Questions_and_Answers_During_Presentation_8.30.16.pdf
PDF 83 KB Posted
- Attached to
- Arch Museum Exhibits (JEFF 199869B) Federal contract opportunity
- Solicitation number
- P16PS00660
About this file
Questions and Answers from Site Visit_08.30.2016
View the file
Other files for this federal contract opportunity
Show all 50
Arch Museum Exhibits (JEFF 199869B) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tuesday August 30, 2016
Pre‐Proposal Meeting ‐ P16PS00660 / JEFF 199869B
Exhibit Questions and Answers During Conference
Question #1 ‐ Do the Mock Ups need to occur in St. Louis?
Answer: Yes, the contract currently states that the fabrication contractor rent a facility in St. Louis for the duration of the contract to include but not limited to a place for Mock Ups. Refer to Section C, Part
E. Project Management, Number 11 – St. Louis Staging and Review Facility.
Question #2 – Can the 5 years relevant experience sated in the evaluation factor be changed to 10‐12 years?
Answer: The Contracting Officer will conduct market research to determine the amount of projects that have been awarded over the last 10 years to determine an appropriate time period for evaluations. If a change is made it will be reflected in an upcoming modification.
Question #3 – Are the following attachments (Attachment‐Q_FMSS_ComponentInventoryForm &
Attachment‐R_FMSS_ComponentInventorySample) required to be submitted with the proposal, what is the purpose of them?
Answer: Those two attachments are required to be filled out after the job is completed. It is an inventory form to be completed and priced out during/after job is completed. Not required in proposal submission.