This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS Blue Ridge, dated 15-APR-2025, focused on preserving a distillate fuel or ballast tank (Tank No. 9-40-0-F) with a 67,051-gallon capacity. The task involves commercial blast cleaning of the tank, visual inspection for structural integrity, and coating application, with work scheduled to start on 7/21/2026 and complete by 10/21/2027.

The instruction details specific procedures including commercial blast cleaning per SSPC-SP 6 specifications, comprehensive visual inspection for tank damage, and coating application. SRF-JRMC will provide supporting services including crane and rigging, utility services, safety inspections, and quality assurance inspections. The task is associated with Job Control Number (JCN) EM04-ZAE9 and meets the intent of LCC CSWT File No. 123-016, with a potential lead hazard noted and a critical coated area identified as CCNY-LCC19-081-25.

View the file

Other files

File Type Posted
Exhibit (A) BLR_5C1_TYCOM5 CDRL_r.pdf PDF
N6264925RA0540003.pdf PDF
N6264925RA0540002.pdf PDF
TGI_3819P59301A01_c0v0.pdf PDF
BLR_5C1_TYCOM5 CDRL.pdf PDF
TGI_3819P51418T01_c0v0.pdf PDF
TGI_3819P52802A01_c0v0.pdf PDF
TGI_3819P52801_T01_c0v0.pdf PDF
TGI_3819P51418T02_c0v0.pdf PDF
TGI_3819P51418A04_c0v0.pdf PDF
TGI_3819P123AFA01_c0v0.pdf PDF
TGI_3819P59301T01_c0v0.pdf PDF
TGI_3819P52808A01_c0v0.pdf PDF
TGI_3819P51413A01_c0v0.pdf PDF
TGI_3819P51420A01_c0v0.pdf PDF
TGI_3819P52802T01_c0v0.pdf PDF
TGI_3819P51419A01_c0v0.pdf PDF
TGI_3819P123AAA01_c0v0.pdf PDF
TGI_3819P52801_A01_c0v0.pdf PDF
TGI_3819P52808T01_c0v0.pdf PDF
TGI_3819P51413T01_c0v0.pdf PDF
TGI_3819P52806A01_c0v0.pdf PDF
TGI_3819P52806_T01_c0v0.pdf PDF
TGI_3819P14218A01_c0v0.pdf PDF
N6264925RA054 Amendment 0001.pdf PDF
Attachment VIII Source of Repair Instruction.pdf PDF
2.01 N6264925RA054 Solicitation.pdf PDF
Attachment VI Quality Assurance Surveillance Plan (QASP).pdf PDF
Attachment III GFP_List_V3 TYCOM5.xlsx XLSX spreadsheet
Attachment VII Warranty Tracking Information.pdf PDF
Attachment V Contract data.pdf PDF
Attachment II Proposal Sheet Generator v1.2.xlsx XLSX spreadsheet
Attachment IV-3 Request for Information Form (SAMPLE).docx DOCX document
Exhibit (A) CDRL BLR_5C1_TYCOM5.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

15-APR-2025 1723

20.14.15.2.9020 (September 2024) ICN: 3819P123AD KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: FO/BLST 9-40-0-F AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: F/O - PRESERVE DISTILLATE FUEL OR BALLAST (9-40-0-F)

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 5

EM04ZAE9

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

HAGA, MASAMICHI 231B 3152432513 14-APR-2025

APPROVED BY: CODE: PHONE: DATE:

TAKAGI, RYOUTA 231B 3152434502 14-APR-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EM04-ZAE9

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

123A11AD

1 SCOPE/PURPOSE:

1.1 Title: Distillate Fuel or Ballast (9-40-0-F); preserve

1.2 Location of Work:

1.2.1 Distillate Fuel or Ballast (9-40-0-F)

1.2.2 Air Conditioning Machinery Room No. One and Refrigeration Machinery Room (7-40-0-E)

1.3 Identification:

1.3.1 Quantity (One EA), Distillate Fuel or Ballast

Tank No.: 9-40-0-F Capacity: 67,051 Gallons

TGI Short Form

15-APR-2025 1723

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P123AD KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: FO/BLST 9-40-0-F AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: F/O - PRESERVE DISTILLATE FUEL OR BALLAST (9-40-0-F)

FOUO Pg 2 of 5

CU PHASE DESCRIPTION (Cont.)

1.3.2 Quantity (11,900 SF), Entire Interior Surface of Distillate Fuel or Ballast (9-40-0-F)

Remarks: The area includes tank side of manhole cover plate(s) and bolting ring

1.4 Security Classification: None.

1.5 Initial Condition:

1.5.1 Critical Coated Area: CCNY-LCC19-081-25 for the area listed in 1.3.2

1.5.2 Potential Lead Hazard.

1.6 Contractor work start date: 7/21/2026

1.7 Contractor work completion date: 10/21/2027

2. PROCEDURE:

2.1 Commercial blast clean each tank listed 1.3.1. Accomplish each requirement of Surface Preparation Specification SSPC-SP 6 of Ref. No. 3.

2.2 Accomplish a visual inspection of each tank listed in 1.3.1 for structural integrity, deterioration, pitting, each crack, and area of damage or distortion, using Ref. No. 4 through Ref. No. 10 for guidance.

2.2.1 Submit one legible copy, in hard copy or approved transferrable media, of a report listing results of the requirements of 2.2 to the SUPERVISOR.

2.3 Accomplish the requirements of 009-032 of Ref. No. One, including Table 4, Line(s) 11, for each area listed in 1.3.2.

2.3.1 Submit new coating data applied to the SUPERVISOR in accordance with Ref. No. 11 and Ref. No. 12.

2.4 Accomplish the requirements of 009-025 of Ref. No. One for a completion air test of each tank listed in 1.3.1. Test pressure must be 2 PSIG. Allowable drop in pressure: None.

2.5 Accomplish the requirements of 009-032 of Ref. No. One for each new and disturbed surface.

2.6 Notes:

2.6.1 Planner: Code 231B M. Haga, 243-2513

2.6.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

2.6.3 Opening, initial cleaning, and closing of each space listed in 1.2.1 will be covered by TGI No. 3819P12316A01 (KTR TGI).

2.6.4 Ref. No. 12 is available on P:\C200\C225\Enclosures\C231\Tank and Void Structural and Coating Condition Survey (MRC G1N5).

2.6.5 This TGI meets the intent of LCC CSWT File No. 123-016.

15-APR-2025 1723

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P123AD KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: FO/BLST 9-40-0-F AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: F/O - PRESERVE DISTILLATE FUEL OR BALLAST (9-40-0-F)

FOUO Pg 3 of 5

CU PHASE DESCRIPTION (Cont.)

2.6.6 JCN EM04-ZAE9 is related to this TGI.

2.7 Government Furnished Material (GFM): None.

2.8 SRF-JRMC will provide the following service work: (TGI No. 3819P123ADS02)

2.8.1 [C740] Crane and crane rigging service.

2.8.2 [X99E] Utility service, electrical.

2.8.3 [X99M] Utility service, including water supply, steam supply, and low pressure air supply except onboard blasting work.

2.8.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.8.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.8.6 [C133] QA inspection for (G) symbol(s) and review of coating application data.

15-APR-2025 1723

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P123AD KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: FO/BLST 9-40-0-F AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: F/O - PRESERVE DISTILLATE FUEL OR BALLAST (9-40-0-F)

FOUO Pg 4 of 5

OTHER SPECIAL REQUIREMENTS:

CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N

3 TM SYSTEMS &

SPECIFICATIONS

SSPC Painting Manual Volume

- N

4 DWG 100-2491001 Shell Plating & Stringer - Fr51- 1/2 Ctr to 4th Dk

H Y ALL

5 DWG 101-2491011 CVK & SHELL LONG FR8-51-

1/2

E Y ALL

6 DWG 101-2491013 Floors FR 8-98 S Y 12, 13, 7 DWG 102-2491030 INNER BOTTOM PLTG FR8-

1/2 - 51-1/2

G Y ALL

8 DWG 103-2491032 2ND PLTF PLATING FR 8-52 G Y ALL

9 DWG 114-2491155 TRANSV BHD FR 40, Pump

RM BHD and Trunk BHD FR 44-45

K Y ALL

10 DWG 114-2491161 DEEP TANK BHD FR 24, 48,

56, & LONG BHD BEL 2ND

PLATF FR 30-76

F Y ALL

11 TM T-9630-AB-MMD-

Corrosion Control Assessment and Maintenance Manual

(CCAMM)

3 N

12 TM NAVSEA 4790/14 Tank and Void Structural and Coating Condition Survey (MRC G1N5)

- N

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

22/KE PC N

22/KE PC N

22/KE PC N

22/KE PC N

22/KE PC N

22/MQ CS N

10/CT OM N

15-APR-2025 1723

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P123AD KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: FO/BLST 9-40-0-F AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: F/O - PRESERVE DISTILLATE FUEL OR BALLAST (9-40-0-F)

FOUO Pg 5 of 5

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P123AD KEY OP: A01