Attachment-O6_Museum_Specification_Vol3.pdf

PDF 8 MB Posted

Attached to
Arch Museum Exhibits (JEFF 199869B) Federal contract opportunity
Solicitation number
P16PS00660
Issued by
Department of the Interior National Park Service National Office

About this file

Contract 1 - Museum Specs Vol 3 of 3

View the file

Other files for this federal contract opportunity

Other files attached to Arch Museum Exhibits (JEFF 199869B), newest first.
File Type Posted
SF30_Amendment_0011.pdf PDF
Q_and_A_Amendment_0011.pdf PDF
Q_and_A_Amendment_0010.pdf PDF
SF30_Amendment_0010.pdf PDF
SF30_Amendment_0009.pdf PDF
Q_and_A_Amendment_0009.pdf PDF
Attachment_O_UPDATE-2_Amendment_0008.pdf PDF
Q_and_A_Amendment_0008.pdf PDF
Q_and_A_Amendment_0007.pdf PDF
Attachment_O_UPDATE_Amendment_0006.pdf PDF
Q_and_A_Amendment_0005.pdf PDF
SF30_Amend_0005.pdf PDF
Attachment_W_SCA_Wage_Rates.pdf PDF
9489_(F)_MWE_502_-_Proposed_Flooring_Layout_Central_Exhibit_Space_Museum_And_The_Hubs-Arch_D .pdf PDF
Attachment_E_Supplementary_Specifications_Amendment_0004.pdf PDF
9489_(Z)_MWE_1530-Arch_D .pdf PDF
9489_(Z)_MWE_1525-Arch_D .pdf PDF
Q_and_A_Amendment_0004.pdf PDF
9489_(-)_MWE_000_-_Drawing_Issue_Register-Arch_D _(1).pdf PDF
Attachment-O3__Museum_Drawings_Pt3.pdf PDF
Attachment-O2__Museum_Drawings_Pt2.pdf PDF
Attachment-O4_Museum_Specification_Vol_1.pdf PDF
Revised_RFP_Amendment_0003.pdf PDF
Attachment-O1_Museum_Drawings_Pt1.pdf PDF
Attachment-O5_Museum_Specification_Vol_2.pdf PDF
Q_and_A_Amendment_0003.pdf PDF
Amendment_0003_to_P16PS00660.pdf PDF
JEFF_Exhibits_Site_Visit_Presentation.pptx PPTX presentation
Questions_and_Answers_During_Presentation_8.30.16.pdf PDF
Amendment_0002_P16PS00660.pdf PDF
Final_Amendment_0001_to_P16PS00660.pdf PDF
Revised_Vol_II_Submission_Package_P16PS00660_Amendment_0001.pdf PDF
Attachment-V_NPS_map-standards.pdf PDF
Attachment-D4_JEFF_199869B_Exhibit_Fabrication_Drawings_pg_151-195.pdf PDF
Attachment-M_NPS_Standards_for_Museum_Exhibit_Display_Conditions.pdf PDF
Attachment-P_ADA_ABA_Access_Guidelines.pdf PDF
Attachment-D5_JEFF_199869B_Exhibit_Fabrication_Drawings_pg_196-245.pdf PDF
Attachment-N_NPS_Ex_Conserv_Guidelines.pdf PDF
Attachment-U_NPS_EditStyleGuide2015.pdf PDF
Attachment-T_NPS_AVEquipSpecs_12-2013.pdf PDF
Attachment-L_Gov_Furnished_Mtls.pdf PDF
Vol_II_Submission_Package_P16PS00660 .pdf PDF
Attachment-G_Accessioned_Object Layouts.pdf PDF
Attachment-S_FMSS_Inspect_Guide_6-26-09.pdf PDF
Attachment-I_AV_ _IT_Software_Specification.pdf PDF
Vol_I_Submission_Package_P16PS00660.pdf PDF
Attachment-C_2_Exhibit_Elements_Detail_Report.pdf PDF
Attachment-D1_JEFF_199869B_Exhibit_Fabrication_Drawings_pg_1-50.pdf PDF
Attachment-C_1_JEFF_MWE_Database_overview_Report.pdf PDF
Attachment-Q_FMSS_ComponentInventoryForm.xlsm XLSM spreadsheet
Show all 50

Arch Museum Exhibits (JEFF 199869B) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JEFFERSON NATIONAL EXPANSION

MEMORIAL

SAINT LOUIS, MISSOURI

MUSEUM OF WESTWARD EXPANSION

AND VISITOR CENTER

JNEM

PMIS NO. 199869

CONTRACT #1

VOLUME 3

CONFORMED SPECIFICATIONS

NATIONAL PARK SERVICE

FEBRUARY 18, 2015

OWNER

United States Department of the Interior

National Park Service (NPS) Denver Service Center (DSC)

CLIENT GROUP PARTNERS

CityArchRiver 2015 Foundation St. Louis, MO

Great Rivers Greenway St. Louis, MO

DESIGN TEAM

Architect and Prime Cooper, Robertson & Partners (CRP) New York, NY

Architect Trivers Associates St. Louis, MO

Architectural Design Consultant James Carpenter Design Associates (JCDA) New York, NY

Landscape Architect Michael Van Valkenburgh Associates, Landscape Architects, Inc., PC (MVVA) Brooklyn, NY

Mechanical and Electrical Engineer

KJWW

St. Louis, MO

Structural Engineer Alper Audi, Inc.

St. Louis, MO

Plumbing and Fire Protection Engineer

KAI

St. Louis, MO

Accessibility and Universal Design Cohen Hilberry Architects (CHA) St. Louis, MO

Glass Engineering Consulting Eckersley O’Callahan (EOC) New York, NY

Lighting Designer Tillotson Design Associates (TDA) New York, NY

Audio-Visual Consulting Jaffe Holden Houston, TX

Acoustical Consulting AcoustiControl St. Louis, MO

Site Security Consulting ABS Consulting St. Louis, MO

Electronic Security and IT Consulting Shen Milsom & Wilke (SMW) Chicago, IL

Vertical Transportation Consulting Van Deusen & Associates (DA) Livingston, NJ

Waterproofing Consulting Henshell and Buccellato Shrewsbury, NJ

LEED Consultant hellmuth + bicknese architects St. Louis, MO

Civil Engineer David Mason & Associates (DMA) St. Louis, MO

Stormwater Civil Engineer Civil Design Incorporated (CDI) St. Louis, MO 63104

Irrigation Design Landtech Design St. Louis, MO

Geotechnical Engineer Geotechnology Inc.

St Louis, MO 63146

Fountain Designer Hydro Dramatics Inc.

St Louis, MO

CONTRACT 1 CONFORMED CONSTRUCTION DOCUMENTS -- FEBRUARY 18, 2015

JNEM - 199869 000110 - 1

TABLE OF CONTENTS

DOCUMENT 000110

TABLE OF CONTENTS

CRP Cooper, Robertson & Partners AA Alper Audi, Inc.

CDI Civil Design Inc.

DDG DDG Inc.

DMA David Mason & Associates GEO Geotechnology HS Haley Sharpe Design HB Henshell and Buccellato HD Hydro Dramatics JCDA James Carpenter Design Associates HS Hayley Sharpe Design JH Jaffe Holden

KAI KAI

KJWW KJWW

LT LandTech MVVA Michael Van Valkenburgh Associates, Landscape Architects, Inc., PC

RBLDI RBLDI

SMW Shen Milsom & Wilke TA Trivers Associates TAO William Tao & Associates, Inc.

TDA Tillotson Design Associates VDA Van Deusen & Associates

PROCUREMENT AND CONTRACTING REQUIREMENTS

INTRODUCTORY INFORMATION

Document 000010 Cover Page CRP Document 000015 Project Directory CRP Document 000110 Table Of Contents CRP

VOLUME 1

SPECIFICATIONS

DIVISION 01 - GENERAL REQUIREMENTS

Section 011000 Contract Modification Procedures CRP Section 011100 Summary Of Work CRP Section 011115 Construction Phasing CRP Section 012700 Definition Of Contract Line Items CRP Section 013100 Project Management And Coordination CRP Section 013216 Construction Schedule CRP Section 013233 Photo Documentation For Historic Preservation Projects CRP Section 013323 Submittal Procedures CRP Section 013513.22 Archeological Protection CRP Section 013523 Safety Requirements CRP Section 013591 Historic Preservation Treatment Procedures CRP Section 014000 Quality Requirements CRP Section 014200 References CRP Section 015000 Temporary Facilities And Controls CRP Section 015719.11 Indoor Air Quality Management CRP Section 015719.12 Noise And Acoustics Management CRP

JNEM - 199869 000110 - 2

TABLE OF CONTENTS

Section 015723 Pollution Prevention Plan CRP Section 016700 Product Requirements CRP Section 017329 Cutting And Patching CRP Section 017340 Execution CRP Section 017419 Construction Waste Management And Disposal CRP Section 017700 Closeout Procedures CRP Section 017823 Operation And Maintenance Data CRP Section 017900 Demonstration And Training CRP Section 018113 Sustainable Design Requirements CRP Section 019113 Commissioning Requirements TAO

DIVISION 02 - EXISTING CONDITIONS

Section 024119 Selective Demolition CRP

DIVISION 03 - CONCRETE

Section 030130 Maintenance Of Cast-In-Place Concrete CRP Section 031500 Waterstops: Injection Hoses HB Section 033000 Cast-in-Place Concrete AA Section 033001 Cast-In-Place Concrete - Miscellaneous. Site Structures DMA Section 033550 Concrete Floor Finishing CRP Section 033816 Unbonded Post-Tensioned Concrete AA Section 034500 Architectural Precast Concrete CRP Section 034900 Glass-Fiber-Reinforced Concrete CRP

DIVISION 04 - MASONRY

Section 042000 Unit Masonry CRP

DIVISION 05 - METALS

Section 051200 Structural Steel Framing AA Section 051201 Structural Steel Framing - Miscellaneous Site Structures DMA Section 051213 Architecturally Exposed Structural Steel Framing CRP Section 054000 Cold Formed Metal Framing AA Section 055000 Metal Fabrications CRP Section 055150 Monumental Stair CRP Section 057000 Decorative Metal CRP Section 057300 Decorative Metal Railings CRP

DIVISION 06 - WOOD, PLASTICS, & COMPOSITES

Section 061000 Rough Carpentry CRP Section 064023 Interior Architectural Woodwork CRP Section 066400 Plastic Paneling CRP

DIVISION 07 - THERMAL & MOISTURE PROTECTION

Section 071326 Self-Adhering Sheet Waterproofing HB Section 071352 Modified Bitumen Sheet Waterproofing HB Section 071418 Cold Fluid Applied Waterproofing For Fountain MVVA Section 071616 Crystalline Waterproofing HB Section 072100 Building Insulation CRP Section 072119 Foamed In Place Insulation CRP Section 072419 Water-Drainage Exterior Insulation And Finish System CRP Section 072616 Underslab Vapor Retarder HB Section 075323 Ethylene Propylene Diene Monomer Roofing HB Section 078120 Spray Applied Fireproofing CRP Section 078400 Firestopping CRP Section 079200 Joint Sealants CRP Section 079513 Expansion Joint Cover Assemblies HB

JNEM - 199869 000110 - 3

TABLE OF CONTENTS

DIVISION 08 - OPENINGS

Section 081113 Hollow Metal Doors And Frames CRP Section 083113 Access Doors And Frames CRP Section 083120 Floor Access Doors CRP Section 083323 Overhead Coiling Doors CRP Section 083326 Overhead Coiling Grilles CRP Section 083343 Deployable Draft Curtains CRP Section 083513.23 Horizontal Sliding, Accordion-Type Fire Doors CRP Section 084126 All-Glass Entrances And Storefronts CRP Section 084233 Revolving Door Entrances CRP Section 084413 Specialty Glazed Enclosure Systems CRP Section 084429 Automatic Swinging Entrances CRP Section 087100 Door Hardware TA Section 088000 Glazing CRP Section 088853 Security Glazing CRP Section 088856 Bullet-Resistant Glazing CRP Section 089000 Louvers And Vents CRP

DIVISION 09 - FINISHES

Section 092400 Cement Plastering CRP Section 092613 Gypsum Veneer Plastering CRP Section 092900 Gypsum Board CRP Section 093000 Tiling CRP Section 095133 Acoustical Metal Ceilings CRP Section 095300 Acoustical Ceiling Assemblies CRP Section 095419 Reflective Panel Ceilings CRP Section 095426 Linear Wood Ceilings CRP Section 095433 Aluminum Tube Ceiling Panel System CRP Section 096513 Resilient Base And Accessories CRP Section 096519 Resilient Tile Flooring CRP Section 096600 Terrazzo Flooring CRP Section 096770 Sealed Concrete Finish CRP Section 096813 Tile Carpeting CRP Section 098000 Acoustical Treatment CRP Section 099100 Painting CRP Section 099600 High-Performance Coatings CRP

DIVISION 10 - SPECIALTIES

Section 101100 Visual Display Surfaces CRP Section 101400 Signage HS Section 102113 Toilet Compartments CRP Section 102226 Operable Partitions CRP Section 102600 Wall And Corner Protection CRP Section 102813 Toilet Accessories CRP Section 104400 Fire Protection Specialties CRP Section 105113 Metal Lockers CRP Section 105120 Phenolic Lockers CRP Section 108200 Welded Wire Trellis CRP

DIVISION 11 - EQUIPMENT

Section 111319 Loading Dock Lifts CRP Section 111413.13 Portable Posts And Railings CRP Section 114000 Food Service Equipment DDG

DIVISION 12 - FURNISHINGS

Section 122413 Roller Window Shades CRP Section 123623 Plastic Countertops CRP Section 124813 Entrance Floor Mats CRP

JNEM - 199869 000110 - 4

TABLE OF CONTENTS

Section 124819 Decorative Floor Gratings And Frames CRP Section 129300 Site Improvements MVVA

DIVISION 13 - SPECIAL CONSTRUCTION

Section 131213 Exterior Water Feature System HD

DIVISION 14 - CONVEYING EQUIPMENT

Section 142400 Hydraulic Elevators VDA Section 142423 Hydraulic Passenger Elevator TA Section 143100 Escalator VDA

VOLUME 2

DIVISION 21 - FIRE SUPPRESSION

Section 210500 Common Work Results For Fire Suppression KAI Section 210548 Vibration And Seismic Controls For Fire Suppression Piping And Equipment KAI Section 211313 Wet-Pipe, Dry-Pipe And Standpipe Systems KAI

DIVISION 22 - PLUMBING

Section 220523 General-Duty Valves For Plumbing Piping KAI Section 220529 Hangers And Supports For Plumbing Piping And Equipment KAI Section 220548 Vibration And Seismic Controls For Plumbing Piping And Equipment KAI Section 220553 Identification For Plumbing Piping And Equipment KAI Section 220700 Plumbing Insulation KAI Section 221116 Domestic Water Piping KAI Section 221119 Domestic Water Piping Specialties KAI Section 221316 Sanitary Waste And Vent Piping KAI Section 221423 Storm Drainage Piping KAI Section 221429 Sump Pumps KAI Section 221430 Existing Sump Pumps KAI Section 223300 Electric Domestic Water Heaters KAI Section 224000 Plumbing Fixtures KAI Section 224700 Electric Water Coolers KAI

DIVISION 23 - HEATING, VENTILATING AND AIR CONDITIONING

Section 230500 Basic HVAC Requirements KJWW Section 230503 Through Penetration Firestopping KJWW Section 230505 HVAC Demolition for Remodeling KJWW Section 230513 Motors KJWW Section 230516 HVAC Expansion Compensation KJWW Section 230529 HVAC Supports and Anchors KJWW Section 230548 HVAC Vibration Isolation KJWW Section 230550 Seismic Requirements for Equipment and Supports KJWW Section 230553 HVAC Identification KJWW Section 230593 Testing, Adjusting, and Balancing KJWW Section 230713 Ductwork Insulation KJWW Section 230716 HVAC Equipment Insulation KJWW Section 230719 HVAC Piping Insulation KJWW Section 230900 Controls KJWW Section 230913 Instrumentation KJWW Section 232100 Hydronic Piping KJWW Section 232123 HVAC Pumps KJWW Section 232200 Steam and Steam Condensate Piping KJWW Section 232218 Steam and Steam Condensate Specialties KJWW Section 232500 Chemical (Water) Treatment KJWW Section 233100 Ductwork KJWW Section 233300 Ductwork Accessories KJWW

JNEM - 199869 000110 - 5

TABLE OF CONTENTS

Section 233416 Centrifugal Fans KJWW Section 233423 Power Ventilators KJWW Section 233600 Air Terminal Units KJWW Section 233700 Air Inlets and Outlets KJWW Section 234000 Air Cleaning KJWW Section 235700 Heat Exchangers KJWW Section 236416 Electric Water Chillers KJWW Section 237200 Energy Recovery Devices KJWW Section 237323 Custom Air Handling Units KJWW Section 237415 Microclimate Generator KJWW Section 238200 Terminal Heat Transfer Units KJWW Section 238216 Air Coils KJWW

DIVISION 26 - ELECTRICAL

Section 260500 Basic Electrical Requirements KJWW Section 260500.1 Basic Electrical Requirements - Site KJWW Section 260505 Electrical Demolition for Remodeling KJWWI Section 260505.1 Electrical Demolition for Remodeling - Site KJWW Section 260513 Wire And Cable KJWW Section 260513.1 Wire And Cable - Site KJWW Section 260517 Electric Heat Trace And Snow Melt KJWW Section 260526 Grounding and Bonding KJWW Section 260526.1 Grounding and Bonding - Site KJWW Section 260527 Supporting Devices KJWW Section 260527.1 Supporting Devices - Site KJWW Section 260533 Conduit and Boxes KJWW Section 260533.1 Conduit And Boxes - Site KJWW Section 260535 Surface Raceways KJWWI Section 260537.1 Manholes - Site KJWW Section 260548 Seismic Requirements for Equipment and Supports KJWW Section 260553 Electrical Identification KJWW Section 260553.1 Electrical Identification - Site KJWW Section 260913 Power Monitoring And Control System KJWWI Section 260923 Lighting Control Devices - Architectural Luminaires TDA Section 260933 Lighting Control Systems KJWWI Section 260943 Networked Exterior Lighting Controls RBLDI Section 262000 Service Entrance KJWW Section 262200 Dry Type Transformers KJWW Section 262413 Switchboards KJWW Section 262416 Panelboards KJWW Section 262423.1 Packaged Power -Center - Site KJWW Section 262716.1 Cabinets And Enclosures - Site KJWW Section 262726 Wiring Devices KJWWI Section 262726.1 Wiring Devices - Site KJWW Section 262813 Fuses KJWW Section 262816 Disconnect Switches KJWW Section 262816.1 Disconnect Switches - Site KJWW Section 262923 Variable Frequency Drives KJWW Section 263353 Static Uninterruptible Power Supply KJWW Section 263600 Transfer Switch KJWW Section 264300 Surge Protection Devices KJWW Section 264300.1 Surge Protection Devices - Site KJWW Section 265100 Lighting KJWW Section 265100 Luminaires - Architectural TDA Section 265000.1 Lighting KJWW Section 265600 Exterior Lighting RBLDI

JNEM - 199869 000110 - 6

TABLE OF CONTENTS

VOLUME 3

DIVISION 27 - COMMUNICATIONS

Section 270500.1 Basic Communications Systems Requirements - Site KJWW Section 270501 Basic Communications Systems Requirements KJWW Section 270505.1 Technology Demolition For Remodeling - Site KJWW Section 270506 Technology Demolition For Remodeling KJWWI Section 270526 Grounding And Bonding For Communications Systems SMW Section 270528 Pathways For Communications Systems SMW Section 270528.33 Conduit And Backboxes For Communications Systems SMW Section 270528.36 Cable Trays For Communications Systems SMW Section 270528 Pathway For Communications Systems SMW Section 270543.1 Exterior Communication Pathways - Site KJWW Section 270553 Identification For Communications Systems SMW Section 270800 Commissioning of Communications Systems SMW Section 271000 Structured Cabling SMW Section 271116 Communications Cabinets, Racks, Frames And Enclosures SMW Section 271119 Communications Termination Blocks And Patch Panels SMW Section 271123 Communications Cable Management And Ladder Rack SMW Section 271300.1 Backbone Cabling Requirements - Site KJWW Section 271313 Communications Copper Backbone Cabling SMW Section 271313.13 Communications Copper Backbone Splicing And Terminations SMW Section 271323 Communications Optical Fiber Backbone Cabling SMW Section 271323.13 Communications Optical Fiber Splicing And Terminations SMW Section 271345 Network Electronics KJWW Section 271500.1 Horizontal Cabling Requirements - Site KJWW Section 271513 Communications Copper Horizontal Cabling SMW Section 271523 Communications Optical Fiber Horizontal Cabling SMW Section 271543 Communications Faceplates And Connectors SMW Section 271619 Communications Patch Cords, Station Cords And Cross Connect Wire SMW Section 271710 Testing KJWWI Section 271710.1 Testing - Site KJWW Section 271720.1 Support And Warranty - Site KJWW Section 274100 Audio Video Systems JH Section 275320 Distributed Antenna System (DAS) KJWW

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

Section 280500 Common Work Results For Electronic Safety And Security SMW Section 280500.1 Basic Electronic Safety And Security System Requirements - Site KJWW Section 280501 Basic Electronic Safety And Security System Requirements KJWW Section 280513 Conductors And Cables For Electronic Safety And Security SMW Section 281300 Access Control SMW Section 282300 Video Surveillance SMW Section 282300.011 Video Surveillance - Site KJWW Section 282301 Video Surveillance KJWW Section 282605 Rescue Assistance Communication System KJWW Section 283100 Fire Alarm and Detection Systems KJWW

DIVISION 31 - EARTHWORK

Section 311000 Site Preparation, Salvage And Clearing MVVA Section 312000 Earthwork DMA Section 312323 EPS Geofoam MVVA Section 313419 Reinforced Slope Systems GEO Section 315000 Excavation Support And Protection DMA Section 316329 Drilled Concrete Piers And Shafts AA Section 316813 Foundation Rock Anchors AA

JNEM - 199869 000110 - 7

TABLE OF CONTENTS

DIVISION 32 - EXTERIOR IMPROVEMENTS

Section 321243 Decomposed Granite Pavement MVVA Section 321313 Concrete Pavements And Curbs MVVA Section 321400 Site Stonework MVVA Section 321700 Fountain Pedestal System MVVA Section 323113 Chain Link Fence MVVA Section 323119 Site Ornamental Metals MVVA Section 323900 Security Bollards MVVA Section 328400 Landscape Irrigation LT Section 329119 Planting Soil System - Installation MVVA Section 329200 Lawn MVVA Section 329300 Planting And Fine Grading MVVA

DIVISION 33 - UTILITIES

Section 331113 Site Water Distribution DMA Section 333100 Sanitary Utility Sewerage Piping CDI Section 334100 Storm Utility Drainage Piping CDI Section 334400 Storm Utility Water Drains CDI Section 334600 Aeration System MVVA Section 334913 Storm Drainage Manholes And Cleanouts CDI

END TABLE OF CONTENTS

CONTRACT 1 CONFORMED CONSTRUCTION DOCUMENTS - FEBRUARY 18, 2015

JNEM - 199869 27 05 00.1 - 1

BASIC COMMUNICATIONS SYSTEMS REQUIREMENTS - SITE

SECTION 27 05 00.1

BASIC COMMUNICATIONS SYSTEMS REQUIREMENTS - SITE

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Basic Communications Systems Requirements specifically applicable to Division 27 sections, in addition to Division 1 - General Requirements.

1.2 SCOPE OF WORK

A. This Specification and the accompanying drawings govern the work involved in relocating, installing, testing and placing into satisfactory operation the Communications Systems as shown and specified herein.

B. Each Contractor shall provide all new materials as indicated in the schedules on the drawings, and/or in these specifications, and all items required to make their portion of the Communications Systems a finished and working system.

C. Description of Systems include but are not limited to the following:

1. Video Surveillance Cabling System including, but not limited to the following for site telecommunications devices:

a. Fiber and copper cabling installation and terminations.

b. Cabling pathways.

c. Testing

2. Relocate existing site surveillance cameras and install new site cameras in new locations.

3. All associated electrical backboxes, conduit, miscellaneous cabling, and power supplies required for proper system installation and operation.

1.3 WORK SEQUENCE

A. All construction work that will produce excessive noise levels and interference with normal park operations, as determined by the Contracting Officer, shall be scheduled with the Contracting Officer. It may be necessary to schedule such work during non-occupied hours. The Contracting Officer shall reserve the right to set policy as to when restricted construction hours will be required.

1.4 DIVISION OF WORK BETWEEN ELECTRICAL AND COMMUNICATIONS CONTRACTORS

A. Division of work is the responsibility of the Prime Contractor. Any scope of work described in the contract document shall be sufficient for including said requirement in the project. The Prime Contractor shall be solely responsible for determining the appropriate subcontractor for the described scope. In no case shall the project be assessed an additional cost for scope that is described in the contract documents. The following division of responsibility is a guideline based on typical industry practice.

JNEM - 199869 27 05 00.1 - 2

B. Definitions:

1. "Electrical Contractor" as referred to herein refers to the Contractors listed in Division 26 of this Specification.

2. “Electrical Contractor” shall also refer to the Contractor listed in Division 27 of this specification when the Consolidated Responsibility Matrix indicates the work shall be provided by the EC. Refer to the Electrical drawings Consolidated Responsibility Matrix.

3. “Communications Contractor” as referred to herein refers to the Contractors listed in Division 27 of this Specification.

4. Low Voltage Communications Wiring: The wiring (less than 120VAC) associated with the Communications Systems, used for analog and/or digital signals between equipment.

C. General:

1. The purpose of these Specifications is to outline typical Electrical and Communications Contractor's work responsibilities as related to Communications Systems including Telecommunications conduit, power wiring and Low Voltage Communications Wiring. The prime contractor is responsible for all divisions of work.

2. The exact wiring requirements for much of the equipment cannot be determined until the systems have been purchased and submittals are approved. Therefore, only known wiring, conduits, raceways, and electrical power as related to such items, is shown on the Communications Drawings. Other wiring, conduits, raceways, junction boxes, and electrical power not shown on the Communications Drawings but required for the successful operation of the systems shall be the responsibility of the Communications Contractor and included in the Contractor’s bid.

3. Where the Electrical Contractor is required to install conduit, conduit sleeves and/or power connections in support of Communications systems, the final installation shall not begin until a coordination meeting between the Electrical Contractor and the Communications Contractor has convened to determine the exact location and requirements of the installation.

4. For cabling from the site to locations inside of the Museum of Westward Expansion this Contractor shall establish Electrical and Communications utility elevations prior to fabrication and installation. The Communications Contractor shall cooperate with the Electrical Contractor and the determined elevations in accordance with the guidelines below. This Contractor shall coordinate utility elevations with other trades. When a conflict arises, priority shall be as follows:

a. Lighting Fixtures

b. Gravity Flow Piping, including Steam and Condensate

c. Sheet Metal

d. Electrical Busduct

e. Cable Trays, including 12” access space

f. Sprinkler Piping and other Piping

g. Conduit and Wireway

h. Open Cabling

JNEM - 199869 27 05 00.1 - 3

D. Electrical Contractor's Responsibility:

1. Assumes all responsibility for all required conduit and power connections when shown on the “Suggested Matrix of Scope Responsibility” to be provided by the Electrical Contractor.

2. Responsible for Communications Systems grounding and bonding.

3. This Contractor is responsible for coordination of utilities with all other Contractors. If any field coordination conflicts are found, the Contractor shall coordinate with other Contractors to determine a viable layout.

E. Communications Contractor’s Responsibility:

1. Assumes all responsibility for the Low Voltage Communications Wiring of all systems, including cable support where open cable is specified.

2. Assumes all responsibility for all required conduit and power connections not specifically shown as being provided by the Electrical Contractor on the “Suggested Matrix of Scope Responsibility.”

3. Assumes all responsibility for providing and installing all cable management hardware (as defined in here-in).

4. Responsible for providing the Electrical Contractor with the required grounding lugs or other hardware for each piece of Communications equipment which is required to be bonded to the Communications ground system.

5. This Contractor is responsible for coordination of utilities with all other Contractors. If any field coordination conflicts are found, the Contractor shall coordinate with other Contractors to determine a viable layout.

1.5 COORDINATION DRAWINGS

A. Definitions:

1. Coordination Drawings: A compilation of the pertinent layout and system drawings that show the sizes and locations, including elevations, of system components and required access areas to ensure that no two objects will occupy the same space.

a. Mechanical trades shall include, but are not limited to, mechanical equipment, ductwork, fire protection systems, plumbing piping, hydronic piping, steam and steam condensate piping, and any item that may impact coordination with other disciplines.

b. Electrical trades shall include, but are not limited to, electrical equipment, conduit 1.5” and larger, conduit racks, pull boxes, transformers, raceway, busway, lighting, ceiling-mounted devices, and any item that may impact coordination with other disciplines.

c. Technology trades shall include, but are not limited to, technology equipment, conduit 1.5” and larger, conduit racks, cable trays, ladder rack, pull boxes, raceway, ceiling-mounted devices, and any item that may impact coordination with other disciplines.

JNEM - 199869 27 05 00.1 - 4

d. Maintenance clearances and code-required dedicated space shall be included.

e. The coordination drawings shall include all underground, underfloor, in-floor, in chase, and vertical trade items.

2. The contractors shall use the coordination process to identify the proper sequence of installation of all utilities above ceilings and in other congested areas, to ensure an orderly and coordinated end result, and to provide adequate access for service and maintenance.

B. Participation:

1. The contractors and subcontractors responsible for work defined above shall participate in the coordination drawing process.

2. One contractor shall be designated as the Coordinating Contractor for purposes of preparing a complete set of composite electronic CAD coordination drawings that include all applicable trades, and for coordinating the activities related to this process.

a. The Coordinating Contractor shall utilize personnel familiar with requirements of this project and skilled as draftspersons/CAD operators, competent to prepare the required coordination drawings.

3. Electronic CAD drawings shall be submitted to the Coordinating Contractor for addition of work by other trades. Contacting Officer will provide electronic file copies of drawings for contractor’s use if the contractor signs and returns an “Electronic File Transfer” waiver provided by Contracting Officer. The Contracting Officer will not consider blatant reproductions of original file copies an acceptable alternative for coordination drawings.

C. Drawing Requirements:

1. The file format and file naming convention shall be coordinated with and agreed to by all contractors participating in the coordination process and the Contracting Officer.

a. Scale of drawings:

1) General plans: 1/4 Inch = 1 '-0" (minimum).

2) Mechanical, electrical, communication rooms, and including the surrounding areas within 10 feet: 1/2 Inch = 1'-0" (minimum).

3) Shafts and risers: 1/2 Inch = 1'-0" (minimum).

4) Sections of shafts and mechanical and electrical equipment rooms: 1/4 Inch = 1 '-0" (minimum).

5) Sections of congested areas: 1/2 Inch = 1'-0" (minimum).

2. Ductwork layout drawings shall be the baseline system for other components.

Ductwork layout drawings shall be modified to accommodate other components as the coordination process progresses.

JNEM - 199869 27 05 00.1 - 5

3. There may be more drawings required for risers, top and bottom levels of mechanical rooms, and shafts.

4. The minimum quantity of drawings will be established at the first coordination meeting and sent to the Contracting Officer for review. Additional drawings may be required if other areas of congestion are discovered during the coordination process.

D. General:

1. Coordination drawing files shall be made available to the Contracting Offer. The Contracting Officer will only review identified conflicts and give an opinion, but will not perform as a coordinator.

2. A plotted set of coordination drawings shall be available at the project site.

3. Coordination drawings are not shop drawings and shall not be submitted as such.

4. The contract drawings are schematic in nature and do not show every fitting and appurtenance for each utility. Each contractor is expected to have included in his/her bid sufficient fittings, material, and labor to allow for adjustments in routing of utilities made necessary by the coordination process and to provide a complete and functional system.

5. The contractors will not be allowed additional costs or time extensions due to participation in the coordination process.

6. The contractors will not be allowed additional costs or time extensions for additional fittings, reroutings or changes of duct size, that are essentially equivalent sizes to those shown on the drawings and determined necessary through the coordination process.

7. The Contracting Officer reserves the right to determine space priority of equipment in the event of spatial conflicts or interference between equipment, piping, conduit, ducts, and equipment provided by the trades.

8. Changes to the contract documents that are necessary for systems installation and coordination shall be brought to the attention of the Contracting Officer.

a. Providing additional access panels shall be considered after other alternatives are reviewed and discarded by the Contracting Officer.

9. Complete the coordination drawing process and obtain sign off of the drawings by all contractors prior to installing any of the components.

10. Conflicts that result after the coordination drawings are signed off shall be the responsibility of the contractor or subcontractor who did not properly identify their work requirements, or installed their work without proper coordination.

11. Updated coordination drawings that reflect as-built conditions may be used as record documents.

JNEM - 199869 27 05 00.1 - 6

1.6 QUALITY ASSURANCE

A. Telecommunications Structured Cabling System Standards:

1. All work and equipment shall conform to the most current ratified version of the following published standards unless otherwise indicated that draft standards are to be followed:

a. ANSI/NECA/BICSI 568 - Standard for Installing Commercial Building Telecommunications Cabling

b. ANSI/TIA-568-C.0 - Generic Telecommunications Cabling for Customer Premises

1) C.1 - Commercial Building Telecommunications Standard

2) C.2 - Balanced Twisted-Pair Telecommunications Cabling and Components Standard

3) C.3 - Optical Fiber Cabling Components Standard

c. ANSI/TIA-569-C - Telecommunications Pathways and Spaces

d. ANSI/TIA-606-B - Administration Standard for Commercial Telecommunications Infrastructure

e. ANSI/TIA-607-B - Commercial Building Grounding (Earthing) and Bonding Requirements for Telecommunications

f. ANSI/TIA-758-B - Customer-Owned Outside Plant Telecommunications Standard

g. ANSI/TIA-1152 - Requirements for Field Test Instruments and Measurements for Balanced Twisted-Pair Cabling

h. ANSI/TIA/EIA-598-C - Optical Fiber Cable Color Coding

i. NFPA 70 (NEC) - National Electrical Code (Current Edition)

j. UL 444 - Standard for Safety for Communications Cable

B. Refer to individual sections for additional Quality Assurance requirements.

C. Qualifications:

1. Only products of reputable manufacturers as determined by the Contracting Officer will be acceptable.

2. The installing Contractor shall be certified by the manufacturer of the structured cabling system. Certification of Contractor shall have been in place for a minimum of one year prior to bidding this project. Documentation of certification is required at the time of bid. Shop drawings will not be approved until proof of certification is submitted. Refer to the end of this specification section for certification documentation requirements.

JNEM - 199869 27 05 00.1 - 7

3. Each Contractor and their subcontractors shall employ only workers who are skilled in their respective trades and fully trained. All workers involved in the termination of cabling shall be individually certified by the manufacturer.

4. The Contractor shall be experienced in all aspects of this work and shall be required to demonstrate direct experience on recent systems of similar type and size.

5. The Contractor shall own and maintain tools and equipment necessary for successful installation and testing of optical and copper structured cabling systems and have personnel adequately trained in the use of such tools and equipment.

6. The Contractor shall obtain the services of a RCDD (Registered Communications Distribution Designer) for the project. The RCDD shall perform the following tasks on the project:

a. Review contractor’s submittals and stamp the submittals with a current RCDD stamp stating the submittals compliance with the contract documents.

b. Provide written and dated confirmation of an observation of the contractor’s installation activities no less than every month during the construction period.

c. Provide a final written and dated confirmation of a final construction review prior to testing.

d. Review final testing of system and provide current RCDD stamp on the documented results or transmittal of the results stating the test results compliance with the contract documents.

7. The Contractor shall have certified BICSI installation technicians on staff to perform the following tasks on the project:

a. Act as the field superintendent or job foreman with the responsibility of monitoring the daily work of each technician.

b. Oversee all testing and termination of cabling.

8. A resume of qualification shall be submitted with the Contractor’s bid indicating the following:

a. Documentation of certification of This Contractor by the proposed structured cabling system manufacturer as required at the end of this specification section.

b. A list of recently completed projects of similar type and size with contact names and telephone numbers for each.

c. A list of test equipment proposed for use in verifying the installed integrity of copper and fiber optic systems on the project.

d. A technical resume of experience for the Contractor’s project manager and on-site installation supervisor assigned to this project.

JNEM - 199869 27 05 00.1 - 8

e. Resume and certification of the RCDD for the project as required by the form at the end of this specification section.

f. Resume and certification of the BICSI installation technician for the project.

D. Compliance with Codes, Laws, Ordinances:

1. This Contractor shall conform to all requirements of the City of St. Louis, Missouri Codes, Laws, Ordinances and other regulations having jurisdiction over this installation.

2. In the event there are no local codes having jurisdiction over this job, the current issue of the National Electrical Code shall be followed.

3. If there is a discrepancy between the codes and regulations having jurisdiction over this installation, and these specifications, the codes and regulations shall determine the method or equipment used.

4. If the Contractor notes, at the time of bidding, any parts of the drawings and specifications which are not in accordance with the applicable codes or regulations, he shall inform the Contracting Officer in writing, requesting a clarification.

E. Permits, Fees, Taxes, Inspections:

1. Procure all applicable permits and licenses.

2. Abide by all applicable laws, regulations, ordinances, and other rules of the State or Political Subdivision wherein the work is done, or as required by any duly constituted public authority.

3. Pay all applicable charges for such permits or licenses that may be required.

4. Pay all applicable fees and taxes imposed by the State, Municipal and/or other regulatory bodies.

5. Pay all charges arising out of required inspections due to codes, permits, licenses or as otherwise may be required by an authorized body.

6. Pay all charges arising out of required contract document reviews associated with the project and as initiated by the Contracting Officer.

7. Pay any charges by the service provider related to the service or change in service to the project.

8. All equipment and materials shall be as approved or listed by the following (unless approval or listing is not applicable to an item by all acceptable manufacturers):

a. Factory Mutual

b. Underwriters' Laboratories, Inc.

JNEM - 199869 27 05 00.1 - 9

F. Examination of Drawings:

1. The drawings for the Communications Systems work are diagrammatic, intended to convey the scope of the work and to indicate the general arrangements and locations of equipment etc., and the approximate sizes of equipment.

2. Contractor shall determine the exact locations of equipment and the exact routing of cabling so as to best fit the layout of the job. Scaling of the drawings will not be sufficient or accurate for determining this layout. Where a specific route is required, such route will be indicated on the drawings.

3. Where job conditions require reasonable changes in indicated arrangements and locations, such changes shall be made by the Contractor at no additional cost to the Contracting Officer.

4. If an item is shown, specified or required for proper operation of the system, it shall be considered sufficient for including same in this contract.

5. The determination of quantities of material and equipment required shall be made by the Contractor from the drawings. Schedules on the drawings and in the specifications are completed as an aid to the Contractor but where discrepancies arise, the greater number shall govern.

6. Where words "provide", "install", or "furnish" are used on the drawings or in the specifications, it shall be taken to mean, to furnish, install and terminate completely ready for operation, the items mentioned.

G. Electronic Media/Files:

1. Construction drawings for this project have been prepared utilizing AutoCAD

MEP.

2. Contractors and Subcontractors may request electronic media files of the contract drawings and/or copies of the specifications. Specifications will be provided in PDF format.

3. Upon request for electronic media, the Contractor shall complete and return a signed “Electronic File Transmittal” form provided by the Contracting Officer.

4. If the information requested includes floor plans prepared by others, the Contractor will be responsible for obtaining approval from the Contracting Officer for use of that part of the document.

5. The electronic contract documents can be used for preparation of shop drawings and as-built drawings only. The information may not be used in whole or in part for any other project.

6. The drawings prepared for bidding purposes may not be used directly for ductwork layout drawings or coordination drawings.

7. The use of these CAD documents by the Contractor does not relieve them from their responsibility for coordination of work with other trades and verification of space available for the installation.

8. The information is provided to expedite the project and assist the Contractor with no guarantee as to the accuracy or correctness of the information provided. The

JNEM - 199869 27 05 00.1 - 10

Contracting Officer accepts no responsibility or liability for the Contractor’s use of these documents.

H. Field Measurements:

1. Before ordering any materials, this Contractor shall verify all pertinent dimensions at the job site and be responsible for their accuracy.

2. Field conditions that will result in telecommunications drops that exceed the length limitations identified in the contract documents shall be brought to the attention of the Contracting Officer prior to installation. The cost of reworking cabling that is too long, that was not brought to the written attention of the Contracting Officer will be borne entirely by the Contractor.

3. This Contractor shall provide the Contracting Officer with written documentation of any cabling drops that will not be able to use the cable tray (where cable tray is available) due to the resulting cabling lengths. This documentation shall be submitted prior to installation and installation shall not commence until approved by the Contracting Officer.

1.7 SUBMITTALS

A. Submittals shall be required for the following items, and for additional items where required elsewhere in the specifications or on the drawings.

1. Submittals list:

Referenced Specification

Section Submittal Item 27 05 43.1 Exterior Communications Pathways 27 15 00.1 Horizontal Cabling Requirements 27 17 10.1 Testing 28 23 00.1 Video Surveillance

B. In addition to the provisions of Division 1, the following is required:

1. Submittals shall include all layout drawings; manufacturers' standard drawings;

schedules; descriptive literature, catalogs and brochures; performance and test data; wiring diagrams; and all other drawings and descriptive data of materials of construction as may be required to show that the materials, equipment or systems and the location thereof conform to the requirements of the contract documents.

2. The Contractor shall submit one electronic copy of each shop drawing for review by the Contracting Officer before releasing any equipment for manufacture or shipment.

3. Shop drawings which are larger than 11" x 17" or are plan size layout drawings such as wiring diagrams, shall be submitted on reproducible media. Submit one reproducible and one print of each drawing or plan. All Contractor approval stamps shall be made on the reproducible. The Contracting Officer will return the reproducible copy of the shop drawings, complete with comments. This Contractor shall copy and distribute these reviewed shop drawings as required.

JNEM - 199869 27 05 00.1 - 11

All costs for copying and distribution of reproducible shop drawings shall be included by This Contractor in their bid.

4. The Contractor shall thoroughly review and approve all shop drawings before submitting them to the Contracting Officer. Contractor’s approval stamp is required on all submittals. Approval will indicate the contractor's review of all material and a complete understanding of exactly what is to be furnished.

Contractor shall clearly mark all deviations from the contract documents on all submittals. If deviations are not marked by the contractor, then the item shall be required to meet all drawing and specification requirements.

5. The Contractor shall provide RCDD stamp on the submittal.

6. The Contractor shall clearly mark each item with the same nomenclature applied on the drawings or in the specifications.

7. The Contractor shall clearly indicate the size, finish, material, etc.

8. All submittals shall be assembled in sets by system.

9. Each set shall be bound in a manufacturer's folder or inside of a manila file folder.

10. Each set shall contain an index of the items enclosed with a general topic description on the cover.

11. Where more than one model is shown on a manufacturer's sheet, the Contractor shall clearly indicate exactly which item and which data is relevant to the work.

12. Failure to comply with the above shall be reason to resubmit all shop drawing submittals.

13. Provide documentation of all warranties required by the contract documents.

14. Submit copy of the Contractor certification form contained at the end of specification section.

C. Provide Schedule of Values for Technology Work:

1. Application forms: Use AIA Document Continuation Sheets G703 (or similar) as the form for application.

2. Provide line items on the Schedule of Values including:

a. Security Systems

1) Surveillance

b. Fiber optic infrastructure

3. Change orders shall have schedule of values broken out as listed above submitted with each change order.

4. Coordinate with the Contracting Officer the items included in the Schedule of Values. The intent is to not create schedules in addition to those the Technology Contractor normally submits to the General Contractor for payment.

JNEM - 199869 27 05 00.1 - 12

1.8 PRODUCT DELIVERY, STORAGE, HANDLING & MAINTENANCE

A. Exercise care in transporting and handling to prevent damage to fixtures, equipment and materials.

B. Store materials on the site so as to prevent damage.

C. Keep fixtures, equipment and materials clean, dry and free from deleterious conditions.

1.9 WARRANTY

A. At a minimum, provide a one year warranty for all equipment, materials, and workmanship. Individual specifications sections within Division 27 may require additional warranty requirements for specific equipment or systems.

B. Provide a structured cabling System Assurance Warranty as described herein.

C. The warranty period for the entire installation described in this Division of the specifications shall commence on the date of substantial completion unless a whole or partial system or any separate piece of equipment or component is put into use for the benefit of any party other than the installing contractor with prior written authorization. In this instance, the warranty period shall commence on the date when such whole system, partial system or separate piece of equipment or component is placed in operation and accepted in writing by the Contracting Officer or their representative.

D. Warranty requirements shall extend to correction, without cost to the final user, of all work and/or equipment found to be defective or nonconforming to the contract documents.

The Contractor shall bear the cost of correcting all damage resulting from such defects or nonconformance with contract documents exclusive of repairs required as a result of improper maintenance or operation, or of normal wear as determined by the Contracting Officer.

1.10 INSURANCE

A. This Contractor shall maintain insurance coverage as set forth in Division 1 of these specifications.

1.11 MATERIAL

A. Where several manufacturers’ names are given, all are considered of acceptable quality required to be used in this contract.

B. Equivalent equipment manufactured by the other named manufacturers may be used.

Contractor shall ensure that all items submitted by these other manufacturers meets all requirements of the drawings and specifications and fits in the allocated space. The Contracting Officer shall make the final determination of whether a product is equivalent.

C. Any material, article or equipment of other unnamed manufacturers which will adequately perform the services and duties imposed by the design and is of a quality equal to or better than the material, article or equipment identified by the drawings and specifications may be used if approval is secured in writing from the Contracting Officer not later than ten days prior to the bid opening date. The Contractor bears full responsibility for the unnamed manufacturers equipment adequately meeting the intent of design. The Contracting Officer may reject manufacturer at time of shop drawing submittal. The Contractor assumes all costs incurred by other trades on the project as a result of

JNEM - 199869 27 05 00.1 - 13

changes necessary to accommodate the offered material, equipment or installation method.

D. Should this Contractor be unable to secure approval from the Contracting Officer for other unnamed manufacturers as outlined above, this Contractor may list voluntary add or deduct prices for alternate materials on the bid form. These items will not be used in determining the low bidder. Should a voluntary alternate material be accepted, This Contractor shall assume all costs that may be incurred as a result of using the offered material, article or equipment necessitating extra expense on This Contractor or on the part of other Contractors whose work is affected.

PART 2 - PRODUCTS

2.1 REFER TO INDIVIDUAL SECTIONS

PART 3 - EXECUTION

3.1 JOBSITE SAFETY

A. Neither the professional activities of the Contracting Officer, nor the presence of the Contracting Officer or his or her employees and subconsultants at a construction site, shall relieve the Contractor and any other entity of their obligations, duties and responsibilities including, but not limited to, construction means, methods, sequence, techniques or procedures necessary for performing, superintending or coordinating all portions of the work of construction in accordance with the contract documents and any health or safety precautions required by any regulatory agencies. The Contracting Officer and his or her personnel have no authority to exercise any control over any construction contractor or other entity or their employees in connection with their work or any health or safety precautions. The Contractor is solely responsible for jobsite safety.

The Contracting Officer and the Contracting Officer’s consultants shall be indemnified and shall be made additional insureds under the Contractor’s general liability insurance policy.

3.2 GENERAL INSTALLATION REQUIREMENTS

A. Installation of all conduit and cabling shall comply with Sections 27 05 43.1, 26 05 33.1 and 26 05 13.1. Additional conduit requirements described within this Division shall be supplemental to the requirement described in Section 26 05 33.1. Should conflicts exist between the two Divisions the more stringent (more expensive material and labor) condition shall prevail until bidding addendum or construction clarification or RFI can be submitted and responded to. In no case shall the Contractor carry the least stringent condition in the pricing.

B. The Contractor shall be responsible for identifying and reporting to the Contracting Officer any existing conditions including but not limited to damage to walls, flooring, ceiling and furnishings prior to start of work. All damage to interior spaces caused by this Contractor shall be repaired at this Contractor’s expense to pre-existing conditions, including final colors and finishes.

C. All cables and devices installed in damp or wet locations, including any underground or underslab location, shall be listed as suitable for use in such environments. Follow manufacturer’s recommended installation practices for installing cables and devices in damp or wet locations. Any cable or device that fails as a result of being installed in a damp or wet location shall be replaced at the Contractor’s expense.

JNEM - 199869 27 05 00.1 - 14

3.3 FIELD QUALITY CONTROL

A. General:

1. Refer to specific Division 27 sections for further requirements.

2. The Contractor shall conduct all tests required and applicable to the work both during and after construction of the work.

3. The necessary instruments and materials required to conduct or make the tests shall be supplied by the Contractor who shall also supply competent personnel for making the tests who has been schooled in the proper testing techniques.

4. In the event the results obtained in the tests are not satisfactory, This Contractor shall make such adjustments, replacements and changes as are necessary and shall then repeat the test or tests which disclose faulty or defective work or equipment, and shall make such additional tests as the Contracting Officer or code enforcing agency deems necessary.

5. All telecommunications tests that fail, including those due to excessive cabling lengths, shall be remedied by the…