S02_CD_Drawings_Reno Dialysis_IC.pdf

PDF 39 MB Posted

Attached to
Z1DA--Renovate Dialysis PN: 636A8-24-001 Iowa City, IA
Solicitation number
36C26326B0005
Issued by

About this file

This document is a comprehensive set of architectural and engineering construction documents for renovating the Dialysis Clinic at the Iowa City VA Health Care System. The project involves a phased renovation approach, first preparing a temporary dialysis clinic and then renovating approximately 5,000 square feet of the existing clinic on the 5th floor. The solicitation is set aside exclusively for Service-Disabled Veteran-Owned Small Businesses (SDVOSB), with an expectation of receiving bids from at least two qualifying contractors.

The construction documents include detailed architectural, structural, mechanical, electrical, plumbing, medical gas, and fire protection plans for the renovation. Key technical aspects include reconfiguring the existing dialysis space, installing new medical equipment, updating building systems, and maintaining infection control protocols during construction. The project requires precise phasing to ensure continuous healthcare operations, with specific requirements for temporary spaces, medical gas systems, HVAC modifications, and adherence to VA and federal building standards. The solicitation number is 36C26326B0005, with the project number designated as 636A8-24-001.

View the file

Other files

File Type Posted
AS06_Amend 0004_ICVA-Dialysis_ADD1_SpecVol2.pdf PDF
AS06_Amend 0004_ICVA-Dialysis_ADD1_Sheets_fullset.pdf PDF
AS06_36C26326B0005_Amendment 0004.pdf PDF
AS06_Amend 0004_PreBid Site Visit Sign-In_Reno Dialysis.pdf PDF
AS06_Amend 0004__Pre-Bid Site Walk QAs_Reno Dialysis.pdf PDF
AS06_Amend 0004_ICVA-Dialysis_ADD1_SpecVol3.pdf PDF
AS06_Amend 0004_SOC Building 1 and Bldg 50 2023.pdf PDF
AS06_DBA WD_IA20260068_2Jan26.pdf PDF
AS06_Amend 0004_SOW Rev 2_Reno Dialysis_IC.pdf PDF
AS06_Amend 4_Round 2 Questions_Reno Dialysis.pdf PDF
AS06_Amend 0004_ICVA-Dialysis_ADD1_SpecVol1.pdf PDF
AS06_Amend 0004_ICVA-Dialysis_ADD1_Narrative.pdf PDF
AS06_36C26326B0005_Amendment 0003.pdf PDF
AS06_36C26326B0005_Amendment 0002.pdf PDF
AS06_Amendment_36C26326B0005 0001_Reno Dialysis_IC.pdf PDF
AS06_Contracting Officers Special Information and Instructions_Revised.docx DOCX document
S02_BNJ_Speakers_Reno Dialysis_IC_Redacted.pdf PDF
S02_BNJ_Patient Lifts_Reno Dialysis_IC_Redacted.pdf PDF
S02_BNJ_Fire Alarm Hardware_Reno Dialysis_IC_Redacted.pdf PDF
S02_BNJ_Door Cylinders_Reno Dialysis_IC_Redacted.pdf PDF
S02_CD_Spec Vol 3_Reno Dialysis.pdf PDF
S02_ICVA-Dialysis_CD_SpecVol2_20251210.pdf PDF
S02_DBA WD_IA20250068_12Dec25.pdf PDF
S02_SOW NARA Contract Language.pdf PDF
S02_ICVA-Dialysis_CD_SpecVol1_20251210.pdf PDF
S02_Final SOW_Reno Dialysis_IC.pdf PDF
S02_36C26326B0005_IFB_Reno Dialysis_IC.pdf PDF
S02_BNJ_Code Green Sys_Reno Dialysis_IC_Redacted.pdf PDF
S02_SOW TMS 20939.pdf PDF
S02_VAAR 852.219-75_VA Notice of Limitations on Subcontracting.pdf PDF
S02_BNJ_Signage_Reno Dialysis_IC_Redacted.pdf PDF
S02_BNJ_Nurse Call Sys_Reno Dialysis_IC_Redacted.pdf PDF
S02_BNJ_Elec Panel Boards_Reno Dialysis_IC_Redacted.pdf PDF
S02_BNJ_ACS_Reno Dialysis_IC_Redacted.pdf PDF
S02_SSJ_BAS_Reno Dialysis_IC_Redacted.pdf PDF
S02_CD Narrative_Reno Dialysis_IC.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

█ ISSUED

NOT ISSUED

ISSUED FOR REFERENCE ONLY

ISSUED AS NOTED

R

N

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

STAMPCONSULTANT

321 4 5 6 7 8 9 10

PROJECT NAME:

SITE ADDRESS:

VA PROJECT NUMBER:

OWNER AND CONSULTANTS:

VICINITY MAP:

DESIGNER OF RECORD

KEY PLAN:

TRUE

NORTH

PLAN

NORTH

TRUE

NORTH

IMEG CORP

2882 106th St,Des Moines, IA 50322 Contact: Dellan Llewellyn

(515) 334-7921

LANDMARK ENVIRONMENTAL

9555 James Ave S - Ste 262, Bloomington, MN 55431 Contact: Mark Meier (952) 295-9410

C U s e rs \p c h o i\ D o c u m e n ts

\1

-I C

V A

F L R

-A -R

Y e u n y o u n g .r v t

/2

/2

:1

:3

A

M

1-I1

COVER SHEET RENOVATE DIALYSIS

IOWA CITY, IA

636A8-24-001

04/24/2025 EM MWC

RENOVATE DIALYSIS

601 HIGHWAY 6 W,

IOWA CITY, IA 52246

636A8-24-001

17909

VA COR:

CONTACT:

ADDRESS:

PHONE:

BRIAN WHITE

IOWA CITY VA MEDICAL CENTER

601 HIGHWAY 6 WEST

IOWA CITY, IA 52246-2209

319-512-9764

SHEET INDEX - ARCHITECTURAL

SHEET

NO. SHEET TITLE C

O

NS

TR

UC

TI

O

N

DO

CU

M

EN

TS

4/

/2

1-A1 5TH FLOOR - OVERALL PLAN █

1-A2 5TH FLOOR - DEMOLITION PLAN - ZONE 1 █

1-A3 5TH FLOOR - DEMOLITION PLAN - ZONE 2 █

1-A4 5TH FLOOR - PARTIAL FLOOR PLAN - ZONE 1 █

1-A5 5TH FLOOR - PARTIAL FLOOR PLAN - ZONE 2 █

1-A6 5TH FLOOR - PARTIAL REFLECTED CEILING PLAN - ZONE 1 █

1-A7 ENLARGED PLANS AND INTERIOR ELEVATIONS █

1-A8 MOUNTING HEIGHTS █

1-A9 OPENING SCHEDULE, TYPES, AND DETAILS █

1-A10 PARTITION TYPES AND DETAILS █

1-A11 PLAN DETAILS █

1-A12 INTERIOR SECTION DETAILS AND CASEWORK GENERAL NOTES █

1-A13 ENLARGED RCP AND CEILING DETAILS █

1-A14 5TH FLOOR - FINISH PLAN - ZONE 1 █

1-A15 MATERIAL AND ROOM FINISH SCHEDULE - ZONE 1 █

1-A16 5TH FLOOR - WAYFINDING PLAN AND SIGN MESSAGE SCHEDULE █

1-A17 SIGNAGE DETAILS █

1-A18 5TH FLOOR - FURNITURE PLAN - ZONE 1 █

1-A19 5TH FLOOR - FURNITURE PLAN - ZONE 2 █

1-A20 5TH FLOOR - EQUIPMENT PLAN █

ZONE 1

ZONE 2

SHEET INDEX - FIRE PROTECTION

SHEET

NO. SHEET TITLE C

O

NS

TR

UC

TI

O

N

DO

CU

M

EN

TS

4/

/2

1-F1 FIRE PROTECTION COVERSHEET

1-F2 FIFTH FLOOR DEMOLITION PLAN - ZONE 1 - FIRE PROTECTION

1-F3 FIFTH FLOOR PLAN - ZONE 1 - FIRE PROTECTION

1-F4 FIRE PROTECTION DETAILS

SHEET INDEX - STRUCTURAL

SHEET

NO. SHEET TITLE C

O

NS

TR

UC

TI

O

N

DO

CU

M

EN

TS

4/

/2

1-S1 FIFTH FLOOR FRAMING PLAN █

1-S2 SIXTH FLOOR FRAMING PLAN █

SHEET INDEX - HAZARDOUS MATERIAL

SHEET

NO. SHEET TITLE C

O

NS

TR

UC

TI

O

N

DO

CU

M

EN

TS

4/

/2

HA001 5TH FL - HAZARDOUS MATERIALS ASBESTOS/ABATEMENT ZONE 1 █

ARCHITECT:

NAME:

ADDRESS:

CONTACT:

ANDERSON ENGINEERING OF MN, LLC

13605 1ST AVE NORTH, SUITE 100

PLYMOUTH, MN 55441

ED MARKFORT

PHONE: 763-412-4000

SHEET INDEX - GENERAL

SHEET

NO. SHEET TITLE C

O

NS

TR

UC

TI

O

N

DO

CU

M

EN

TS

4/

/2

1-I1 COVER SHEET █

1-I2 ABBREVIATIONS █

1-I3 5TH FLOOR - LIFE SAFETY PLAN █

1-I4 INFECTION CONTROL AND PHASING NOTES █

1-I5 3RD AND 4TH FLOOR - INFECTION CONTROL & PHASING PLAN █

1-I6 5TH FLOOR - INFECTION CONTROL & PHASING PLAN █

1-I7 ICRA DETAIL █

SHEET INDEX - ELECTRICAL SYSTEM

SHEET

NO. SHEET TITLE C

O

NS

TR

UC

TI

O

N

DO

CU

M

EN

TS

4/

/2

1-FA1 ELECTRICAL SYSTEMS COVERSHEET

1-FA2 FIFTH FLOOR DEMOLITION PLAN - ZONE 1 - SYSTEMS

1-FA3 FIFTH FLOOR PLAN - ZONE 1 - SYSTEMS

I HEREBY CERTIFY THAT THIS ENGINEERING DOCUMENT

WAS PREPARED BY ME OR UNDER MY DIRECT PERSONAL

SUPERVISION AND THAT I AM A DULY LICENSED

PROFESSIONAL ENGINEER UNDER THE LAWS OF THE STATE

OF IOWA.

DATE

MY LICENSE EXPIRATION DATE IS: 12/31/2025

PAGES OR SHEETS COVERED BY THIS SEAL:

I O W A

S E

D

PROFESS IONA

21081

L

IC

E N

L E

N G

I N E

E R

KRISTEN L.

SPINA KRISTEN L. SPINA

ELECTRICAL, TECHNOLOGY

I HEREBY CERTIFY THAT THIS ENGINEERING DOCUMENT

WAS PREPARED BY ME OR UNDER MY DIRECT PERSONAL

SUPERVISION AND THAT I AM A DULY LICENSED

PROFESSIONAL ENGINEER UNDER THE LAWS OF THE STATE

OF IOWA.

DATE

MY LICENSE EXPIRATION DATE IS: 12/31/2026

PAGES OR SHEETS COVERED BY THIS SEAL:

I O W A

S E

D

PROFESS IONA

27052

L

IC

E N

L E

N G

I N E

E R

DELLAN

LLEWELLYN DELLAN LLEWELLYN

MECHANICAL, MEDICAL GAS, PLUMBING, FIRE PROTECTION

I HEREBY CERTIFY THAT THE PORTION OF THIS TECHNICAL

SUBMISSION DESCRIBED BELOW WAS PREPARED BY ME OR

UNDER MY DIRECT SUPERVISION AND RESPONSIBLE

CHARGE. I AM A DULY LICENSED ARCHITECT UNDER THE

LAWS OF THE STATE OF IOWA.

DATE

MY LICENSE EXPIRATION DATE IS: 06/30/2025

PAGES OR SHEETS COVERED BY THIS SEAL:

THOMAS OLESAK, AIA

GENERAL, ARCHITECTURAL

SHEET INDEX - MECHANICAL HVAC

SHEET

NO. SHEET TITLE C

O

NS

TR

UC

TI

O

N

DO

CU

M

EN

TS

4/

/2

1-H1 HVAC COVERSHEET

1-H2 FIFTH FLOOR DEMOLITION PLAN - ZONE 1 - HVAC

1-H3 SIXTH FLOOR DEMOLITION PLAN - ZONE 1 - HVAC

1-H4 FIFTH FLOOR PLAN - ZONE 1 - VENTILATION

1-H5 SIXTH FLOOR PLAN - ZONE 1 - VENTILATION

1-H6 FIFTH FLOOR PLAN - ZONE 1 - PIPING

1-H7 HVAC DETAILS

1-H8 HVAC DETAILS

1-H9 HVAC DIAGRAMS

1-H10 HVAC SCHEDULES

SHEET INDEX - ELECTRICAL

SHEET

NO. SHEET TITLE C

O

NS

TR

UC

TI

O

N

DO

CU

M

EN

TS

4/

/2

1-E1 ELECTRICAL COVERSHEET

1-E2 ELECTRICAL LIGHTING COVERSHEET

1-E3 FIFTH FLOOR DEMOLITION PLAN - ZONE 1 - ELECTRICAL

1-E4 FIFTH FLOOR PLAN - ZONE 1 - LIGHTING

1-E5 FIFTH FLOOR PLAN - ZONE 1 - POWER

1-E6 FIFTH FLOOR PLAN - ZONE 2 - POWER

1-E7 SIXTH FLOOR PLAN - ZONE 1 - POWER

1-E8 ELECTRICAL DETAILS

1-E9 ELECTRICAL DIAGRAMS

1-E10 ELECTRICAL SCHEDULES

1-E11 ELECTRICAL PANEL SCHEDULES

SHEET INDEX - TECHNOLOGY

SHEET

NO. SHEET TITLE C

O

NS

TR

UC

TI

O

N

DO

CU

M

EN

TS

4/

/2

1-T1 TECHNOLOGY COVERSHEET

1-T2 SECOND FLOOR PLAN - TECHNOLOGY

1-T3 FIFTH FLOOR DEMOLITION PLAN - ZONE 1 - TECHNOLOGY

1-T4 FIFTH FLOOR DEMOLITION PLAN - ZONE 2 - TECHNOLOGY

1-T5 FIFTH FLOOR PLAN - ZONE 1 - TECHNOLOGY

1-T6 FIFTH FLOOR PLAN - ZONE 2 - TECHNOLOGY

1-T7 TECHNOLOGY ENLARGED PLANS

1-T8 TECHNOLOGY DETAILS

1-T9 TECHNOLOGY DETAILS

1-T10 TECHNOLOGY RISER DIAGRAMS

1-T11 TECHNOLOGY RISER DIAGRAMS

1-T12 TECHNOLOGY SCHEDULES

SHEET INDEX - MEDICAL GAS

SHEET

NO. SHEET TITLE C

O

NS

TR

UC

TI

O

N

DO

CU

M

EN

TS

4/

/2

1-MG1 MEDICAL GAS COVERSHEET

1-MG2 FIFTH FLOOR DEMOLITION PLAN - ZONE 1 - MEDICAL GAS

1-MG3 FIFTH FLOOR PLAN - ZONE 1 - MEDICAL GAS

1-MG4 MEDICAL GAS DETAILS

SHEET INDEX - PLUMBING

SHEET

NO. SHEET TITLE C

O

NS

TR

UC

TI

O

N

DO

CU

M

EN

TS

4/

/2

1-P1 PLUMBING COVERSHEET

1-P2 THIRD LEVEL FLOOR DEMOLITION PLAN - ZONE 1 - PLUMBING

1-P3 FOURTH FLOOR DEMOLITION PLAN - ZONE 1 - PLUMBING

1-P4 FIFTH FLOOR DEMOLITION PLAN - ZONE 1 - PLUMBING

1-P5 FIFTH FLOOR - ABANDON PIPING DEMOLITION - ZONE 1 - PLUMBING

1-P6 THIRD LEVEL FLOOR PLAN - ZONE 1 - PLUMBING

1-P7 FOURTH FLOOR PLAN - ZONE 1 - PLUMBING

1-P8 FIFTH FLOOR PLAN - ZONE 1 - PLUMBING

1-P9 FIFTH FLOOR PLAN - ZONE 2 - PLUMBING

1-P10 PLUMBING DIAGRAMS

1-P11 PLUMBING DETAILS

1-P12 PLUMBING SCHEDULES

STRUCTURAL ENGINEER:

NAME:

ADDRESS:

CONTACT:

ANDERSON ENGINEERING OF MN, LLC

13605 1ST AVE NORTH, SUITE 100

PLYMOUTH, MN 55441

ADAM ADAMS

PHONE: 763-412-4000

MECHANICAL/PLUMBING/FIRE PROTECTION ENGINEER:

NAME:

ADDRESS:

CONTACT:

IMEG CORP

2882 106th STREET

DES MOINES, IA 50322

DELLAN J. LLEWELLYN

PHONE: 515-334-7921

ELETRICAL/TECHNOLOGY ENGINEER:

NAME:

ADDRESS:

CONTACT:

IMEG CORP

2882 106th STREET

DES MOINES, IA 50322

ZACHARY ROSS

HAZARDOUS MATERIALS (ASBESTOS/ABATEMENT):

NAME:

ADDRESS:

CONTACT:

LANDMARK ENVIROMENTAL

9555 JAMES AVENUE SOUTH, SUITE 262

BLOOMINGTON, MN 55431

MARK MEIER

PHONE: 952-295-9410

I HEREBY CERTIFY THAT THIS ENGINEERING DOCUMENT

WAS PREPARED BY ME OR UNDER MY DIRECT PERSONAL

SUPERVISION AND THAT I AM A DULY LICENSED

PROFESSIONAL ENGINEER UNDER THE LAWS OF THE STATE

OF IOWA.

DATE

MY LICENSE EXPIRATION DATE IS: 12/31/2025

PAGES OR SHEETS COVERED BY THIS SEAL:

I O W A

S E

D

PROFESS IONA

22449

L

IC

E N

L E

N G

I N E

E R

ADAM

ADAMS ADAM ADAMS

STRUCTURAL

Revisions: Date:

04/24/2025 04/24/2025 nder the laws of the St

04/24/2025 04/24/2025

ARCHITECTURAL ABBREVIATIONS

A/C

A/C UNIT

A/E

AAMA

AAP

AB

ABC

ACC

ACI

ACT

ACS DR

ACS FLR

ACS PNL

ACST

AD

ADA

ADC

ADDL

ADDN

ADH

ADJ

ADMIN

AFF

AFG

AFS

AGC

AGGR

AHJ

AHR

AHU

AIA

AISC

ALT

ALT NO

ALUM

AMT

ANOD

ANSI

ANT

AP

APA

APC

APPD

APPROX

AR

ARCH

ASB

ASI

ASKLR

ASPH

ASSN

ASTM

ATCH

ATM

AUTO

AUX

AV

AVG

AW

AWI

AWPA

AWS

B PL

BAT

BD

BD FT

BEV

BHMA

BI FLD DR

BITUM

BKG

BLD

BLDG

BM

BOT

BRCG

BRDG

BRDG JST

BRG

BRG PL

BRKT

BRZ

BSMT

BTWN

BUR

C CONC

C TO C

CAB

CAC

CB

CBB

CCD

CCTV

CCW

CD

CEM

CEM PLAS

CER

CF

CF/CI

CF/OI

CFLG

CFMF

CG

CGSFU

CH

CHEM

CHFR

CHK

CI

CIP

CIR

CIRC

CJ

CL

CLDG

CLG

CLR

CM

CMU

AIR CONDITION

AIR CONDITIONING UNIT

ARCHITECT/ENGINEER

AMERICAN ARCHITECTURAL MANUFACTURERS ASSN

ALARM ANNUNCIATOR PANEL

ANCHOR BOLT

AGGREGATE BASE COURSE

ACCESSIBLE

AMERICAN CONCRETE INSTITUTE

ACOUSTICAL CEILING TILE

ACCESS DOOR

ACCESS FLOOR

ACCESS PANEL

ACOUSTIC

AREA DRAIN

AMERICANS WITH DISABILITIES ACT

AUTOMATIC DOOR CLOSER

ADDITIONAL

ADDITION

ADHESIVE

ADJACENT, ADJOINING, OR ADJUSTABLE

ADMINISTRATION

ABOVE FINISHED FLOOR

ABOVE FINISHED GRADE

ABOVE FINISHED SLAB

ASSOCIATED GENERAL CONTRACTORS

AGGREGATE

AUTHORITY HAVING JURISDICTION

ANCHOR

AIR HANDLING UNIT

AMERICAN INSTITUTE OF ARCHITECTS

AMERICAN INSTITUTE OF STEEL CONSTRUCTION

ALTERNATE

ALTERNATE NUMBER

ALUMINUM

AMOUNT

ANODIZE

AMERICAN NATIONAL STANDARDS INSTITUTE

ANTENNA

ACCESS PANEL

AMERICAN PLYWOOD ASSOCIATION

ARCHITECTURAL PRECAST CONCRETE

APPROVED

APPROXIMATE

AS REQUIRED

ARCHITECT

ASBESTOS

ARCHITECT'S SUPPLEMENTAL INSTRUCTION

AUTOMATIC SPRINKLER

ASPHALT

ASSOCIATION

AMERICAN SOCIETY FOR TESTING AND MATERIALS

ATTACHMENT

AUTOMATIC TELLER MACHINE

AUTOMATIC

AUXILIARY

AUDIO VISUAL

AVERAGE

ACID WASTE

ARCHITECTURAL WOODWORKING INSTITUTE

AMERICAN WOOD PRESERVERS' ASSOCIATION

AMERICAN WELDING SOCIETY

BASE PLATE

BATTEN

BOARD

BOARD FEET (FOOT)

BEVEL

BUILDER'S HARDWARE MANUFACTURER'S ASSOCIATION

BIFOLDING DOORS

BITUMINOUS

BACKING

BUILD

BUILDING

BEAM OR BENCHMARK

BOTTOM

BRACING

BRIDGING

BRIDGING JOIST

BEARING

BEARING PLATE

BRACKET

BRONZE

BASEMENT

BETWEEN

BUILT-UP ROOFING

CAST CONCRETE

CENTER TO CENTER

CABINET

CEILING ATTENUATION CLASS

CATCH BASIN OR CORNER BEAD

CEMENTITIOUS (BACKER) BOARD

CONSTRUCTION CHANGE DIRECTIVE

CLOSED CIRCUIT TELEVISION

COUNTERCLOCKWISE

CONSTRUCTION DOCUMENTS OR CONTRACT DOCUMENTS

CEMENT

CEMENT PLASTER

CERAMIC

CONTRACTOR FURNISHED

CONTRACTOR FURNISHED/CONTRACTOR INSTALLED

CONTRACTOR FURNISHED/OWNER INSTALLED

COUNTERFLASHING

COLD-FORMED METAL FRAMING

CORNER GUARD

CERAMIC GLAZED STRUCTURAL FACING UNITS

COAT HOOK

CHEMICAL

CHAMFER

CHECK

CAST IRON

CAST-IN-PLACE

CIRCLE

CIRCULAR

CONSTRUCTION JOINT OR CONTROL JOINT

CENTER LINE

CLADDING

CEILING

CLEAR

CONSTRUCTION MANAGEMENT

CONCRETE MASONRY UNIT

CNR

CNTR

CRTP

CO

CO2

COL

COM

COMB

COMM

COMP

CONC

CONC FLR

COND

CONF

CONN

CONSTR

CONT

CONTR

COORD

CORR

CPM

CPRS

CR

CRS

CRSI

CSB

CSG

CSI

CSK

CSMT

CSWK

CTG

CTR

CTRL

CTV

CU FT

CU IN

CU YD

CURT

CYL

CYL L

D

DAT

DBL

DBL GLZ

DCS

DP

DEG

DEL

DEMO

DEPT

DET

DF

DIA

DIAG

DIFF

DIM

DIR

DISP

DIST

DIV

DL

DOC

DR

DR CL

DR FR

DR OPNG

DS

DSGN

DW

DWG

E

EA

EFF

EFS

EIFS

EJ

EL

ELAST

ELEC

ELEC DR OP

ELEV

EMER

EMER SHR

ENCL

ENGR

ENVIR

EO

EPA

EPDM

EPO

EPS

EQ

EQL SP

EQUIP

EQUIV

ERD

ESC

ESMT

ESP

EST

ETC

EW

EWC

EWS

EXH

EXIST

EXP

EXP BT

EXST GR

EXT

EXT GR

CORNER

COUNTER

COUNTERTOP

CARBON MONOXIDE

CARBON DIOXIDE

COLUMN

COMMON

COMBINATION, COMBINED

COMMUNICATION

COMPONENT

CONCRETE

CONCRETE FLOOR

CONDENSER OR CONDITION

CONFERENCE

CONNECT

CONSTRUCTION

CONTINUE

CONTRACTOR

COORDINATE

CORRIDOR

CRITICAL PATH METHOD

COMPRESSIBLE

CARD READER

COLD ROLLED STEEL

CONCRETE REINFORCING STEEL INSTITUTE

CONCRETE SPLASH BLOCK

CASING

CONSTRUCTION SPECIFICATIONS INSTITUTE

COUNTER SUNK

CASEMENT

CASEWORK

COATING

CENTER

CONTROL

CABLE TELEVISION

CUBIC FEET

CUBIC INCH

CUBIC YARD

CURTAIN

CYLINDER

CYLINDER LOCK

DEPTH OR PENNY (NAIL)

DATUM

DOUBLE

DOUBLE GLAZE

DIAPER CHANGING STATION

DECORATIVE PANEL

DEGREE

DELETE

DEMOLITION

DEPARTMENT

DETAIL

DRINKING FOUNTAIN

DIAMETER

DIAGONAL

DIFFERENCE OR DIFFUSER

DIMENSION

DIRECTION

DISPENSER

DISTANCE

DIVIDE OR DIVISION

DEAD LOAD

DOCUMENT

DOOR, DRAIN, DRESSING ROOM, OR DRIVE

DOOR CLOSER

DOOR FRAME

DOOR OPENING

DOWNSPOUT

DESIGN

DISHWASHER

DRAWING

EAST

EACH

EFFICIENCY

EXTERIOR FINISH SYSTEM

EXTERIOR INSULATION AND FINISH SYSTEM

EXPANSION JOINT

ELEVATION

ELASTOMERIC

ELECTRIC

ELECTRIC DOOR OPENER

ELEVATOR

EMERGENCY

EMERGENCY SHOWER

ENCLOSURE

ENGINEER

ENVIRONMENT

ELECTRICAL OUTLET

ENVIRONMENTAL PROTECTION AGENCY

ETHYLENE PROPYLENE DIENE MONOMER

EMERGENCY POWER OFF

EXPANDED POLYSTYRENE BOARD (INSULATION)

EQUAL

EQUALLY SPACED

EQUIPMENT

EQUIVALENT

EXISTING ROOF DRAIN

ESCAPE OR ESCUTCHEON

EASEMENT

ESPECIALLY

ESTIMATE

AND SO FORTH OR ET CETERA

EACH WAY

ELECTRIC WATER COOLER

EYE WASH STATION

EXHAUST

EXISTING

EXPANSION OR EXPOSED

EXPANSION BOLT

EXISTING GRADE

EXTERIOR, EXTERNAL, OR EXTINGUISHER

EXTERIOR GRADE

F

FA

FAB

FAC

FACIL

FAS

FAS BD

FCU

FCO

FCTY

FD

FDC

FDTN

FE

FEC

FF

FF EL

FF&E

FHC

FHP

FIG

FIL

FIN

FIN FLR

FIN GR

FIN WD

FIXT

FL

FLASH

FLDG

FLEX

FLG

FLR

FLR FIN

FLR SK

FLUOR

FLUOR FIX

FM

FM-G

FO

FOC

FOF

FOM

FOS

FOUNT

FOW

FP

FR

FR SNK

FREQ

FRMG

FRP

FRZ

FS

FSB

FSTNR

FT

FTG

FURG

FURN

FUT

FVC

GA

GAL

GALV

GALV STL

GB

GC

GD

GDR

GEN

GFRC

GFRG

GFRP

GI

GL

GL BLK

GLU LAM

GP

GR FL

GRAN

GRTG

GSB

GSM

GSU

GT

GUAR

GUT

GYP

GYP BD

GYP PLAS

H

HAZ MAT

HB

HC

HCWD

HDBD

HDO

HDR

HDW

HDWD

HEPA

HEX

HGR

HM

HMD

HMDF

HMF

HNDRL

HO

HORIZ

HOSP

HP

HPD

HPDL

HQ

HS

HSE

HSKPG

FAHRENHEIT OR FEMALE

FIRE ALARM

FABRIC

FACTOR

FACILITY

FASCIA

FASCIA BOARD

FAN COIL UNIT

FLOOR CLEANOUT

FACTORY

FLOOR DRAIN

FIRE DEPARTMENT CONNECTION

FOUNDATION

FIRE EXTINGUISHER

FIRE EXTINGUISHER CABINET

FINISH FACE

FINISH FLOOR ELEVATION

FURNITURE, FIXTURE, AND EQUIPMENT

FIRE HOSE CABINET

FULL HEIGHT PARTITION

FIGURE

FILLET

FINISH

FINISH FLOOR

FINISH GRADE

FINISH WOOD

FIXTURE

FLOORLINE

FLASHING

FOLDING

FLEXIBLE

FLOORING

FLOOR

FLOOR FINISH

FLOOR SINK

FLUORESCENT

FLUORESCENT FIXTURE

FACTORY MUTUAL

FACTORY MUTUAL GLOBAL

FINISHED OPENING

FACE OF CONCRETE OR FACE OF CURB

FACE OF FINISH

FACE OF MASONRY

FACE OF SLAB OR FACE OF STUD

FOUNTAIN

FACE OF WALL

FIRE PROTECTION OR FIREPROOF

FIRE RATING, FIRE RESISTANT, OR FRAME

FLUSHING RIM SINK

FREQUENCY

FRAMING

FIBERGLASS REINFORCED PLASTIC

FREEZER

FEDERAL SPECIFICATION

FOLDING SHOWER BENCH

FASTENER

FEET OR FOOT

FOOTING

FURRING

FURNISH OR FURNITURE

FUTURE

FIRE VALVE CABINET

GAGE OR GYPSUM ASSOCIATION

GALLON

GALVANIC OR GALVANIZED

GALVANIZED STEEL

GRAB BAR

GENERAL CONTRACTOR

GUARD

GUARD RAIL

GENERAL OR GENERATOR

GLASS-FIBER-REINFORCED CONCRETE

GLASS-FIBER-REINFORCED GYPSUM

GLASS-FIBER-REINFORCED PLASTIC

GALVANIZED IRON

GLASS

GLASS BLOCK

GLUED LAMINATED WOOD

GRAB BAR

GROUND FLOOR

GRANITE

GRATING

GYPSUM SHEATHING BOARD

GALVANIZED SHEET METAL

GLAZED STRUCTURAL UNIT

GROUT

GUARANTEE

GUTTER

GYPSUM

GYPSUM BOARD

GYPSUM PLASTER

HIGH OR HUMIDISTAT

HAZARDOUS MATERIALS

HOSE BIBB

HOLLOW CORE

HOLLOW CORE WOOD DOOR

HARDBOARD

HIGH DENSITY OVERLAY

HEADER

HARDWARE

HARDWOOD

HIGH EFFICIENCY PARTICULATE AIR (FILTER)

HEXAGON

HANGER

HOLLOW METAL

HOLLOW METAL DOOR

HOLLOW METAL DOOR AND FRAME

HOLLOW METAL FRAME

HANDRAIL

HOLD OPEN

HORIZONTAL

HOSPITAL

HIGH PRESSURE

HYGIENE PRODUCT DISPOSAL

HIGH PRESSURE DECORATIVE LAMINATE

HEADQUARTERS

HEAT-STRENGTHENED (GLASS) OR HIGH STRENGTH

HOUSE

HOUSEKEEPING

HST

HSS

HT

HVAC

HVY

HW

HYD

HYDR

IAQ

IBC

IC

ICW

ID

ID NO

ILLUM

INCL

IND

INFO

INSUL

INT

INTL

IWH

JAN

KD

KIT

KO

KPL

LAB

LAD

LAM

LAM GL

LAU

LAV

LBR

LBS

LCS

LD BRG

LDR

LED

LF

LIB

LIN

LIQ

LKR

LKR RM

LL

LMST

LRG

LRV

LS

LT

LT GA

LT WT

LTG

LTNG

LVD

LVR

LWC

LWIC

LYR

MACH

MACH RM

MAINT

MAN

MATL

MATV

MAX

MBD

MCB

MD

ME

MEAS

MECH

MECH RM

MED

MEK

MEMB

MEMO

MEZZ

MF

MFD

MFG

MFR

MFR REC

MGT

MIC

MID

MIL STD

MIN

MIR

MISC

MIT

MKR

ML

MLDG

MLWK

mm

MO

MOD

MOD BIT

MON

MOPR

MR

MS

MTD

MTG

MTL

MULL

MW

MWP

HOIST

HOLLOW STRUCTURAL STEEL

HEIGHT

HEATING, VENTILATING, AND AIR CONDITIONING

HEAVY

HOT WATER

HYDRANT

HYDRAULIC

INDOOR AIR QUALITY

INTERNATIONAL BUILDING CODE

INFECTION CONTROL

INFECTION CONTROL WALL

INSIDE DIAMETER

IDENTIFICATION NUMBER

ILLUMINATION

INCLUDED

INDEPENDENT OR INDUSTRIAL

INFORMATION

INSULATION

INTERIOR

INTERNATIONAL

INSTANTANEOUS WATER HEATER

JANITOR

KILN DRIED OR KNOCKED DOWN

KITCHEN

KNOCKOUT

KICKPLATE

ANGLE

LABORATORY

LADDER

LAMINATE

LAMINATED GLASS

LAUNDRY

LAVATORY

LUMBER

POUND

LOCKABLE CHARTING STATION/MED CABINET

LOAD-BEARING

LEADER

LIGHT EMITTING DIODE

LINEAR FEET (FOOT)

LIBRARY

LINEAR

LIQUID

LOCKER

LOCKER ROOM

LEAD LINED

LIMESTONE

LARGE

LOUVERED ROOF VENT

LIGHT SWITCH

LIGHT

LIGHT GAGE

LIGHTWEIGHT

LIGHTING

LIGHTNING

LOUVERED

LOUVER

LIGHTWEIGHT CONCRETE

LIGHTWEIGHT INSULATING CONCRETE

LAYER

MACHINE

MACHINE ROOM

MAINTENANCE

MANUAL

MATERIAL

MASTER ANTENNA TELEVISION SYSTEM

MAXIMUM

MARKER BOARD

METAL CORNER BEAD

DECK

MECHANICAL ENGINEER

MEASURE

MECHANICAL

MECHANICAL ROOM

MEDICAL, MEDIUM

METHYL ETHYL KETONE

MEMBRANE

MEMORANDUM

MEZZANINE

MILL FINISH

MANUFACTURED

MANUFACTURING

MANUFACTURER

MANUFACTURER'S RECOMMENDATION

MANAGEMENT

MICROPHONE

MIDDLE

MILITARY STANDARD

MINIMUM

MIRROR

MISCELLANEOUS

MITER

MARKER

METAL LATH

MOLDING (MOULDING)

MILLWORK

MILLIMETER

MASONRY OPENING

MODEL, MODIFY OR MODULE

MODIFIED BITUMEN

MONITOR

MOP RACK

MOISTURE RESISTANT

MOP SINK

MOUNTED

MOUNTING

METAL

MULLION

MICROWAVE

MEMBRANE WATERPROOFING

N

NA

NAT

NATL

NC

NCOMBL

NEC

NEG

NEMA

NEUT

NFC

NFPA

NIC

NO

NOM

NR

NRC

NRCA

NRP

NS

NUM

O/O O

OA

OC

OCC

OCT

OD

OD

OF/CI

OFD

OFF

OF/OI

OH

OH DR

OPH

OPNG

OPP

OPR

OPT

OR

ORD

ORG

ORIG

ORN

OSHA

OUT

OZ

P

PAR

PARA

PART

PAT

PB

PBD

PC

PCA

PCC

PCCP

PCD

PCF

PCP

PCT

PED

PEN

PEND

PERF

PERIM

PERP

PHAR

PHOTO

PKG

PL

PL GL

PLAM

PLAS

PLBG

PLYWD

PMTL

PNEU

PNL

PO

POLY

PP

PR

PRCST

PREFAB

PREFIN

PRELIM

PREP

PRESS

PREV

PRKG

PRMLD

PROJ

PROP

PSF

PSI

PT

PTD

PTN

PTS

PVC

PVG

PWR

QA

QC

QRY

QTR

QTY

QUAD

QUAL

R

RA

RAD

RBM

RBR

NORTH

NOT APPLICABLE

NATURAL

NATIONAL

NOISE CRITERIA OR NURSE CALL

NONCOMBUSTIBLE

NATIONAL ELECTRICAL CODE

NEGATIVE

NATIONAL ELECTRICAL MANUFACTURERS ASSN

NEUTRAL

NATIONAL FIRE CODE

NATIONAL FIRE PROTECTION ASSOCIATION

NOT IN CONTRACT

NUMBER

NOMINAL

NOISE REDUCTION

NOISE REDUCTION COEFFICIENT

NATIONAL ROOFING CONTRACTORS ASSOCIATION

NONREMOVABLE

NARROW STILE

NUMERAL

OUT TO OUT

OXYGEN

OUTSIDE AIR OR OVERALL

ON CENTER

OCCUPY

OCTAGON

OUTSIDE DIAMETER, OUTSIDE DIMENSION

OUTSIDE DIAMETER/OUTSIDE DIMENSION

OWNER FURNISHED/CONTRACTOR INSTALLED

OVERFLOW DRAIN

OFFICE

OWNER FURNISHED/OWNER INSTALLED

OVERHANG

OVERHEAD (COILING) DOOR

OPPOSITE HAND

OPENING

OPPOSITE

OPERABLE

OPTIONAL

OPERATING ROOM OR OUTSIDE RADIUS

ORDNANCE OR OVERFLOW ROOF DRAIN

ORGANIC

ORIGINAL

ORNAMENTAL

OCCUPATIONAL SAFETY AND HEALTH ADMINSTRATION

OUTLET

OUNCE

PAINT

PARALLEL OR PARAPET

PARAGRAPH

PARTIAL

PATTERN

PUSHBUTTON

PARTICLEBOARD

PIECE, POLYCARBONATE OR PORTLAND CEMENT

PORTLAND CEMENT ASSOCIATION

PRECAST CONCRETE

CONCRETE PAVEMENT

PAPER CUP DISPENSER

POUNDS PER CUBIC FOOT

PORTLAND CEMENT PLASTER

PRIVACY CURTAIN TRACK

PEDESTAL

PENETRATE

PENDANT

PERFORATED

PERIMETER

PERPENDICULAR

PHARMACY

PHOTOGRAPH

PACKAGE

PROPERTY LINE

PLATE GLASS

PLASTIC LAMINATE

PLASTER OR PLASTIC

PLUMBING

PLYWOOD

PAINTED METAL

PNEUMATIC

PANEL

POST OFFICE, PURCHASE ORDER

POLYETHYLENE (PLASTIC)

PUSH PLATE

PAIR

PRECAST

PREFABRICATE

PREFINISH

PRELIMINARY

PREPARATION

PRESSURE

PREVIOUS

PARKING

PREMOLDED

PROJECT

PROPERTY

POUNDS PER SQUARE FOOT

POUNDS PER SQUARE INCH

PORCELAIN TILE OR PRESSURE TREATED

PAPER TOWEL DISPENSER

PARTITION

PNEUMATIC TUBE STATION

POLYVINYL CHLORIDE (PLASTIC)

PAVING

POWER

QUALITY ASSURANCE

QUALITY CONTROL

QUARRY

QUARTER

QUANTITY

QUADRANT

QUALITY

RADIUS OR RISER

RETURN AIR

RADIATOR

REINFORCED BRICK MASONRY

RUBBER

RC

RCP

RCVR

RD

REC

RECD

RECPT

RECT

REF

REFR

REG

REINF

REP

REPL

REQ

REQD

RET

REV

RFG

RFI

RFP

RFS

RL

RLG

RM

RM LT

RND

RO

ROW

RS

RSV

RT

RV

RVS

RWL

S

SA

SALV

SAMP

SAN

SB

SBS

SBSTR

SC

SCH

SCHED

SCHEM

SCP

SCRN

SCT

SCWD

SD

SDG

SECT

SEG

SEL

SEP

SF

SFTWD

SGD

SGL

SHR

SHR HD

SHRD

SHT

SHTHG

SHV

SIM

SJ

SJI

SK

SKLT

SLDG

SLNT

SM

SMK

SND INS

SPEC

SPKLR

SPKR

SPLY

SPR

SQ

SQ IN

SQ YD

SST

ST

STC

STD

STIF

STL JST

STL LNTL

STL PL

STL RF DK

STL TB

STL TR

STNLS

STOR

STR

STRUCT

STRUCT STL

SUB

SURF

SUSP

SUSP CLG

SW

SWDR

SYM

SYNTH

SYS

REMOTE CONTROL

REFLECTED CEILING PLAN

RECEIVER

ROAD OR ROOF DRAIN

RECESSED

RECEIVED

RECEPTACLE

RECTANGLE

REFERENCE OR REFRIGERATOR

REFRACTORY, REFRIGERATION

REGISTER

REINFORCE

REPAIR

REPLACE

REQUIRE

REQUIRED

RETURN

REVISION

ROOFING

REQUEST FOR INFORMATION

REQUEST FOR PROPOSAL

ROOM FINISH SCHEDULE

ROOF LEADER

RAILING

ROOM

NURSE CALL LIGHT/ROOM LIGHT

ROUND

ROUGH OPENING

RIGHT OF WAY

ROUGH SAWN

RESILIENT SHEET VINYL

RIGHT

ROOF VENT

REVERSE

RAIN WATER LEADER

SOLID SURFACE

SUPPLY AIR

SALVAGE

SAMPLE

SANITARY

SPLASH BLOCK

STYRENE BUTADIEN STYRENE

SUBSTRATE

SHARPS CONTAINER

SCHOOL

SCHEDULE

SCHEMATIC

SCUPPER

SCREEN

SHOWER CURTAIN TRACK

SOLID CORE WOOD DOOR

SMOKE DETECTOR/SOAP DISPENSER

SIDING

SECTION

SEGMENT

SELECT

SEPARATE

SQUARE FOOT (FEET)

SOFTWOOD

SLIDING GLASS DOOR

SINGLE

SHOWER

SHOWER HEAD

SHOWER DRAIN

SHEET

SHEATHING

SHELVING

SIMILAR

SCORED JOINT

STEEL JOIST INSTITUTE

SKETCH

SKYLIGHT

SLIDING

SEALANT

SHEET METAL

SMOKE

SOUND INSULATION

SPECIFICATION

SPRINKLER

SPEAKER

SUPPLY

SINGLE PLY ROOF SYSTEM

SQUARE

SQUARE INCH

SQUARE YARD

STAINLESS STEEL

STAIRS OR STREET

SOUND TRANSMISSION CLASS

STANDARD

STIFFENER

STEEL JOIST

STEEL LINTEL

STEEL PLATE

STEEL ROOF DECK

STEEL TUBE

STEEL TRUSS

STAINLESS

STORAGE

STRINGERS

STRUCTURAL

STRUCTURAL STEEL

SUBSTITUTE

SURFACE

SUSPEND

SUSPENDED CEILING

SWITCH

SWING DOOR

SYMBOL

SYNTHETIC

SYSTEM

T T&M

TB

TBD

TECH

TEL

TEMP

THERM

THK

THRES

THRU

THRUOUT

TMPD

TMPD GL

TN

TO

TO FDN

TOB

TOM

TOP

TOS

TOW

TPD

TRANS

TRTD

TS

TSTAT

TV

TYP

U

UC

UGND

UL

ULT

UNFIN

UNO

UPS

UR

UTIL

UV

VAC

VAR

VD

VEH

VENT

VERT

VEST

VFD

VIC

VID

VIF

VNR

VOC

VOL

VR

VTR

W/ W/O

WBL

WC

WD

WDW

WF

WFR

WFS

WH

WHSE

WP

WPM

WR

WS

WSCT

WT

X BRACE

XPS

YD

TREAD OR THERMOSTAT

TIME AND MATERIALS

TOWEL BAR

TACK BOARD

TECHNICAL

TELEPHONE

TEMPERATURE OR TEMPORARY

THERMAL

THICKNESS

THRESHOLD

THROUGH

THROUGHOUT

TEMPERED

TEMPERED GLASS

TRUE NORTH

TOP OF ___

TOP OF FOUNDATION

TOP OF BEAM

TOP OF MASONRY

TOP OF PARAPET

TOP OF STEEL

TOP OF WALL

TOILET PAPER DISPENSER

TRANSOM

TREATED

TUBE STEEL

THERMOSTAT

TELEVISION

TYPICAL

HEAT TRANSFER COEFFICIENT

UNDERCUT

UNDERGROUND

UNDERWRITERS LABORATORIES

ULTIMATE

UNFINISH

UNLESS NOTED OTHERWISE

UNINTERRUPTIBLE POWER SUPPLY

URINAL

UTILITY

ULTRAVIOLET

VACUUM

VARIES

VOICE AND DATA

VEHICLE

VENTILATION

VERTICAL

VESTIBULE

VARIABLE FREQUENCY DRIVE

VICINITY

VIDEO

VERIFY IN FIELD

VENEER

VOLATILE ORGANIC COMPOUND

VOLUME

VAPOR RETARDER

VENT THROUGH ROOF

WITH

WITHOUT

WOOD BLOCKING

WATER CLOSET

WOOD

WINDOW

WIDE FLANGE

WOOD FRAME

WOOD FURRING STRIPS

WATER HEATER

WAREHOUSE

WATERPROOFING

WATERPROOF MEMBRANE

WEATHER RESISTANT

WEATHERSTRIP OR WALL SCONCE

WAINSCOT

WEIGHT OR WINDOW TREATMENT

CROSS BRACE

EXTRUDED POLYSTYRENE BOARD

YARD

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

DESIGNER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

IMEG CORP

2882 106th St,Des Moines, IA 50322 Contact: Dellan Llewellyn

(515) 334-7921

LANDMARK ENVIRONMENTAL

9555 James Ave S - Ste 262, Bloomington, MN 55431 Contact: Mark Meier (952) 295-9410

C U s e rs \p c h o i\ D o c u m e n ts

\1

-I C

V A

F L R

-A -R

Y e u n y o u n g .r v t

/2

/2

:4

:2

P

M

1-I2

ABBREVIATIONS RENOVATE DIALYSIS

IOWA CITY, IA

636A8-24-001

04/24/2025 EM MWC

17909

Revisions: Date:

NOGENERAL TYPE OF PROJECT

REMODEL, LESS THAN 50% OF FLOOR (5 SOUTH)

ADDITION

NEW BUILDING

PROJECT DESCRIPTION

CODE SUMMARY

Interior renovation of an existing 4,013 sf dialysis space to improve the condition of the unit. The project will use 2,150 sf of existing space on the same floor for a temporary dialysis ward during the construction process. NO

CHANGE OF OCCUPANCY?

New Patient Care Nonsleeping Suite in New

Health Care

SEPARATED OCCUPANCIES?

OCCUPANCY CLASSIFICATION IN 5 SOUTH

OCCUPANCIES

(Change from Existing Healthcare Suite to New

Healthcare Suite - Remodeling over 50%)

2024 LSC (TABLE 6.1.14.1)

(LSC CH 18)

YES

YES

(Section 8.3)FIRE BARRIER RATING(S) SEE LIFE SAFETY PLANS

SEPARATED OCCUPANCIES: ABOVE AND BELOW FLOORS?

TESTRATING (HRS)

EXTERIOR DOORS AND WINDOWS

SHAFTS AND EXIT PASSAGEWAYS

OTHER

ROOF CONSTRUCTION

PRIME & SEC. FLOOR BEAMS, JOISTS

FLOOR/CEILING ASSEMBLY

FLOOR CONSTRUCTION

INTERIOR

NON-BEARING WALLS AND PARTITIONS

BEARING WALLS

COLUMNS

GIRDERS

TRUSSES

ROOF/CEILING ASSEMBLY

PRIME & SEC. ROOF BEAMS, JOISTS

EXTERIOR

INTERIOR BEARING WALLS

EXTERIOR BEARING WALLS

STRUCTURAL FRAME

AREA SEPARATIONS / FIRE WALLS

FIRE-RESISTIVE REQUIREMENTS

TYPE(S) OF CONSTRUCTION

CONSTRUCTION TYPE(S)

ADDITIONAL NOTES

SEE LIFE SAFETY PLANS

See Life Safety Plans

EXISTING HEALTH CARE

-- Common path:

-- Dead-end: 30' -- Total distance: 200'

EXISTING PATIENT CARE NONSLEEPING SUITE

-- Path to exit access: 100' -- Total distance: 200'

OCCUPANT LOAD OF CONSTRUCTION ZONES

SF/OCCUPANT OCCUPANTSACTUAL AREAAREA LOCATION

ZONE 1

ZONE 2

4,013 sf

2,150 sf 150 sf/occ

1 1/2

(NFPA 220 TABLE 4.1.1) Type I (332)

PLUMBING FIXTURES

TOILETS

LAVATORIES

DRINKING FOUNTAINS

SERVICE SINKS

PROVIDED RQD FACTOR

3 UNISEX 1 E, 1 CR

1/25 (care recipient treatment area)

3 UNISEX 1 E, 1 CR

1 per floor

1--

URINALS -- -- --

(IBC CH 29)

1/100

AREAS OF REFUGE REQUIRED

MEANS OF EGRESS CAPACITY (width in inches)

EGRESS

36" Stair or 48" Corridor

NOYES

ACCESSIBLE MEANS OF EGRESS ("MOE") REQUIRED

ELEVATOR REQUIRED AS MEANS OF EGRESS

NOYES

FIRE RESISTIVE CORRIDORS?

CORRIDOR TO LIMIT THE TRANSFER OF SMOKE

INCIDENTAL USE AREA RATING(S) SEE PLANS

MISCELLANEOUS

1/50 (care recipient treatment area)

NO CHANGE

NO CHANGE

1 1/2

ZONE 1a 325 sf

150 sf/occ

300 sf/occ 2

NO

CHANGE OF OCCUPANCY?

Existing Patient Care Nonsleeping Suite in Existing Health Care

SEPARATED OCCUPANCIES?

OCCUPANCY CLASSIFICATION IN 5 WEST

OCCUPANCIES

(If Remodeling)

2024 LSC (TABLE 6.1.14.1)

(LSC CH 19) YES

(Section 8.3)FIRE BARRIER RATING(S) SEE LIFE SAFETY PLANS

SEPARATED OCCUPANCIES: ABOVE AND BELOW FLOORS?

ADDITIONAL NOTES

EXISTING HEALTH CARE

-- Common path:

-- Dead-end: 30' -- Total distance: 200'

EXISTING PATIENT CARE NONSLEEPING SUITE

-- Path to exit access: 100' -- Total distance: 200'

ZONE 2a 2,150 sf 150 sf/occ 15

APPLICABLE REGULATIONS

NFPA NATIONAL FIRE CODES (EXCEPTION: NFPA 5000 & 900)

2022 FGI GUIDELINES

2024 NFPA 101 (LIFE SAFETY CODE)

ABA STANDARDS (2015) (ABAAS)

2024 IBC (WHEN REFERENCED OR NFPA DOES NOT ADRESS ISSUE)

VA BARRIER FREE DESIGN STANDARD (PG-18-13)

NOYESAUTHORITIES HAVING JURISDICTION (AHJ's)

THE JOINT COMMISSION (JC)

U.S. DEPARTMENT OF VETERANS AFFAIRS (VA)

OSHA STANDARDS

VA SEISMIC DESIGN REQUIREMENTS H-18-8

NATIONAL ELECTRIC CODE (NEC)

ASME BOILER AND PRESSURE VESSEL CODE

ASME CODE FOR PRESSURE PIPING

BUILDING CODE REQUIREMENTS FOR REINFORCED CONCRETE,

AMERICAN CONCRETE INSTITUTE AND COMETARY (ACI 318)

ENERGY POLICY ACT OF 2005 (EPAct)

DOE INTERIM FINAL RULE: ENERGY CONSERVATION STANDARDS

FOR NEW FEDERAL, COMMERCIAL AND MULTI-FAMILY HIGH-RISE

RESIDENTIAL BUILDINGS AND NEW LOW-RISE RESIDENTIAL

BUILDINGS, 10 CFR PARTS 433,434 AND 435

FEDERAL LEADERSHIP IN HIGH PERFORMANCE AND SUSTAINABLE

BUILDINGS: MEMORANDUM OF UNDERSTANDING (MOU)

EXECUTIVE ORDER 13834

THE PROVISIONS FOR CONSTRUCTION AND SAFETY SIGNS. STATED

IN THE GENERAL REQUIREMENTS SECTION 01010 OF THE VA

MASTER CONSTRUCTION SPECIFICATION

VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY - ASHRAE

STANDARD 62.1-2004

SAFETY STANDARD FOR REFRIGERATION SYSTEMS - ASHRAE

STANDARD 15 -2007

VA FIRE PROTECTION DESIGN MANUAL

VA DIRECTIVES, DESIGN MANUALS, MASTER SPECIFICATIONS, VA

NATIONAL CAD STANDARD APPLICATION GUIDE, AND OTHER

GUIDANCE ON THE TECHNICAL INFORMATION LIBRARY (TIL)

VA PHYSICAL SECURITY AND RESILIENCE DESIGN MANUAL (PSRDM)

REMODEL, LESS THAN 50% OF FLOOR (ALL OTHERS)

TR

AV

EL

D

IS

TA

NC

E

7'

-0

E X

IT

'-5

'-7

E X

IT

E X

IT

EXIT

TR

AV

EL

D

IS

TA

NC

E

1'

TRAVEL DISTANCE

101'

5W12B

CLEAN

UTILITY

5W105W08

PATIENT

ROOM

5W08A

TOILET

5W11A

TOILET

5W11

PATIENT

ROOM

5W13

BREAKROOM

5C W03B

OFFICE

5W15

PROVIDER

WORKSTATIONS

5W21

MED PREP

5W15B

TOILET

5W29A

TOILET

5W29

DIALYSIS

STATIONS

5W27

TOILET

5W25

HSKPG

5W19

MEDICAL

REPAIR

ROOM

5W20

ISO BED

DIALYSIS

STATION

5W20A

TOILET

5W18A

TOILET

5W19A

TOILET

5W17A

TOILET

5W18

EQUIP

PROCESSING

5W17

DIALYSIS

STATIONS

5W14

SOILED

UTILITY

5W16

TOILET

5W12

CHARTING &

RECEPTION

5CW02

CORRIDOR

5CW01

CORRIDOR

5CW05

CORRIDOR

196 SF

5S24

R.O.

TREATMENT

157 SF

5C S02A

CORRIDOR

96 SF

5S18

SOILED

UTILITY

ROOM

189 SF

5S21

MEDICAL

REPAIR

ROOM

20 SF

5S23

LINEN

151 SF

5S25

BREAKROOM

33 SF

5S20

HSKPG

33 SF

5S22

STAFF

TOILET

167 SF

5S14A

EQUIP

CLEAN

STORAGE

138 SF

5S17

EQUIP

PROCESSING

50 SF

5S19

PATIENT

TOILET

188 SF

5S07

NURSE

STATION

76 SF

5S11

MED PREP

82 SF

5S09

CLEAN

SUPPLY

56 SF

5S04B

ISO TOILET

146 SF

5S04

ISO

DIALYSIS

BED

52 SF

5S04A

ANTE ROOM

52 SF

5S03

RECEPTION

109 SF

5S01

CHIEF

OFFICE

977 SF

5S02

CORRIDOR

ZONE 1

ZONE 2

5W07

TELECOM

5W09

PATIENT

ROOM

5W31

DIALYSIS

STATIONS

5W33

STORAGE

5W34

DIALYSIS

STATIONS

5W32

DIALYSIS

STATIONS

5W30

DIALYSIS

STATION

5W32A

TOILET

5W34A

TOILET

5W31A

TOILET

5W33A

TOILET

5W30A

TOILET

5E02

OFFICE

5E01

OFFICE

5E03

EQUIPMENT

5W09A

TOILET

5C01

ELEVATOR

LOBBY

5W06

PATIENT

ROOM

5W06A

TOILET

FEC

FEC

132'-0 1/2"

'-1

FEC

FEC

FEC

FEC

FEC

FEC

TRAVEL DISTANCE

75'

ZONE 1a

ZONE 1a

5S16

MECHANICAL

ROOM

5ST05

STAIR

5CE04

CORRIDOR

A1

ELEVATOR

A2

ELEVATOR

A3

ELEVATOR

A4

ELEVATOR

A5

ELEVATOR

5W01

DUMBWAITER

5N01 5W02

5ST04

STAIR

5W24

5W01A 5W03

5N05

5CW01A

5E04

PAT RM 6

5E04A

TLT

5E06

PAT RM 5

5E06A

TOILET

5E05A

TOILET

5E05

PATIENT

ROOM 7

PALLIATIVE

CARE

5E07

FAMILY

ROOM

5E09A

TOILET

5W04

B3

ELEVATOR

B2

ELEVATOR

B1

ELEVATOR

5W22

5W23

5CW04

5W12A

5W100

TELECOM

ZONE 2a

5ST01

STAIR

5W101

5W35

5ST13

STAIR

5CN01

LOBBY

5CW03A

CORRIDOR

FE

FEC

'-1

0"

16'-5 1/4"

46'-0 1/2"

SHAFT

SHAFT

SHAFT

SHAFT

SHAFT

LIFE SAFETY SYMBOLS

SMOKE TIGHT

ASSEMBLY

2 HOUR FIRE &

SMOKE BARRIER

1 HOUR FIRE &

SMOKE BARRIER

2 HOUR FIRE &

SMOKE BARRIER

HE

TRAVEL DISTANCE

100'-10"

TRAVEL DISTANCE

EA

EDEXIT EXIT

HORIZONTAL EXIT

EXIT DISCHARGE

EXIT ACCESS

FIRE

EXTINGUISHER

FE

FIRE

EXTINGUISHER

CABINET

FEC

LIMITS OF

CONSTRUCTION

SMOKE

COMPARTMENT

BOUNDARY

HEALTH CARE

SUITE

NOTE: NOT ALL SYMBOLS MY BE USED ON EACH PLAN

OCCUPANCY

SEPARATION

SHAFT

ADJACENT SYMBOLS SHOW PARTITION RATING AND

DAMPER REQUIREMENTS

HAZARDOUS USE

ADJACENT SYMBOLS SHOW PARTITION RATING.

OPENINGS REQUIRE CLOSER & LATCH

EXIT PASSAGEWAY

RATE AS STAIR

ALL OPENINGS TO BE RATED AS STAIR SHAFT

NOT IN SCOPE

NO CONSTRUCTION IN THIS AREA AS PART OF

THIS PROJECT.

ADJUNCT CORRIDOR or PSYCHIATRIC AREA or CONSTRUCTED WITH MIN. 4'-0" CLEAR

WITH (PER CHAPTER 19)

CORRIDOR

SMOKE ZONE

BARRIER

KEYPLAN - BUILDING 1, 5TH FLOOR

TRUE

NORTH

ZONE 1

ZONE 2

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

DESIGNER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

IMEG CORP

2882 106th St,Des Moines, IA 50322 Contact: Dellan Llewellyn

(515) 334-7921

LANDMARK ENVIRONMENTAL

9555 James Ave S - Ste 262, Bloomington, MN 55431 Contact: Mark Meier (952) 295-9410

C U s e rs \p c h o i\ D o c u m e n ts

\1

-I C

V A

F L R

-A -R

Y e u n y o u n g .r v t

/2

/2

:2

:0

A

M

1-I3

5TH FLOOR - LIFE SAFETY PLAN RENOVATE DIALYSIS

IOWA CITY, IA

636A8-24-001

04/24/2025 EM MWC

17909

1/8" = 1'-0"

FIFTH FLOOR - LIFE SAFETY PLAN

0 8' 16'4'

VHA INFECTION CONTROL RISK ASSESSMENT FOR CONSTRUCTION, RENOVATION AND MAINTENANCE

TABLE 1 - CONSTRUCTION, RENOVATION, AND/OR MAINTENANCE ACTIVITY CATEGORY

Category A

INSPECTION AND/OR FACILITY UPKEEP GENERALLY DEFINED AS FOLLOWS:

• WORK CAN BE COMPLETED IN A SINGLE SHIFT, NOT TO EXCEED 10 HOURS.

• PATIENTS AND/OR EMPLOYEES MAY BE IN THE AREA DEPENDING ON THE ACTIVITY.

• WORK THAT DOES NOT CREATE DUST OR DEBRIS.

• REMOVAL OF CEILING TILE OR ACCESS TO MECHANICAL OR ELECTRICAL CHASE FOR

VISUAL INSPECTION LIMITED TO 1 TILE PER 50 SQUARE FEET WITH LIMITED EXPOSURE

TIME (NOT TO EXCEED AN HOUR FOR EACH TILE) WITHIN THE SHIFT.

• MINOR INTERIOR UPDATES (E.G., REPLACING FLOOR OR CEILING TILES, CARPENTRY

WORK TO INCLUDE HANGING SIGNAGE, AND PAINTING WITHOUT SANDING) THAT DO NOT

CREATE DUST OR DEBRIS.

• LIMITED BUILDING SYSTEM MAINTENANCE SUCH AS PLUMBING ON POTABLE SYSTEMS

LIMITED TO FAUCET REPLACEMENT ETC. AND ELECTRICAL WORK SUCH AS

REPLACEMENT OF BULBS, RECEPTACLES, OR SWITCHES.

Category B

GENERAL MAINTENANCE AND REPAIR WORK GENERALLY DEFINED AS FOLLOWS:

• PROLONGED INSPECTION AND WORK THAT MAY TAKE LONGER THAN A SINGLE SHIFT

BUT NOT EXCEEDING A WEEK.

• PATIENTS AND EMPLOYEES ARE NOT TO BE IN THE AREA UNTIL ACTIVITY IS

COMPLETED.

• WORK THAT CREATES MINIMAL DUST AND DEBRIS.

• INTERIOR FINISH OR SURFACE REPAIRS, UPDATES, OR MODIFICATIONS SUCH AS

REPAIR OF FIREWALLS AND BARRIERS, AND NEW FLOORING THAT PRODUCES MINIMAL

DUST AND DEBRIS. CONTROLLED SANDING ACTIVITIES (E.G., WET OR DRY SANDING)

THAT PRODUCE MINIMAL DUST AND DEBRIS.

• PLUMBING WORK SUCH AS INSTALLATION OR REPLACEMENT OF A SINGLE FIXTURE OR

PIPING FOR A SINGLE FIXTURE. ANY WORK ON SANITARY PLUMBING INCLUDING

SNAKING OF DRAINS.

• ELECTRICAL WORK SUCH AS INSTALLATION OF CABLING/WIRING/CONDUIT FOR A

SINGLE DEVICE, INSTALLATION OF NEW DEVICE SUCH AS A LIGHT FIXTURE THAT

PRODUCES MINIMAL DUST AND DEBRIS.

• AIR HANDLER AND/OR FAN SHUTDOWN/STARTUP AND HVAC WORK SUCH AS

REPLACEMENT OF A SINGLE DIFFUSER, SINGLE TERMINAL UNIT OR A SINGLE DEVICE

THAT PRODUCES MINIMAL DUST AND DEBRIS.

Category C

SMALL-SCALE CONSTRUCTION, RENOVATION, OR MAINTENANCE GENERALLY DEFINED AS FOLLOWS:

• WORK REQUIRING LONGER THAN A SINGLE WEEK TO COMPLETE BUT NOT EXCEEDING

6 MONTHS.

• PATIENTS AND EMPLOYEES ARE NOT TO BE IN THE AREA UNTIL ACTIVITY IS

COMPLETED.

• DEMOLITION/REMOVAL OF PREEXISTING FLOOR COVERING, CASEWORK, LAY-IN

CEILING, OR OTHER ARCHITECTURAL ELEMENTS.

• DEMOLITION/REMOVAL OF MORE THAN 32 FT2 OF DRYWALL/FRAMING, HARD CEILINGS,

AND DOORS/FRAMING AND MINIMAL INFRASTRUCTURE SUCH AS ELECTRICAL CIRCUITS

AND BRANCH PIPING.

• INSTALLATION OF NEW WALLS, CEILINGS AND DOORS INCLUDING FRAMING,

DRYWALL/PLASTER AND ASSOCIATED WORK.

• PLUMBING WORK SUCH AS THE INSTALLATION OF NEW SINKS, SHOWERS AND TOILETS

AND ASSOCIATED PLUMBING.

• SHUT DOWN OF SECTIONS OF POTABLE WATER SYSTEMS.

• ELECTRICAL WORK SUCH AS INSTALLATION OF CONDUIT AND WIRE FOR LIGHTING,

RECEPTACLES AND SWITCHES FOR AN AREA, THE INSTALLATION OF CONDUIT AND

WIRE FOR NEW DEVICES SUCH AS TERMINAL UNITS, FANS ETC.

• MODIFICATION OF EXISTING FIRE ALARM AND SUPPRESSION SYSTEMS.

• MECHANICAL WORK SUCH AS THE INSTALLATION OF DUCTWORK, DIFFUSERS, AND

TERMINAL UNITS FOR AN AREA.

Category D

LARGE-SCALE CONSTRUCTION, RENOVATION, OR MAINTENANCE GENERALLY DEFINED AS FOLLOWS:

• WORK EXCEEDING 6 MONTHS IN DURATION.

• PATIENTS AND EMPLOYEES ARE NOT TO BE IN THE AREA UNTIL ACTIVITY IS

COMPLETED.

• LARGE-SCALE DEMOLITION OF BUILDING COMPONENTS AND INFRASTRUCTURE

INCLUDING REMOVAL OF MULTIPLE DOORS, WALLS, FRAMING, CEILINGS, FLOORING,

PIPING, ELECTRICAL AND HVAC.

• THE INSTALLATION BUILDING COMPONENTS SUCH AS NEW WALLS, CEILINGS AND

DOORS INCLUDING FRAMING, DRYWALL AND ASSOCIATED PLASTER WORK.

• PLUMBING WORK SUCH AS THE INSTALLATION OF:

• NEW MEDICAL GAS SYSTEMS,

• STEAM/HEATING HOT WATER, CONDENSATE SYSTEMS,

• MULTIPLE SINKS, SHOWERS AND TOILETS INCLUDING ASSOCIATED PLUMBING.

• SHUTDOWN OF POTABLE WATER, STEAM/HEATING HOT WATER, CONDENSATE, AND

MEDICAL GAS SYSTEMS.

• ELECTRICAL WORK SUCH AS INSTALLATION OF ELECTRICAL FEEDERS, DISTRIBUTION

PANELS, CONDUIT AND WIRE FOR LIGHTING, RECEPTACLES AND SWITCHES FOR AN

AREA, THE INSTALLATION OF CONDUIT AND WIRE FOR NEW DEVICES SUCH AS

TERMINAL UNITS, FANS ETC.

• INSTALLATION OF FIRE ALARM AND SUPPRESSION SYSTEMS.

• ELECTRICAL SHUTDOWN OF MULTIPLE PANELS.

• MECHANICAL WORK SUCH AS THE INSTALLATION OF AIR HANDLING EQUIPMENT,

ASSOCIATED DUCTWORK, DIFFUSERS, HEAT EXCHANGERS, TERMINAL UNITS AND

CONTROLS.

ACTIVITY AREA**

ACTIVITY CATEGORY

PATIENT RISK

CATEGORY A B C D

LOW RISK

MEDIUM RISK

HIGH RISK

HIGHEST RISK

I II II III

I II III IV

I II IV

II IVIII IV

IV

AN INFECTION PREVENTION AND CONTROL PERMIT IS REQUIRED FOR LEVEL III AND LEVEL IV.

CONSULT WITH INFECTION PREVENTION AND CONTROL FOR LEVEL I AND LEVEL II.

TABLE 3 - PATIENT RISK CATEGORY

SERVICE(S)/TYPE(S) OF AREA(S)

(E.G., OR, UNIT/WARD, STERILE

PROCESSING, ADMINISTRATIVE,

ETC.)*

AREA POINT OF CONTACT (POC)SERVICE(S)/TYPE(S) OF AREA(S)

(E.G., OR, UNIT/WARD, STERILE

PROCESSING, ADMINISTRATIVE,

ETC.)*

POC CONTACT

INFORMATION

AREA ABOVE

AREA BELOW

ADJACENT AREA 1

ADJACENT AREA 2

ADJACENT AREA 3

ADJACENT AREA 4

* THERE MAY BE MORE THAN ONE SERVICE/TYPE OF AREA FOR EACH ROW. LIST ALL.

** LIST THE AREA(S) IN WHICH THE CONSTRUCTION/RENOVATION/MAINTENANCE ACTIVITY WILL OCCUR. NOTE:

WHEN THE ACTIVITY CATEGORY IS B, C, OR D, THE CONTROL MEASURES ARE DETERMINED BY THE PATIENT

RISK IN THE ADJACENT AFFECTED AREAS

LOW RISK MEDIUM RISK HIGH RISK HIGHEST RISK

• PUBLIC HALLWAYS AND

GATHERING AREAS NOT IN

CLINICAL AREAS

• OFFICE AREAS NOT IN

CLINICAL AREAS

• BREAKROOMS NOT IN

CLINICAL AREAS

• BATHROOMS OR LOCKER

ROOMS NOT IN CLINICAL

AREAS

• MECHANICAL/ELECTRICAL

ROOMS NOT IN CLINICAL

AREAS

• WAITING AREAS

• CLINICAL ENGINEERING

(BIOMEDICAL)

• MATERIALS MANAGEMENT

• STERILE PROCESSING

DEPARTMENT – DIRTY SIDE

• KITCHEN, CAFETERIA, GIFT

SHOP, COFFEE SHOP, AND

FOOD KIOSKS

• PATIENT CARE ROOMS AND

AREAS, INCLUDING SPINAL

CORD INJURY UNITS

• ALL ACUTE CARE UNITS,

INCLUDING MENTAL HEALTH

• ALL OUTPATIENT UNITS AND

CLINICS

• EMERGENCY DEPARTMENT

• COMMUNITY LIVING

CENTERS, DOMICILIARIES,

AND TRANSITIONAL

RESIDENCES

• EMPLOYEE HEALTH

• PHARMACY – GENERAL

WORK ZONE

• MEDICATION ROOMS AND

CLEAN UTILITY ROOMS

• IMAGING SUITES –

DIAGNOSTIC IMAGING

• LABORATORY

• ALL TRANSPLANT UNITS

• ALL INTENSIVE CARE UNITS

• ALL ONCOLOGY UNITS AND

CHEMOTHERAPY/INFUSION

CENTERS

• OR THEATERS AND

RESTRICTED AREAS

• HEMODIALYSIS UNITS

• PROCEDURAL ROOMS*

• PHARMACY COMPOUNDING

AREA

• STERILE PROCESSING

DEPARTMENT – CLEAN SIDE

• TRANSFUSION SERVICES

• IMAGING SUITES –

INTERVENTIONAL IMAGING

• DEDICATED ISOLATION

WARDS/UNITS FOR

INFECTIOUS DISEASES

NON-PATIENT CARE AREAS

SUCH AS:

PATIENT CARE SUPPORT AREAS

SUCH AS:

PATIENT CARE AREAS

SUCH AS:

PROCEDURAL, INVASIVE,

STERILE SUPPORT AND HIGHLY

COMPROMISED PATIENT CARE

AREAS SUCH AS:

* PROCEDURAL ROOMS ARE DESIGNATED FOR THE PERFORMANCE OF PATIENT CARE ACTIVITIES THAT MAY REQUIRE HIGH-LEVEL DISINFECTED OR STERILE INSTRUMENTS AND SOME ENVIRONMENTAL CONTROLS BUT IS NOT REQUIRED TO BE PERFORMED WITH THE ENVIRONMENTAL CONTROLS OF AN OPERATING ROOM (OR). THE ROOM IS INTENDED FOR PROCEDURES THAT ARE PERFORMED IN AN ASEPTIC SURGICAL FIELD AND PENETRATES THE PROTECTIVE SURFACES OF A PATIENT’S BODY (E.G., SUBCUTANEOUS TISSUE, MUCOUS MEMBRANES, CORNEA) OR ENTRY INTO OR OPENING OF A STERILE BODY CAVITY. EXAMPLES OF THESE SPACES INCLUDE CARDIAC CATHETERIZATION SUITES, ELECTROPHYSIOLOGY SUITES, ENDOVASCULAR/GI SUITES, ANGIO SUITES AND OTHER SPACES WHICH MAY HAVE

HIGH RISK PATIENT POPULATIONS.

TABLE 4 - LEVEL OF INFECTION PREVENTION AND CONTROL PRECAUTIONS

TABLE 2 - AFFECTED AREA ASSESSMENT

VHA INFECTION CONTROL RISK ASSESSMENT FOR CONSTRUCTION,

RENOVATION AND MAINTENANCE

TABLE 5 - REQUIRED INFECTION PREVENTION AND CONTROL MEASURES, BY LEVEL OF PRECAUTIONS

CONTROLS DEFINED BELOW FOR THE LEVEL OF PRECAUTIONS IDENTIFIED FOR THE ACTIVITY MUST BE IN PLACE BEFORE THE ACTIVITY BEGINS AND MAINTAINED UNTIL WORK IS COMPLETED AND THE AREA IS ACTIVATED. CONTROL MEASURES FOR EACH PRECAUTION LEVEL MUST ALSO INCLUDE THE CONTROL MEASURES IN THE PRECEDING LEVEL(S).

AS THE ACTIVITY PROGRESSES, A FULL RE-EVALUATION OF REMAINING ACTIVITY TYPE AND PATIENT RISK IS REQUIRED PRIOR TO

DOWNGRADING THE LEVEL OF PRECAUTIONS.

LEVEL OF

PRECAUTIONS

CONTROL MEASURES

LEVEL I

1. PERFORM WORK ACTIVITY IN A MANNER THAT DOES NOT CREATE DUST.

2. IMMEDIATELY REPLACE ANY CEILING TILE, CLOSE ACCESS PANELS, ETC., UPON COMPLETION OF WORK.

ANY MATERIALS AND EQUIPMENT BEING BROUGHT INTO THE FACILITY MUST BE FREE OF CONTAMINANTS AND LOOSE

MATERIAL.

TABLE 6 - MINIMUM INFECTION PREVENTION AND CONTROL MEASURES REQUIRED UPON COMPLETION OF THE ACTIVITY

CONTROLS DEFINED BELOW SHALL BE COMPLETED UPON COMPLETION OF THE ACTIVITY AND INSPECTED PRIOR TO TERMINATING

MEASURES DEFINED IN TABLE 5.

LEVEL OF

PRECAUTIONS

MEASURES

LEVELS I - II

CLEANING:

1. CLEAN WORK AREAS INCLUDING ALL ENVIRONMENTAL SURFACES, HIGH HORIZONTAL SURFACES AND

FLOORING MATERIALS.

2. CHECK ALL SUPPLY AND RETURN AIR REGISTERS FOR DUST ACCUMULATION ON UPPER SURFACES AS

WELL AS AIR DIFFUSER SURFACES.

HVAC SYSTEMS:

1. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED. VERIFY THAT

HVAC SYSTEMS ARE CLEAN AND OPERATIONAL.

2. VERIFY THE HVAC SYSTEMS MEET ORIGINAL AIRFLOW AND AIR EXCHANGE DESIGN SPECIFICATIONS.

WATER SYSTEMS:

UNTIL THE POTABLE WATER SYSTEM IS ACTIVATED AND IN USE, FLUSHING SHALL CONTINUE AT LEAST TWICE PER WEEK

IN ACCORDANCE WITH VHA DIRECTIVE 1061.

LEVELS III - IV

CONSTRUCTION AREAS MUST BE INSPECTED BY AN INFECTION PREVENTIONIST AND ENGINEERING REPRESENTATIVE (AND OTHERS AS DETERMINED BY THE FACILITY) FOR FINAL ACTIVITY/PROJECT CLOSE OUT AND REMOVAL OF INFECTION

PREVENTION AND CONTROL MEASURES.

WORK AREA CLEANING:

1. CLEAN WORK AREAS INCLUDING ALL ENVIRONMENTAL SURFACES, HIGH HORIZONTAL SURFACES AND

FLOORING MATERIALS.

2. CHECK ALL SUPPLY AND RETURN AIR REGISTERS FOR DUST ACCUMULATION ON UPPER SURFACES AS

WELL AS AIR DIFFUSER SURFACES.

REMOVAL OF CRITICAL BARRIERS:

1. CRITICAL BARRIERS MUST REMAIN IN PLACE DURING ALL WORK INVOLVING DRYWALL REMOVAL, CREATION OF DUST AND ACTIVITIES BEYOND SIMPLE TOUCH-UP WORK. THE BARRIER MAY NOT BE REMOVED UNTIL A WORK AREA CLEANING HAS BEEN PERFORMED. ADDITIONAL CLEANING MAY BE

NEEDED AFTER REMOVAL OF BARRIER.

2. ALL (PLASTIC OR HARD) BARRIER REMOVAL ACTIVITIES MUST BE COMPLETED IN A MANNER THAT PREVENTS DUST RELEASE. USE THE FOLLOWING PRECAUTIONS WHEN REMOVING HARD BARRIERS:

A. CAREFULLY REMOVE SCREWS AND PAINTER TAPE.

B. IF DUST WILL BE GENERATED DURING SCREW REMOVAL, USE HAND-HELD HEPA VACUUM.

C. DRYWALL CUTTING IS PROHIBITED DURING REMOVAL PROCESS.

D. CLEAN ALL STUD TRACKS WITH HEPA VACUUM BEFORE REMOVING OUTER HARD BARRIER.

E. USE A PLASTIC BARRIER TO ENCLOSE AREA IF DUST COULD BE GENERATED.

NEGATIVE AIR REQUIREMENTS:

1. THE USE OF NEGATIVE AIR MUST BE DESIGNED TO REMOVE CONTAMINANTS FROM THE WORK AREA.

2. NEGATIVE AIR DEVICES (FANS, FILTERS, MONITORING AND DOCUMENTATION EQUIPMENT) MUST

REMAIN OPERATIONAL AT ALL TIMES AND IN PLACE FOR A PERIOD AFTER COMPLETION OF DUST CREATING ACTIVITIES TO REMOVE CONTAMINANTS FROM THE WORK AREA AND BEFORE REMOVAL OF

CRITICAL BARRIERS.

HVAC SYSTEMS:

1. UPON REMOVAL OF CRITICAL BARRIERS, REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE

WORK IS BEING PERFORMED.

2. VERIFY THAT HVAC SYSTEMS ARE CLEAN AND OPERATIONAL.

3. VERIFY AND DOCUMENT THROUGH A TAB THE HVAC SYSTEMS MEETS ORIGINAL AIRFLOW AND AIR

EXCHANGE DESIGN SPECIFICATIONS.

WATER SYSTEMS:

UNTIL THE POTABLE WATER SYSTEM IS ACTIVATED AND IN USE, FLUSHING SHALL CONTINUE AT LEAST TWICE PER WEEK

IN ACCORDANCE WITH VHA DIRECTIVE 1061.

LEVEL II

ALL CONTROL MEASURES IN LEVEL I AND THE FOLLOWING:

1. PROVIDE ACTIVE MEANS TO CONTROL AIRBORNE DUST FROM DISPERSING INTO OCCUPIED AREAS AND/OR WATER

MIST SURFACE TO CONTROL DUST (E.G., MOBILE DUST CONTAINMENT CART OR SOME OTHER SYSTEM).

2. ENSURE WORKER CLOTHING IS CLEAN AND FREE OF VISIBLE DUST BEFORE LEAVING THE WORK AREA.

3. REMOVE OR ISOLATE AIR DIFFUSERS (SUPPLY AND RETURN) TO PROTECT THE HVAC SYSTEM FROM DUST AND

REDUCE AIR TURBULENCE. REBALANCE SYSTEM TO ADDRESS DIFFUSER ISOLATION.

4. WHEN THE WORK INVOLVES OR IMPACTS POTABLE WATER SYSTEMS INCLUDING STAGNATION DUE TO REDUCED

USAGE, THE PIPING SHALL BE FLUSHED TWICE A WEEK OR ISOLATED FROM THE MAIN SYSTEM.

5. SEAL DOORS TO PREVENT DUST MIGRATION.

6. CONTAIN ALL TRASH AND DEBRIS IN THE WORK AREA. PERFORM DAILY CLEANING AND DISPOSAL OF TRASH

(COVERED) FROM WORK AREA USING AN IDENTIFIED EXIT ROUTE.

7. ANY EQUIPMENT, TOOLS, OR MATERIALS REMOVED FROM THE WORK AREA MUST BE IN SEALED CONTAINERS

AND/OR CLEANED OF DUST AND DEBRIS PRIOR TO REMOVAL FROM THE AREA.

8. NONPOROUS/SMOOTH AND CLEANABLE CONTAINERS (WITH A HARD LID) MUST BE USED TO TRANSPORT TRASH AND

DEBRIS FROM THE CONSTRUCTION AREAS. THESE CONTAINERS MUST BE DAMP-WIPED CLEANED AND FREE OF

VISIBLE DUST/DEBRIS BEFORE LEAVING THE CONTAINED WORK AREA.

9. INSTALL A STICKY (DUST COLLECTION) MAT AT ENTRANCE OF CONTAINED WORK AREA BASED ON FACILITY POLICY.

STICKY MATS MUST BE CHANGED ROUTINELY AND WHEN VISIBLY SOILED.

10. MAINTAIN CLEAN SURROUNDINGS WHEN AREA IS NOT CONTAINED BY DAMP MOPPING OR HEPA VACUUMING

SURFACES AT LEAST DAILY.

LEVEL III

ALL CONTROL MEASURES IN LEVELS I AND II AND THE FOLLOWING:

1. ENSURE AVAILABILITY OF EQUIPMENT FOR CLEANING HANDS.

2. CONSTRUCT AND COMPLETE CRITICAL BARRIERS MEETING NFPA 241 REQUIREMENTS. BARRIERS MUST EXTEND TO

THE CEILING OR IF CEILING TILE IS REMOVED, TO THE DECK ABOVE.

3. ALL (PLASTIC OR HARD) BARRIER CONSTRUCTION ACTIVITIES MUST BE COMPLETED IN A MANNER THAT PREVENTS

DUST RELEASE. PLASTIC BARRIERS MUST BE EFFECTIVELY AFFIXED TO FLOOR AND CEILING (OR FLOOR/ROOF DECK

ABOVE) AND SECURE FROM MOVEMENT OR DAMAGE.

4. SEAL ALL PENETRATIONS IN CONTAINMENT BARRIERS, INCLUDING FLOORS AND CEILING, USING APPROVED

MATERIALS (UL SCHEDULE FIRESTOP IF APPLICABLE FOR BARRIER TYPE).

5. MAINTAIN .01 INCHES /WATER GAUGE NEGATIVE PRESSURIZATION OF THE ENTIRE WORKSPACE BY USE OF HEPA EXHAUST AIR SYSTEMS DIRECTED OUTDOORS (UNLESS A WORK SPECIFIC WAIVER IS APPROVED BY VHA’S OFFICE OF HEALTHCARE ENGINEERING); THIS MUST BE MAINTAINED CONTINUOUSLY 24/7 FOR THE DURATION OF THE PROJECT. EXHAUST DISCHARGED DIRECTLY TO THE OUTDOORS THAT IS 25 FEET OR GREATER FROM ENTRANCES, AIR INTAKES AND WINDOWS IS NOT REQUIRED TO BE HEPA-FILTERED. EXHAUSTING DISCHARGED AIR INTO SHARED OR RECIRCULATING HVAC SYSTEMS, OR OTHER SHARED EXHAUST SYSTEMS (E.G., BATHROOM EXHAUST) IS

PROHIBITED.

6. INSTALL A DIFFERENTIAL PRESSURE SENSING DEVICE (E.G., MAGNEHELIC, MANOMETER, OR DIGITAL MONITORING) ON EXTERIOR OF WORK CONTAINMENT TO CONTINUALLY MONITOR AND DOCUMENT NEGATIVE PRESSURIZATION.

THE “BALL IN THE WALL” OR SIMILAR APPARATUS ARE NOT ACCEPTABLE.

LEVEL IV

ALL CONTROL MEASURES IN LEVELS I, II AND III AND THE FOLLOWING:

1. BARRIERS MUST BE HARD BARRIERS UNLESS TEMPORARY TO INSTALL FINAL BARRIER.

2. CONTAINMENT MUST INCLUDE AN ANTEROOM TO ENSURE PRESSURE CONTROL. ANTEROOM MUST BE LARGE

ENOUGH FOR EQUIPMENT STAGING, CART CLEANING, WORKERS’ PPE AND CLEANING.

3. WORKER CLOTHING AND/OR PPE MUST BE REMOVED OR CLEAN AND FREE OF VISIBLE DUST BEFORE LEAVING THE

WORK AREA ANTEROOM. HEPA VACUUMING OF CLOTHING OR USE OF COVER SUITS IS ACCEPTABLE.

4. WORKERS MUST WEAR SHOE COVERS OR HAVE A METHOD TO CLEAN SHOES IN ANTEROOM. SHOE COVERS MUST BE

REMOVED PRIOR TO EXITING THE ANTEROOM TO THE OCCUPIED SPACE (NON-WORK AREA). DAMAGED SHOE

COVERS MUST BE CHANGED IMMEDIATELY.

INFECTION CONTROL & CONSTRUCTION

BARRIER GENERAL NOTES

1. SEE SPEC SECTION 01 35 26 SAFETY REQUIREMENTS FOR ADDITIONAL

INFORMATION

2. THE INTENT OF INFECTION CONTROL ISOLATION IS TO CONTAIN DUST AND

PARTICULATE MATTER TO THE CONSTRUCTION AREA. CONSTRUCTION AREA

PERIMETER NEEDS TO BE SEALED COMPLETELY WITH SHEET PLASTIC AS

SPECIFIED AND DUCT TAPE DURING OPERATIONS, WHERE PERMITTED BY CLASS.

ICRA - CONSTRUCTION BARRIER TO BE PROVIDED AS SPECIFIED AND LISTED IN

ICRA CLASS.

3. PROVIDE NEGATIVE PRESSURE MONITORS DURING CONSTRUCTION OPERATIONS

AS SPECIFIED. MONITOR TO MEASURE PRESSURE DIFFERENTIAL BETWEEN

CONSTRUCTION AREA AND ADJACENT CORRIDOR OR ROOM AS DIRECTED BY VA.

4. AS CONSTRUCTION PROGRESSES, FROM TYPE D TO TYPE C AND THEREON,

PROVIDE A REQUEST VIA "INFECTION CONTROL CONSTRUCTION PERMIT" TO THE

VA INFECTION CONTROL NURSE. UPON AUTHORIZATION, PROCEED TO NEXT TYPE

OF CONSTRUCTION. PROVIDE AT LEAST TEN (10) WORKING DAYS NOTICE FOR

EACH PERMIT.

5. CONSTRUCT IC (INFECTION CONTROL) CONSTRUCTION BARRIER(S) FROM FLOOR

TO DECK/FLOOR ABOVE. EXCEPTION. IF BARRIER IS ADJACENT TO SMOKE, FIRE,

OR EXISTING WALL CONSTRUCTION WHICH WILL NOT BE DEMOLISHED AND

TERMINATES TO FLOOR/DECK ABOVE, THEN CONSTRUCT DUST PROOF IC

BARRIER, SEE DETAIL(S). TAPE, MUD, SAND JOINTS AND PAINT ON NON-

CONSTRUCTION SIDE OF BARRIER.

6. INFECTION CONTROL BARRIERS ARE TO BE INSTALLED AND REMOVED ONLY

BEFORE 7:00 AM AND AFTER 8:00 PM OR DIRECTED BY COR

7. DURING CONSTRUCTION OPERATIONS IN EACH ENCLOSED AREA PROVIDE

NEGATIVE PRESSURE MONITORS, MINIMUM (1) ONE IN AREAS LESS THAN 1000 SF,

(2) TWO MINIMUM IN AREAS BETWEEN 1000 SF AND 5000 SF, AND (3) THREE FOR

AREAS BETWEEN 5000 SF AND 10000 SF.

8. LIFE SAFETY EGRESS IS TO BE MAINTAINED AT ALL TIMES.

9. THE CONTRACTOR MUST PROVIDE ENOUGH NEGATIVE AIR MACHINES TO

COMPLETELY EXCHANGE THE REGULATED AREA AIR VOLUME (4) FOUR ACTUAL

TIMES PER HOUR. THE COMPETENT PERSON SHALL DETERMINE THE NUMBER OF

UNITS NEEDED FOR EACH REGULATED AREA BY DIVIDING THE CUBIC FEET IN THE

REGULATED AREA BY (15) FIFTEEN AND THEN DIVIDING THAT RESULT BY THE

ACTUAL CUBIC FEET PER MINUTE (CFM) FOR EACH UNIT TO DETERMINE THE

NUMBER OF UNITS NEEDED TO EFFECT (4) FOUR AIR CHANGES PER HOUR.

PROVIDE A STANDBY UNIT IN THE EVENT OF MACHINE FAILURE AND/OR

EMERGENCY IN AN ADJACENT AREA.

10. PRIOR TO ANY REMOVAL OF SMOKE BARRIER FIRE RATED PARTITIONS,

CONSTRUCT NEW SMOKE BARRIER/APPROPRIATE FIRE RATED PARTITIONS PER

PLANS OR CONSTRUCT INFECTION CONTROL BARRIER TO ACT AS SMOKE

BARRIER.

3RD FLOOR MODIFICATION_____________________

ZONE 1

CONSTRUCTION ZONE 3

CONSTRUCTION PROJECT ACTIVITY: B

INFECTION CONTROL RISK GROUP: MEDIUM

CLASS OF PRECAUTION: II

INFECTION CONTROL RISK ASSESSMENT (ICRA) BY PROJECT AREA USE AND PHASE

ZONE 2

CONSTRUCTION ZONE 5.2.A

CONSTRUCTION PROJECT ACTIVITY: B

INFECTION CONTROL RISK GROUP: HIGH

CLASS OF PRECAUTION: II

CONSTRUCTION ZONES

5.2.B, 5.2.C, 5.2.D, 5.2.E, 5.2.F, 5.2.G, 5.2.H

CONSTRUCTION PROJECT ACTIVITY: A

INFECTION CONTROL RISK GROUP: HIGH

CLASS OF PRECAUTION: I

CONSTRUCTION ZONE 5.2.I

CONSTRUCTION PROJECT ACTIVITY: B

INFECTION CONTROL RISK GROUP: LOW

CLASS OF PRECAUTION: II

5TH FLOOR MODIFICATIONS______________________________________________________________________________________

ZONE 1

CONSTRUCTION ZONE 5.1 A

CONSTRUCTION PROJECT ACTIVITY: D

INFECTION CONTROL RISK GROUP: HIGH

CLASS OF PRECAUTION: IV

CONSTRUCTION ZONE 5.1 B

CONSTRUCTION PROJECT ACTIVITY: C

INFECTION CONTROL RISK GROUP: MEDIUM

CLASS OF PRECAUTION: III

CONSTRUCTION ZONE 5.1 C

CONSTRUCTION PROJECT ACTIVITY: C

INFECTION CONTROL RISK GROUP: LOW

CLASS OF PRECAUTION: II

CONSTRUCTION ZONES 5.1 D

CONSTRUCTION PROJECT ACTIVITY: B

INFECTION CONTROL RISK GROUP: LOW

CLASS OF PRECAUTION: II

4TH FLOOR MODIFICATIONS_____________________

ZONE 1

CONSTRUCTION ZONES

4.1.A, 4.1.B, 4.1.C, 4.1.D, 4.1.E

CONSTRUCTION PROJECT ACTIVITY: B

INFECTION CONTROL RISK GROUP: HIGHEST

CLASS OF PRECAUTION: III

EXISTING

STRUCTURE

ABOVE

CONTINUOUS 1 HR

RATED FIRE CAULK

SEAL EACH SIDE

AT CEILING

COMPRESSIBLE

INSULATION

CONTINUOUS 1 HR

RATED FIRE CAULK SEAL

EACH SIDE AT FLOOR

EXISTING

FINISHED

FLOOR

(1) LAYER 5/8" GYP BD EACH SIDE.

FINISH OCCUPIED SIDE WITH GLOSS

PAINT. SEE SPECIFICATIONS.

3 5/8" STEEL STUDS @ 16" OC WITH SOUND

ATTENUATING INSULATION FULL HEIGHT

CLOSE OPEN DUCTS WITH 6

MIL POLYETHYLENE BARRIER.

SEAL EDGES WITH

CONTINUOUS DUCT TAPE

CONSTRUCTION SIDE OF BARRIER OCCUPIED SIDE

OF BARRIER

COMPRESSIBLE

INSULATION

REMOVE PORTION OF

CEILING OR ENTIRE

CEILING AS REQUIRED

ON CONSTRUCTION SIDE

OF BARRIER TO INSTALL

CONSTRUCTION /ICRA

BARRIER.

REMOVE PORTION OF CEILING AS

REQUIRED TO INSTALL

CONSTRUCTION/ICRA BARRIER.

MODIFY CEILING AT BARRIER ON

OCCUPIED SIDE

6 MIL POLY OVER

CEILING PENETRATION

NOTES:

1. ALL CORNERS TO FORM 90 ANGLE WITH NO RADIUS

2. SEAL ALL SIDES OF POLY WITH DUCT TAPE

3. SEAL ALL CRACKS WITH DUCT TAPE.

6 MIL POLY OVER

EQUIPMENT OR

FURNISHING

6 MIL POLY OVER

WALL PROTRUSION

FLOOR

DOOR

BEYOND

WINDOW

BEYOND

CEILING

6 MIL POLY OVER

WALL OPENINGS

6 MIL POLY OVER

DOORS & WINDOWS

CEILING

CONSTRUCTION PHASING GENERAL NOTES

1. THE WORK UNDER THIS CONTRACT MUST BE DIVIDED INTO PHASES. A PHASE

CAN INVOLVE MULTIPLE LOCATION AREAS. SEE SPECIFICATIONS SECTION 01 00 00

1.6.H PHASING.

2. THE GENERAL CONTRACTOR MUST COORDINATE ALL PHASING AND SEQUENCING

WITH ALL TRADES AND THE OWNER. THE GENERAL CONTRACTOR MUST PROVIDE

A WRITTEN NARRATIVE TO OUTLINE CONSTRUCTION PHASING AND SEQUENCE

PLANS, VALIDATING AND ELABORATING ON THIS PHASING DESCRIPTION.

3. THE GENERAL CONTRACTOR MUST COOPERATE FULLY WITH THE OWNER SO

WORK MAY BE CARRIED OUT SMOOTHLY, WITHOUT INTERFERING WITH OR

DELAYING WORK UNDER THIS CONTRACT, OR OTHER CONTRACTS ON THE

PROJECT SITE OR WORK BY OWNER.

4. THE GENERAL CONTRACTOR'S CONSTRUCTION SCHEDULE MUST INDICATE THE

SEQUENCE, COMMENCEMENT AND COMPLETION DATES, OWNER INSPECTION AND

APPROVAL DATES AND MOVE-OUT AND MOVE-IN DATES OF OWNER'S PERSONNEL

FOR ALL PHASES OF THE WORK.

5. THE GENERAL CONTRACTOR MUST PERFORM THE WORK IN EACH PHASE IN THE

SEQUENCE SHOWN ON THE PHASING PLAN DRAWING(S) AND CONSTRUCTION

PHASING DESCRIPTION.

6. THE GENERAL CONTRACTOR MUST COMPLETE ALL WORK IN EACH PHASE WITH

THE VA INSPECTING AND ACCEPTING THE WORK PRIOR TO VA OCCUPANCY AND

THE CONTRACTOR PROCEEDING TO THE NEXT SCHEDULED PHASE. UPON

COMPLETION OF A PARTICULAR PHASE, THE ENTIRE AREA COVERED BY THAT

PHASE CAN BE OCCUPIED BY THE VA PERSONNEL…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .