FY20 MCON PROJECT P-459B, MCB CAMP BLAZ PARKING, US NAVSUPPACT MCB, GUAM
Solicitation number
N62742-23-R-1308
Issued by

About this file

This document summarizes a request for proposal for design-build services for a parking lot project at Marine Corps Base Camp Blaz in Guam. Key details include that the project scope involves the design and construction of a 240-space parking lot within 10,350 square yards, including grading, landscaping and site lighting. The estimated value is between $10-25 million. The NAICS code is 238990 and the period of performance is 500 calendar days. The acquisition is set aside 100% for small businesses. The RFP was issued on February 14, 2023 and proposals are due on April 14, 2023. A site visit is scheduled for March 08, 2023 and interested offerors must submit required forms by February 09, 2023 to attend. The Navy is the contracting agency.

View the file

Other files

File Type Posted
P459B_Pt6-AttachB-RefDwgs_Amd6.pdf PDF
23R1308_Amd0006-Issued.pdf PDF
P459B_Pt6-AttachB-RefDwgs_Amd6_J-001B Specs.pdf PDF
23R1308_Amd0006-Specs.pdf PDF
23R1308-P459B Note 6-Issued.pdf PDF
23R1308_Amd0005-Issued.pdf PDF
23R1308-P459B Note 5-Issued.pdf PDF
P459B_Pt6-AttachB-RefDwgs_Amd5.pdf PDF
23R1308_Amd0004-Issued.pdf PDF
P459B_Pt6-AttachB-RefDwgs_Amd3.pdf PDF
23R1308_Amd0003-Issued.pdf PDF
23R1308-P459B Note 3-Issued.pdf PDF
23R1308_Amd0003-Specs.pdf PDF
23R1308-P459B Note 2-Issued.pdf PDF
23R1308_Amd0002-Issued.pdf PDF
23R1308_P459B_Amd2-Specs.pdf PDF
23R1308-P459B Note 1.pdf PDF
AMD 01 23R1308.pdf PDF
N_DPRI_ProjectsCulturalHistoricResourcePA_AppendixG.pdf PDF
A. J-037 Boring Logs.pdf PDF
A. J-001B Boring Logs.pdf PDF
A. J-301 Boring Logs.pdf PDF
D. 3D_J001B DP3FINAL WELLHD PROTECT PLAN 04JAN19.pdf PDF
C_ComprehensiveConstructionSWPPP(Nov 2014).pdf PDF
I_COMPREHENSIVE_WMP(Updated July 2015)-P459.pdf PDF
G_SMART_GRID_REQUIREMENTS_v4.0_8-23-2019.pdf PDF
M_DPRI_ProjctsCultrlHistrcResrceProcedre_for_InadvrtntDiscoveries.pdf PDF
J_GEPA_GuamSoilandErosionControlRegulations(April2000).pdf PDF
P_FinalGuamLandscapingGuidelines29June2011.pdf PDF
R_DesignApprovalConstructionPermitting(DACP).pdf PDF
B. J-001B_Dwgs_23Aug2019.pdf PDF
CDP_20140221.pdf PDF
N62742-23-R-1308 DB RFP.pdf PDF
O_(Alt) COCONUT RHINOCEROS BEETLE (CRB) AND LITTL FIRE ANT (LFA) MANAGEMENT PROCEDU.pdf PDF
O_CoconutRhinocerosBeetle(CRB)ManagementProcedures.pdf PDF
L_Clarif_of_Guidelnes Restrictns_for_Condctng_Topo_Survey.pdf PDF
D_MRESS_Amend No 7 Jan20r.pdf PDF
E. MILCON_Bedrock_Determination_Map.pdf PDF
F_Pre-Final_InstallationMasterPlan16April2018.pdf PDF
Q_OSD_WaterUseforLandscapeArch(3-10-17).pdf PDF
E_MCBG IAP_Final(April2011).pdf PDF
F. 02_210301 - J-301 Civil Dwgs - Rev2_signed.pdf PDF
K_GuamDPRI_PesticideSoilsManagementPlan_Nov2011.pdf PDF
C. J001B DOC DP2FINAL V9 DRAINAGE RPT 21NOV19.pdf PDF
A_MDACS-Final(Sept 2017).pdf PDF
H_MMTP.pdf PDF
B_NFM_PWUC_Rev2_(2018-11-15)Final(ApprovedSigned).pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE NAVY

NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND PACIFIC

258 MAKALAPA DR STE 100

PEARL HARBOR HI 96860-3134

Notice No. 4 5 April 2023

PRE-PROPOSAL QUESTIONS & ANSWERS

RFP N62742-23-R-1308

FY20, MCON PROJECT P-459B, MCB CAMP BLAZ PARKING,

US NAVSUPPACT, MCB CAMP BLAZ, GUAM

NOTE: The following questions and answers are provided for INFORMATION ONLY.

The RFP remains unchanged unless it is amended in writing on a Standard Form 30.

34. Please clarify the response to question #29 in Notice 3.

Is section G20201.1 permeable pavement no longer allowed on the project?

Please note our preliminary calculations using the criteria of the SDDCTEA show that it may not be possible to achieve the minimum required parking spaces of 235 within 70% of the 10,150 square yards provided for impermeable surfaces and still comply with the pamphlet for minimum parking space size, aisle width, and offsets and setbacks.

We are respectfully requesting a three-week extension to allow for our team including NAVFAC to assess our concerns since it will have a major impact on achieving the project’s program. The additional time will ensure a complete and thorough assessment and incorporate changes into our design and technical narrative.

RESP: Permeable pavement will not be allowed for the project. The 10,150 SY BFR is the total allowable paved area that may be constructed. The Contractor should utilize this entire amount for parking, not just 70%. Proposal receipt date remains unchanged.

35. The RFP states that the connection point to the 13.8kV three phase 60 Hertz electrical power system is Pad Mounted Switchgear SW574-8. Please provide “as-built” or record drawings showing the location of Pad Mounted Switchgear SW574-8.

RESP: See forthcoming Amendment 0004, refer to sheet E-131 in “2021-2-15 PCO 002 Site.”

36. The RFP states to extend the 13.8kV three phase 60 Hertz electrical power system across Iceberg Street using two existing 6 inch PVC Schedule 40 conduits. Please provide “as-built” or record drawings showing the location of the two existing 6 inch PVC Schedule 40 conduits.

RESP: See forthcoming Amendment 0004, refer to sheet E-131 in “2021-2-15 PCO 002 Site” and E-518 in “J-001B DWGS FINAL (PART 12)_Signed.”

Subj: RFP N62742-23-R-1308, FY20, MCON PROJECT P-459B, MCB CAMP BLAZ

PARKING, US NAVSUPPACT, MCB CAMP BLAZ, GUAM

37. In reference to the shared boring logs for J-001B Project, it was shown that B-14 has reddish-brown elastic silt soil which is very soft if over-excavation due to soft soils and cavities/voids is encountered during the construction will this be considered additional work to the contractor? Or can the government provide a separate line item for the over-excavation for bid uniformity?

RESP: Boring B-14 was drilled prior to the start of the grading work of the J-001B project. The plan drawings for the J-001B project have been also included with the RFP. Over-excavation due to soft soils and cavities/voids encountered during construction should be included in the cost for earthwork.

38. In reference to Q&A item 31, it was mentioned that no spare conduits are available.

Please confirm if the intent of the RFP is to construct a new duct bank up to the existing SW574-8 that will cross the existing asphalt road for bid uniformity.

RESP: The intent of the RFP is to construct a new duct bank from SW574-8 to the two existing 6 inch PVC schedule 40 conduits shown on sheet E-131 in “2021-2-15 PCO 002 Site”, and construct a new duct bank from the other end of the same two existing 6 inch PVC schedule 40 conduits to the project site.

End of Notice