ATTACHMENT G P1395 PRICE PROPOSAL FORM.pdf
PDF 401 KB Posted
- Solicitation number
- N40085-19-R-9148
About this file
This document contains a price proposal form and details for a federal construction contract solicitation. The solicitation is for the construction of Marine Raider Regiment headquarters facilities at Marine Corps Air Station Camp Lejeune, including buildings, utilities, parking, and site work. The base bid includes all work up to five feet outside buildings. Optional line items include designing and providing furniture, fixtures and equipment and audiovisual packages, and procuring and installing those items. Pricing must be provided for the base work and each optional line item. The completion period is 730 calendar days from award. Award will be made to the lowest priced responsive bidder meeting all requirements.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P1395 Bid Schedule
CLINS Description:
0001 BASE BID
FFP
0001 Price includes the following:
0001A Price for the entire work, complete to the 5 foot line outside the building, in accordance with the drawings and specifications, but excluding work described in Contract Line Item (CLIN)0001B, 0002, 0003, 0004, and 0005.
Total Price for Item 0001A: $__________________________
0001B Price for the entire project Work Site, outside the 5 foot line, complete in accordance with the drawings and specifications, but excluding work described in Contract Line Item (CLIN)0001C, 0002, 0003, 0004, and 0005.
Total Price for Item 0001B: $__________________________
OPTION ITEMS:
0002 Option Item No. 1 – Price to design and provide the final, best valued Furniture, Fixtures and Equipment (FF&E) package for the Project, complete.
Price for obtaining the services for an Interior Designer, certified by the National Council for Interior Design Qualification (NCIDQ), to prepare supporting plans and procurement data, in accordance with the design schedule. Tasks shall include but are not limited to: gathering the Activity’s project FF&E; execution of the FF&E Best Value Determination process; coordination of the building systems, and as-built conditions are identified and noted on the floor plans and construction drawings; development of Final FF&E Package to include furniture/equipment plans, procurement data sheets, cost summary, 8.5”x11” FF&E finish boards and any supplementary documentation; attend meetings with the Activity and NAVFAC MIDLANT; and perform final FF&E walk-through and punch list(s). Refer to specification section 01 30 01.00 22
DESIGN, PROCUREMENT AND INSTALLATION OF FURNITURE, FIXTURES AND
EQUIPMENT in Administrative Requirements. It is the Government’s intent to award this Option at or around time of Contract Award.
TOTAL PRICE FOR ITEM 0002: $
0003 Option Item No. 2 – Price to design and provide the final, best valued Audio/Visual (A/V) package for the Project, complete.
Price for obtaining the services for an A/V Certified Technology Specialist-Design (CTS-D), and to prepare supporting plans and procurement data, in accordance with the design schedule. Price for CTS-D tasks shall include but are not limited to: gathering the Activity’s project A/V requirements; execution of the A/V Best Value Determination process; coordination of the building systems and as-built conditions are identified and noted on the floor plans and construction drawings; development of Final A/V Package to include equipment plans, procurement data sheets, cost summary, and supplementary documentation if needed; attend meetings with the Activity and NAVFAC MIDLANT; and perform final A/V walk-through and punch list(s). Additionally, provide A/V floor plans indicating equipment locations and A/V riser diagrams for all A/V systems and coordinate equipment locations and power requirements with power plans. The Final A/V package shall be fully integrated into the design, construction, and construction schedule for the building. The A/V package shall be designed by the Contractor’s CTS-D as a separate from but coordinated with the FF&E package. The design, procurement, and installation of the A/V package shall comply with all of the same requirements as those defined for the FF&E package in specification section 01 30 01.00 22 DESIGN, PROCUREMENT AND INSTALLATION OF FURNITURE, FIXTURES AND EQUIPMENT in Administrative Requirements
TOTAL PRICE FOR ITEM 0003: $
0004 Planned Modification Item 1 - Price includes the following:
Price to procure and supervise installation, required for the Furniture, Fixtures, and Equipment (FF&E) complete in accordance with the plans and specifications and in accordance with the following schedule:
0004 GOVERNMENT FF&E HAR TOTAL
PRICE FOR
DESCRIPTION FF&E ESTIMATE (NTE 5%) 0004
0004 $ 1,817,208 ________% $_____________
Procurement, installation, including all labor, material, equipment, transportation, and supervision required for the Furniture, Fixtures, and Equipment (FF&E) and Audio/Visual (A/V).
0005 Planned Modification Item 2 - Price includes the following:
Price to procure and supervise installation, required for the Audio/Visual (A/V) complete in accordance with the plans and specifications and in accordance with the following schedule:
0005 GOVERNMENT FF&E HAR TOTAL
PRICE FOR
DESCRIPTION A/V ESTIMATE (NTE 5%) 0005
0005 $ 767,408 ________% $_____________
Procurement, installation, including all labor, material, equipment, transportation, and supervision required for the Furniture, Fixtures, and Equipment (FF&E) and Audio/Visual (A/V).
SUM OF ALL ABOVE TOTAL PRICE FOR
0001, 0002, 0003, 0004, and 0005 THIS SOLICITATION
CONTRACT LINE ITEM NOTES
General
1. Award will be made on the total sum of Item 0001, 0002, 0003, 0004 and 0005.
2. FAR 52.217-5, Evaluation of Options (Jul 1990) - Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interest, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
3. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.
4. The Government is not obligated to award the FF&E and A/V line items. Should the Government choose to award the FF&E and A/V, the line items will be awarded as a negotiated modification to the contract/task order. The contractor's proposed HAR will be applied to all vendor/supplier costs for the FF&E and A/V. The FF&E and A/V modifications shall be awarded at least six months prior to the contract completion date. A minimum of six months is required for the contractor to purchase, deliver and install the FF&E and A/V without impacting the overall completion date of the project. The contractor’s schedule should assume the award of the FF&E and A/V as a modification. No schedule extensions shall be granted if the modification is awarded at least six months prior to the contract completion date. If the Government decides to negotiate and award the furniture modification with less than six months prior to the contract completion date, the contractor may be entitled to a contract extension and extended field overhead. A contract extension and extended field overhead will only be granted in those cases where the prime contractor demonstrates that accepted Final FF&E and A/V packages were submitted within the approved schedule deadlines and sufficient lead time for the FF&E and A/V is not available and the Government’s award of the modification is in the last six months of the contract.
5. If Item 0002, and 0003 are exercised, additional bonding and consent of surety will be required. Consequently, the Performance and Payment Bond shall reflect 100 percent of the aggregate amount of all items.
6. The Government reserves the unilateral right to award the Option(s) to the Contractor at the negotiated price within 120 Calendar Days after the Contract Award Date. A Firm Fixed proposed price is required for Items: 0001 thru 0005. No provision is made for economic price adjustment. If Options are exercised, the Contract Completion Date remains: 630 Calendar Days after award of the contract.
PLANNED MODIFICATION BID NOTES
These notes apply to Planned Modification
a. The estimated amount for FF&E and A/V have been supplied by the Government to provide offerors with the projected magnitude of effort. The estimated amount includes the actual cost of the FF&E and A/V including freight and installation charges. The Government FF&E and A/V Estimate is only an estimated amount.
b. If awarded, line items will be funded separately after completion of FF&E and A/V design package review by the Government, and receipt of appropriate funding by the Government. Requirements and details are provided in specification section 01 30 01.00 22.
DESIGN, PROCUREMENT AND INSTALLATION OF FURNITURE, FIXTURES AND
EQUIPMENT in Administrative Requirements
c. Bonding is not required for the design, procurement and installation of 0004 FF&E and 0005 A/V equipment.
d. Offerors may propose a Handling and Administration Rate (HAR) for the FF&E and A/V not to exceed 5 percent. This fee will account for all administrative costs, overhead, bonding fees, administration of subcontracts, profit, and any other costs associated with and related to the coordination and processing of the procurement and installation of FF&E and A/V. The proposed HAR percentage will be incorporated into the contract award and will not be adjusted regardless of fluctuations from the estimate amount for the FF&E and A/V. The proposed HAR is a fixed rate.
e. The Final FF&E and AV packages shall be submitted no later than 9 months prior to building completion. The Government is not obligated to award the Planned Modification line items. Should the Government choose to award the Planned Modification, the line item will be awarded as a negotiated modification to the contract/task order. The Contractor's proposed HAR will be applied to all vendor/supplier costs for the FF&E and A/V.
f. If awarded, the FF&E and A/V modifications will be awarded at least six months prior to the contract completion date. A minimum of six months is required for the Contractor to purchase, deliver and install the FF&E and A/V without impacting the overall completion date of the project. The Contractor's schedule must assume the award of the FF&E and A/V as a modification. No schedule extensions will be granted if the modification is awarded at least six months prior to the contract completion date. If the Government decides to negotiate and award the furniture modification with less than six months prior to the contact completion date, the Contractor may be entitled to a contract extension and extended field overhead. A contract extension and extended field overhead will only be granted in those cases where the Contractor demonstrates that an accepted Final FF&E and A/V packages were submitted within the approved schedule deadlines and sufficient lead time for the FF&E and A/V is not available and the Government's award of the modification is in the last six months of the contract.
g. Upon Government approval of the Best Value Determination (BVD) Analysis solicitation package, a BVD will be made and will be the rationale for selecting the FF&E and A/V vendors for the project. Accordingly, the price[s] provided by the selected vendors, using predominately negotiated price schedules from BPA, GSA or other Federal contracts, will be the basis for the actual cost of the Final FF&E and A/V Packages. The actual total cost of the awarded planned modifications will be the total of the accepted Final FF&E and A/V Package and the HAR rate applied to the accepted Final FF&E and A/V Packages. See specification section 01 30 01.00 22.
DESIGN, PROCUREMENT AND INSTALLATION OF FURNITURE, FIXTURES AND
EQUIPMENT in Administrative Requirements
COMPLETION DATE: 730 Calendar Days after contract award.
-- End of Document --