This solicitation is for a design-build contract to construct a parking lot consisting of approximately 240 stalls within 10,350 square yards at Marine Corps Base Camp Blaz in Guam. The work includes grading, landscaping, and site lighting with an estimated value between $10-25 million. The contract completion period is 500 calendar days. The solicitation issued on February 14, 2023 and is set aside 100% for small businesses. The Navy Facilities Engineering Command is the contracting agency. Proposals are due on April 11, 2023 and will be evaluated on technical approach, experience, safety, and past performance on a best value tradeoff basis. An optional site visit is scheduled for March 08, 2023 for interested offerors to familiarize themselves with jobsite conditions. The solicitation and any amendments will be posted to SAM.gov.
View the file
Other files
Show all 47
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GEPA SUBMITTAL
WHEN
REQUIRED SUBMITTAL COMPONENTS WHO PREPARES
NAVY QC
REVIEWER
WHO SUBMITS
SUBMITTAL
METHOD
SUBMITTAL
APPROVED BY
ANTICIPATED
APPROVAL TIME NOTES / COMMENTS
D E
S
IG
N
SITING Approval Requirements:
Refer to "GEPA SDWA Approval Checklist."
DESIGN Approval Requirements:
(30% BoD Submittal)
Refer to "GEPA SDWA Approval Checklist."
Provide ONLY water system information including mechanical details relevant to the water system.
I-H: NAVFAC CI
A-E / DB: A-E (NBG)
or DB A-E (AAFB)
A-E / DBB: A-E
1. CI (technical)
2. EV (submittal package)
3. DACP Office (when established)
1. NFM EV (interim period until DACP office is established)
2. DACP office (when established)
Deliver 2 hard-copy sets (1 fullsize and 1 halfsize) and 1 electronic set to NFM
EV.
NFM EV will deliver 1 fullsize set to GEPA.
1. NFM EV approves submittal for transmitting to GEPA
2. GEPA approves submittal
1 month review & approval period by
GEPA.
If submittal is not complete or correct, review period re-starts.
(See Note **** below.)
Early consultation with GEPA is highly recommended by NFM EV (interim period) and DACP Office (when established).
If a 30% Consulation Meeting with GEPA is held, NFM shall draft and submit to GEPA the meeting minutes for their review. Approval of the meeting minutes = approval of the 30% Submittal.
For 30% Basis of Design (BoD) Submittal:
1. DB Projects - Pre-Final RFP (NBG); 30% DB Design
(AAFB)
2. DBB Projects - 30% Design BoD
P R
E -F
IN
A
L
0%
D E
S
IG
N DESIGN Approval Requirements:
(90% BoD Submittal)
Refer to "GEPA SDWA Approval Checklist."
Provide ONLY water system information including mechanical details relevant to the water system.
Additional Requirements:
1. Calculations and Modeling Data
2. Disinfection Specifications (or notation to be provided by the contractor as appropriate)
3. Material Specifications (including references to NSF 61, Sections 8 & 9)
4. Notes detailing how comments from 30% Submittal were addressed in the 90% Submittal and revised pages or plans.
I-H: NAVFAC CI
A-E / DB: A-E
A-E / DBB: A-E
1. CI (technical)
2. EV (submittal package)
3. DACP Office (when established)
DB projects:
Above 3 + FEAD /
ROICC
1. NFM EV (interim period until DACP office is established)
2. DACP office (when established)
Deliver 2 hard-copy sets (1 fullsize and 1 halfsize) and 1 electronic set to NFM
EV.
NFM EV will deliver 1 fullsize set to GEPA.
1. NFM EV approves submittal for transmitting to GEPA
2. GEPA approves submittal
1 month review & approval period by
GEPA.
If submittal is not complete or correct, review period re-starts.
1. For DBB projects, it is recommended that NFM EV (interim period) or DACP Office (when established) meet with GEPA to discuss project.
2. For DB projects, it is recommended that NFM EV (interim period) or DACP Office (when established) meet with GEPA to discuss project.
3. In the event there are no funds available for travel, a less preferable option would be via video conference, or teleconference.
4. GEPA meeting travel requirements should be specified in design contracts and DB RFPs.
For 90% Basis of Design (BoD) Submittal:
1. DB Projects - Pre-Final DB Design
2. DBB Projects - Pre-Final Design BoD
F
IN
A L
D E
S
IG
N
DESIGN Approval Items:
(Final BoD Submittal)
Refer to "GEPA SDWA Approval Checklist."
Provide ONLY water system information including mechanical details relevant to the water system.
I-H: NAVFAC CI
A-E / DB: A-E
A-E / DBB: A-E
1. CI (technical)
2. EV (submittal package)
3. DACP Office (when established)
DB projects:
Above 3 + FEAD /
ROICC
1. NFM EV (interim period until DACP office is established)
2. DACP office (when established)
Deliver 2 hard-copy sets (1 fullsize and 1 halfsize) and 1 electronic set to NFM
EV.
NFM EV will deliver 1 fullsize set to GEPA.
1. NFM EV approves submittal for transmitting to GEPA
2. GEPA approves submittal
1 month review & approval period by Guam EPA
If submittal is not complete or correct, review period re-starts.
For Final Basis of Design (BoD) Submittal:
1. DB Projects - Identify how and where all 90% GEPA review comments were addressed. Include revised drawings and/or specs.
2. DBB Projects - Identify how and where all 90% GEPA review comments were addressed. Include revised drawings and/or specs.
C O
N S
T R
U C
T
IO
N Inspection Requirements: (During Construction) Refer to "GEPA SDWA Approval Checklist."
Final Site Inspection:
Refer to "GEPA SDWA Approval Checklist."
NFM FEAD/ROICC NFM FEAD/ROICC GEPA
P O
S T
-C O
N S
T R
U C
T
IO
N As-Built/Record Drawings I-H: NAVFAC CI
A-E / DB: DB A-E
A-E / DBB: A-E
NF CI NFM EV Deliver 1 fullsize hard-copy set and 1 electronic set to NFM
EV.
NVM EV will deliver 1 fullsize set to GEPA.
NFM FEAD/ROICC
NF CI
Provide to GEPA within 60 days of construction completion.
APPLICABILITY:
All new water projects or projects that make "significant alterations" to the public water system.
Significant Alterations include:
1) >10 new residential units;
2) >200' of >=6" waterline added to an existing system;
OR,
3) addition of new drinking water processes and/or materials (includes new source -well/spring/surface, booster pumps, storate tank, transmission line, new location).
Notes:
Does not include repair by replacement.
All significant alterations require construction approval, and those that "increase the capacity of the existing PWS" also require siting approval.
Projects that "increase the capacity of the existing PWS" means improve or increase the capacity of the distribution system, transmission system, water storage, and/or source facilities in a new location OR location that will expand the boundaries of an exising site OR location with systems built prior to 1978.
Completely separate requirements apply for well drilling, construction and operations.
P O
T A
B L
E W
A T
E R
S Y
S T
E M
D E
S
IG
N S
U B
M
IT
T A
L S
S
D W
A
DESIGN APPROVAL CONSTRUCTION PERMITTING (DACP) FOR GUAM PROJECTS
This matrix is not intended to replace the GEPA Water/Sewer/Wellhead Approval Checklists and Instructions developed by NF MAR. NAVFAC, A-E, or DB A-E should follow and complete all applicable checklists.
Guam EPA (GEPA) Submittals and Approvals Process
(APPLICABLE TO ALL CONSTRUCTION PROJECTS ON GUAM)
1 of 2 8/4/2012
GEPA SUBMITTAL
WHEN
REQUIRED SUBMITTAL COMPONENTS WHO PREPARES
NAVY QC
REVIEWER
WHO SUBMITS
SUBMITTAL
METHOD
SUBMITTAL
APPROVED BY
ANTICIPATED
APPROVAL TIME NOTES / COMMENTS
DESIGN APPROVAL CONSTRUCTION PERMITTING (DACP) FOR GUAM PROJECTS
This matrix is not intended to replace the GEPA Water/Sewer/Wellhead Approval Checklists and Instructions developed by NF MAR. NAVFAC, A-E, or DB A-E should follow and complete all applicable checklists.
Guam EPA (GEPA) Submittals and Approvals Process
(APPLICABLE TO ALL CONSTRUCTION PROJECTS ON GUAM)
D E
S
IG
N
DESIGN Approval Requirements:
(30% BoD Submittal)
Refer to "GEPA SDWA Approval Checklist."
Provide ONLY water system information including mechanical details relevant to the water system.
I-H: NAVFAC CI
A-E / DB: A-E
A-E / DBB: A-E
1. CI (technical)
2. EV (submittal package)
3. DACP Office (when established)
1. NFM EV (interim period until DACP office is established)
2. DACP office (when established)
Deliver 2 hard-copy sets (1 fullsize and 1 halfsize) and 1 electronic set to NFM
EV.
NFM EV will deliver 1 fullsize set to GEPA.
1. NFM EV approves submittal for transmitting to GEPA
2. GEPA approves submittal
1 month review & approval period by
GEPA.
If submittal is not complete or correct, review period re-starts.
(See Note **** below.)
Early consultation with GEPA is highly recommended by Navy EV (interim period), DACP Office (when established).
D E
S
IG
N
(I f
G E
P A i n d ic at es
0%
S u b m it ta l is re q u ir ed f ro m t h e
S u b m it ta
l) DESIGN Approval Items: (90% BoD Submittal)
Refer to "GEPA Sewer Design Plan Review Requirements."
Provide ONLY sewer system information.
I-H: NAVFAC CI
A-E / DB: Contractor's A-E
A-E / DBB: A-E
1. CI (technical)
2. EV (submittal package)
3. DACP Office (when established)
DB projects:
Above 3 + FEAD /
ROICC
1. NFM EV (interim period until DACP office is established)
2. DACP office (when established)
Deliver 2 hard-copy sets (1 fullsize and 1 halfsize) and 1 electronic set to NFM
EV.
NFM EV will deliver 1 fullsize set to GEPA.
1. NFM EV approves submittal for transmitting to GEPA
2. GEPA approves submittal
1 month review & approval period by
GEPA.
If submittal is not complete or correct, review period re-starts.
1. For DBB projects, it is recommended that NFM EV (interim period) or DACP Office (when established) meet with GEPA to discuss project.
2. For DB projects, it is recommended that NFM EV (interim period) or DACP Office (when established) meet with GEPA to discuss project.
3. In the event there are no funds available for travel, a less preferable option would be via video conference, or teleconference.
4. GEPA meeting travel requirements should be specified in design contracts and DB RFPs.
D E
S
IG
N
30% DESIGN Approval Requirements:
Refer to GEPA "Wellhead Protection Submittals Checklist."
I-H: NAVFAC CI
A-E / DB: Contractor's A-E
A-E / DBB: A-E
1. CI (technical)
2. EV (submittal package)
3. DACP Office (when established)
1. NFM EV (interim period until DACP office is established)
2. DACP office (when established)
Deliver 2 hard-copy sets (1 fullsize and 1 halfsize) and 1 electronic set to NFM
EV.
NFM EV will deliver 1 fullsize set to GEPA.
1. NFM EV approves submittal for transmitting to GEPA
2. GEPA approves submittal
30 days by GEPA
D E
S
IG
N
90% DESIGN Approval Requirements:
Refer to GEPA "Wellhead Protection Submittals Checklist."
I-H: NAVFAC CI
A-E / DB: Contractor's A-E
A-E / DBB: A-E
1. CI (technical)
2. EV (submittal package)
3. DACP Office (when established)
DB projects:
Above 3 + FEAD /
ROICC
1. NFM EV (interim period until DACP office is established)
2. DACP office (when established)
Deliver 2 hard-copy sets (1 fullsize and 1 halfsize) and 1 electronic set to NFM
EV.
NFM EV will deliver 1 fullsize set to GEPA.
1. NFM EV approves submittal for transmitting to GEPA
2. GEPA approves submittal
30 days by GEPA
F
IN
A L
D E
S
IG
N
FINAL DESIGN Approval Requirements:
Required only if DoD needs to address 90% review comments received from GEPA, or if specifically requested GEPA.
Refer to GEPA "Wellhead Protection Submittals Checklist."
I-H: NAVFAC CI
A-E / DB: Contractor's A-E
A-E / DBB: A-E
1. CI (technical)
2. EV (submittal package)
3. DACP Office (when established)
DB projects:
Above 3 + FEAD /
ROICC
1. NFM EV (interim period until DACP office is established)
2. DACP office (when established)
Deliver 2 hard-copy sets (1 fullsize and 1 halfsize) and 1 electronic set to NFM
EV.
NFM EV will deliver 1 fullsize set to GEPA.
1. NFM EV approves submittal for transmitting to GEPA
2. GEPA approves submittal
14 days by GEPA
For NF PAC designed projects, NF PAC CI and EV offices. When the DACP Office is established, DACP will perform this function for DPRI projects; for non-DPRI projects, unless otherwise advised, review to be performed by NF CI and EV.
** - For NF PAC DPRI projects, NF PAC EV will transmit submittals to NF MAR EV for submission to GEPA. When the DACP Office is established, DACP will submit to GEPA.
*** - Files to be uploaded into e-Permits to be limited to 15 MB each in size. No limit on the number of files associated with each project. Format to be in Adobe Acrobat. Uploads to be done after review by responsible EV office (interim) or DACP office.
**** - GEPA has agreed with NF MAR that if no review or action is taken for the 30% Water System and/or the 30% Sewer System submittals, it is implied that the submittal is approved (i.e., no other submittals are required).
APPLICABILITY:
All new sewer projects OR projects that make "significant alterations" to a sewage collection system.
Significant Alterations include:
1) >2 new manholes;
2) >600' of >8" gravity sewer line added to an existing system;
3) any new or modified sewage pump station and force main;
OR,
3) addition of new processes and/or materials (includes new source -well/spring/surface, booster pumps, storate tank, transmission line, new location).
Notes:
Does not include repair by replacement.
APPLICABILITY:
Projects requiring septic tank(s), leach field(s), sanitary sewer, storm water disposal, liquid waste storage/ disposal/treatment located within the Ground Water Management Protection Zone (GWMPZ) and any Wellhead Protection Area (WHPA).
High Risk Activities/Land Uses requiring GEPA approval in WHPAs include -
A. Vehicle Fueling Stations B. Vehicle Service and Maintenance Facilities C. Vehicle and Equipment Cleaning Facilities D. Outdoor Loading or Unloading Facilities (storage, warehouse, commercial) E. Facilities Generating or Storing Liquid Saste, Solid Waste, or Hazardous Waste F. Dining/Food Preparation Facilities G. Engineering Training Pit (outdoor area to train operators using earthmoving or other large equipment) H. Stormwater Disposal Facilities (unlined stormwater basins) I. Projects with new exposed parking areas (> 12 stalls)
S E
W E
R S
Y S
T E
M D
E S
IG
N
S U
B M
IT
T
A L
S W
E L
L H
E A
D P
R O
T E
C T
IO
N
S U
B M
IT
T
A L
S
S D
W A
Notes:
* - For NF MAR designed projects, NF MAR CI and EV offices. When the DACP Office is established, DACP will perform this function for DPRI projects; for non-DPRI projects, unless otherwise advised, review to be performed by NF CI and EV.
2 of 2 8/4/2012
DESIGN APPROVAL CONSTRUCTION PERMITTING (DACP) FOR GUAM PROJECTS
Guam EPA (GEPA) Submittals and Approvals Process
(APPLICABLE TO ALL CONSTRUCTION PROJECTS ON GUAM)
INTERIM GEPA DACP APPROVAL PROCESS FLOWCHART (Until DACP Office is Established)
EV reviews for completeness
CI/DM submits to NF EV
EV provides comments to CI/DM
(as required)
NFM reviews GEPA Submittal
OTHER NOTES:
For D‐B projects, the Contractor's A‐E (Designer ‐of‐Record) prepares the 90% and Final GEPA DACP Approval Submittals and submits them to the NFM CM/FEAD/ROICC. The GEPA Submittals are reviewed by NFM CM/FEAD/ROICC, NF CI, and NF EV. NFM EV will submit the GEPA Submittals to GEPA as decribed above.
DBB AE
prepares
GEPA Submittal
CI/DM
reviews for technical accuracy
AE submits to
NF CI/DM
AE revises GEPA Submittal (as required)
AE delivers GEPA Submittal
NFM EV submits Submittal to GEPA
GEPA reviews Submittal and provides comments to NFM EV.
NFM EV consolidates and obtains clarification from GEPA (as necessary).
NFM EV forwards GEPA Comments to NF CI/DM (and NFP EV for PAC projects) for inclusion in follow‐on/Final Submittal.
1 of 1 8/4/2012
1 Does not include all requirements for well drilling, construction, operation
Guam EPA Safe Drinking Water Requirements for Construction1 Department of Defense Projects
Applies to all new water projects or those projects that make “significant alterations” to the public water system (PWS).
Significant alteration means more than 10 new residential units, more than 200 feet of >/= 6” water line added to an existing system, or the addition of new drinking water processes and/or materials (includes reservoirs, wells, booster pumps, etc.). Does not include repair by replacement. All significant alterations require construction approval, and those that “increase the capacity of the existing PWS” also require siting approval.
“Projects that increase the capacity of the existing PWS” means improve or increase the capacity of the distribution system, transmission system, water storage, and/or source facilities in a new location OR location that will expand the boundaries of an existing site OR location with systems built prior to 1978.
Siting approval requirements Approval will be within 15 days of meeting with the Safe Drinking Water program and, if there is a source water project, with the Water Resource Program if there are no issues to address that require DoD to provide additional information.
Design approval requirements Basis of Design. Required at 30%, however for DoD Design/Build projects may not be available until 60%. If MILCON may be satisfied by the 1391.
Guam EPA wants to review specs prior to ordering of materials; option is to run the risk of unacceptable materials that cannot be used. DoD is developing specifications that meet all GEPA requirements and have them approved in advance.
Submittals Do not include extraneous information; submittal must be pared down to include only SDWA requirements.
Siting requirements – as above.
30% Basis of Design
1. MILCON
a. 30% “Basis of Design” submittal: pre-final RFP package OR 1391
2. Design Build Projects
a. 30% “Basis of Design” submittal: pre-final RFP package for NBG, 30% design submittal for AAFB
b. 90% submittal: Pre-final package
c. Final: page identifying how and where all GEPA comments on 90% were addressed and all appropriate project pages to confirm
3. Design-Bid-Build Projects
a. 30% “Basis of Design” submittal: 30% design submittal
b. 90% submittal: Pre-final package
c. Final: same as DB
Guam Environmental Protection Agency Approval Checklist Safe Drinking Water Act
Rev 07/12/2012
New source (well, spring or surface) Booster pump Storage Tank Transmission line New location If any of the above are checked, project requires SITING APPROVAL.
Projects requiring Siting Approval >= 10 residential units >= 200 feet of new water line If any of the above are checked, project is a SIGNIFICANT ALTERATION and it will need DESIGN APPROVAL
SITING APPROVAL REQUIREMENTS
Purpose/Description of Project Population served Location map NEPA documentation (all above should be included in NEPA documentation)
DESIGN APPROVAL REQUIREMENTS
Submittals to Administrator cc: Chief Engineer
30% Basis of Design submittal Water System basis of design including calculations One-line drawing showing min and max pressures at key nodes (or as much information as is available at the time to show how the basis was determined) Project description for RFP or 1391 Optional meeting with GEPA (meeting minutes approved by GEPA will be
“approval” of 30%) “Fast Track” Submittals 1 set of material specifications for any materials ordered prior to 90% design review
90% Submittal 1 set of plans (full sized hard copy) showing water system and details. Include a hand-delivered copy to and checked in by Chief Engineer or his designee Detail showing all fire hydrants protected by bollards 1 set of specifications (recommend including below on plans in general notes) Include disinfection using either 14-day or 7-day flushing Include NSF 61§8 (materials) and 9 (fixtures) approved materials (follow lead-free standards in IBC potable water supply section) Boring logs One-line drawing clearly showing the hydraulic analysis (e.g. clearly demonstrate that project creates no pressure or other problems for existing system) (90% requirements continued on next page)
Guam Environmental Protection Agency Approval Checklist Safe Drinking Water Act
Rev 07/12/2012
Hydraulic analysis LARGE PROJECTS – hydraulic analysis from source (e.g. tank, well, etc.) to project showing key pressure points OR SMALL PROJECTS (e.g. single facility) – hydraulic analysis from point of connection to existing system Cross-connection control (pending GEPA requirement, existing DoD requirement) on fire systems and other areas as needed
Final Design submittal 1 set of final drinking water design plans GEPA comments on 90% and responses showing how those comments are addressed and referencing appropriate submittal sheets
CONSTRUCTION REQUIREMENTS
Inspection requirements Routine inspections – GEPA’s option. GEPA will provide 24-hour notice.
If GEPA has specific inspection requirements these will be defined during the design plan reviews.
48 hour notice of inspection items identified in GEPA approval (“concurrence”) letter
Final site inspection Provide GEPA with 48-hr notice of disinfection (may or may not attend) Ensure disinfection procedure was submitted during 90% review Provide disinfection procedure to licensed Level 2 Water System Operator who will be on-site for procedure Level 1 Water System Operator OR laboratory technician currently employed by laboratory must take samples GEPA will issue approval letter prior to line tapping Provide GEPA with 48-hr notice of tapping (may or may not attend) Level 2 Distribution System Operator required to operate valves on system.
POST-CONSTRUCTION REQUIREMENTS
Provide GEPA with as-built drawing within 60 days of project completion
Rev 07/12/2012
Guam EPA Sewer Design Plan Review Requirements
Applies to all new sewer projects or those projects that make “significant alterations” to a sewage collection system.
Significant alteration means more than 2 new manholes, more than 600 feet of > 8” gravity sewer line added to an existing system, any new or modified sewage pump station and force main or the addition of new processes and/or materials. Does not include repair by replacement.
Does your project include:
Sewage pump or lift station Force main > 2 manholes > 600 feet of gravity sewer line that is > 8” diameter If any of the above are checked, project requires DESIGN APPROVAL.
Guam EPA will have 30 days to review submittals; more time may be required if additional information is requested.
DESIGN APPROVAL REQUIREMENTS
Submittals to Administrator cc: Chief Engineer and as noted below
30% Submittal (RFP for DB or 1391; 30% submittal where RFP doesn’t provide basis) Basis of design – describe purpose of project and basis of sewer design
90% Submittal (required only if requested by Guam EPA during 30% approval) 1 set of plans (hard copy). Include a hand-delivered copy to and checked in by Chief
Engineer or his designee Hydraulic analysis: Calculations/modeling runs clearly showing system capacity for proposed project Include downstream capacity as needed to demonstrate adequacy of system LARGE PROJECTS – downstream analysis to receiving sewage pump station or wastewater treatment plant OR SMALL PROJECTS (e.g. single facility) – hydraulic analysis to point of connection to existing system and showing adequate capacity in receiving gravity sewer or sewage pump station
Page 1 Rev 07/12/2012
WELLHEAD PROTECTION SUBMITTALS
FOR GUAM PROJECTS
1. APPLICABILITY
In accordance with 22 GAR-GEPA, Chapter 7, Section 7130, “…no person shall construct, utilize, operate, occupy or cause, allow or let, permit or suffer or to be constructed, utilized, operated or occupied any land use served or to be served by septic tank and leached field, sanitary sewer, storm water disposal method, or liquid waste storage, disposal or treatment method, and which is within the GWMPZ1 and within any 1,000 feet radius of any public utility potable water supply well, until the person has obtained the prior written approval of the Administrator…”
The intent of the regulation is to protect Guam’s Water Resource and avoid impairing drinking water quality. Therefore projects partially or entirely located within 1,000 feet radius of any public utility potable water supply well, DoD must obtain Guam EPA’s approval to construct such facilities. In the event that Guam EPA has specific supporting data that shows surface pollutant sources from activities located more than 1,000 feet away affecting the water quality of a given potable water well, Guam EPA may request DoD to submit that particular project for Guam EPA’s review.
2. HIGH RISK ACTIVITIES OR LAND USES TO BE APPROVED BY GEPA IN WELLHEAD
PROTECTION AREAS (WHPA) 2
The following land uses or activities located within the WHPA shall be submitted for GEPA’s approval since they generate or have a higher potential to generate pollutants:
A. Vehicle fueling stations B. Vehicle service and maintenance facilities C. Vehicle and equipment cleaning facilities D. Outdoor loading or unloading facilities (storage, warehouse, commercial) E. Facilities generating or storing liquid waste, solid waste, or hazardous waste F. Dining /food preparation facilities G. Engineering Training Pit (outdoor area to train operators using earthmoving or other large equipment.)
H. Stormwater disposal facilities (unlined stormwater basins).
In addition to the eight categories above, parking lots is a feature commonly found in many land uses, in addition to the eight above, and is recognized to be a generator of pollutants as well. The Revised Final Best Management Practices for Wellhead Protection dated December 2010 will be used as a guide to select BMPs for parking lots. Non-high risk projects with new exposed parking areas of greater than 12 stalls will be submitted for Guam EPA’s review and approval.
Use the flowchart shown in Attachment A to determine if your project is located within the wellhead protection area (WHPA) and if your project needs to be reviewed and approved by Guam EPA.
1 Ground Water Management Protection Zone 2 Wellhead Protection Area is defined in Guam regulations as, “the surface and subsurface area with a minimum of 1,000 ft radius around water well or wellfield, supplying a public water system through which contaminants are reasonably likely move towards and reach such water well or wellfield.”
Page 2 Rev 07/12/2012
3. SUBMITTAL COMPONENTS
AT 30% DESIGN STAGE
Project Location Map superimposed 1,000’ WHPA circle(s), Project Site Plan and description, Activity Category and anticipated pollutants generated, Stormwater drainage, treatment and disposal concept, Proposed BMPs, IMPs, and treatment trains, and Preliminary calculations if available (hydrology, stormwater facility sizing)
90% DESIGN
Project site plans, hard copy and electronic. Include a hand-delivered copy to and checked in by Chief Engineer or his designee Full sized plans showing drainage facilities, and/or landscaping features used to treat or infiltrate stormwater Any revisions to the 30% submittal components above. All changes to documents shall be highlighted and changes to plan sheets (drawings) shall be bubbled, Hydrology, hydraulic or sizing calculations for stormwater facilities, Selected BMPs, IMPs, and treatment trains, and Response to Guam EPA’s comments from 30% submittal.
FINAL DESIGN:
This is required only if DoD needs to address comments received from Guam EPA from the 90% design submittal, or if specifically requested Guam EPA, Revised final full sized plans, Any revisions to the 90% submittal components above. All changes to documents shall be highlighted and changes to plan sheets (drawings) shall be bubbled Final hydraulic, hydrology or sizing calculations.
Final response to Guam EPA’s comments from 90% submittal.
4. OTHER INFORMATION
Guam EPA will review the submittal documents and provide comments within the following time periods:
- 30 days for 30% Submittals from submittal by DoD or its contractors,
- 30 days for 90% Submittals “ “ “ “ “ “ “ , and
- 14 days for Final Submittals “ “ “ “ “ “ “.
Formal approval for the 90% Submittal or Final Submittal will be in the form of a letter from Guam EPA to DoD.
In the event the submittal is not complete, Guam EPA’s review period would restart upon receipt of additional, required information.
The Best Management Practices for Wellhead Protection – Northern Guam Lens Aquifer, December 2010 document will be used as a guide for the selection of best management practices and Low Impact Development Integrated Management Practices.
The use of Class V Underground Injection Control (UIC) features should be avoided. See Guam EPA’s UIC Permit Determination Flow Chart in Attachment B.
Page 3 Rev 07/12/2012
ATTACHMENT A – DoD WELLHEAD PROTECTION SUBMITTAL FLOWCHART
Start Here
Is does the project GEPA have located within 1,000 specific data to support feet from a production or demonstrate groundwater potable water well? no influence from activities yes more than 1,000 ft from the well?
yes no does the project fall into one of the 8 high risk categories listed in Section 2?
no yes does the facility include a new, exposed parking yes with an area greater than no 12 stalls?
Wellhead protection Wellhead protection Submittal REQUIRED submittal NOT required
Review Exclusions by GEPA (not requiring wellhead protection submittals):
1. All proposed improvements are contained under an existing roof, and
2. The type of activity (or land use) does not change, and
3. There is no net increase in impervious area.
Some examples: interior renovation in a building; replacing an engine generator; floor, door or window replacements.
Page 4 Rev 07/12/2012
ATTACHMENT B – UIC PERMIT DETERMINATION FLOWCHART