engineers
7.14
Who is responsible for testing, for and consequent remediation, of contaminated soils? Testing can be accounted for if required, remediation costs can only be accounted for if VA quantifies.
Testing and remediation shall be the responsibility of contractor See. 4.2 for unit cost reimbursement.
7.15
Is there any asbestos remediation that will be required as part of this contract? Who is responsible for testing for and consequent remediation of, asbestos containing materials? Please quantify if required.

see 6.12 response above

7.16
Is there any lead-based paint remediation that will be required as part of this contract Who is responsible for testing for, and consequent remediation, of lead-based paint? Please quantify if required.

No.

7.17
Will the VA provide laydown/storage areas? If so, where will they be located?

See 6.10 above responses

7.18
Will the VA provide an area for a dumpster? If so, where will that be located?

See 6.10 above responses

7.19
Will the VA provide fabrication areas? If so, where will they be located?

See 6.10 above responses

7.20
Please provide specifications for temporary structures
Temporary structures are part of the contractor's responsibility per their means and methods.
7.21
On Drawing M601, note 6 for the expansion joint schedule requires a 0.625” lateral movement in addition to the design axial movement. Lateral movement for this type of expansion joint is not possible. Please provide clarification.

Zero lateral movement is required

7.22
Are CAD files available for all of the issued drawings?
CAD drawings are available after the contract is awarded.
7.23
The anchor load schedule M601 calls out ANC-09-1-D and ANC-09-1-D as existing. MI003 shows ANC-09-1-D through ANC-09-6-D as existing. Please Clarify.
ANC-09-1-D through ANC-09-6-D are all existing, however, no new analysis was done on ANC-09-1-D and ANC-09-2-D
7.24
Are contractors able to work on federal holidays that are not typical union/labor holidays?

Yes.

7.25
Are there any liquidated damages or other penalties associated with this contract?

No.

7.26
Are employees required to be Covid tested prior to work on site?

No.

7.27
Is WIFI available in the construction areas?
There is guest Wi-Fi in and near the buildings.
7.28
Will owner QA/QC inspection be available at our convenience as long as they are scheduled in advance?

Yes. Notify the COR at least 1 week in advance.

7.29
Are there any new plantings to replace existing trees that are being removed?
No large tree replacement is anticipated, but contractor is responsible for landscaping and restoration afterwards.
7.30
Will the Owner mitigate the extreme heat conditions within the existing structures where the contractor personnel will need to enter for construction purposes? During our site visit it was witnessed that the existing conditions at vault 9 are not compatible with human occupancy.

See 5.1 above response

7.31
Is the existing underground water main located at new vault 9.2 supplied by multiple directions?

See 5.2 above response

7.32
On drawing CD-100, Note 14: What size are all three legs of this water main that needs to be relocated? What is the depth?

See 5.3 above response

7.33
On drawing CD-100, Note 14: Can the contractor reutilize the existing pipe, valves, and fittings for the relocation of this water main?

See 5.4 above response

7.34
Can the water main be shut down for any length of time? How long of an outage is acceptable?

See 5.5 above response

7.35
Earth Retention Systems – drilled beams and wood lagging – installed for the vaults construction, remain in place?

See 5.8 above response

7.36
Will a water supply be available for hydro-vacuum excavation trucks? Will the contractor be charged for water? If so – at what rate will the contractor be charged?

See 5.9 response- Yes-no charge.

7.37
Existing storm sewers that need to be removed and replaced:

See 5.11 above response

7.38
Drawing CU-100 – 30” S.S / 12” S.S. / 2 each 6” S.S. – what is type of pipe material?

See 5.11 above response

7.39
Drawing CU-200 – 24” S.S. / Unknown S.S. - what is type of pipe material?

See 5.11 above response

7.40
Drawing CU-201 – 30” S.S. – what is type of pipe material?

See 5.11 above response

7.41
Please provide voltage of existing electrical lines and what they service. Can any be temporarily put out of service?

See 5.12 above response

7.42
Existing Communication – Fiber Optic – CATV lines. Can any be temporarily put out of service?

See 5.13 above response

7.43
Due to the extent and in some cases - unknown location and/or type of utilities, would the VA consider a Contract Allowance for the protection/relocation of the existing Electrical – Communications – Fiber Optic – CATV lines?

See 5.14 above responses

7.44
The existing Natural Gas Line at Station 9+37.73 – shown on Drawing CU-201 – is less than 2’ above the proposed Box Conduit. Please advise as to how this line is to be relocated? Who is responsible for the relocation: the gas utility provider or the contractor?

See 5.15 above responses

7.45
Will the VA be providing an electronic submittal program, or is it expected that the general contractor provides this? Are there programs or software that are acceptable?

See 6.5 above response

F. QUESTIONS 8.1 – 8.4 (Contractor questions received 6/9/2023):

8.1
1. How current are the utility locations? Is it expected for the contractor to hire an independent utility locate service?
They are current as of November 2022. Contractor to do their own survey per Note 22 on CS-002
8.2
2. When is the RFP due? SAM.gov its on June 22nd. Documents say otherwise.
Proposals and guarantee bonds must be delivered, via email, to Kristi.Kluck3@va.gov Wednesday, 07/19/2023 at 23:45 CST. A hard copy of the guarantee/bid bond is due NLT 16:00 CST, Wednesday, July 19, 2023.
8.3
3. Are there working hours restrictions on the roof of the senior living?

See 5.6 above response

8.4
4. When is the start of the heating season for Hines?
See the SOW (revised copy attached)

F. QUESTIONS 9.1 – 9.12 (Contractor questions received 6/30/2023):

9.1
Are the Underground Leak Detection, Steam Trap Monitoring System, and Sump Pump High Level Water Alarm Systems coming with separate packaged control panels (i.e., panels that have the devices included as noted below for example, steam piping leak detection sensor, pressure condensate return leak detection sensor, strobe/horn)? If so, we need to know if they are coming with a BACnet NIC card, or ModBus NIC card, or other protocol? We need to know how we are picking up the alarm signals? If we are hardwiring to dry contacts, then there’s going to be individual DDC panels installed locally to wherever these systems are going to reside. We cannot seem to find where these systems are being physically installed. The chart below from the drawings indicates one (1) new controller for the Exhaust Fan. But, we still don’t understand if ALL four (4) of these systems are going to reside in the same valve station enclosure where we could install a single controller to connect to NIC cards or, do we need four (4) separate controllers located in four (4) different locations?
See Drawings EP 601, EP500, PL500, M700, Specifications 23 09 23 DDC controls and 22 14 29 Sump pump section 2.1G. Monitoring panels at the Control Room Boiler plant, Control and communication wiring to run with power from each vault to Control Room Boiler plant. DDC controls and Sump pump controls to stay outside the vaults in a cabinet for environmental reasons. EP601 indicates the (5) five new vaults 9.1, 9.2, 5.1, 5.2, and 5.3 will have leak detectors, steam trap monitoring and pumps controllers. Additionally, existing Pit 5 will have exhaust fan and pumps installed. Implementation details, network architecture, communication protocols and components per selected vendor subject to VA approval at submittal.
9.2
Would it be acceptable for the contractor to temporarily shut down Tripp avenue entirely if this work is performed over a weekend, rather than work in one lane at a time during regular hours?
It is the government's opinion this work cannot be performed over a single weekend because there is extensive excavation and concrete tunnel construction involved before the pipe and insulation can be installed. There are several logistical issues to coordinate including but not limited to the PACE bus service and emergency services. However, Hines is open to discuss options to perform the tunnel work on Vault 9 as it crosses Tripp Ave. that may include road closure or a temporary re-route. The contractors are instructed to base their cost estimates on the contract documents. Any options regarding means and methods can be discussed with the winning contractor after award and a modification to the contract may be executed.
9.3
Detail 5 / SB700 shows waterproofing membrane around entirety of the box conduit, however this seems to contradict detail 1 / SB502 which shows the precast plank “to be removeable for future access.” Detail 5 / SB700 also indicates an additional box conduit top between the waterproofing layer and precast panel, however this is not indicated anywhere else in the drawing set and seems to obstruct the ability to remove the precast planks for future access. Please clarify how this precast plank is to be attached to the box conduit and how it is to be sealed watertight?

For future maintenance work, Precast Plank is removable. After work is completed, the Precast Plank is to be re-mounted and water proofing to be re-applied and restored.

9.4
Details 1&2 on page SB516 show a new steel assembly, however no other drawings within the plan set tag this detail as a point of reference. Please clarify where these details are intended to be implemented?

See SS103, MS103, MS104 - Refers to Bldg. 221/217 walkway

9.5
Will it be acceptable to drive the soldier piles for ERS with a hammer? There would be noise associated with this, but the vibrations are not dangerous (structurally)
Yes, a pile driver may be used and working hours are to be coordinated with the quiet hours at the patient care facilities.

Also, see Q&A 5.6 above "Follow safety precautions for crane lifts, etc. to protect occupants. Quiet hours will be established for noise producing work such as hammer drills, pile driving, excavation, etc. Quiet hours for Building 217 are daily from 11:00 PM to 8:00 AM but 10:00 AM is preferred. Quiet hours for Building 221 are daily from 9:00 PM to 7:00 AM. This applies to weekends as well."

9.6
During our site visit it was evident that the existing conditions within these structures would not allow humans to enter without changing the environmental conditions within these structures. We cannot determine whether the existing systems are faulty or that we could possibly be able to vent these structures effectively for personnel to enter. For this reason, we ask if the VA will be able to remediate the existing site conditions that will allow for opening these structures and allowing our personnel to enter this space to work safely?
Vault 9 can be shut down between May and October as long as the west side section of steam line is operational and Buildings 217 and 221 receive steam. Contractor is to determine safe means and methods to be implemented on this project. In this case, it may include forced ventilation. Contractor to assess and submit requirements for working in any confined space.
9.7
There are no details of how to tie in the steam and condensate at pit #5. Are we to assume that we are to tie into the existing Perm-a-pipe on the outside of this structure?
See Dwg M502 – FLASH TANK DETAIL PIT 5. Pump and Flash tank tie-ins are inside the pit.
9.8
Various hanger designs are shown within the new vaults themselves. Some show hangers from roof structures and some from floor supports. What should we assume to use in these structures or is this up to the contractor’s discretion?

See Dwg SB523, SB524 SB526 typical for using Epoxy Adhesive Hilti anchors

9.9
If coal contaminated soils are encountered, who will be responsible for the testing of the soils and determining the limits of the coal contaminated soils? The Contracts Documents already include the IEPA LPC-663 Clean Soils Certification for the existing soils. The extent of any coal contaminated soil cannot be quantified
According to survey samples in the solicitation documents, the soil is not contaminated. The contractor shall perform its own due diligence per the requirement of its selected CCD ( Clean Construction and Demolition Debris) Facility. For any contamination discovered, the differential soil disposal cost imposed by its CCD facility for the contaminated soil shall be addressed in a change order.
9.10
Where are the locations of the quazite in ground pull boxes to be? Seeing that these new vaults all have new steam box conduits going to them per the design shown on the drawings?
After award, the contractor shall setup a meeting with the VA's representatives to field locate and coordinate position.
9.11
Please confirm the parking lot near Building 27 is to be patched only, rather then having a complete mill and overlay.
Assuming this question actually refers to the Building 37, not Building 27, parking lot. The Parking Lot for B37 will not require a full mill & overlay. The drawings show full-depth pavement restoration where the parking lot is disturbed to install the new box conduit and vault. The pavement restoration extent shown would be more than what is shown if any portion of the box conduit trench is open cut, rather than shored, as assumed in drawings where the alignment crosses under existing road, driveway, or parking lot pavement.
9.12
Please provide wiring schematic showing engineer’s intent for monitoring sump pumps. Is it the intent to monitor these sump pumps remotely? If so, from where and how many wires and sizes are there from each vault? Or is the intent to monitor these sump pumps at the control panels at each vault

Please refer to Question 9.1 above

G. (10) VA General Comments: The following clarifications and Items are requested to be noted by the bidder. Bidders to include all required material and labor costs. Revised drawings, where needed, shall be made part of awarded contract

10.1
All items listed on the Scope of Work document shall be made part Drawing General Note. G101.
10.2
Contractor shall complement stress analysis presented in the bid documents with its own stress analysis per submittal requirements of specification 336300 specification to ensure workability of the design based on field conditions as verified by the contractor.
10.3
The drawing detail indicated on the Drawing M501, MI005 indicate steam tracing of condensate line. It should be electrical heat tracing instead of steam tracing. Revised drawing note to read: IN LIEU OF STEAM HEAT TRACING SHOWN, CONTRACTOR TO PROVIDE ELECTRIC HEAT TRACING. SHOULD INCLUDE CABLING, POWER SOURCE, AND ALL OTHER ANCILLARY DEVICES TO REGULATE TEMPERATURE. ELECTRIC HEAT TRACING TO BE RATED FOR HIGH TEMPERATURE OF 400 DEGREES F.
10.4
Contractor shall provide unit cost of the following items to cover changes from the drawing due to field conditions with supports:

a. 12-inch dia. underground steam line cost per ft with insulations.

b. 2-inch dia. underground steam line cost per ft with insulations.

c. 6-inch dia. underground condensate line cost per ft with insulations.

d. 12-inch dia. aboveground steam line cost per ft with insulations.

e. 2-inch dia. aboveground steam line cost per ft with insulations.

f. 6-inch dia. aboveground condensate line cost per ft with insulations.

g. 1.5-inch dia. aboveground steam line cost per ft with insulations.

h. Concrete tunnel, 7.5 (CLIN 2A) 7 ft (CLIN 1) wide by 6 ft higgh, per ft constructed typical per design without the cost of steam and condensate cost. Shown SB502

i. Cost of excavation and fill per cubic ft for non-contaminated soil.

j. Cost of excavation and fill per cubic ft for contaminated soil - where discovered.

These unit costs must include labor, material, equipment, overhead, profit, insurance and bonds.

See Amendment 0004 “Att OFFER SCHEDULE.Rev1 578-17-027 2023.07.11” for revised CLIN breakdown that should be included with proposal.

10.5
Steam drip leg connection to condensate line is shown with a single sparger. For two-way connection flexibility and redundancy a double sparger system instead shall be used with additional valving. Revised Drawings. MS404, MS405, MI003, MI004 will be issued with finalized contract drawings at time of award.
10.6
Contractor shall provide an ADA crossing work at Tripp Avenue – boiler plant. Updated ES001 and Civil Details CI500 will be issued with finalized contract drawings at time of award.
10.7
Steam trap conflict resolved per VA directive. Drawings indicate Thermodynamic Spirax Sarco TD52 steam trap stainless steel changed to Inverted Bucket Spirax Sarco HM34 (carbon steel body and stainless-steel internals). Updated Drawing M602 will be issued with finalized contract drawings at time of award.

ITEM 8 - QUESTION 11.1 (Contractor question received 7/6/2023):

11.1
“Pumps in existing vaults are not equipped to meet the new 200-degree operating requirement , weil pumps, and primary controls. This is the case in multiple locations including vaults #9, #8, #6, #1, #10, #11, #2, #3, #12, and #7). Please clarify”
Refer to Task 1 of the SOW. Contractor to provide new controllers (3.a.3) in new above ground enclosures (3.a.1).

The following item has been added to the SOW:

"3.a.8. Provide and install new high temperature (200°F) critical duty pumps for each vault to replace the existing pumps. Return old pumps to the Hines pipe shop for condition evaluation to stock as spare parts."

See Amendment 0004 “Att SOW.R2 578-17-027 2323.07.07” for new updated details.

A revised copy of the proposal summary sheet is attached. This must be filled out and included with your proposal.

A hard copy of the guarantee/bid bond is due NLT 16:00 CST, Wednesday, July 19, 2023.

Proposals must be delivered, via email, to Kristi.Kluck3@va.gov NLT Wednesday, July 19, 2023 at 23:45 CST.

ATTACHMENTS

See attached document: S06 36C25223R0026 0004 Att Q5.5 Photos.

See attached document: S06 36C25223R0026 0004 Att Q6.10 Photo Stockpile_Trailer.

See attached document: S06 36C25223R0026 0004 Att Q6.12.a Spec 028211 Asbestos Abatement.

See attached document: S06 36C25223R0026 0004 Att Q6.12.b Spec 028213.13 Glovebag Abatement.

See attached document: S06 36C25223R0026 0004 Att Q7.3 Spec 014500 Quality Control.

See attached document: S06 36C25223R0026 0004 Att SOW.R2 578-17-027 2023.07.07.

See attached document: S06 36C25223R0026 0004 Att OFFER SCHEDULE.Rev1 578-17-027 2023.07.11.