S02_ICVA-Dialysis_CD_SpecVol1_20251210.pdf

PDF 4 MB Posted

Attached to
Z1DA--Renovate Dialysis PN: 636A8-24-001 Iowa City, IA
Solicitation number
36C26326B0005
Issued by

About this file

This document is a comprehensive technical specification for asbestos floor tile and mastic abatement for the Iowa City VA Health Care System. The project involves renovating the Dialysis Clinic, with work to be performed in multiple phases including preparing a temporary dialysis clinic and then renovating 5,000 square feet of the existing clinic. The solicitation is specifically set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under the Veterans First Contracting Program, with an expectation of receiving offers from at least two SDVOSB construction firms.

The technical specification provides extensive detailed requirements for asbestos abatement, including strict protocols for containment, personnel protection, respiratory safety, decontamination procedures, air monitoring, and waste disposal. Key requirements include maintaining negative air pressure in regulated areas, using specific personal protective equipment, conducting air quality testing, and following precise removal and cleanup procedures. The contractor must be prepared to handle approximately 10 square feet of gray adhesive on wall plaster, with comprehensive documentation, safety, and environmental compliance mandated throughout the abatement process.

View the file

Other files

File Type Posted
AS06_Amend 0004_ICVA-Dialysis_ADD1_Narrative.pdf PDF
AS06_DBA WD_IA20260068_2Jan26.pdf PDF
AS06_Amend 0004_SOW Rev 2_Reno Dialysis_IC.pdf PDF
AS06_Amend 4_Round 2 Questions_Reno Dialysis.pdf PDF
AS06_Amend 0004_ICVA-Dialysis_ADD1_SpecVol1.pdf PDF
AS06_Amend 0004_ICVA-Dialysis_ADD1_SpecVol2.pdf PDF
AS06_Amend 0004_ICVA-Dialysis_ADD1_Sheets_fullset.pdf PDF
AS06_36C26326B0005_Amendment 0004.pdf PDF
AS06_Amend 0004_PreBid Site Visit Sign-In_Reno Dialysis.pdf PDF
AS06_Amend 0004__Pre-Bid Site Walk QAs_Reno Dialysis.pdf PDF
AS06_Amend 0004_ICVA-Dialysis_ADD1_SpecVol3.pdf PDF
AS06_Amend 0004_SOC Building 1 and Bldg 50 2023.pdf PDF
AS06_36C26326B0005_Amendment 0003.pdf PDF
AS06_36C26326B0005_Amendment 0002.pdf PDF
AS06_Amendment_36C26326B0005 0001_Reno Dialysis_IC.pdf PDF
AS06_Contracting Officers Special Information and Instructions_Revised.docx DOCX document
S02_VAAR 852.219-75_VA Notice of Limitations on Subcontracting.pdf PDF
S02_BNJ_Signage_Reno Dialysis_IC_Redacted.pdf PDF
S02_BNJ_Nurse Call Sys_Reno Dialysis_IC_Redacted.pdf PDF
S02_BNJ_Elec Panel Boards_Reno Dialysis_IC_Redacted.pdf PDF
S02_BNJ_ACS_Reno Dialysis_IC_Redacted.pdf PDF
S02_SSJ_BAS_Reno Dialysis_IC_Redacted.pdf PDF
S02_CD Narrative_Reno Dialysis_IC.pdf PDF
S02_CD_Drawings_Reno Dialysis_IC.pdf PDF
S02_BNJ_Code Green Sys_Reno Dialysis_IC_Redacted.pdf PDF
S02_SOW TMS 20939.pdf PDF
S02_BNJ_Speakers_Reno Dialysis_IC_Redacted.pdf PDF
S02_BNJ_Patient Lifts_Reno Dialysis_IC_Redacted.pdf PDF
S02_BNJ_Fire Alarm Hardware_Reno Dialysis_IC_Redacted.pdf PDF
S02_BNJ_Door Cylinders_Reno Dialysis_IC_Redacted.pdf PDF
S02_CD_Spec Vol 3_Reno Dialysis.pdf PDF
S02_ICVA-Dialysis_CD_SpecVol2_20251210.pdf PDF
S02_DBA WD_IA20250068_12Dec25.pdf PDF
S02_SOW NARA Contract Language.pdf PDF
S02_Final SOW_Reno Dialysis_IC.pdf PDF
S02_36C26326B0005_IFB_Reno Dialysis_IC.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Anderson Engineering of Minnesota, LLC

13605 1st Avenue North

Plymouth, MN 55441

Phone: 763-412-4000 Fax: 763-412-4090

Prepared in association with the following:

IMEG Corp 2882 106th Street

Des Moines, IA 50322 Phone: 515-334-9906

Renovate Dialysis

VA PROJECT NUMBER: 636A8-24-001

601 HWY 6 West

Iowa City, IA 52246

TECHNICAL SPECIFICATIONS

Volume 1: DIVISIONS 00 - 14

ANDERSON ENGINEERING OF MN, LLC

Project Number: 17909

Issue for

Construction Documents

April 24, 2025

Iowa City VA Health Care System VA Project 636A8-24-001

Renovate Dialysis April 24, 2025

601 HWY 6 West CONSTRUCTION DOCUMENTS

Iowa City, IA 52246

CERTIFICATIONS PAGE

Architect and Coordinating Professional:

Typed or Printed Name: Thomas Allen Olesak

License Number: ARC07582

License Expiration Date: 06/30/2025

Professional Engineer: (Structural)

Typed or Printed Name: Adam Adams

License Number: P22449

License Expiration Date: 12/31/2025

04/24/2025

601 HWY 6 West CONSTRUCTION DOCUMENTS

Iowa City, IA 52246

Professional Engineer: (Mechanical, Medical Gas, Plumbing, Fire Protection)

Typed or Printed Name: Dellan Llewellyn

License Number: P27052

License Expiration Date: 12/31/2026

Professional Engineer: (Electrical, Technology)

Typed or Printed Name: Kristen L. Spina

License Number: P21081

License Expiration Date: 12/31/2025

- - - END - - -

nder the laws of the St

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 06-01-24

00 01 10-1

TABLE OF CONTENTS

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21 01 32 16.15 Project Schedules Small Projects – Design/Bid/Build 01-24 01 33 23 Shop Drawings, Product Data, and Samples 11-23 01 35 26 Safety Requirements 05-24 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 57 19 Temporary Environmental Controls 01-21 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 04-22 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 04-22

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17 02 82 13.13 Glovebag Asbestos Abatement 01-21 02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21 02 82 13.31 Asbestos Transite Abatement 01-21

DIVISION 03 – CONCRETE

03 30 53 (Short-Form) Cast-in-Place Concrete 01-21

DIVISION 04 – MASONRY

DIVISION 05 – METALS

05 50 00 Metal Fabrications 08-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 06-01-24

00 01 10-2

TABLE OF CONTENTS

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation 01-21 07 01 50.19 Preparation for Re-Roofing 01-21 07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 04-22

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21 08 14 00 Interior Wood Doors 01-21 08 31 13 Access Doors and Frames 04-22 08 32 13 ICU Sliding Doors 08 71 00 Door Hardware 03-24 08 71 13 Automatic Door Operators 01-21 08 80 00 Glazing 01-21

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 30 00 Specialty Moldings and Trim 01-23 09 30 13 Ceramic/Porcelain Tiling 01-21 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 01-21 09 65 16 Resilient Sheet Flooring 06-22 09 91 00 Painting 01-21 09 96 59 Resinous Specialty Glazed Coating Systems for Walls, Ceilings, Wallboard, and Block CMU (RES-W1, RES-W2) 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21 10 21 23 Cubicle Curtain Tracks 01-21 10 26 00 Wall and Door Protection 01-21 10 28 00 Toilet, Bath, and Laundry Accessories 01-21 10 44 13 Fire Extinguisher Cabinets 08-18

DIVISION 11 – EQUIPMENT

11 05 12 General Motor Requirements for Equipment 01-21 11 73 00 Ceiling Mounted Patient Lift System 08-20 11 73 00.1 Ceiling Mounted Patient Lift System Checklist Rev 2.1

DIVISION 12 – FURNISHINGS

12 24 00 Window Shades 08-17 12 32 00 Manufactured Wood Casework 01-21

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 06-01-24

00 01 10-3

TABLE OF CONTENTS

SECTION NO DIVISION AND SECTION TITLES DATE

12 36 00 Countertops 12-23

DIVISION 21- FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 01-23 22 05 19 Meters and Gages for Plumbing Piping 09-20 22 05 23 General-Duty Valves for Plumbing Piping 09-20 22 07 11 Plumbing Insulation 09-19 22 11 00 Facility Water Distribution 05-21 22 13 00 Facility Sanitary and Vent Piping 09-20 22 40 00 Plumbing Fixtures 05-24 22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 05-23 22 63 00 Gas Systems for Laboratory and Healthcare Facilities 05-23

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 03-23 23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 03-23

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment

03-23

23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 03-23 23 09 23 Direct-Digital Control System for HVAC 03-23 23 25 00 HVAC Water Treatment 03-23 23 31 00 HVAC Ducts and Casings 03-23 23 34 00 HVAC Fans 03-23 23 36 00 Air Terminal Units 03-23 23 37 00 Air Outlets and Inlets 03-23

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 11-22 26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22 26 05 26 Grounding and Bonding for Electrical Systems 11-22 26 05 33 Raceway and Boxes for Electrical Systems 11-22 26 05 73 Overcurrent Protective Device Coordination Study 11-22 26 08 00 Commissioning of Electrical Systems 11-22 26 09 23 Lighting Controls 11-22 26 24 16 Panelboards 11-22 26 27 26 Wiring Devices 11-22 26 29 11 Motor Controllers 11-22 26 29 21 Enclosed Switches and Circuit Breakers 11-22

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 06-01-24

00 01 10-4

TABLE OF CONTENTS

SECTION NO DIVISION AND SECTION TITLES DATE

26 43 13 Surge Protective Devices 11-22 26 51 00 Interior Lighting 03-24

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19 27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Raceways and Boxes for Communications Systems 10-18 27 05 61 Leased Space, Communication Equipment and Systems 06-15 27 08 00 Commissioning of Communications Systems 11-16 27 11 00 Telecommunications Room Fittings 06-15 27 15 00 Communications Structured Cabling 01-16 27 52 23 Nurse Call and Code Blue Systems 10-18

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and

Security 10-18

28 05 26 Grounding and Bonding for Electronic Safety and Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and Security

09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16 28 13 00 Physical Access Control System 10-11 28 31 00 Fire Detection and Alarm 10-11

APPENDICES –INFORMATION AND REPORTS

Appendix A – Pre-Renovation Asbestos Survey Appendix B – Reverse Osmosis Information Appendix C – VA Provided Risk Assessment Informaton

- - - E N D - - -

601 HWY 6 West CONSTRUCTION DOCUMENTS

Iowa City, IA 52246 05-01-20

00 01 15 - 1

LIST OF DRAWING SHEETS

SECTION 00 01 15

LIST OF DRAWINGS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

1-I1 COVER SHEET

1-I2 ABBREVIATIONS

1-I3 5TH FLOOR - LIFE SAFETY PLAN

1-I4 INFECTION CONTROL AND PHASING NOTES

1-I5 3RD AND 4TH FLOOR - INFECTION CONTROL & PHASING PLAN

1-I6 5TH FLOOR - INFECTION CONTROL & PHASING PLAN

1-I7 ICRA DETAIL

HAZARDOUS MATERIAL

HA001 5TH FL – HAZARDOUS MATERIAL ASBESTOS ABATEMENT

STRUCTURAL

1-S1 FIFTH FLOOR FRAMING PLAN

1-S2 SIXTH FLOOR / ROOF FRAMING PLAN

ARCHITECTURAL

1-A1 5TH FLOOR - OVERALL PLAN

1-A2 5TH FLOOR - DEMOLITION PLAN - ZONE 1

1-A3 5TH FLOOR - DEMOLITION PLAN - ZONE 2

1-A4 5TH FLOOR – PARTIAL FLOOR PLAN - ZONE 1

1-A5 5TH FLOOR – PARTIAL FLOOR PLAN - ZONE 2

1-A6 5TH FLOOR – PARTIAL REFLECTED CEILING PLAN

1-A7 ENLARGED PLANS AND INTERIOR ELEVATIONS

1-A8 MOUNTING HEIGHTS

1-A9 OPENING SCHEDULE, TYPES, AND DETAILS

1-A10 PARTITION TYPES AND DETAILS

1-A11 PLAN DETAILS

1-A12 INTERIOR SECTION DETAILS AND CASEWORK GENERAL NOTES

1-A13 ENLARGED RCP AND CEILING DETAILS

1-A14 5TH FLOOR - FINISH PLAN – ZONE 1

1-A15 MATERIAL AND ROOM FINISH SCHEDULE – ZONE 1

1-A16 5TH FLOOR - WAYFINDING PLAN AND SIGN MESSAGE SCHEDULE

1-A17 SIGNAGE DETAILS

601 HWY 6 West CONSTRUCTION DOCUMENTS

Iowa City, IA 52246 05-01-20

00 01 15 - 2

LIST OF DRAWING SHEETS

1-A18 5TH FLOOR - FURNITURE PLAN – ZONE 1

1-A19 5TH FLOOR - FURNITURE PLAN - ZONE 2

1-A20 5TH FLOOR - EQUIPMENT PLAN

FIRE PROTECTION

1-F1 FIRE PROTECTION COVERSHEET

1-F2 FIFTH FLOOR DEMOLITION PLAN - ZONE 1 - FIRE PROTECTION

1-F3 FIFTH FLOOR PLAN - ZONE 1 - FIRE PROTECTION

1-F4 FIRE PROTECTION DETAILS

PLUMBING

1-P1 PLUMBING COVERSHEET

1-P2 THIRD FLOOR DEMOLITION PLAN - ZONE 1 - PLUMBING

1-P3 FOURTH FLOOR DEMOLITION PLAN - ZONE 1 - PLUMBING

1-P4 FIFTH FLOOR DEMOLITION PLAN - ZONE 1 - PLUMBING

1-P5

FIFTH FLOOR - ABANDON PIPING DEMOLITION - ZONE 1 -

PLUMBING

1-P6 THIRD FLOOR PLAN - ZONE 1 - PLUMBING

1-P7 FOURTH FLOOR PLAN - ZONE 1 - PLUMBING

1-P8 FIFTH FLOOR PLAN - ZONE 1 - PLUMBING

1-P9 FIFTH FLOOR PLAN - ZONE 2 - PLUMBING

1-P10 PLUMBING DIAGRAMS

1-P11 PLUMBING DETAILS

1-P12 PLUMBING SCHEDULES

MEDICAL GAS

1-MG1 MEDICAL GAS COVERSHEET

1-MG2 FIFTH FLOOR DEMOLITION PLAN - ZONE 1 - MEDICAL GAS

1-MG3 FIFTH FLOOR PLAN - ZONE 1 - MEDICAL GAS

1-MG4 MEDICAL GAS DETAILS

MECHANICAL HVAC

1-H1 HVAC COVERSHEET

1-H2 FIFTH FLOOR DEMOLITION PLAN - ZONE 1 - HVAC

1-H3 SIXTH FLOOR DEMOLITION PLAN - ZONE 1 - HVAC

1-H4 FIFTH FLOOR PLAN - ZONE 1 - VENTILATION

1-H5 SIXTH FLOOR PLAN - ZONE 1 - VENTILATION

1-H6 FIFTH FLOOR PLAN - ZONE 1 - PIPING

1-H7 HVAC DETAILS

1-H8 HVAC DETAILS

601 HWY 6 West CONSTRUCTION DOCUMENTS

Iowa City, IA 52246 05-01-20

00 01 15 - 3

LIST OF DRAWING SHEETS

1-H9 HVAC DIAGRAMS

1-H10 HVAC SCHEDULES

ELECTRICAL

1-E1 ELECTRICAL COVERSHEET

1-E2 ELECTRICAL LIGHTING COVERSHEET

1-E3 FIFTH FLOOR DEMOLITION PLAN - ZONE 1 - ELECTRICAL

1-E4 FIFTH FLOOR PLAN - ZONE 1 - LIGHTING

1-E5 FIFTH FLOOR PLAN - ZONE 1 - POWER

1-E6 FIFTH FLOOR PLAN - ZONE 2 - POWER

1-E7 SIXTH FLOOR PLAN - ZONE 1 - POWER

1-E8 ELECTRICAL DETAILS

1-E9 ELECTRICAL DIAGRAMS

1-E10 ELECTRICAL SCHEDULES

1-E11 ELECTRICAL PANEL SCHEDULES

TECHNOLOGY

1-T1 TECHNOLOGY COVERSHEET

1-T2 SECOND FLOOR PLAN - TECHNOLOGY

1-T3 FIFTH FLOOR DEMOLITION PLAN - ZONE 1 - TECHNOLOGY

1-T4 FIFTH FLOOR DEMOLITION PLAN - ZONE 2 - TECHNOLOGY

1-T5 FIFTH FLOOR PLAN - ZONE 1 - TECHNOLOGY

1-T6 FIFTH FLOOR PLAN - ZONE 2 - TECHNOLOGY

1-T7 TECHNOLOGY ENLARGED PLANS

1-T8 TECHNOLOGY DETAILS

1-T9 TECHNOLOGY DETAILS

1-T10 TECHNOLOGY RISER DIAGRAMS

1-T11 TECHNOLOGY RISER DIAGRAMS

1-T12 TECHNOLOGY SCHEDULES

ELECTRICAL SYSTEMS

1-FA1 ELECTRICAL SYSTEMS COVERSHEET

1-FA2 FIFTH FLOOR DEMOLITION PLAN - ZONE 1 - SYSTEMS

1-FA3 FIFTH FLOOR PLAN - ZONE 1 - SYSTEMS

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -1

GENERAL REQUIREMENTS

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work as required by drawings and specifications.

B. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting Officer.

C. Offices of Anderson Engineering of MN, LLC, as

Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -2

GENERAL REQUIREMENTS

permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

F. Normal working hours for this contract will be from 7:00AM to 4:30PM (local time) Monday through Friday except for weekends and established Federal Holidays.

1. Performing on-site work outside normal working hours will require approval from the Contracting Officer and the

COR. Requests shall be submitted via email at least 72 hours prior to the requested date and at no additional cost to the Government. Approvals are subject to the availability of on-site staff.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, necessary removal of existing structures and construction and certain other items. Work includes all labor, material, equipment, and supervision to perform the required demolition and construction work on this project including Hazardous Material Abatement, Structural and Architectural Modifications, Equipment, Fire

Protection Systems, Plumbing Systems, Mechanical Systems, Electrical Systems, and Telecommunication Systems as described in the Basis of Design and Indicated on the

Construction Documents.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -3

GENERAL REQUIREMENTS

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. The General Contractor’s employees shall not be permitted at the Iowa City VA Medical Center without an appropriate badge. Employees that will be on site for less than 5 business days throughout the entirety of the project must be escorted by an existing badge holder. For all other employees, the VA will conduct the appropriate background investigation based on the individual employee’s access needs.

2. In order to initiate the background check and badge request, the General Contractor shall submit the following documents to the VA COR at least one month before starting work for every employee that requires a badge:

a. Declaration of Federal Employment

b. OF 306

c. Contractor Background Investigation Request

d. Self-Certification of Continuous Service

e. Contractor Request Form

3. Following submittal of the background check documents to the VA COR, the General Contractor shall ensure their employee makes an appointment with the VA to provide their fingerprints. Employees shall bring a completed

Fingerprint Request Form with them to their

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -4

GENERAL REQUIREMENTS

fingerprinting appointment. Fingerprints are required by the VA as part of the background check process.

4. Favorable adjudication of the background investigation and badge issuance is required before the employee shall be permitted on site. Processing times vary and could take up to several months.

5. General Contractor’s employees may also be subject to inspection of their personal effects when entering or leaving the project site.

6. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

7. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The

General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Guards: Not used.

D. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall install all permanent cores at completion of the work. See Section 08 71 00, DOOR

HARDWARE and coordinate.

E. Document Control:

1. Before starting any work, the General Contractor/Sub

Contractors shall submit an electronic security

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -5

GENERAL REQUIREMENTS

memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or

“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of

“sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an

Engineering Document Management Software (EDMS).

Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

F. Motor Vehicle Restrictions

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -6

GENERAL REQUIREMENTS

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access.

Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of permits shall be issued for General

Contractor and its employees for parking in designated areas only. A maximum of 2 parking permits will be provided. Parking spaces are not guaranteed. Carpooling will be required. Contractor to coordinate with VA

Medical Center Facility Manager.

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The

Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the

Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the

Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -7

GENERAL REQUIREMENTS

as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as shown on the drawings as determined by the COR

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.

Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by

Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

sha

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -8

GENERAL REQUIREMENTS

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of

Contractor's materials and equipment will be permitted subject to fire and safety requirements.

G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the

Contractor.

H. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

The work to be outlined shall include, but not be limited to:

To ensure such executions, Contractor shall furnish the

COR with a schedule of approximate phasing dates on which

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -9

GENERAL REQUIREMENTS

the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.

Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor, as follows:

Phase I: Prepare 5 Floor West (Zone 2) for temporary Dialysis

Clinic. Construct wall and door 5CW01A in Zone 2a.

Provide 14 days between phase 1 and 2 to allow for the

VA to remove equipment prior to demo/construction.

Phase II: Construct enclosure around decontamination unit and remove asbestos-containing building elements.

Phase III: Demolish 5 Floor South (Zone 1) as described in construction documents and prepare elements for new construction.

Phase IV: Cap and remove piping in 4 Floor ceiling. Replace sanitary pipe on 3 Floor.

Phase V: Construct 5 Floor South (Zone 1) including work on roof above and floors below as necessary.

Phase VI: Restore 5 Floor West (Zone 2) to pre-existing condition or better. Reinstall replaced lavatory and removed bathroom doors. Take care that each door is reinstalled in same frame as before Phase I. Remove wall and door 5CW01A in Zone 2a. Patch walls in Zone

2a.

I. Building No. 1 will be occupied during performance of work;

but immediate areas of alterations will be vacated.

1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -10

GENERAL REQUIREMENTS

property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.

Coordinate alteration work in areas occupied by

Department of Veterans Affairs so that Medical Center operations will continue during the construction period.

2. Immediate areas of alterations not mentioned in preceding

Subparagraph 1 will be temporarily vacated while alterations are performed.

J. Utilities Services: Maintain existing utility services for

Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems

(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -11

GENERAL REQUIREMENTS

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center

Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR

ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR

COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK

RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COR, in writing via Contractor Request Form, at least 14 days in advance of the proposed interruption.

Request form shall state reason, date, exact shutdown time, and approximate duration of such interruption. In addition, all utility shutdowns involving or effecting any medical gas system will require at least 21 days advance notice to the COR via Contractor Request Form.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical

Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -12

GENERAL REQUIREMENTS

the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the

Contractor.

K. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions;

so that they are completely behind the finished surfaces.

L. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

M. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -13

GENERAL REQUIREMENTS

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of

VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the

Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by

Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -14

GENERAL REQUIREMENTS

SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-

4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved.

They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by

Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -15

GENERAL REQUIREMENTS

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the

Government are identified by attached tags or noted on drawings or in specifications as items to be stored.

Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the

Contractor and be removed by Contractor from Medical

Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.

When rooms and spaces are vacated by the Department of

Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the

Government in advance of work to avoid interfering with

Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)

A. The Contractor shall preserve and protect all structures, and equipment, on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract.

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -16

GENERAL REQUIREMENTS

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The

Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL

CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage

Areas" for additional instructions concerning repair of damage to structures and site improvements.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -17

GENERAL REQUIREMENTS

B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by

Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.11 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -18

GENERAL REQUIREMENTS

the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.12 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21

Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting

Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the

Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -19

GENERAL REQUIREMENTS

and telephone numbers within the company of the

Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and Maintenance manuals.

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -20

GENERAL REQUIREMENTS

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance & Payment Bonds: The Performance & Payment

Bonds must remain effective throughout the construction period.

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the

Government at the contractor’s expenses, the Contracting

Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -21

GENERAL REQUIREMENTS

follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the

Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the

Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for

Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the

Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service

Requirements:

E. Following oral or written notification by the Contracting

Officer, the Contractor shall respond to construction warranty service requirements in accordance with the

“Construction Warranty Service Priority List” and the three

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -22

GENERAL REQUIREMENTS

categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within

4 hours, initiate work within 6 hours and work continuously to completion or relief.

2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within

8 hours, initiate work within 24 hours and work continuously to completion or relief.

3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

a) Code 1-Life Safety Systems Fire suppression systems.

Fire alarm system(s).

b) Code 1-Air Conditioning Systems Air conditioning leak in part of the building, if causing damage.

Air conditioning system not cooling properly.

c) Code 1 Doors

Overhead doors not operational, causing a security, fire or safety problem.

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -23

GENERAL REQUIREMENTS

Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

d) Code 3-Doors Overhead doors not operational.

Interior/exterior personnel doors or hardware not functioning properly.

e) Code 1-Electrical Power failure (entire area or any building operational after 1600 hours).

Security lights.

Smoke detectors.

f) Code 2-Electrical Power failure (no power to a room or part of building). Receptacle and lights not operational (in a room or part of building).

g) Code 3-Electrical Exterior lights not operational.

h) Code 1-Gas Leaks and pipeline breaks.

i) Code 1-Heat Power failure affecting heat.

j) Code 1-Plumbing Hot water heater failure.

Leaking water supply pipes

k) Code 2-Plumbing Flush valves not operating properly Fixture drain, supply line or any water pipe leaking.

Toilet leaking at base.

l) Code 3- Plumbing

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -24

GENERAL REQUIREMENTS

Leaky faucets.

m) Code 3-Interior

Floors damaged.

Paint chipping or peeling.

Casework damaged.

n) Code 1-Roof Leaks Damage to property is occurring.

o) Code 2-Water (Exterior) No water to facility.

p) Code 2-Water (Hot) No hot water in portion of building listed.

q) Code 3 All work not listed above.

i. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer.

Attach each tag with a copper wire and spray with a silicone waterproof coating.

Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

Warranty Tags

Type of product/material

Model number

601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -25

GENERAL REQUIREMENTS

Warranty Tags

Serial number

Contract number

Warranty period from/to

Inspector’s signature

Construction Contractor

Address

Telephone number

Warranty Contact

Address

Telephone number

Warranty response time priority code

1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system must be given by

COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, 601 HWY 6 West CONSTRUCTION DOCUMENTS Iowa City, IA 52246 11-01-21

01 00 00 -26

GENERAL REQUIREMENTS

National Electrical Code, (2014 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded.

This is the start of the file's text. The full file is on GovTribe.