PDX 2026-5 (48) E5.02.pdf
PDF 342 KB Posted
- Attached to
- Portland International Airport Taxiway K West Gates E3 to E6 and Vehicle Service Road Rehabilitation
- Solicitation number
- 146992
- Issued by
- Multnomah County, Oregon
About this file
This is a specification document for the Portland International Airport (PDX) Taxiway K West Gates E3 to E6 and Vehicle Service Road Rehabilitation project managed by the Port of Portland, Oregon. The project encompasses the rehabilitation of Taxiway K West, including associated gates E3 through E6, and the vehicle service road infrastructure. The scope of work includes pavement reconstruction, drainage improvements, lighting modifications, and associated site work to restore the taxiway and service road to operational standards. Specific quantities and detailed project components are outlined in the technical specifications section. The document establishes the baseline requirements for bidders to prepare accurate proposals and includes provisions for site visits and pre-bid meetings to familiarize contractors with project conditions and requirements. The contract term and any renewal options are contingent upon project completion milestones and performance standards established by the Port of Portland.
Pricing shall be submitted on a lump-sum or unit-price basis as specified in the bidding documents, with payment structured according to project milestones and completion of work phases. The project is subject to prevailing wage requirements applicable to public works projects in Oregon. Bidders must demonstrate compliance with bonding requirements, insurance provisions, and any applicable small business set-asides or disadvantaged business enterprise (DBE) participation goals established by the Port of Portland. Funding sources and project budget allocations are determined by the Port of Portland's capital improvement program and may include federal, state, or local revenue sources. All proposals must conform to the technical specifications, contract terms, and administrative requirements outlined in the bidding documents to be considered for award.
View the file
Other files
Show 40 more
Latest 50 of 60 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PF IN-PAVEMENT LIGHT,
FLANGE RING, AND CF SHIMS
FINAL LIFT OF ACP
CF 30" BRAIDED GROUND
STRAP AND CF GROUND LUG
TARGET
PLATE
FINISH GRADE
AC PAVEMENT
MULTIPLE LIFTS
SEALANT
3" EXTENSION, FLANGE
RING AND SHIMS
3"
AC
P
D
EP
TH
V
AR
IE
S
SE
E C
IV
IL
P
LA
N S
PF FLANGE RING, SEE DETAIL
3" EXTENSION (PF)
CONCRETE ANCHOR (P-610)
2" PVC IN ACP, SEE DETAIL
P-610 CONCRETE
REINFORCING SHALL BE #4 BAR, 5 VERT. AND
3 HORIZ., EVENLY SPACED (CF), SEE DETAIL
BASE MATERIAL
PF 12" DIA., 24" DEEP
L-868 BASE CAN
3/4" X 10' GND ROD, 6" BELOW
GRADE AND 10" FROM BASE CAN
AND #6 BARE CONDUCTOR (CF)
36" DIAMETER CORE
VA
R
IE
S
VA
R
IE
S
2" PVC IN ACP
CONCRETE (P-610)
REINFORCING BAR CAGEGROUND ROD AND
BARE CONDUCTOR
13.5" DIA. CORE
APPLY SILICONE LIQUID GASKET
SEALANT BETWEEN EXTENSIONS,
SHIMS AND FLANGE RINGS
COUNTERPOISE
#6 BARE CONDUCTOR WITH
EXOTHERMIC WELD TO
GROUND ROD
CONDUITS BETWEEN BASE CANS SHALL BE
ON A STRAIGHT LINE ALIGNMENT BETWEEN
THE CENTERS OF BASE CANS.
E5.03
E5.03
E5.03
E5.04
GENERAL:
CAREFUL PLANNING, SURVEYING, AND INSTALLATION IS REQUIRED FOR
COMPLIANCE WITH FAA REGULATIONS. CORRECT PLACEMENT OF THE
LIGHTS IS OF PRIME IMPORTANCE. THE CENTERLINE LIGHT BEAM MUST
BE ALIGNED PARALLEL TO THE CENTERLINE WITH A TOLERANCE OF
PLUS OR MINUS 1/2- DEGREE. THE FIXTURE MUST BE LEVEL WITH THE
TOP EDGE BETWEEN PLUS 0-INCH AND MINUS 1/16-INCH FROM THE
PAVEMENT FINAL FINISH GRADE. REMEDIAL WORK WILL BE THE
RESPONSIBILITY OF THE CONTRACTOR AND IS VERY COSTLY.
STEP 1:
1. SURVEY, AND IDENTIFY CONDUIT, LIGHT LOCATIONS AND ELEVATIONS.
2. FOLLOWING THE INSTALLATION OF THE P-209 ROCK BASE, PREPARE A TRENCH
TO INSTALL THE 2" PVC BETWEEN THE LIGHT LOCATIONS WITH CONDUIT
SUPPORT WITHIN 10 FEET MINIMUM. FOLLOWING INSPECTION AND
ACCEPTANCE OF THE TRENCH BY THE PORT, FILL THE TRENCH WITH P-610
CONCRETE WITH NO VOID UNDER THE CONDUITS. STRAP THE CONDUITS
DOWN TO AVOID FLOATATION.
3. INSTALL THE COUNTERPOISE AT THE TOP OF THE P-610 LAYER.
4. JUST BEFORE THE FINAL LIFT OF ASPHALT PAVING, LOCATE THE LIGHT
LOCATIONS. AT EACH NEW FIXTURE LOCATION, CORE DRILL A 36-INCH
DIAMETER HOLE TO THE REQUIRED DEPTH AS CALCULATED USING
APPROPRIATE INSTALLATION DETAILS AS SHOWN ON DETAIL 1 OF THIS
DRAWING.
5. REMOVE AND DISPOSE OF THE CORES AND ALL LOOSE DEBRIS.
6. SURVEY AND CONFIRM THE DEPTH OF EACH OPENING BEFORE PROCEEDING
FURTHER.
STEP 2:
1. USING CONTRACTOR DESIGNED AND CONSTRUCTED JIGS, TEMPORARILY SET
EACH BASE CAN AT THE PROPER ELEVATION. ORIENTATION IS CRITICAL SINCE
THE BOLT HOLES WILL DETERMINE THE FINAL BEAM ACCURACY. IT IS
EQUALLY IMPORTANT THAT THE COVER BE ABSOLUTELY LEVEL BOTH
DIRECTIONS.
2. PROVIDE AND INSTALL GROUND ROD AND BOND IT TO LIGHT BASE. INTERCEPT
THE CONDUITS AND EXTEND INTO THE LIGHT CANS. INSTALL REINFORCING
CAGE AS DETAILED.
3. USING THE CONCRETE SPECIFIED, FILL THE VOID BELOW AND AROUND THE
CAN TO THE TOP OF THE TEMPORARY PAVEMENT GRADE.
4. ALLOW AMPLE TIME FOR FULL CONCRETE SET BEFORE REMOVING JIG.
5. FOLLOWING THE CONCRETE SET, REPLACE THE PLYWOOD COVER WITH A
1/2-INCH THICK TARGET PLATE (OR EQUIVALENT THICKNESS), PORT
FURNISHED. THE TARGET MUST BE ON TOP.
STEP 3:
1. PLACE FOIL OVER TEMPORARY TARGET PLATE TO PREVENT BONDING OF THE
ASPHALT OVERLAY.
2. DEPENDING UPON EXISTING CONDITIONS AT THIS PHASE OF THE
CONSTRUCTION, THE CONTRACTOR MAY ELECT TO INSTALL CIRCUIT
CONDUCTORS, CONNECTORS AND TRANSFORMERS. IF SO, INSTALL A
TEMPORARY RUBBER PLUG IN THE TRANSFORMER SECONDARY CONNECTOR.
CONNECT TRANSFORMER TO CIRCUIT SPECIFIED ON LAYOUT DRAWINGS.
STEP 4:
1. FOLLOWING INSTALLATION OF FINAL AC OVERLAY, SURVEY
BASE CAN CENTER LOCATION.
2. CORE DRILL A 3-INCH HOLE THROUGH AC OVERLAY TO THE
TEMPORARY STEEL TARGET PLATE AND LOCATE TARGET
CENTER ON STEEL COVER.
3. MEASURE THE EXACT THICKNESS OF THE OVERLAY AT EACH
FIXTURE LOCATION, INCLUDING THE TARGET PLATE
THICKNESS. DETERMINE THE COMBINATION OF EXTENSION,
SPACER RINGS, AND/OR SHIMS REQUIRED TO BRING THE
COMPLETED FIXTURE INSTALLATION FLUSH WITH THE FINAL
PAVEMENT FINISH.
STEP 5:
1. UTILIZING THE TARGET WHICH WILL BE VISIBLE AT THE BOTTOM
OF THE 3-INCH CORE, ACCURATELY POSITION THE CORING
MACHINE SO THAT WHEN THE 13.5-INCH CORE IS COMPLETED,
THE ENTIRE TARGET PLATE AT THE BOTTOM OF THE CORE
HOLE IS EXPOSED. IF NOT PROPERLY CENTERED AND
ALLOWING A REASONABLY EQUAL CLEAR SPACE COMPLETELY
AROUND THE FUTURE EXTENSION OR SHIM, RE-CORING WILL BE
REQUIRED. A MINIMUM OF 1/2-INCH OF SPACE MUST BE
PROVIDED FOR FINAL SEALANT INSTALLATION.
2. REMOVE CORE, FOIL, TAPE AND TARGET PLATE. DISPOSE OF
REMAINING DEBRIS OFF PORT PROPERTY. RETURN TARGET
PLATE TO THE PORT.
STEP 6:
1. IF THE WIRING WAS NOT INSTALLED EARLIER, INSTALL THE
CONDUCTORS, CONNECTORS, AND TRANSFORMERS PER THE
DETAILS AND AS DESCRIBED IN STEP 3.
2. CLEAN THE TOP OF THE BASE CAN WITH SOLVENT, SELECT
COMPONENTS PREVIOUSLY CALCULATED TO RAISE LIGHT TO ITS
FINISH ELEVATION. INSTALL SELECTED EXTENSION, SPACER RING
AND SHIMS ON BASE CAN APPLYING SILICONE SEALANT BETWEEN
ADJOINING SURFACES. DO NOT APPLY TO THE TOP OF THE
GROOVED FLANGE RING. UTILIZE PROPERLY SIZED BOLTS WITH A
MINIMUM OF TWO THREADS EXTENDING BELOW THE BASE CAN
THREADED ATTACHMENT RING. TORQUE PER MANUFACTURER'S
SPECIFICATIONS. FINAL COVER PLATE INSTALLATION SHALL BE
FLUSH WITH THE ADJACENT A.C. SURFACE WITHIN THE FAA
SPECIFIED ALIGNMENT QUOTED ABOVE. THE METHOD OF RAISING
EACH LIGHT WILL VARY DEPENDING ON THE TOTAL ELEVATION
CHANGE REQUIRED. DO NOT INSTALL FIXTURE UNTIL AFTER
SEALANT IS IN PLACE. REPLACE PLYWOOD COVER.
3. FILL THE GAP AROUND THE EXTENSION WITH THE P-606 SEALANT.
CARE SHALL BE TAKEN TO AVOID LEAVING AIR BUBBLES OR VOIDS,
PRESSURE APPLY FROM THE BOTTOM UP. AVOID ALLOWING ANY
SEALANT OVER THE DAM OR ON THE ADJACENT PAVEMENT
SURFACES. CLEAN IMMEDIATELY SHOULD THIS OCCUR.
4. FOLLOWING THE P-606 PLACEMENT, FILL THE REMAINING VOID TO
THE TOP OF THE FLANGE RING WITH P-605 SEALANT. AVOID
ALLOWING ANY SEALANT OVER THE DAM OR ON THE ADJACENT
PAVEMENT SURFACES. CLEAN IMMEDIATELY SHOULD THIS OCCUR.
5. AFTER THE SEALANT HAS COOLED, CLEAN AND VACUUM ALL
DEBRIS FROM CAN AND FLANGE RING. INSTALL FIXTURE AND
THOROUGHLY CLEAN AROUND THE LIGHT UNIT AND BASE CAN.
ALL DEBRIS SHALL BE REMOVED FROM THE PROJECT SITE.
RETURN SURPLUS PORT FURNISHED ITEMS TO THE PORT.
CONNECT LIGHT TO CIRCUIT SPECIFIED ON LAYOUT DRAWINGS.
IN-PAVEMENT LIGHT IN ACP INSTALLATION SEQUENCE - RECOMMENDED PROCESS:
RE
GIS
TERED PROFESSIONAL
SERGIO LEGUIRE PERRY
MA RCH 14 , 2 017
EXP: 12/31/2026
OREGON
92070PE
ENGINEER
1/7/2026
C
AN
Y O
U S
EE
T
H E
AI
R
PL
AN
ES
T H
E
AD
JA
C
EN
T
SA
M
PL
ES
S H
O W
T H
R
EE
D
IF
FE
R
EN
T
LE
VE
LS
O
F
SH
AD
IN
G
SE
TT
IN
G
S
FO
R V
IE
W
IN
G
A N
D P
R
IN
TI
N
G D
R
AW
IN
G
C O
N
TE
N T
AR
E
O
PT
IM
IZ
ED
W
H
EN
AL
L
TH
R
EE
P
LA
N
ES
A
R E
VI
SI
BL
E.
T H
IS
G
U
ID
AN
C
E
IS
P R
O
VI
D
ED
F O
R R
EF
ER
EN
C
E O
N
LY
PRINTED:
lig ht da rk gr ay bl ac k
DESIGN NUMBER PROJECT NUMBER
2"
G R
AP
H
IC
S
C
AL
E
- F
O R
R
EF
ER
EN
C E
O N
LY
gr ay
4:52:48 PM DETTMM R:\Aviation\PDX\2026\0005 - Taxiway K West E3-E6 and VSR Rehab\SHEETS - ELEC\ELECTRICAL DETAILS - TWY K WEST.dwg
DISC. SHT. NO.
DRAWING SCALE IS REDUCED 50% WHEN SHEET SIZE IS 11" x 17"
DESIGN BY
DRAWN BY
CHECKED BY
DATE
SHEET NO.
SUBMITTED BY
DRAWING NO.
TYPE:
1/
4" 1/
2" 1"
1/
4" 1/
2" 1"
DATE BY REVISION APPDATE BY REVISION APP ##
IF ELECTRONIC SIGNATURE IS BROKEN OR MISSING - THIS IS NOT A LEGAL DRAWING
PORTLAND INTERNATIONAL AIRPORT
TAXIWAY K WEST GATES E3 TO E6 & VEHICLE SERVICE ROAD REHABILITATION
IN-PAVEMENT LIGHT IN ACP INSTALLATION DETAILS
CHRIS EDWARDS
M. TIEASKIE
M. DETTMER
S. PERRY
OCT 2026
48 CD
PDX 2026-5 E5.022025D033 103134
SCALE:
IN-PAVEMENT LIGHT INSTALLATION IN AC PAVEMENT
N.T.S.1
SCALE:
STEP TWO AND THREE SECTION
N.T.S.2
SCALE:
STEP FIVE SECTION
N.T.S.3
SCALE:
STEP SIX SECTION
N.T.S.4
| DIGITALLY SIGNED | |
| 2026-09-24T06:43:21-0700 | |
| Sergio Perry |
File details come from the government source that posted it. Updated .