This is an appendix to a Performance Work Statement (PWS) for T56 engine maintenance and overhaul operations, effective 06 December 2024, that specifies exemptions from Material Review Board (MRB) disposition requirements.
The document outlines seven categories of material that are exempt from MRB disposition by the Government and may be dispositioned to scrap when determined to meet specified criteria and fall beyond Technical Order (T.O.) overhaul reparable limits through Contractor local engineering review. Exempt materials include: (a) material with replacement cost less than $5,000; (b) superseded or replaced configurations, specifically non-rub-tolerant 2nd and 3rd stage T56-A15 turbine vanes, non-stiffened main diaphragms, Hastelloy C T56-A15 turbine vane cases, and prop shaft seals and nose bearing plates identified by part numbers; (d) bearings; (e) electrical components rejected for electrical test criteria lacking T.O. rework specifications; (f) Consumable Floating Material (CFM) except parts and assemblies with life limits; and (g) common hardware including brackets, fasteners, and 100% replacement items such as seals, packings, and O-rings. The Government reserves the right to revise or update the exemption list based on evolving requirements, and deviations to MRB review requirements may be identified and finalized by the Procuring Contracting Officer (PCO) or Administrative Contracting Officer (ACO).
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
T56 PWS ATTACHMENT D
Material Review Board Exemptions 06 Dec 24 NOTE: Government retains the right to revise or update this list based on Government requirements.
The following material is exempt from MRB disposition by the Government. It may be dispositioned to scrap when it is determined to meet the following criteria and be beyond T.O.
overhaul reparable limits by Contractor local engineering review The Government retains the right to amend the list below. Deviations to MRB review requirements may be identified by the Contractor or Government and finalized by the PCO/ACO.
(a) Material of less than $5,000 replacement cost
(b) Material configuration has been superseded, or replaced by improved configuration and listed below:
Non rub-tolerant 2nd and 3rd stage T56-A15 turbine vanes Non-stiffened main diaphragm Hastelloy C T56-A15 turbine vane cases Prop shaft seal and Nose bearing plate, P/N 6851491/6846127/6875798, and 6788467/6877391
(d) Bearings
(e) Electrical components rejected for electrical test criteria where no T.O. rework criteria is specified in applicable manuals
(f) Material is CFM, except for parts and assemblies with life limits.
(g) Common hardware; brackets, fasteners, etc. and 100% replacement items; e.g. seals, packings, O-rings, etc.