This amendment document updates the Request for Proposals schedule for RFP #32701-04678, issued by the Tennessee Department of Environment and Conservation, for a Wireless-as-a-Service provider to implement comprehensive wireless connectivity across eleven Tennessee state parks. The RFP seeks a vendor to deliver end-to-end network services including site surveys, network design, equipment installation, network management dashboards, 24/7 technical support, and guest internet access for campground areas. The pre-response conference is scheduled for October 28, 2025, with a Notice of Intent to Respond deadline of October 29, 2025. Written questions and comments are due November 4, 2025, with the state providing responses by January 13, 2026, followed by a second round of questions due January 23, 2026 and state responses by February 11, 2026. The technical response deadline is February 25, 2026, with state completion of evaluations by March 17, 2026. Mandatory site visits for qualified respondents are scheduled for March 27, 2026, followed by cost proposal submission on March 31, 2026, with opening and scoring on April 1, 2026. Optional negotiations are scheduled for April 6-8, 2026, with the state releasing notice of intent to award on April 9, 2026. The contractor signature deadline is April 24, 2026, and the performance bond deadline is April 30, 2026. The initial contract term is sixty months with two optional thirty-month renewal periods, not exceeding one hundred twenty months total.
Evaluation will be based on general qualifications (10 points), technical qualifications and approach (60 points), and cost proposal (30 points), with only the top three technically-scored respondents advancing to cost proposal submission. The RFP explicitly welcomes responses from minority-owned, women-owned, service-disabled veteran-owned, and small business enterprises. Respondents must hold valid Tennessee Electrician and Contractor licenses and maintain specified insurance coverage. The contract includes a maximum liability cap of $10 million and a required performance bond of $5 million, which can be structured as either a comprehensive bond or annual renewals. Pricing must accommodate seasonal rate adjustments and allow for per-site or per-facility expansion, with all costs submitted as a complete, all-inclusive proposal covering equipment installation, maintenance, network upgrades, user support, and management services. Vendors must demonstrate robust business continuity and disaster recovery capabilities with 120-hour Recovery Point Objectives and 48-hour Recovery Time Objectives, along with comprehensive IT security standards including SOC 2 Type 2 annual compliance audits, annual penetration testing, and $10 million in cyber liability insurance.
View the file
Other files
Show 40 more
Latest 50 of 74 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP # 32701-04678 – Amendment # 3 Page 1 of 2
STATE OF TENNESSEE
TENNESSEE DEPARTMENT OF ENVIRONMENT AND CONSERVATION
REQUEST FOR PROPOSALS # 32701-04678
AMENDMENT # 3
FOR WIRELESS-AS-A-SERVICE PROVIDER FOR
TENNESSEE STATE PARKS
DATE: January 6, 2026
RFP # 32701-04678 IS AMENDED AS FOLLOWS:
1. This RFP Schedule of Events updates and confirms scheduled RFP dates. Any event, time, or date containing revised or new text is highlighted.
EVENT
TIME
(central time zone)
DATE
1. RFP Issued October 20, 2025
2. Disability Accommodation Request Deadline 2:00 p.m. October 24, 2025
3. Pre-response Conference 2:00 p.m. October 28, 2025
4. Notice of Intent to Respond Deadline 2:00 p.m. October 29, 2025
5. Written “Questions & Comments” Deadline 2:00 p.m. November 4, 2025
6. State Response to Written “Questions & Comments”
January 13, 2026
7. Second Round Written “Questions and Comments” Deadline
January 23, 2026
8. State Response to Second Round Written “Questions and Comments”
February 11, 2026
9. Technical Response Deadline 2:00 p.m. February 25, 2026
10. State Completion of Technical Response Evaluations
March 17, 2026
11. State Schedules State Visit with Qualified Respondents
March 20, 2026
12. Site Visits for Qualified Respondents March 27, 2026
13. Cost Proposal Submission Deadline 2:00 p.m. March 31, 2026
14. State Opening & Scoring of Cost Proposals 2:00 p.m. April 1, 2026
15. Negotiations (Optional) 4:30 p.m. April 6-8, 2026
RFP # 32701-04678 – Amendment # 3 Page 2 of 2
16. State Notice of Intent to Award Released and RFP Files Opened for Public Inspection
2:00 p.m. April 9, 2026
17. End of Protest Period April 16, 2026
18. State sends contract to Contractor for signature
April 20, 2026
19. Contractor Signature Deadline 2:00 p.m. April 24, 2026
20. Performance Bond Deadline 4:30 p.m. April 30, 2026
2. RFP Amendment Effective Date. The revisions set forth herein shall be effective upon release. All other terms and conditions of this RFP not expressly amended herein shall remain in full force and effect.