This Task Group Instruction (TGI) details a naval maintenance project for the USS Blue Ridge (LCC-19) involving the replacement of Collecting, Holding, and Transfer (CHT) discharge piping. The work involves replacing approximately 60 feet of 4-inch CHT discharge piping, transitioning from existing Cu-Ni 90-10 material to Cu-Ni 70-30 material, located in crew washroom and decontamination stations between frames 99 and 100 on the port side. The project is classified as a Class P-2 piping replacement with Level III cleanliness requirements, with a planned contractor work period from July 21, 2026 to November 21, 2027. The U.S. Fleet Forces Command (SRF-JRMC) will provide government-furnished materials and supporting services including crane rigging, utility services, and quality assurance inspections.
The material list includes multiple copper-nickel tubes, elbows, sleeves, and backing components, with specific stock numbers and quantities specified for procurement. Special requirements note potential asbestos and lead hazards during the work. The project involves detailed technical specifications, including hydrostatic testing at 60 PSIG using clean fresh water, and will be executed under Job Control Number ER01-3539. The task is intended to clear a specific Depot Facility Submission (DFS No. LCC-19-0023-2024) and involves coordination between multiple departments and personnel, including a planner from Code 234 and a Work Integration Manager from Code 333.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
21-DEC-2024 1020
20.14.15.2.9020 (September 2024) ICN: 3819P52806 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT DISCH 5-100-2-L AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - REPLACE CHT DISCHARGE PIPING IN 5-100-2-L
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 5
ER013539
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
KOMOTO, HIDEKI 234 3152430975 18-DEC-2024
APPROVED BY: CODE: PHONE: DATE:
INOMATA, YOSHIYUKI 234 3152434536 20-DEC-2024
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
ER01-3539
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
528A0006
1. SCOPE/PURPOSE:
1.1 Title: Collecting, Holding, and Transfer (CHT) Piping; replace
1.2 Location of work:
1.2.1 Crew Washroom, Shower and Decontamination Station (5-98-2-L)
1.2.2 Crew W.R. WC, SH and Decontn Station (5-100-2-L)
1.3 Identification:
1.3.1 Quantity (Approx. 60 FT), CHT Discharge Piping, runs from located in frames between 99 and 100 at port side in 1.2.1 to deck sleeve for 4TH deck in 1.2.2
Size: 4 Inch IPS (4.500 OD X 0.109 WT) Material: Cu-Ni 90-10 (Existing) / Cu-Ni 70-30 (New) Specification: MIL-T-16420
TGI Short Form
21-DEC-2024 1020
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52806 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT DISCH 5-100-2-L AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - REPLACE CHT DISCHARGE PIPING IN 5-100-2-L
FOUO Pg 2 of 5
CU PHASE DESCRIPTION (Cont.)
Remarks: See followings for location detail.
Ref. No. 3: Sheet 4 (Zone 15-D of Part Plan 5TH Deck)
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Potential Asbestos Hazard.
1.5.2 Potential Lead Hazard.
1.6 Contractor work start date: 7/21/2026
1.7 Contractor work completion date: 11/21/2027
2. PROCEDURE:
2.1 Remove existing, fabricate and install each new CHT discharge piping listed in 1.3.1, using Ref. No. 3 for guidance.
2.1.1 Accomplish the requirements of 009-09 of Ref. No. One for the certification process.
2.1.2 Accomplish the requirements of 009-12 of Ref. No. One, including Table One, Column(s) A, Lines One through 10.
2.1.3 Accomplish the requirements of 009-71 of Ref. No. One for hydrostatic test, using clean, fresh water at 60 PSIG, for each new and disturbed CHT discharge piping systems.
2.1.3.1 Document shop hydrostatic test results on QA Form 28 Enclosure-01-1.
2.2 Accomplish the requirements of 009-32 of Ref. No. One for each new and disturbed surface.
2.3 Notes:
2.3.1 Planner: Code 234 H. Komoto, 070-7787-2047
2.3.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
2.3.3 This TGI is issued to clear DFS No. LCC-19-0023-2024
2.3.4 JCN ER01-3539 is related to this TGI.
2.4 Government Furnished Material (GFM):
2.4.1 SRF-JRMC will provide GFM listed in the Material List.
2.5 SRF-JRMC will provide the following service work: (TGI No. 3819P52806S02)
2.5.1 [C740] Crane and crane rigging service.
2.5.2 [X99E] Utility service, electrical.
21-DEC-2024 1020
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52806 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT DISCH 5-100-2-L AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - REPLACE CHT DISCHARGE PIPING IN 5-100-2-L
FOUO Pg 3 of 5
CU PHASE DESCRIPTION (Cont.)
2.5.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
2.5.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.5.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.5.6 [C133] QA inspection for (G) symbol(s).
21-DEC-2024 1020
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52806 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT DISCH 5-100-2-L AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - REPLACE CHT DISCHARGE PIPING IN 5-100-2-L
FOUO Pg 4 of 5
OTHER SPECIAL REQUIREMENTS:
CLASS P-2 PIPING.
CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III.
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY25 Standard Items - ORG N 2 LI FY25 Local Standard Items - ORG N
3 DWG 528-4346220 CHT PIPING SYSTEM
SUCTION & DISCHARGE TKS
#1,2,3 & 4
C Y 4
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
N
N
N
N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
001 M TUBE,METALLIC, 4 INCH IPS,
CU-NI 70-30
ORDERED FOR: KTR
ORIG: C234 H. KOMOTO 070-
7787-2047
9B 4710 006048328 NA 4 N 60/FT
002 M TUBE,METALLIC, 4 INCH IPS,
CU-NI 70-30
ORDERED FOR: KTR
ORIG: C234 H. KOMOTO 070-
7787-2047
9B 4710 006048328 NA 4 N 60/FT
003 M TUBE,METALLIC, 4 INCH IPS,
CU-NI 70-30
ORDERED FOR: KTR
ORIG: C234 H. KOMOTO 070-
7787-2047
9B 4710 006048328 NA 4 N 60/FT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P52806 KEY OP: A01
21-DEC-2024 1020
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52806 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT DISCH 5-100-2-L AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - REPLACE CHT DISCHARGE PIPING IN 5-100-2-L
FOUO Pg 5 of 5
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
004 M ELBOW,TUBE, 4 INCH IPS, CU-
NI 70-30, 45, BW, CL200
ORDERED FOR: KTR
ORIG: C234 H. KOMOTO 070-
7787-2047
9B 4730 007254005 NA 4 N 8/EA
005 M ELBOW,PIPE, 4 INCH IPS, CU-
NI 70-30, 90, BW, CL200
ORDERED FOR: KTR
ORIG: C234 H. KOMOTO 070-
7787-2047
9B 4730 014283175 NA 4 N 8/EA
006 M SLEEVE,, 4 INCH IPS, CU-NI 70-
30, BW, CL200
ORDERED FOR: KTR
ORIG: C234 H. KOMOTO 070-
7787-2047
9C 4730 LL4462305 NA 4 N 10/EA
007 M BACKING, 4 INCH IPS, CU-NI
70-30, BW, 200 PSI
ORDERED FOR: KTR
ORIG: C234 H. KOMOTO 070-
7787-2047
9C 4730 LL4358122 NA 4 N 30/EA
ATTACHMENT LIST
TITLE FILE NAME SAVED DATE
ENCLOSURE-01 3819P52806A01-QA28.docx 18-DEC-2024 0000
COMUSFLTFORCOMINST 4790.3 REV D CHG 3
07 Nov 2023
SHOP TEST RECORD Page 1 of 1
QA FORM 28 Planning must fill in blocks identified by a prior to issuing
1. SHIP HULL NO. 2. JCN 3. LWC/SHOP 4. CWP/REC SER NO. 5. SYSTEM/COMPONENT/ROTATABLE POOL SER NO.
USS BLUE RIDGE LCC19 ER01-3539 KTR N/A CHT DISCHARGE SYSTEM PIPING
6. REFERENCES: TEST REF (E.G., MS, TECH MAN) & OTHER REFS (E.G., VLV DWG) 7. TEST GAGE RANGE /INSTRUMENT USED SERIAL NO. CAL DUE DATE 8. RELIEF VLV SET POINT
A. S9086-RK-STM-010/CH-505 Rev. 6
B. LAR-XXXXX/LCC19/12L056
C. .
D. .
9. TEST REQUIREMENTS & RESULTS
TEST TYPE KEY H = STRENGTH AND POROSITY/ELEVATED PRESSURE TEST J = MECHANICAL JOINT TIGHTNESS ST = SEAT TIGHTNESS OP = OPERATIONAL O = OTHER
(SPECIFY): ______________________
TE
ST
T Y
PE
(S
EE
K
EY
) PARAGRAPH
DESCRIBING
VALVE POSITION
AND POINT OF
ENTRY
REF
LTR
GAGE
USED
(LTR
FROM
BLK 7)
REQUIRED
MEDIUM
MEDIUM
USED
REQUIRED
PRESSURE
ACTUAL
PRESSURE
MINIMUM
DURATION
ACTUAL
DURATION
ALLOWED
LEAKAGE
ACTUAL
LEAKAGE SAT/UNSAT SIGNATURE, BADGE NO. & DATE
H 2.1.3 A, B Clean Fresh Water 60 PSIG 30 minutes None
10. REMARKS. (CRAFTSMAN/QAI SUBMIT A DF TO RESOLVE UNSAT DATA)
11. QA INSPECTOR/SHOP SUPERVISOR SIGNATURE/BADGE NO. (RECORD
REVIEWED FOR FINAL ACCEPTANCE)
DATE 12. QAS SIGNATURE/BADGE NO. (RECORD HAS BEEN REVIEWED FOR
COMPLETENESS)
DATE
3819P52806A01 ENCLOSURE-01-1 TOTAL 1