P1395 RFP for N40085-19-R-9148.pdf

PDF 779 KB Posted

Attached to
P1395 SOF MARINE RAIDER REGIMENT HQ, MCAS, CAMP LEJEUNE
Solicitation number
N40085-19-R-9148
Issued by

About this file

This federal solicitation seeks design-build construction services for a Marine Raider Regiment headquarters facility at Marine Corps Air Station Camp Lejeune in North Carolina. Key details include:

  • The project scope involves constructing 2,788 square meters of headquarters buildings, support structures, utilities, parking, roadways and site work. Structures will be single-story steel buildings with brick, metal panels and standing seam roofs.

  • Proposals are due on August 13, 2020 by 2:00 PM Eastern with award anticipated thereafter. The period of performance is 730 calendar days from notice to proceed. The total project value is estimated between $10-25 million.

  • The soliciting agency is the Naval Facilities Engineering Command. The North American Industry Classification code is 236220 and the small business size standard is $39.5 million.

  • Evaluation will be based on price and non-price factors including corporate experience, safety, and past performance. Award will be to the lowest priced technically acceptable offer.

View the file

Other files

File Type Posted
C-514.pdf PDF
CG103.pdf PDF
CE106.pdf PDF
C-513.pdf PDF
CG107.pdf PDF
CD04-20201022 GER P1395 Marine Raider Bn HQS R4 -ALZ Sealed.pdf PDF
CG108.pdf PDF
REVISION 001.pdf PDF
B-104.pdf PDF
C-507.pdf PDF
B-103.pdf PDF
B-102.pdf PDF
CE103.pdf PDF
B-101.pdf PDF
C-515.pdf PDF
CE102.pdf PDF
AMENDMAENT 0004 FOR P1395.pdf PDF
01 30 01.00 22.pdf PDF
P1395 08052020 Arch Revisions.pdf PDF
20_0622_P1395_Marine-Raider_HQ_FInal_Interior_Sheets.pdf PDF
P-1395-E-Revision 1_2020-08-05.pdf PDF
P1395 AMENDMENT 0003.pdf PDF
P1395 MARINE RAIDER FF-E Est Cost Summary_FINAL_20_0810.pdf PDF
09 69 13.pdf PDF
Part 1-P1395 BVD Request for Pricing Bid Form Spreadsheet.pdf PDF
UPDATED P1395 BID SCHEDULE.pdf PDF
P1395 PPI LOG 03.pdf PDF
AMENDMENT 0002 FOR P1395.pdf PDF
PPI LOG 02 Document..pdf PDF
P1395 SOF PPIs LOG 01.pdf PDF
10 51 00.pdf PDF
13 42 75.pdf PDF
AMENDMENT 0001 P1395.pdf PDF
1603164spc01of01.pdf PDF
Attachment E - Past Performance Questionnaire.docx DOCX document
Attachment F - Small Business Subcontracting Plan.docx DOCX document
1603164dwg01of03.pdf PDF
ATTACHMENT G P1395 PRICE PROPOSAL FORM.pdf PDF
1603164dwg03of03.pdf PDF
Attachment B - Construction Experience Project Data Sheet.docx DOCX document
Attachment D - Small Business Participation and Commitment Strategy.docx DOCX document
1603164dwg02of03.pdf PDF
Attachment A - Pre-Proposal Inquiries Form.xlsx XLSX spreadsheet
Attachment C - Small Business Subcontracting Record.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NO. N40085-19-R-9148 DESIGN-BID-BUILD (DBB) P1395 SOF MARINE RAIDER REGIMENT HQ, MARINE CORPS AIR STATION, CAMP LEJEUNE, NC

PROPOSALS ARE DUE ON THURSDAY, 13 AUGUST 2020, AT 2:00 EDT. REFER TO SECTION 00 10 00 FOR PROPOSAL DELIVERY INFORMATION.

PRE-PROPOSAL INQUIRIES (PPI) CUT-OFF IS 10 DAYS PRIOR TO PROPOSAL DUE DATE, AT 5:00 PM EDT. ALL PPIs SHALL BE SUBMITTED TO

GEORGIA SCOTT VIA EMAIL AT GEORGIA.SCOTT@NAVY.MIL

MAGNITUDE OF CONSTRUCTION FOR THIS PROJECT IS BETWEEN $10,000,000 AND $25,000,000 IN ACCORDANCE WITH DFARS 236.204.

NAICS CODE IS 236220 – Commercial and Institutional Building Construction, AND THE SMALL BUSINESS SIZE STANDARD IS $39,500,000.

THIS ACQUISITION IS BEING SOLICITED ON AN UNRESTRICTED BASIS WITH FULL AND OPEN COMPETITION.

WAGE DETERMINATION GENERAL DECISION NUMBER: NC20200038 01/03/2020

GEORGIA A. SCOTT 757-322-8277

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

14-Jul-2020

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

X

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______15 calendar days and complete it w ithin ________730 calendar days after receiving aw ard, notice to proceed. This performance period is X mandatory, negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________12 Aug 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

NAVFAC MID ATLANTIC

ACQUISITION CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

N4008519R9148 45

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section 00 00 00 - Procurement and Contracting Requirements

WAGE DETERMINATION

"General Decision Number: NC20200038 01/03/2020

Superseded General Decision Number: NC20190038

State: North Carolina

Construction Type: Building

County: Onslow County in North Carolina.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.

If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate, if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/03/2020

IRON0848-005 02/01/2018

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 25.00 13.50

* PLUM0421-003 07/01/2018

Rates Fringes

PIPEFITTER.......................$ 28.00 12.01

SUNC2011-019 08/24/2011

Rates Fringes

BRICKLAYER.......................$ 19.00 0.00

CARPENTER (Drywall Hanging Only)............................$ 13.83 0.00

CARPENTER (Form Work Only).......$ 13.38 1.80

CARPENTER, Excludes Drywall Hanging, and Form Work...........$ 16.39 4.26

CEMENT MASON/CONCRETE FINISHER...$ 15.80 0.00

ELECTRICIAN......................$ 20.64 6.68

HVAC MECHANIC (HVAC Duct Installation Only)...............$ 17.37 1.82

LABORER: Common or General......$ 11.13 0.32

LABORER: Landscape & Irrigation.......................$ 9.13 0.28

LABORER: Pipelayer..............$ 13.35 2.80

LABORER: Mason Tender-Brick/Cement/Concrete.....$ 12.00 0.00

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 18.47 2.41

OPERATOR: Bulldozer.............$ 16.00 1.87

OPERATOR: Crane.................$ 19.77 4.48

OPERATOR: Forklift..............$ 13.86 0.00

OPERATOR: Grader/Blade..........$ 15.72 1.49

OPERATOR: Loader................$ 16.17 0.25

PAINTER: Brush, Roller and Spray............................$ 12.35 0.00

PLUMBER..........................$ 18.48 3.93

ROOFER...........................$ 11.75 1.06

SHEET METAL WORKER, Excludes HVAC Duct Installation...........$ 15.81 1.40

TRUCK DRIVER.....................$ 13.38 1.48

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

Section 00 10 00 - Solicitation

INSTRUCTIONS TO OFFEORS

INSTRUCTIONS TO OFFERORS

1. GENERAL

1.1 GENERAL OVERVIEW OF PROCUREMENT PROCESS

1.2 GENERAL OVERVIEW OF CONTRACT

2. BASIS FOR AWARD

3. EVALUATION FACTORS FOR AWARD

4. PROPOSAL REQUIREMENTS

4.1 PRE-PROPOSAL CONFERENCE AND SITE VISIT

4.2 PROPOSAL SUBMISSION INSTRUCTIONS

4.3 PRE-PROPOSAL INQUIRIES (PPIs)

4.4 BETA.SAM.GOV (BETASAM)

5. INCORPORATION OF TECHNICAL PROPOSAL

6. ATTACHMENTS: LOCATED ON BETA SAM

5.1 ATTACHMENT A - PRE-PROPOSAL INQUIRY LOG

5.2 ATTACHMENT B - CONSTRUCTION EXPERIENCE AND PROJECT DATA SHEET

5.3 ATTACHMENT C – SMALL BUSINESS SUBCONTRACTING RECORD

5.4 ATTACHMENT D - SMALL BUSINESS PART. AND COMMITMENT STRATEGY

5.5 ATTACHMENT E - PAST PERFORMANCE QUESTIONAIRE

5.6 ATTACHMENT F – SMALL BUSINESS SUBCONTRACTING PLAN TEMPLATE

5.7 ATTACHMENT G – PRICE PROPOSAL FORM

1. GENERAL OVERVIEW OF PROCUREMENT PROCESS

1.1.1 This solicitation is being issued as Unrestricted Full and Open Competition.

1.1.2 The NAICS code for this procurement is 236220 and the size standard is $39,500,000

1.1.3 This acquisition will be advertised utilizing FAR Part 36, Design Bid Build Source Selection Procedures and 15 – Contracting by Negotiations resulting in a Firm Fixed Price (FFP) contract for construction services.

1.1.4 Magnitude of Construction: Between $10,000,000 and $25,000,000.

1.2 GENERAL OVERVIEW OF CONTRACT

This work constructs 2,788 SM (30,000 SF) of Headquarters Facilities and includes miscellaneous supporting structures, utilities, parking, roadways, sidewalks, running trails, and site work. The structures will be single-story steel frame buildings with brick veneer over metal studs, standing seam metal roofs, metal soffits, and translucent wall panels. Special construction features include soil surcharge loads, and storm water best management practices. Electrical systems include primary power distribution, lighting, energy monitoring/control systems, intrusion detection system, telephone/data switch/server rooms, electrical switch gear, transformers, circuits, and fire alarms. Mechanical systems include plumbing, fire protection, compressed air, dehumidification, air conditioning systems, and digital controls. Information systems include telephone, data, local area network, mass notification and intercom. Site work will include building utility systems, traffic control, parking, domestic water, fire protection water, sanitary sewer, sewage conveyance, propane gas networks, perimeter security fencing, gates, storm water management, fiber/copper communications, cable television, and area lighting. Department of Defense principles for high performance and sustainable building requirements will be included in the design and construction of the project in accordance with federal laws and Executive Orders. Low Impact Development features will be included in the design and construction of this project as appropriate. This project will provide Anti- Terrorism/Force Protection (AT/FP) features to comply with Department of Defense (DoD) Minimum Anti-Terrorism Standards for Buildings and MCO 5530.14A Marine Corps Physical Security. This project includes Geospatial Data Surveying/Mapping.

A. BASIS FOR AWARD

1. The Government reserves the right to eliminate from consideration for award any or all offers at any time prior to award of the contract to negotiate with offerors in the competitive range; and to award the contract to the offeror submitting the lowest priced, technically acceptable offer.

2. As stated in the solicitation, the Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

3. The LPTA process is selected as appropriate for this acquisition because the best value is expected to result from selection of the technically acceptable proposal with the lowest evaluated price.

4. In order to permit efficient competition, the Navy will utilize the following methodology. Proposals will initially be screened for price and placed in order (lowest price to highest price). The Navy will then evaluate the technical factors of the lowest priced proposal. In the event the proposal is deemed Unacceptable, the process described will be conducted again as many times as necessary, until such time as the Government identifies a technical acceptable proposal. The Navy will make award to the lowest priced technically acceptable proposal from among the lowest priced proposals. However, the Navy, at its sole discretion, reserves the right to increase the number of proposals it will review under this methodology. Accordingly, under this methodology, the technical factors of some proposals may not be evaluated by the Navy. If discussions are deemed necessary by the Contracting Officer, all proposals will be evaluated (both technical and price) for the purpose of establishing a competitive range.

5. An overall non-price factors rating must be at least

“ACCEPTABLE” in order to be eligible for award. An “UNACCEPTABLE” rating in any factor results in the overall non-price factors proposal being rated “UNACCEPTABLE” unless corrected through discussions, if held. An overall non-price factors rating of “UNACCEPTABLE” makes a proposal ineligible for award.

B. EVALUATION FACTORS FOR AWARD

1. The solicitation requires the evaluation of price and the following non-price factors:

Factor 1 – Corporate Experience

Factor 2 – Safety

Factor 3 – Past Performance

The distinction between Corporate Experience and Past

Performance is Corporate Experience pertains to the types of work and volume of work completed by a contractor that are comparable to the types of work covered by this requirement, in terms of size, scope, and complexity. Past Performance pertains to both the relevance of recent efforts and how well a contractor has performed on the contracts.

2. Basis of Evaluation and Submittal Requirements for Each Factor.

(a) Price:

(1) Solicitation Submittal Requirements:

Price Binder: Price shall be submitted on the Price Proposal Form included in the solicitation. The offeror shall submit one (1) original electronically, marked “Original” in accordance with the directions and submission requirements detailed in the solicitation or subsequent amendments. Additionally, the offeror shall submit one (1) hard copy Original, marked “Original”; one (1) CD-ROM; and one (1) hard copy, marked “Copy”, in accordance with the directions and submission requirements detailed in the solicitation or subsequent amendments. All hard copies shall be in separate 3-ring binders. All submissions shall including the following:

Cover page with solicitation number, solicitation title, offeror name, address, phone number, fax number, DUNS, cage code, point of contact (POC), POC phone number, and POC email address;

Completed SF 1442 signed with all amendments acknowledged;

Price Proposal Form;

Copy of Representation and Certifications and proof of registration in System for Award Management (SAM);

Confirmation of filing of Veterans' Employment and Training

(VETS) VETS-4212 for the 2017 filing cycle.

Bid Guarantee in accordance with FAR Clause 52.228-1, Bid

Guarantee. Amount shall be at least 20 percent of the proposed price, but shall not to exceed $3 million;

Responsibility Determination information (see below) Small Business Subcontracting Plan (see below)

The offeror is required to submit a complete Price Proposal Form that includes completion of all contract line item numbers (CLINs). Failure to complete all CLINs may result in the proposal being rejected or otherwise not considered.

In the event of a discrepancy between the original and copies, the original electronic copy marked “original” of the proposal will govern. Furthermore, any price information within the technical proposal (non-price proposal) will not be considered. Likewise, any technical/non-price information within the price proposal will not be considered.

ADDITIONAL INFORMATION TO BE SUBMITTED WITH PRICE PROPOSAL

PACKAGE:

RESPONSIBILITY DETERMINATION INFORMATION – In order to be eligible for award, the offeror must be determined responsible in accordance with FAR Part 9, specifically 9.104-1, General Standards. In a separate tab, the offeror shall provide the following information in the price proposal package:

1. One (1) signed bank reference demonstrating adequate financial resources. If offeror’s firm has a line of credit – provide information on how many figures offeror can borrow against the line of credit (i.e. medium 6 figures – exact line of credit is not required).

2. The offeror shall provide the latest three complete fiscal year financial statements for the prime contractor, certified by an independent accounting firm, if practicable, or signed by an authorized officer of the organization. Submit evidence of availability of working/operating capital, which will be used for the performance of the resultant contract. For Joint Venture arrangements, submit the latest three complete fiscal year financial statements for each company in the Joint Venture and discuss the financial responsibilities among the companies. The Government may also utilize Dun & Bradstreet reports to evaluate the financial capacity of the offeror.

3. Description of offeror’s facilities and equipment.

4. Other offeror’s work presently under contract.

Although required to be submitted with offeror’s price proposal, this information will not be evaluated as part of the price proposal. This information forms the basis of your firm’s responsibility determination should your firm be considered for award. Proposal packages from unsuccessful offerors will not be returned to the offeror, but shall be destroyed by the Contracting Officer. No certificate of destruction will be issued.

SMALL BUSINESS SUBCONTRACTING PLAN INFORMATION – reference FAR 52.219-9 Alt II and DFARS 252.219-7003).

NAVFAC’s command-wide small business subcontracting targets are shown below. These may be higher or lower than percentages that would represent realistic, challenging small business subcontracting goals for this acquisition. Offerors representing as other than small businesses shall establish small business subcontracting plan goals and shall document in their subcontracting plans the basis for all proposed goals. Plans shall be submitted with initial offers.

SB 40%

SDB 5%

HUBZone SB 3%

WOSB 9%

SBVOSB 3%

Small businesses identified by name shall be listed in small business subcontracting plans submitted pursuant to FAR 52.219-9 in order to facilitate compliance with 252.219-7003(e).

See the Small Business Subcontracting Plan Template (Attachment F) for format.

(2) Basis of Evaluation: The Government will evaluate price based on the total price. Total price consists of the basic requirements and all option items (see Section B of the solicitation). The Government intends to evaluate all options and has included the provision FAR 52.217-5, Evaluation of Options (JUL 1990) in Section 00700 of the solicitation. In accordance with FAR 52.217-5, Evaluation of Options will not obligate the Government to exercise the option(s). Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:

(i) Comparison of proposed prices received in response to the RFP.

(ii) Comparison of proposed prices with the IGCE.

(iii) Comparison of proposed prices with available historical information.

(iv) Comparison of market survey results.

(b) Technical Factors:

Non-price binder: The offeror shall submit one (1) original electronically, marked

“Original” in accordance with the directions and submission requirements detailed in the solicitation or subsequent amendments. Additionally, the offeror shall submit one (1) hard copy Original, marked “Original”; one (1) CD-ROM; in accordance with the directions and submission requirements detailed in the solicitation or subsequent amendments. All hard copies shall be in separate 3-ring binders. All submissions shall including the following:

Cover page with Solicitation Number, Solicitation Title, Prime Contractor

Name, Address, Phone Number, Fax Number, DUNS, Cage Code, Point of Contact, Phone Number, and Email Address;

8 ½ x 11 paper, 12-point font;

Refer to individual factors for page limitations. Pages that exceed indicated page limitations shall not be evaluated;

Additionally, include an electronic version of the price and non-price proposals on one CD-ROM.

In the event of a discrepancy between the original and copies, the original electronic copy marked “original” of the proposal will govern. Furthermore, any price information within the technical proposal (non-price proposal) will not be considered. Likewise, any technical/non-price information within the price proposal will not be considered.

(b) Non-cost/price Factors:

Factor 1 – Corporate Experience:

(i) Solicitation Submittal Requirements:

The offeror shall submit the following information:

Submit a minimum of two (2) up to a maximum of five (5) relevant construction projects that best demonstrates experience as a prime contractor on relevant projects that are similar in size, scope and complexity to the RFP. For the purposes of this evaluation, a relevant project is further defined as:

Size: A single building with a cumulative square footage of 25,000 SF or greater and a final construction cost of $15,000,000 or greater.

Scope: New construction projects of either a headquarters or administrative building. Either building type must demonstrate experience with associated parking and road construction.

Renovations or additions will not be considered.

Complexity: Projects demonstrating construction experience of complex network security and intrusion detection.

Projects submitted for the offeror shall be completed within the past seven (7) years of the date of issuance of this RFP. Projects must clearly state the construction completion date or may be considered Not Relevant. Also, projects completed outside of this window will be considered “Not Relevant.”

Ensure that the project description clearly identifies whether the project is new construction or repair/renovation, addresses how the project meets the size, scope, and complexity requirements as delineated above, and provides the final construction cost.

A project is defined as a construction project performed under a single task order or contract.

For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project; rather offerors shall submit the work performed under a task order as a project. Projects which are not complete as of the date of issuance of this RFP shall not be considered by the SSEB.

The attached Construction Experience Project Data Sheet (Attachment B) is MANDATORY and SHALL be used to submit project information. Except as specifically requested, the Government will not consider information submitted in addition to this form nor will the Government consider information submitted via any other medium. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed one (1) double-sided page (or two (2) single-sided pages). The Government will not consider information beyond this page limit.

For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP (i.e., unique features, area, construction methods). Projects that are not sufficiently described so as to clearly demonstrate compliance with the above Size, Scope, and Complexity requirements may be deemed Not Relevant.

If the offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, relevant projects may be submitted for the Joint Venture members. Offerors who fail to submit relevant experience for all Joint Venture members may be rated lower. Offerors are still limited to a total of five (5) projects combined.

If an offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement in the performance of the contract.

Experience of proposed subcontractors will not be considered. Likewise, the Government will not consider the offeror’s experience as a subcontractor.

(ii) Basis of Evaluation:

The basis of evaluation will include the offeror’s demonstrated experience and depth of experience in performing relevant construction as defined above in the solicitation submittal requirements. The assessment of the offeror’s relevant experience will be used as a means of evaluating the capability of the offeror to successfully meet the requirements of the RFP. The Government will only review five (5) projects total. Any projects submitted in excess of the first five (5) will not be considered. An offeror that does not submit a minimum of two (2) relevant projects as defined above will receive a rating of “Unacceptable” and will not be eligible for award unless corrected through discussions, if held.

Factor 2 – Safety

The offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each contractor who is part of the partnership or joint venture; however, only one safety narrative is required. EMR, DART and TRC Rates shall not be submitted for subcontractors.)

Experience Modification Rate (EMR): Include three previous complete calendar years’ (2017, 2018, 2019) worth of data. This rate compares company’s annual losses in insurance claims against its policy premiums. The offeror may submit an insurance company-provided equivalent rate if no EMR exists. If the offeror has no EMR or premium, for any year, the offeror must affirmatively state so and explain why. Any extenuating circumstances that affect the EMR and negative trends must be addressed as part of the factor submission.

OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate: Submit three previous complete calendar years’ (2017, 2018, 2019) worth of data. If an offeror cannot submit an OSHA DART, for any year, the offeror must affirmatively state so and an explanation must be provided. Any extenuating circumstances that affected the OSHA and DART data negatively must be addressed as part of this factor submission.

Total Recordable Case (TRC) Rate: Submit three previous complete calendar years’ (2017, 2018, 2019) worth of data. If an offeror cannot submit TRC rates, for any year, the offeror must affirmatively state so and an explanation must be provided. Any extenuating circumstances that affected the TRC rate data negatively must be addressed as part of this factor submission.

Technical Approach for Safety: The technical approach to safety narrative shall be limited to one (1) double-sided page (or two (2) single-sided pages), and must address all items below.

The offeror shall describe the plan for safety that will be implemented to evaluate safety performance of potential subcontractors as part of the selection process for all levels of subcontractors.

The offeror shall fully describe the safety management system that they will use to oversee the safety compliance and performance of self-performed and subcontractor performed work.

The offeror shall describe any innovative methods that will be employed to ensure and monitor safe work practices at self-performed and/or all subcontractor levels.

The offeror shall describe their methodology to execute an effective program that facilitates sound mishap prevention techniques and processes, employee reporting of unsafe conditions, unsafe activities, and near-miss mishaps.

(ii) Basis of Evaluation: The evaluation will collectively consider the following:

Experience Modification Rate (EMR) OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Total Recordable Case (TRC) Rates Offeror Technical Approach to Safety Other sources of information available to the Government

Experience Modification Rate (EMR): For the three previous complete calendar years (2017, 2018, 2019), the offeror will submit EMR. If no EMR exists, the offeror may submit an insurance company-provided equivalent rate explaining why not. If an insurance company-provided equivalent rate is provided, it will be treated the same as an EMR. Any extenuating circumstances that affected the EMR and negative trends should be addressed as part of this selection factor. The board will evaluate the EMR to determine if the offeror has demonstrated a history of safe work practices taking into account any negative trends and extenuating circumstances that impact the rating.

OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rates: For the three previous complete calendar years (2017, 2018, 2019), the offeror will submit their OSHA DART, as defined by the U.S. Department of Labor, Occupational Safety and Health Administration. If unable to submit OSHA DART rates, the offeror must affirmatively state so, and an explanation must be provided. Any extenuating circumstances that affected the OSHA DART data and negative trends should be addressed as part of this element. The board will evaluate the OSHA DART rates to determine if the offeror has demonstrated a history of safe work practices taking into account any upward trends and extenuating circumstances that impact rates.

Total Recordable Case (TRC) Rates: For the three previous complete calendar years (2017, 2018, 2019), the offeror will submit their TRC, as defined by the U.S. Department of Labor, Occupational Safety and Health Administration. If unable to submit TRC rates, the offeror must affirmatively state so, and an explanation must be provided. Any extenuating circumstances that affected the TRC rate data and negative trends should be addressed as part of this element. The board will evaluate the TRC rates to determine if the Offeror has demonstrated a history of safe work practices taking into account any upward trends and extenuating circumstances that impact rates.

Technical Approach to Safety: The offeror will describe their plan to evaluate their safety performance and that of potential subcontractors. Also, describe any innovative methods that the Offeror will employ to ensure and monitor safe work practices at all subcontractor levels. The Safety Narrative shall be limited to two pages. The Government will not consider information beyond this page limit. The board will evaluate the narrative to determine the degree to which subcontractor safety performance will be considered in the selection of all levels of subcontractors on the upcoming project. The board will evaluate the narrative to determine the degree to which innovations are being proposed that may enhance safety on this procurement and validate the contractor has addressed methodology to be used in the execution of an effective program that facilitates sound mishap prevention techniques/processes, employee reporting of unsafe conditions, unsafe activities, and near-miss mishaps. Those offerors whose plan demonstrates a commitment to hire subcontractors with a culture of safety and who propose innovative methods to enhance a safe working environment may be given greater weight in the evaluation.

Other Sources of Information Available to the Government: Other sources for safety may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS) in Enterprise Safety Applications Management System (ESAMS), Contractor Performance Assessment Reporting System (CPARS) and other related databases.

Factor 3, Past Performance:

FOR EACH PROJECT SUBMITTED WITH ITS PROPOSAL FOR FACTOR 1 –

CORPORATE EXPERIENCE, IF A COMPLETED CPARS EVALUATION IS AVAILABLE;

IT SHALL BE SUBMITTED WITH THE PROPOSAL. IF THERE IS NOT A COMPLETED

CPARS EVALUATION, the Past Performance Questionnaire (PPQ) included in the solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 1 – Corporate Experience. AN OFFEROR SHALL NOT

SUBMIT A PPQ WHEN A COMPLETED CPARS IS AVAILABLE.

IF A CPARS EVALUATION IS NOT AVAILABLE, ensure correct phone numbers and email addresses are provided for the client point of contact. Completed PPQs should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror must complete and submit with the proposal the first page of the PPQ (Attachment E), which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Georgia Scott via email at georgia.scott@navy.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs or CPARS previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.

In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/Entity Identifier numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), and any other known sources not provided by the offeror.

While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the offeror. It is the responsibility of the offeror to provide accurate points of contact for each identified contract and current telephone numbers and/or email addresses.

The Government reserves the right to contact references for verification or additional information. The Government’s inability to contact any of the offeror’s references or the references’ unwillingness to provide the information requested may affect the Government’s evaluation of this factor.

Offerors are strongly encouraged to provide any information on problems encountered and the corrective actions taken on projects submitted under Factor 1 – Corporate Experience. Offerors are also strongly encouraged to address any adverse past performance issues. Such explanations shall not exceed two (2) double-sided pages (or four (4) single-sided pages) in total.

Performance award or additional information submitted will not be considered.

(ii) Basis of Evaluation:

This evaluation focuses on how well the offeror performed on the relevant projects submitted under Factor 1 – Corporate Experience and past performance on other relevant projects currently documented in known sources.

The degree to which past performance evaluations and all other past performance information reviewed by the Government (e.g., PPIRS, Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), performance recognition documents, and information obtained from any other source) reflect a trend of satisfactory performance including, but not limited to:

- A pattern of successful completion of tasks;

- A pattern of deliverables that are timely and of good quality;

and

- A pattern of cooperativeness and teamwork with the Government at all levels (task managers, contracting officers, auditors, etc.); and

- Recency of tasks performed that are identical to, similar to, or related to the task at hand

- A respect for stewardship of Government funds

N4008519R9148

The Government will consider the currency and relevance of the information, the source of the information, context of the data, and general trends in the Contractor’s performance. This evaluation is separate and distinct from the Contracting Officer’s responsibility determination. The assessment of the offeror’s past performance will be used as a means of evaluating the offeror’s probability to successfully meet the requirements of the RFP.

4. PROPOSAL REQUIREMENTS

4.1. PRE-PROPOSAL CONFERENCE AND SITE VISIT: There will be NO Site Visit or Pre-Proposal Conference for this solicitation.

4.2. In response to this request for proposal, the complete proposal shall include the Price Proposal and the Non-Price Factors Proposal, submitted in accordance with the above Basis of Evaluation and Submittal Requirements for Each Factor and as follows:

i. The Price Proposal and the Non-Price Proposal shall be submitted in separate 3-ring binders. All pages shall be numbered and binders shall be appropriately tabbed, conforming to the proposal submittal requirements’ structure for each evaluation factor. Price and Non-Price Proposals must be submitted in sealed envelopes/boxes. Any pricing information included in the Non-Cost/Price Proposal will not be considered. Similarly, any Non- Price information included in the Price Proposal will not be considered. Proposals shall be labeled

“PRICE PROPOSAL OR NON-COST/PRICE PROPOSAL FOR RFP N40085-19-R-9148,

ATTN: GEORGIA SCOTT ; DO NOT OPEN IN MAIL ROOM”.

“Proposal Due Date:

Electronic Copy due: Thursday, August 13, 2020 2:00 p.m. Eastern Time Hard Copy due: Thursday, August 20, 2020 12:00 p.m. Eastern Time

LATE PROPOSALS WILL NOT BE CONSIDERED.

Electronic Proposal Delivery Information via DOD Safe Site:

Contractors shall send their Electronic Proposal submission to Georgia Scott through the DOD Safe Site (safe.apps.mil). Only DoD SAFE is authorized for the submission of the electronic original proposal in response to this solicitation. Further guidance is provided below for submission of hard copy submissions.

The contractor shall send the contract specialist, Georgia Scott at Georgia,scott@navy.mil, the email address of the offeror’s point of contact who will be receiving the Drop-Off invitation to upload proposals to the DOD Safe Site no later than August 10, 2020 by 1400, unless that date and time are changed via Solicitation Amendment.

The Contract Specialist, Georgia Scott, will “Request a Drop-Off” through DoD SAFE utilizing the provided offeror’s point of contact email address. The recipient will receive an automated email containing the information for the request and instructions for uploading. Requests from DoD SAFE will be sent on Wednesday, August 12, 2020. If you do not receive an email containing drop off instructions on that date, please contact the Contract Specialist. Only the identified POC will be able to drop-off proposals or proposal revisions in DOD SAFE. Failure to provide accurate POC information will preclude the offeror from using DoD SAFE. Note: only two email addresses may be provided per Offeror.

To submit the proposal, the offeror will utilize the link provided in the automated email to take you to DoD SAFE at https://safe.apps.mil. The system will allow for inclusion of a short note to the Recipient and then the offeror will click to add files or drag and drop them. Click “Drop-Off Files” to send the files to the recipient. You should receive a notification on the site “Drop-Off Completed” “Your files have been sent successfully.” Please keep this for your records. The file(s) are uploaded and an email will be sent to the recipient notifying them of the “drop-off”.

[Additional details can be viewed in the DoD SAFE User Guide available at https://safe.apps.mil]. Note that the submission of any proposal must be completed no later than the due date and time, unless the date and time are changed via Solicitation Amendment, using the link sent by the contract specialist via DOD Safe. The DoD SAFE system will record the date and time of package submittal. The date and time of package submittal recorded in DoD SAFE shall govern the timeliness of any proposal submission.

Offerors shall allow adequate time to upload files which may be slower for non-DoD users and to avoid other technical difficulties that may be encountered. Offerors are also responsible for submitting files in the format specified and consistent with requirements stated elsewhere in this solicitation. Files that cannot be opened, or are otherwise missing the required content are the responsibility of offerors. The maximum file size of a package is 8 GB. Up to 25 packages may be uploaded per link.

It is the sole responsibility of the Offeror to obtain the RFP files, along with any amendments, from Opportunities (www.beta.sam.gov).

Mailed Hard Copies In addition, one (1) original and one (1) copy of the hard copy proposal shall be delivered by mail on the date and time listed below, respectively, unless those dates are changed via Solicitation Amendment.

Proposal shall be labeled “PRICE PROPOSAL OR NON-COST/PRICE FACTORS

PROPOSAL FOR RFP N4008519R9148, ATTN: GEORGIA SCOTT; DO NOT OPEN IN

MAIL ROOM”.

Hand delivered proposals will not be accepted.

Express Mail to:

Naval Facilities Engineering Command, Mid-Atlantic 9324 Virginia Avenue

Building Z-140, Room 225 Norfolk, Virginia 23511 Attn:Georgia Scott, AQ

4.3. PRE-PROPOSAL INQUIRIES (PPIs): All inquiries must be submitted in writing and received by the Contract Specialist by 10 calendars days prior to proposal due date in order to permit adequate time to reply to the inquiry. There is no guarantee that PPI’s submitted after the cut-off date will be answered before the solicitation closes. Submit all questions to georgia.scott@navy.mil. Use of the PPI Log template is REQUIRED. The PPI Log Template (Attachment A) can be found on the BETASAM website under the Additional Documents section.

4.4. Amendments will be posted directly to beta.sam.gov. The drawings and specifications will be posted on beta.sam.gov under the Additional Documents section of this RFP. Additionally, other postings will be made to beta.sam.gov, such as the pre-proposal inquires (PPI) log, revised drawings, etc., under the Additional Documents section of the RFP.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .