This Task Group Instruction (TGI) details a valve replacement project for the USS Blue Ridge. The task involves replacing a Collecting, Holding, and Transfer (CHT) Waste Cutout Valve (COV) in multiple ship locations, including the Division Officer's Office, Crew Work and Decontamination Stations, and Crew Messroom. The existing valve from Cooper Industries Inc. will be replaced with a new valve from Cunico Corporation, which meets MIL-V-24509 specification.

The project is scheduled to start on 7/21/2026 and complete by 11/21/2027, with specific technical requirements including valve cycling, remote operating gear connection, and gasket installation. SRF-JRMC will provide government-furnished material and services, including crane and utility services, safety inspections, and quality assurance. The task requires Level III cleanliness standards for piping systems and involves multiple reference documents for guidance, with a total of two material items ordered: one plug valve and one rubber sheet.

View the file

Other files

File Type Posted
Exhibit (A) BLR_5C1_TYCOM5 CDRL_r.pdf PDF
N6264925RA0540003.pdf PDF
N6264925RA0540002.pdf PDF
TGI_3819P59301A01_c0v0.pdf PDF
BLR_5C1_TYCOM5 CDRL.pdf PDF
TGI_3819P51418T01_c0v0.pdf PDF
TGI_3819P52802A01_c0v0.pdf PDF
TGI_3819P52801_T01_c0v0.pdf PDF
TGI_3819P51418T02_c0v0.pdf PDF
TGI_3819P51418A04_c0v0.pdf PDF
TGI_3819P123AFA01_c0v0.pdf PDF
TGI_3819P59301T01_c0v0.pdf PDF
TGI_3819P52808A01_c0v0.pdf PDF
TGI_3819P51413A01_c0v0.pdf PDF
TGI_3819P51420A01_c0v0.pdf PDF
TGI_3819P52802T01_c0v0.pdf PDF
TGI_3819P51419A01_c0v0.pdf PDF
TGI_3819P123AAA01_c0v0.pdf PDF
TGI_3819P52808T01_c0v0.pdf PDF
TGI_3819P51413T01_c0v0.pdf PDF
TGI_3819P52806A01_c0v0.pdf PDF
TGI_3819P123ADA01_c0v0.pdf PDF
TGI_3819P52806_T01_c0v0.pdf PDF
TGI_3819P14218A01_c0v0.pdf PDF
N6264925RA054 Amendment 0001.pdf PDF
Attachment VIII Source of Repair Instruction.pdf PDF
2.01 N6264925RA054 Solicitation.pdf PDF
Attachment VI Quality Assurance Surveillance Plan (QASP).pdf PDF
Attachment III GFP_List_V3 TYCOM5.xlsx XLSX spreadsheet
Attachment VII Warranty Tracking Information.pdf PDF
Attachment V Contract data.pdf PDF
Attachment II Proposal Sheet Generator v1.2.xlsx XLSX spreadsheet
Attachment IV-3 Request for Information Form (SAMPLE).docx DOCX document
Exhibit (A) CDRL BLR_5C1_TYCOM5.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

20-DEC-2024 1111

20.14.15.2.9020 (September 2024) ICN: 3819P52801 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT WASTE CO 6-40-3 AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *F/O - REPLACE CHT WASTE COV 6-40-3 6-40-3-Q

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 6

ER01L024

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

FUDO, MASATAKA 232 3152434512 09-DEC-2024

APPROVED BY: CODE: PHONE: DATE:

KINOSHITA, TAKAHIRO 232 3152432491 12-DEC-2024

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

ER01-L024

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

528A1101

1. SCOPE/PURPOSE:

1.1 Title: Collecting, Holding, and Transfer (CHT) Waste Cutout Valve (COV), 6-40-3; replace

1.2 Location of Work:

1.2.1 Division Officer’s Office (6-40-3-Q)

1.2.2 Crew WR, WC, SH and DECONTH STA (5-40-1-L)

1.2.3 Crew Messroom (4-40-0-L)

1.3 Identification:

1.3.1 Quantity (One EA), Remote Operating Gear (ROG) for CHT Waste COV, 6-40-3

Mfr: Elliott Manufacturing Co

TGI Short Form

20-DEC-2024 1111

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52801 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT WASTE CO 6-40-3 AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *F/O - REPLACE CHT WASTE COV 6-40-3 6-40-3-Q

FOUO Pg 2 of 6

CU PHASE DESCRIPTION (Cont.)

Type: UNIFLEX

1.3.2 Quantity (One EA), Existing CHT Waste COV, 6-40-3

Mfr: Cooper Industries Inc Model: 3132166-3-1/2 Type: Plug, Straight Way, Flanged 2 Port Size: 3.50 Inch IPS

APL: 882080115

1.3.3 Quantity (One EA), New CHT Waste COV, 6-40-3

Mfr: Cunico Corporation Mfr Id: DD-1876 Specification: MIL-V-24509 Type: Plug, Straight Way, Flanged 2 Port Size: 3.50 Inch IPS

APL: 882081319

1.4 Security Classification: None.

1.5 Initial Condition: None.

1.6 Contractor work start date: 7/21/2026

1.7 Contractor work completion date: 11/21/2027

2. PROCEDURE:

2.1 Accomplish the requirements of 009-09 of Ref. No. One for CHT certification process.

2.2 Disconnect the remote operating gear listed in 1.3.1 from the existing valve listed in 1.3.2, using Ref. No. 3 for guidance.

2.2.1 Verify disconnected remote operating gear for freely operation.

2.3 Remove existing valve listed in 1.3.2, using Ref. No. 4 and Ref. No. 5 for guidance.

2.3.1 Restore each mating surface exposed by valve removal. Repair by removing each high spot, burr, abrasion, and foreign matter, where removal can be accomplished by hand tools.

2.3.2 Inspect each fastener intended for reuse for wear and defects, using Paragraph 075-8.3 of Ref. No. 6 for accept or reject criteria.

2.3.2.1 Clean each fastener free of foreign matter (including paint).

2.3.2.2 Chase and tap exposed threaded areas.

2.4 Install new valve listed in 1.3.3, using Ref. No. 4 and Ref. No. 7 for guidance.

20-DEC-2024 1111

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52801 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT WASTE CO 6-40-3 AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *F/O - REPLACE CHT WASTE COV 6-40-3 6-40-3-Q

FOUO Pg 3 of 6

CU PHASE DESCRIPTION (Cont.)

2.4.1 Install each new gasket. Gasket must conform to MIL-PRF-1149, Type II, Class 2, synthetic rubber.

2.4.2 Cycle the valve from fully closed to fully open to fully closed 4 times. Allowable binding: None.

(V) “VALVE CYCLING”

2.5 Connect the remote operating gear listed in 1.3.1 to the new valve listed in 1.3.3, using Ref. No. 3 for guidance.

2.5.1 Align each valve station actuator and valve coupling. The universal joint must be installed as straight as possible.

Maximum/Allowable operating angle is less than 15 DEG.

2.5.2 Adjust the position indicator of operating station to match the valve opening,

2.5.3 Verify the remote operating gear listed in 1.3.1 for ease of operation and proper alignment by opening and closing each valve from its remote operating station through 3 complete cycles. Allowable binding: None.

(V) “VALVE CYCLING”

2.5.3.1 Notify the Chief Test Engineer (CTE) prior to cycling the valve listed in 1.3.3 with remote operating gear.

2.6 Accomplish the requirements of 009-32 of Ref. No. One for each new and disturbed surface.

2.7 Notes:

2.7.1 Planner: Code 232 M. Fudo, 243-4512

2.7.2 Work Integration Manager (WIM): C333 T. Yaginuma, 080-5419-0598

2.7.3 This TGI is issued to clear DFS No. LCC-19-1011-2022.

2.7.4 JCN ER01-L024 is related to this TGI.

2.8 Government Furnished Material (GFM):

2.8.1 SRF-JRMC will provide GFM listed in the Material List.

2.9 SRF-JRMC will provide the following service work: (TGI No. 3819P52801S02)

2.9.1 [C740] Crane and crane rigger service.

2.9.2 [X99E] Utilities service, electrical.

2.9.3 [X99M] Utilities service, including low pressure air supply, water supply, and steam supply.

2.9.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.9.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.9.6 [C133] QA Inspection for (G) symbol(s).

20-DEC-2024 1111

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52801 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT WASTE CO 6-40-3 AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *F/O - REPLACE CHT WASTE COV 6-40-3 6-40-3-Q

FOUO Pg 4 of 6

CU PHASE DESCRIPTION (Cont.)

20-DEC-2024 1111

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52801 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT WASTE CO 6-40-3 AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *F/O - REPLACE CHT WASTE COV 6-40-3 6-40-3-Q

FOUO Pg 5 of 6

OTHER SPECIAL REQUIREMENTS:

CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N

3 DWG 6-40-3 UNIFLEX 9:1 SYSTEM, 6-40-3

4" 2W2P BALL VALVE W/1 3/4

SQ STEM, 1/4 TURN

A Y ALL

4 DWG 528-4346214 COLLECTING HOLDING &

TRANSFER SYSTEM PIPING

ARRANGEMENT FR30-52 1ST

PLATF & BELO

A Y ALL

5 DWG 3132166 ROUND PORT, NAVY STD,

FLANGED ENDS, BRONZE

PLUG VALVE OUTLINE DWG

F Y 1

6 TM S9086-CJ-STM-

010/CH-075

Fasteners 7 N

7 DWG DD-1876 3-1/2 150# CUNICO FRP-2

BODY MIL FLANGE (MIL-F-

20042)

D Y ALL

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

2.1 QA

2.2 OMCH

2.3 OMCH

2.4 OMCH

2.5 OMCH

2.6 PNTR, QA

Machinery Work CFM $ 3600 for Marine Chemist and MISC.

Process Funding Document.

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P52801 KEY OP: A01

20-DEC-2024 1111

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52801 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CHT WASTE CO 6-40-3 AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *F/O - REPLACE CHT WASTE COV 6-40-3 6-40-3-Q

FOUO Pg 6 of 6

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

001 M VALVE,PLUG, ORIG. C232 M.

FUDO, 243-4512

ORDERED FOR KTR

3B 4820 016709076 NA 4 N 1/EA

002 M RUBBER SHEET,SOLID, ORIG.

C232 M. FUDO, 243-4512

ORDERED FOR KTR

9B 9320 010415249 NA 4 N 1/SH