This is a Question & Answer document for a Request for Proposal issued by Union Gospel Mission for preconstruction and construction services at the Simonka Place Women's Shelter in Keizer, OR. The document, dated December 10, 2024, addresses questions from potential bidders regarding project details.

The document clarifies that the total project budget, including add-alternates, is approximately $3.38 million. Additionally, it confirms that there are no E-Verify requirements included in the contract provisions. This Q&A document appears to be part of the broader procurement process for the shelter renovation project, which includes upgrades to the 22,181 square foot facility and involves design-build services funded partially through a federal HOME-ARP grant administered by Marion County.

View the file

Other files

File Type Posted
OregonBuys Posting Page for UGM.pdf PDF
UGM Simonka_A4.1 SECTIONS_12.19.24.pdf PDF
UGM Simonka_A1.1 SITE PLAN_12.19.24.pdf PDF
UGM Simonka_AD2.1 DEMO FLOOR PLAN_12.19.24.pdf PDF
Addendum 2~1.pdf PDF
RFP UGM Simonka 2025 Remodel RFP 112524 F.pdf PDF
UGM Simonka_A2.6 WALL SCHEDULES_12.19.24.pdf PDF
UGM Simonka_AD3.1 DEMO ELEVATIONS_12.19.24.pdf PDF
SP - Attendance - Tours for Bidding_.docx DOCX document
UGM Simonka_A2.1 FLOOR PLAN_12.19.24.pdf PDF
UGM Simonka_A3.2_Elevations_11.19.24.pdf PDF
Medical Examiner Request for Proposals.pdf PDF
UGM Simonka_A2.3 FLOOR FINISH PLAN_12.19.24.pdf PDF
Findings for Design Build Exemption Jan 23 2025.pdf PDF
UGM Simonka_A5.1 SECTIONS_12.19.24.pdf PDF
pre-bid conf agenda.pdf PDF
Notice of Intent to Award~16.pdf PDF
UGM Simonka RFP Pre-Bid Questions_Final.pdf PDF
UGM Simonka RFP Pre-Bid Questions.pdf PDF
UGM Simonka_AD3.2 DEMO ELEVATIONS_12.19.24.pdf PDF
Addendum1.pdf PDF
UGM Simonka_A2.2.1 CEILING DETAILS_12.19.24.pdf PDF
UGM Simonka_A2.2 CEILING PLAN_12.19.24.pdf PDF
UGM Simonka_RFP SET REV1_12.19.24.pdf PDF
UGM Simonka_A3.1 ELEVATIONS_12.19.24.pdf PDF
UGM Simonka_A3.2 ELEVATIONS_12.19.24.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Proposal Preconstruction Services/Construction Services

Union Gospel Mission Simonka Place Women’s Shelter (Keizer, OR)

Question & Answer #1

December 10, 2024

Question 1: What is the intended budget for the project or the funds that are allocated for the work?

ANSWER 1: The project budget, including add-alternates, is approximately $3.38 million.

Question 2: Will there be E-Verify requirements regarding the contract?

ANSWER 2: There is no requirement for E-Verify provisions to be included in the contract.