TGI_3819P52802T01_c0v0.pdf

PDF 96 KB Posted

Attached to
USS BLUE RIDGE 5C1 DSRA TYCOM 5
Solicitation number
N6264925RA054
Issued by

About this file

This is a WebAIM Short Form Task Group Instruction (TGI) for the USS Blue Ridge, dated 16-DEC-2024, focusing on a Plumbing Waste Water System (Gray Water) tightness and operational test. The document details a contractor (KTR) task involving three work types: Contractor work (22/KE), Quality Assurance work (33/G1), and Support/Facilities work (ER01), all of which are to accomplish and document the tightness and operational test in accordance with technical procedure TP 59312-3-300KTR. The task is associated with project 19P, system 59312, and involves work on the naval vessel LCC-19, with key personnel including Sawamura Hayato (preparer) and Ohta Jason Y. (approver), and Yaginuma Takehide listed as the zone manager.

View the file

Other files

File Type Posted
Exhibit (A) BLR_5C1_TYCOM5 CDRL_r.pdf PDF
N6264925RA0540003.pdf PDF
N6264925RA0540002.pdf PDF
TGI_3819P59301A01_c0v0.pdf PDF
BLR_5C1_TYCOM5 CDRL.pdf PDF
TGI_3819P51418T01_c0v0.pdf PDF
TGI_3819P52802A01_c0v0.pdf PDF
TGI_3819P52801_T01_c0v0.pdf PDF
TGI_3819P51418T02_c0v0.pdf PDF
TGI_3819P51418A04_c0v0.pdf PDF
TGI_3819P123AFA01_c0v0.pdf PDF
TGI_3819P59301T01_c0v0.pdf PDF
TGI_3819P52808A01_c0v0.pdf PDF
TGI_3819P51413A01_c0v0.pdf PDF
TGI_3819P51420A01_c0v0.pdf PDF
TGI_3819P51419A01_c0v0.pdf PDF
TGI_3819P123AAA01_c0v0.pdf PDF
TGI_3819P52801_A01_c0v0.pdf PDF
TGI_3819P52808T01_c0v0.pdf PDF
TGI_3819P51413T01_c0v0.pdf PDF
TGI_3819P52806A01_c0v0.pdf PDF
TGI_3819P123ADA01_c0v0.pdf PDF
TGI_3819P52806_T01_c0v0.pdf PDF
TGI_3819P14218A01_c0v0.pdf PDF
N6264925RA054 Amendment 0001.pdf PDF
Attachment VIII Source of Repair Instruction.pdf PDF
2.01 N6264925RA054 Solicitation.pdf PDF
Attachment VI Quality Assurance Surveillance Plan (QASP).pdf PDF
Attachment III GFP_List_V3 TYCOM5.xlsx XLSX spreadsheet
Attachment VII Warranty Tracking Information.pdf PDF
Attachment V Contract data.pdf PDF
Attachment II Proposal Sheet Generator v1.2.xlsx XLSX spreadsheet
Attachment IV-3 Request for Information Form (SAMPLE).docx DOCX document
Exhibit (A) CDRL BLR_5C1_TYCOM5.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

16-DEC-2024 1033

20.14.15.2.9020 (September 2024) ICN: 3819P52802 KeyOp: T01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 59312-3-300KTR TT T 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 59312

CU PHASE TITLE: PLUMBING WASTE WATER SYS (T & OP) - KTR

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 2

ER013513 * ER013514 * ER013504 * ER013505 * ER013509 * ER013527

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

SAWAMURA, HAYATO 246.2 3152434416 26-NOV-2024

APPROVED BY: CODE: PHONE: DATE:

OHTA, JASON Y. 246.2 3152435901 11-DEC-2024

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

ER01-3504 * ER01-3505 * ER01-3509 * ER01-3513 * ER01-3514 * ER01-3527

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

528A1102

Tightness & Operational Test of Plumbing Waste Water System (GRAY WATER) - KTR.

TGI Short Form

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

16-DEC-2024 1033

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P52802 KeyOp: T01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 59312-3-300KTR TT T 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 59312

CU PHASE TITLE: PLUMBING WASTE WATER SYS (T & OP) - KTR

FOUO Pg 2 of 2

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 TP 59312-3-300KTR PLUMBING WASTE WATER

SYS (T & OP) - KTR

LAT Y

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

(V) Contractor work:

Accomplish/document the tightness & operational test in accordance with reference, TP 59312-3-300KTR.

22/KE PC N

(G) QA work:

Accomplish/document the tightness & operational test in accordance with reference, TP 59312-3-300KTR.

33/G1 QA N

(S) S/F work:

Accomplish/document the tightness & operational test in accordance with reference, TP 59312-3-300KTR.

/ ER01 N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P52802 KEY OP: T01