N4425519R6006_Attachment_J.M-3,_Past_Performance_Questionnaire.pdf

PDF 68 KB Posted

Attached to
LTMOM
Solicitation number
N4425519R6006
Issued by

About this file

This document contains a past performance questionnaire for the solicitation N4425519R6006 issued by the Department of the Navy Naval Facilities Engineering Command for long term monitoring, operations, and maintenance services. The questionnaire is to be completed by both the contractor and a client to provide performance ratings on quality, schedule, customer satisfaction, management, cost, safety, and overall performance. The client is asked to provide ratings in these categories using an adjective scale from exceptional to unsatisfactory. Space is also provided for the client to comment on strengths, weaknesses, deficiencies, or other insights to assist in evaluating the contractor's performance risk for the solicitation.

N4425519R6006_Attachment_J.M-3,_Past_Performance_Questionnaire.pdf

View the file

Other files

File Type Posted
N4425519R6006_N4425519R6006_Amendment_0008.pdf PDF
N4425519R6006_Attachment_J.B-1_BidSked-rev.4.xlsx XLSX spreadsheet
N4425519R6006_N4425519R6006_Amendment_0007.pdf PDF
N4425519R6006_Attachment_J.C-1_PWS_rev.2.pdf PDF
N4425519R6006_Attachment_J.B-1_BidSked_rev.3.xlsx XLSX spreadsheet
N4425519R6006_N4425519R6006_Amendment_0006.pdf PDF
N4425519R6006_PWS_Attachment_G,_Adak_rev.1.doc DOC document
N4425519R6006_PWS_Attachment_H,_Adak_rev.1.doc DOC document
N4425519R6006_N4425519R6006_Amendment_0005.docx DOCX document
N4425519R6006_PWS_Attachment_M__JPHC-NHB_rev.1.doc DOC document
N4425519R6006_PWS_Attachment_K.2_NBK-Brem.xlsx XLSX spreadsheet
N4425519R6006_PWS_Attachment_K_NBK-Brem_rev.1.docx DOCX document
N4425519R6006_PWS_Attachment_J_Barrow_rev.1.docx DOCX document
N4425519R6006_PWS_Attachment_F_NAS_Whidbey_rev.1.docx DOCX document
N4425519R6006_PWS_Attachment_I_Pt._McIntyre_rev.1.doc DOC document
N4425519R6006_Attachment_J.B-1_BidSked_rev.2.xlsx XLSX spreadsheet
N4425519R6006_N4425519R6006_Amendment_0004.pdf PDF
N4425519R6006_Attachment_J.C-1_PWS_rev.1.docx DOCX document
N4425519R6006_N4425519R6006_Amendment_0003.pdf PDF
N4425519R6006_Attachment_J.G-1,_Proposal_Template.xlsx XLSX spreadsheet
N4425519R6006_Attachment_J.B-1_Sub_Line_Item_Numbers_Bid_Schedule_rev.1.xlsx XLSX spreadsheet
N4425519R6006_N4425519R6006_Amendment_0002.pdf PDF
Website Link —
N4425519R6006_N4425519R6006_Amendment_0001.pdf PDF
N4425519R6006_Attachment_J.L-1,_Pre-Proposal_Inquiry_rev.1.pdf PDF
N4425519R6006_PPC_Attendance_and_Slides.pdf PDF
N4425519R6006_Attachment_J.B-1_Sub_Line_Item_Numbers_(SLINs)_Bid_Schedule.xlsx XLSX spreadsheet
N4425519R6006_Attachment_J.M-1,_Relevant_Contract_Experience_Data_Sheet.pdf PDF
N4425519R6006_Attachment_J.L-1,_Pre-Proposal_Inquiry.pdf PDF
Attachment_J.M-2,_Safety_Past_Performance.pdf PDF
Attachment_J.F-1,_Schedule_of_Deliverables.pdf PDF
Attachment_J-1,_SCA_Wage_Determintation.pdf PDF
Attachment_J.B-1_Sub_Line_Item_Numbers_(SLINs)_Bid_Schedule.pdf PDF
N4425519R6006_N4425519R6006.pdf PDF
N4425519R6006_Attachment_J.C-1,_Performance_Work_Statement.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Long Term Monitoring, Operations and Maintenance N44255-19-R-6006

Naval Facilities Engineering Command, Northwest

Revised April 2012 1

SOLICITATION ATTACHMENT J.M-3

SOLICITATION ATTACHMENT J.M-3

NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0)

CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. Contractor Information Firm Name: CAGE Code:

Address: Entity Identifier Number:

Phone Number:

Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:

Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information Name:

Title:

Phone Number:

Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE

RATING DEFINITION NOTE

(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit.

The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.

(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.

(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.

(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.

A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.

(U) Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.

An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.

(N) Not Applicable No information or did not apply to your contract Rating will be neither positive nor negative.

Contractor Information (Firm Name): ________________________________________________ Client Information (Name): ________________________________________________________

TO BE COMPLETED BY CLIENT

PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

1. QUALITY:

a) Quality of technical data/report preparation efforts E VG S M U N

b) Ability to meet quality standards specified for technical performance E VG S M U N

c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance E VG S M U N

d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)

E VG S M U N

2. SCHEDULE/TIMELINESS OF PERFORMANCE:

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)

E VG S M U N

b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract E VG S M U N

3. CUSTOMER SATISFACTION:

a) To what extent were the end users satisfied with the project? E VG S M U N

b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes;

responsiveness to administrative reports, businesslike and communication)

E VG S M U N

c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer? E VG S M U N

d) Overall customer satisfaction E VG S M U N

4. MANAGEMENT/ PERSONNEL/LABOR

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force? E VG S M U N

b) Ability to hire, apply, and retain a qualified workforce to this effort E VG S M U N

c) Government Property Control E VG S M U N

d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N

e) Utilization of Small Business concerns E VG S M U N

f) Ability to simultaneously manage multiple projects with multiple disciplines E VG S M U N

g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes E VG S M U N

h) Effectiveness of overall management (including ability to effectively lead, manage and control the program) E VG S M U N

5. COST/FINANCIAL MANAGEMENT

a) Ability to meet the terms and conditions within the contractually agreed price(s)? E VG S M U N

Contractor Information (Firm Name): ________________________________________________

Client Information (Name): ________________________________________________________

b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client E VG S M U N

c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)

E VG S M U N

d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section. Yes No

e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.

Yes No

f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below. Yes No

6. SAFETY/SECURITY

a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues?

(Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)

E VG S M U N

b) Contractor complied with all security requirements for the project and personnel security requirements. E VG S M U N

7. GENERAL

a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).

E VG S M U N

b) Compliance with contractual terms/provisions (explain if specific issues) E VG S M U N

c) Would you hire or work with this firm again? (If no, please explain below) Yes No

d) In summary, provide an overall rating for the work performed by this contractor. E VG S M U N

Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):

File details come from the government source that posted it. Updated .