TGI_3819P52801_A01_c0v0.pdf
PDF 185 KB Posted
- Attached to
- USS BLUE RIDGE 5C1 DSRA TYCOM 5
- Solicitation number
- N6264925RA054
About this file
This Task Group Instruction (TGI) details a valve replacement project for the USS Blue Ridge. The task involves replacing a Collecting, Holding, and Transfer (CHT) Waste Cutout Valve (COV) in multiple ship locations, including the Division Officer's Office, Crew Work and Decontamination Stations, and Crew Messroom. The existing valve from Cooper Industries Inc. will be replaced with a new valve from Cunico Corporation, which meets MIL-V-24509 specification.
The project is scheduled to start on 7/21/2026 and complete by 11/21/2027, with specific technical requirements including valve cycling, remote operating gear connection, and gasket installation. SRF-JRMC will provide government-furnished material and services, including crane and utility services, safety inspections, and quality assurance. The task requires Level III cleanliness standards for piping systems and involves multiple reference documents for guidance, with a total of two material items ordered: one plug valve and one rubber sheet.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
20-DEC-2024 1111
20.14.15.2.9020 (September 2024) ICN: 3819P52801 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT WASTE CO 6-40-3 AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - REPLACE CHT WASTE COV 6-40-3 6-40-3-Q
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 6
ER01L024
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
FUDO, MASATAKA 232 3152434512 09-DEC-2024
APPROVED BY: CODE: PHONE: DATE:
KINOSHITA, TAKAHIRO 232 3152432491 12-DEC-2024
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
ER01-L024
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
528A1101
1. SCOPE/PURPOSE:
1.1 Title: Collecting, Holding, and Transfer (CHT) Waste Cutout Valve (COV), 6-40-3; replace
1.2 Location of Work:
1.2.1 Division Officer’s Office (6-40-3-Q)
1.2.2 Crew WR, WC, SH and DECONTH STA (5-40-1-L)
1.2.3 Crew Messroom (4-40-0-L)
1.3 Identification:
1.3.1 Quantity (One EA), Remote Operating Gear (ROG) for CHT Waste COV, 6-40-3
Mfr: Elliott Manufacturing Co
TGI Short Form
20-DEC-2024 1111
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52801 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT WASTE CO 6-40-3 AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - REPLACE CHT WASTE COV 6-40-3 6-40-3-Q
FOUO Pg 2 of 6
CU PHASE DESCRIPTION (Cont.)
Type: UNIFLEX
1.3.2 Quantity (One EA), Existing CHT Waste COV, 6-40-3
Mfr: Cooper Industries Inc Model: 3132166-3-1/2 Type: Plug, Straight Way, Flanged 2 Port Size: 3.50 Inch IPS
APL: 882080115
1.3.3 Quantity (One EA), New CHT Waste COV, 6-40-3
Mfr: Cunico Corporation Mfr Id: DD-1876 Specification: MIL-V-24509 Type: Plug, Straight Way, Flanged 2 Port Size: 3.50 Inch IPS
APL: 882081319
1.4 Security Classification: None.
1.5 Initial Condition: None.
1.6 Contractor work start date: 7/21/2026
1.7 Contractor work completion date: 11/21/2027
2. PROCEDURE:
2.1 Accomplish the requirements of 009-09 of Ref. No. One for CHT certification process.
2.2 Disconnect the remote operating gear listed in 1.3.1 from the existing valve listed in 1.3.2, using Ref. No. 3 for guidance.
2.2.1 Verify disconnected remote operating gear for freely operation.
2.3 Remove existing valve listed in 1.3.2, using Ref. No. 4 and Ref. No. 5 for guidance.
2.3.1 Restore each mating surface exposed by valve removal. Repair by removing each high spot, burr, abrasion, and foreign matter, where removal can be accomplished by hand tools.
2.3.2 Inspect each fastener intended for reuse for wear and defects, using Paragraph 075-8.3 of Ref. No. 6 for accept or reject criteria.
2.3.2.1 Clean each fastener free of foreign matter (including paint).
2.3.2.2 Chase and tap exposed threaded areas.
2.4 Install new valve listed in 1.3.3, using Ref. No. 4 and Ref. No. 7 for guidance.
20-DEC-2024 1111
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52801 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT WASTE CO 6-40-3 AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - REPLACE CHT WASTE COV 6-40-3 6-40-3-Q
FOUO Pg 3 of 6
CU PHASE DESCRIPTION (Cont.)
2.4.1 Install each new gasket. Gasket must conform to MIL-PRF-1149, Type II, Class 2, synthetic rubber.
2.4.2 Cycle the valve from fully closed to fully open to fully closed 4 times. Allowable binding: None.
(V) “VALVE CYCLING”
2.5 Connect the remote operating gear listed in 1.3.1 to the new valve listed in 1.3.3, using Ref. No. 3 for guidance.
2.5.1 Align each valve station actuator and valve coupling. The universal joint must be installed as straight as possible.
Maximum/Allowable operating angle is less than 15 DEG.
2.5.2 Adjust the position indicator of operating station to match the valve opening,
2.5.3 Verify the remote operating gear listed in 1.3.1 for ease of operation and proper alignment by opening and closing each valve from its remote operating station through 3 complete cycles. Allowable binding: None.
(V) “VALVE CYCLING”
2.5.3.1 Notify the Chief Test Engineer (CTE) prior to cycling the valve listed in 1.3.3 with remote operating gear.
2.6 Accomplish the requirements of 009-32 of Ref. No. One for each new and disturbed surface.
2.7 Notes:
2.7.1 Planner: Code 232 M. Fudo, 243-4512
2.7.2 Work Integration Manager (WIM): C333 T. Yaginuma, 080-5419-0598
2.7.3 This TGI is issued to clear DFS No. LCC-19-1011-2022.
2.7.4 JCN ER01-L024 is related to this TGI.
2.8 Government Furnished Material (GFM):
2.8.1 SRF-JRMC will provide GFM listed in the Material List.
2.9 SRF-JRMC will provide the following service work: (TGI No. 3819P52801S02)
2.9.1 [C740] Crane and crane rigger service.
2.9.2 [X99E] Utilities service, electrical.
2.9.3 [X99M] Utilities service, including low pressure air supply, water supply, and steam supply.
2.9.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.9.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.9.6 [C133] QA Inspection for (G) symbol(s).
20-DEC-2024 1111
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52801 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT WASTE CO 6-40-3 AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - REPLACE CHT WASTE COV 6-40-3 6-40-3-Q
FOUO Pg 4 of 6
CU PHASE DESCRIPTION (Cont.)
20-DEC-2024 1111
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52801 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT WASTE CO 6-40-3 AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - REPLACE CHT WASTE COV 6-40-3 6-40-3-Q
FOUO Pg 5 of 6
OTHER SPECIAL REQUIREMENTS:
CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N
3 DWG 6-40-3 UNIFLEX 9:1 SYSTEM, 6-40-3
4" 2W2P BALL VALVE W/1 3/4
SQ STEM, 1/4 TURN
A Y ALL
4 DWG 528-4346214 COLLECTING HOLDING &
TRANSFER SYSTEM PIPING
ARRANGEMENT FR30-52 1ST
PLATF & BELO
A Y ALL
5 DWG 3132166 ROUND PORT, NAVY STD,
FLANGED ENDS, BRONZE
PLUG VALVE OUTLINE DWG
F Y 1
6 TM S9086-CJ-STM-
010/CH-075
Fasteners 7 N
7 DWG DD-1876 3-1/2 150# CUNICO FRP-2
BODY MIL FLANGE (MIL-F-
20042)
D Y ALL
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
2.1 QA
2.2 OMCH
2.3 OMCH
2.4 OMCH
2.5 OMCH
2.6 PNTR, QA
Machinery Work CFM $ 3600 for Marine Chemist and MISC.
Process Funding Document.
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P52801 KEY OP: A01
20-DEC-2024 1111
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52801 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT WASTE CO 6-40-3 AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - REPLACE CHT WASTE COV 6-40-3 6-40-3-Q
FOUO Pg 6 of 6
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
001 M VALVE,PLUG, ORIG. C232 M.
FUDO, 243-4512
ORDERED FOR KTR
3B 4820 016709076 NA 4 N 1/EA
002 M RUBBER SHEET,SOLID, ORIG.
C232 M. FUDO, 243-4512
ORDERED FOR KTR
9B 9320 010415249 NA 4 N 1/SH