Q and A #1 Dec10-2024~1.pdf
PDF 75 KB Posted
- Solicitation number
- S-C25102-00012036
- Issued by
- Marion County, Junction City, Oregon
About this file
This is a Question & Answer document for a Request for Proposal issued by Union Gospel Mission for preconstruction and construction services at the Simonka Place Women's Shelter in Keizer, OR. The document, dated December 10, 2024, addresses questions from potential bidders regarding project details.
The document clarifies that the total project budget, including add-alternates, is approximately $3.38 million. Additionally, it confirms that there are no E-Verify requirements included in the contract provisions. This Q&A document appears to be part of the broader procurement process for the shelter renovation project, which includes upgrades to the 22,181 square foot facility and involves design-build services funded partially through a federal HOME-ARP grant administered by Marion County.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Proposal Preconstruction Services/Construction Services
Union Gospel Mission Simonka Place Women’s Shelter (Keizer, OR)
Question & Answer #1
December 10, 2024
Question 1: What is the intended budget for the project or the funds that are allocated for the work?
ANSWER 1: The project budget, including add-alternates, is approximately $3.38 million.
Question 2: Will there be E-Verify requirements regarding the contract?
ANSWER 2: There is no requirement for E-Verify provisions to be included in the contract.