This is a Cost Proposal and Scoring Guide spreadsheet for the Tennessee Department of Environment and Conservation's Request for Proposals for Wireless-as-a-Service across eleven state parks. The RFP solicits comprehensive wireless connectivity solutions including site surveys, network design, equipment installation, network management dashboards, 24/7 technical support, and guest internet access for campground areas. A mandatory pre-response conference is scheduled for October 28, 2025, with a technical response deadline of February 25, 2026, followed by mandatory site visits on March 27, 2026. Cost proposals are due March 31, 2026, with contract award anticipated on April 9, 2026, and signature deadline of April 24, 2026. The contract term is 60 months (April 24, 2026 to April 24, 2031) with two optional 30-month renewal periods, not to exceed 120 months total. Only the top three technically-scored respondents will be invited to submit cost proposals.
Respondents must submit detailed pricing for both site visit costs and non-site visit costs using the provided spreadsheet template. Site visit costs include line items for site surveys, project management, network design and installation, conduit and fiber optic installation, electrical work, pole installation, and equipment components such as wireless access points, routers, controllers, switches, and backhaul systems. Non-site visit costs include estimates for 500 end-user support incidents, 300 hours of technician onsite support, monthly service and monitoring for 40 wireless access points (in-season) and 20 units (off-season) across all network components, 22 hours of training, and 44 annual on-site equipment inspections. The cost proposal carries 30 percent weight in the overall evaluation, with site visit costs weighted at 18 percent and non-site visit costs at 12 percent. All monetary amounts must be submitted in U.S. currency limited to two decimal places, and the cost proposal must remain valid for at least 120 days following the opening date.
View the file
Other files
Show 40 more
Latest 50 of 74 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions RFP # Wifi As A Service for Tennessee State Parks
| COST PROPOSAL & SCORING GUIDE |
| NOTICE: THIS COST PROPOSAL MUST BE COMPLETED EXACTLY AS REQUIRED |
| COST PROPOSAL SCHEDULE— The Cost Proposal, detailed below, shall indicate the proposed price for goods or services defined in the Scope of Services of the RFP Attachment 6.6., Pro Forma Contract and for the entire contract period. The Cost Proposal shall remain valid for at least one hundred twenty (120) days subsequent to the date of the Cost Proposal opening and thereafter in accordance with any contract resulting from this RFP. All monetary amounts shall be in U.S. currency and limited to two (2) places to the right of the decimal point. |
| Instructions: On each tab, please complete the yellow fields only. For the Site Visit Costs, the Respondent shall enter their quantities and costs for each line item based on the site visit. The Respondent must enter a cost for all line items. If the item is not necessary based on the Site Visit, the Respondent should enter a quantity of zero. For the Non-Site Visit Costs, the Respondent must enter a cost for all line items. |
| NOTICE: The Evaluation Factor associated with each cost item is for evaluation purposes only. The evaluation factors do NOT and should NOT be construed as any type of volume guarantee or minimum purchase quantity. The evaluation factors shall NOT create rights, interests, or claims of entitlement in the Respondent. Notwithstanding the cost items herein, pursuant to the second paragraph of the Pro Forma Contract section C.1. (refer to RFP Attachment 6.6.), “The State is under no obligation to request work from the Contractor in any specific dollar amounts or to request any work at all from the Contractor during any period of this Contract.” This Cost Proposal must be signed, in Attachment 6.2. , by an individual empowered to bind the Respondent to the provisions of this RFP and any contract awarded pursuant to it. If said individual is not the President or Chief Executive Officer, this document must attach evidence showing the individual’s authority to legally bind the Respondent. |
RESPONDENT SIGNATURE:
PRINTED NAME & TITLE:
DATE:
Site Visit Costs
| Site Visit Costs | ||||
| Cost Item Description | Quantity | Unit of Measure | Price | Total Line Item Price |
| Site Survey (including all travel expenses) | per day | $ - 0 | ||
| Project Management | per hour | $ - 0 | ||
| Network Design (manhours) | per hour | $ - 0 | ||
| Network Installation (manhours) | per hour | $ - 0 | ||
| Conduit Installation | per linear foot | $ - 0 | ||
| Fiber Optic Installation | per linear foot | $ - 0 | ||
| Ethernet Installation | per linear foot | $ - 0 | ||
| Electrical Installation (dedicated circuit, commonly, but not limited to within campgrounds) | per installation | $ - 0 | ||
| Pole Installation | per installation | $ - 0 | ||
| Wireless Access Point | per each | $ - 0 | ||
| Network Router | per each | $ - 0 | ||
| Network Controller | per each | $ - 0 | ||
| Network Switch | per each | $ - 0 | ||
| Wireless Backhaul | per each | $ - 0 | ||
| Wireless Bridge | per each | $ - 0 | ||
| Fiber Media Converter | per each | $ - 0 | ||
| Sinewave Batter Backup | per each | $ - 0 | ||
| Battery Backup | per each | $ - 0 | ||
| Network Equipment Enclosure/Rack | per each | $ - 0 | ||
| Ethernet Patch Cables | per each | $ - 0 | ||
| Fiber Patch Cables | per each | $ - 0 |
TOTAL SITE VISIT COST $ - 0
Non-Site Visit Costs
| Non-Site Visit Costs | ||||
| Cost Item Description | State's Estimated Quantity | Unit of Measure | Price | Total Line Item Price |
| Wifi End User Support | 500 | per support incident | $ - 0 | |
| Technician Onsite Support, Troubleshooting, Repair, and Upgrades | 300 | per hour | $ - 0 | |
| Wifi Service and Monitoring In-Season: Wireless Access Point | 40 | per wireless access point per month (April-November) | $ - 0 | |
| Wifi Service and Monitoring In-Season: Network Router | 40 | per network route per month (April-November) | $ - 0 | |
| Wifi Service and Monitoring In-Season: Network Controller | 40 | per network controller per month (April-November) | $ - 0 | |
| Wifi service and Monitoring In-Season: Switch | 40 | per switch per month (April-November) | $ - 0 | |
| Wifi Service and Monitoring In-Season: Wireless Backhaul | 40 | per wireless backhaul per month (April-November) | $ - 0 | |
| Wifi Service and Monitoring In-Season: Wireless Bridge | 40 | per wireless bridge per month (April-November) | $ - 0 | |
| Wifi Service and Monitoring Off-Season: Wireless Access Point | 20 | per wireless access point per month (December-March) | $ - 0 | |
| Wifi Service and Monitoring Off-Season: Network Router | 20 | per network route per month (December-March) | $ - 0 | |
| Wifi Service and Monitoring Off-Season: Network Controller | 20 | per network controller per month (December-March) | $ - 0 | |
| Wifi service and Monitoring Off-Season: Switch | 20 | per switch per month (December-March) | $ - 0 | |
| Wifi Service and Monitoring Off-Season: Wireless Backhaul | 20 | per wireless backhaul per month (December-March) | $ - 0 | |
| Wifi Service and Monitoring Off-Season: Wireless Bridge | 20 | per wireless bridge per month (December-March) | $ - 0 | |
| Training | 22 | per hour | $ - 0 | |
| Annual On-Site Equipment Inspection | 44 | per inspection | $ - 0 |
TOTAL NON-SITE VISIT COST $ - 0
Cost Score Matrix *For CPO Solicitation Coordinator Completion Only*
Site Visit Cost Total
| Site Visit Cost Raw Score | Weighting | Site Visit Cost Score | |
| Lowest Site Visit Cost from All Proposals | ERROR:#DIV/0! | 18 | ERROR:#DIV/0! |
| Site Visit Cost Amount Being Evaluated |
Non-Site Visit Cost Total
| Non-Site Visit Cost Raw Score | Weighting | Non-Site Visit Cost Score | |
| Lowest Non-Site Visit Cost from All Proposals | ERROR:#DIV/0! | 12 | ERROR:#DIV/0! |
| Non-Site Visit Cost Amount Being Evaluated |
| Site Visit Score | ERROR:#DIV/0! |
| Non-Site Visit Score | ERROR:#DIV/0! |
Total Cost Score ERROR:#DIV/0!