Amendment 0005 PPI Responses.pdf

PDF 226 KB Posted

Attached to
Solicitation N4008526R0187 MULTIPLE BARRACKS RENOVATION AT SOUTH CAROLINA MARINE CORPS BASES
Solicitation number
N4008526R0187
Issued by

About this file

This document is a Questions and Answers (Q&A) record containing 208 Pre-Proposal Inquiries (PPIs) and Government Responses for federal construction projects at MCAS Beaufort and MCRD Parris Island.

The document addresses three primary construction scopes: renovation of Buildings 1245 and 1246 (barracks) at MCAS Beaufort under a design-bid-build contract, and renovation of Building 332 (permanent party unaccompanied housing) at MCRD Parris Island under a design-build contract. For Buildings 1245 and 1246, the government confirmed that contractors bear no Design Liability Insurance responsibility, both buildings will remain unoccupied during construction while adjacent Buildings 1244 and 1247 stay occupied, and furniture removal/reinstallation applies to 120 total rooms with storage at MCAS Supply Warehouse Building 612, Bay 16. The scope includes options for roof deck replacement with insulation, ceiling repairs, door frame replacement for 72 openings, parking lot milling and restriping (7,500 linear feet), and exterior masonry cleaning. Key clarifications specify that only basketball court restriping is required (no court milling), exterior window perimeter caulking before painting is mandated, and all bathroom fixtures must be evaluated for replacement if damaged or cleaned and reinstalled if functional.

For Building 332, the design-build contract encompasses full interior demolition to structural systems, with a 734-day period of performance and site disturbance limited to below 8,000 square feet to avoid stormwater permitting requirements. Major scope items include roof replacement (with photovoltaic rooftop analysis and life-cycle cost analysis required), parapet demolition and replacement with gable pediments at both entry porches, EIFS repair and coating work (approximately 530 square feet), interior renovation with impact-resistant gypsum board and ceramic tile bathrooms, mechanical systems upgrade with building automation system integration to existing MCRD utility monitoring systems, fire alarm system upgrade to Siemens Fire Finder XLS with Class A circuits, and provision of 10-20 washers and dryers based on UFC 4-721-01 requirements for 142 residents. The government clarified that Building 332 will be vacated prior to construction start, existing site lighting remains with new electrical connections, telecommunications will reuse existing spaces, and the design-builder is responsible for completing 65%, 98%, and final design milestones with commissioning and acceptance activities integrated concurrently throughout construction rather than as a final phase. Proposal due date was extended to August 27 to allow adequate contractor response time.

View the file

Other files

File Type Posted
Amendment 0011.pdf PDF
Amendment 0011 PPI response.pdf PDF
Amendment 0010.pdf PDF
Amendment 0009 PPI Responses.pdf PDF
Amendment 0009.pdf PDF
2501 2026.08.25 Revised Documents for PPIs.pdf PDF
2501 2026.08.25 Continuation Sheet.pdf PDF
Amendment 0008.pdf PDF
_CIVIL.B332 RFP Revised.pdf PDF
Amendment 0007.pdf PDF
PI B332 RFP - Revised FP Sheets.pdf PDF
Amendment 0006 PPI Responses.pdf PDF
Amendment 0006.pdf PDF
Amendment 0005.pdf PDF
Beaufort Site Visit Sheet 1245 and 1246.pdf PDF
Parris Island B332 Site Visit Sheet.pdf PDF
Amendment 0004.pdf PDF
Amendment 0003.pdf PDF
Amendment 0003 Revised Price Proposal Schedule.pdf PDF
Amendment 0002 Revised Price Proposal Schedule.pdf PDF
Amendment 0002.pdf PDF
Attachment K - PI2501M Bldg 332.pdf PDF
Attachment J6 - 18918-18954.pdf PDF
Attachment J5 - 18619-18954-ASBUILT.pdf PDF
Attachment J7 - Bldg 1244-1248 Fl-Dim-Evac.pdf PDF
Attachment J4 - 13943-14077Part2.pdf PDF
Attachment J1 - Drawings 1246.pdf PDF
Amendment 0001.pdf PDF
Attachment J2 - Drawings 1245.pdf PDF
Attachment J3 - 13943-14077Part1.pdf PDF
Attachment I - MCRD VISIT REQUEST.xlsx XLSX spreadsheet
Attachment A - Drawings and Specs Bldg 1245 and 1246.pdf PDF
Attachment B - SOW Bldg 1245 and 1246.pdf PDF
Attachment F - PIEE Vendor Access Instructions.pdf PDF
Attachment E - Pre-Proposal Inquiry Log.xlsx XLSX spreadsheet
Attachment H - SECNAV 5512.pdf PDF
Attachment C - Price Proposal Schedule.pdf PDF
N4008526R0187 General Requirements.pdf PDF
Attachment D - Davis-Bacon Act WD SC20260008.pdf PDF
Attachment G - Contractor Base Access Request Form Bldg 1245 and 1246.docx DOCX document
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page Section Para.

25 RFP, Contract Reqs Buildings 1245 & 1246: Please confirm that for the design-bid-build, MCAS Beaufort buildings

(1245 and 1246), there is no expectation that the contractor is to pick up Design Liability

Insurance. Correct

26 CS101B Buildings 1245: Building Section North of

Breezway indicates UNOCCUPIED. Please confirm that the Both G and H Barracks (Buildings 1245 and 1246) will be unoccupied throughout construction. Building 1247 and the F Barracks (Building

1244) will be occupied. These two building are included in the entire

Phase IV Barracks complex, therefore, work must not disrupt the occupants in Buildings 1244 and 1247. There will be minimal work required near these buildings.

27 CS101C Buildings 1246:

PPI

No.

REFERENCE

QUESTION GOVERNMENT RESPONSE

28 CLINs 0001B and

0002B

Buildings 1245 & 1246: Where it lists for these

CLINs, "Move furniture and appliances to

Supply warehouse, move back to the Barracks"

Can the government provide a location of the

Supply Warehouse.

The furniture in all rooms needs to be moved out of both buildings. There are 120 total rooms (60 Rooms per building). The following is a list of all furniture, fixtures, and equipment to be removed and re-installed after the project is completed:

200-Twin Sized Beds

(40-1 person rooms and 160-2 person rooms)

200-Twin Sized Mattress

(40-1 person rooms and 160-2 person rooms)

400-Underbed Storage

(80-1 person rooms and 320-2 person rooms)

200-Dresser

(40-1 person rooms and 160-2 person rooms)

200-Nightstand

(40-1 person rooms and 160-2 person rooms)

200-Media Chest

(40-1 person rooms and 160-2 person rooms)

200-Lamp

(40-1 person rooms and 160-2 person rooms)

200-Desk

(40-1 person rooms and 160-2 person rooms)

200-Desk Chair

(40-1 person rooms and 160-2 person rooms)

40-Sofa

120-Micro-Fridge/freezer Combo

(40-1 person rooms and 160-2 person rooms)

120-Dual Roller Window Shades

(40-1 person rooms and 160-2 person rooms)

The items are to be stored in the MCAS Supply Warehouse, Building 612, Bay 16.

29 CLINs 0001B and

0002B

Buildings 1245 & 1246: For the work under these

CLINs is there an expectation that the contractor op checks all refrigerators, microwaves, etc.

before moving out and moving back in appliances to ensure there are not issues with responsibility of replacement upon move back and turnover of the buildings?

Yes. All the furniture, fixtures, and equipment was recenlty installed and will be checked and documented by the contractor prior to removing from the buildings. The condition will be documented and reported to the CM prior to removal. All furniture, fixtures, and equipment will be moved back into both buildings and the condition after installed will be verify, by the contractor, that everything is in its original condition.

30 I-001 CLIN 0001B Building 1245: Where it lists for these options, "Move furniture and appliances to Supply warehouse, move back to the Barracks" Please provide reference for the furniture and appliances to be moved. For instance from the site visit, the room we were able to observe had a single bed, couch, nightstand, lamp, desk and small chair, medium dresser, small dresser/file, microwave and small refrigerator. Is this the extent of the items to be moved for a total of 60 rooms?

See Response to PPI 28

31 I-001 CLIN 0002B Building 1246: Where it lists for these options, "Move furniture and appliances to Supply warehouse, move back to the Barracks" Please provide reference for the furniture and appliances to be moved. For instance from the site visit, the room we were able to observe had a single bed, couch, nightstand, lamp, desk and small chair, medium dresser, small dresser/file, microwave and small refrigerator. Is this the extent of the items to be moved for a total of 60 rooms?

See Response to PPI 28

32 CS101C (Typ) 01 50 00 3.4.2 Buildings 1245 & 1246: Is there an area designated for contractor laydown for these buildings? The areas within the temp fence lines will not allow for this necessary means. Please also clarify if this area requires temporary fencing.

There will be an area designated for contractor laydown. The contractor will use the previous area for the laydown area but will need to provide a plan for approval. Once the laydown area is determined, The site will require temporary fencing.

33 CS101C (Typ) 01 50 00 3.4 Buildings 1245 & 1246: Is there an area designated for contractor trailer for these buildings? The areas within the temp fence lines will not allow for this necessary means. Please also clarify if this area requires temporary fencing.

Once awarded the governement field office will help locate a place for the contractor trailer. A plan will need to be submitted for approval.

Temporary fence may be required depending on the location of the trailer.

34 CS101C (Typ) 01 50 00 3.2 Buildings 1245 & 1246: Along with the PPI for the proposed trailer location, what temporary utilities may be used to support the project trailer including water, sewer and electrical. Electrical and water. For water, you will need to get a water utility account from building 601

35 CS101C (Typ) 01 50 00 3.1 Buildings 1245 & 1246: Is there an area designated for contractor parking for these buildings?

Yes. The government field office will coordinate with the contractor the location of contractor parking.

36 01 45 00.00 1.5.1 Buildings 1245 & 1246: Please confirm that the

Quality Control Manager is per project and not per building. I.e. the QCM can cover both 1245 and 1246 buildings. The QCM can cover both 1245 and 1246.

37 01 35 26 1.7.1 Buildings 1245 & 1246: Please confirm that the combo Superintendent / Safety Manager is per project and not per building. I.e. the

Superintendent / Safety Manager can cover both

1245 and 1246 buildings. Correct, they can work on both building 1245 and 1246.

38 Civil

Drawings

Building 1245: 1. Please confirm there is no landscaping work, nor site amenities to replace as these are not shown in the drawings. It is reasonable to assume that vegetation that is disturbed is to be replaced with sod, hence the 32

92 23 specification but it would be fair to know the expectation for this work. 2. Should it be assumed to resod all areas within the LOD?

There will not be any landscaping for this project, however, all disturbed site areas are required to go back to their original state. All turff, paving, concrete, etc. must be restored to the original condition. Paving and concrete will be repaired and/or repalced to meet current design requirements. Turf must be maintained until matured to the point it can survive under natural conditions.

39 Civil

Drawings

Building 1246: 1. Please confirm there is no landscaping work, nor site amenities to replace as these are not shown in the drawings. It is reasonable to assume that vegetation that is disturbed is to be replaced with sod, hence the 32

92 23 specification but it would be fair to know the expectation for this work. 2. Should it be assumed to resod all areas within the LOD?

See Response to PPI 38

40 01 35 13 Buildings 1245 & 1246: Please confirm/deny that specification 01 35 13 does or does not apply to this project due to its proximity away from the airfields.

The contractor will not be allowed to access the Level 2 secure area.

However, the use of cranes may require coordination and approval for use by Airfield Operations. This Specification will remain for this reason.

41 01 45 35 1.3.13 Buildings 1245 & 1246: This section states that the Schedule of Special Inspections (SSI) is included in the design drawings. Can the government please clarify where this is listed for each building or is this what accompanies this spec as the "Statement of Special Inspections" starting on page 151?

If a special inspection is required, it will be identified in the notes on

Desing drawings within and/or in their specification sections, i.e.

foundations (concrete, structural steel, roof, etc.).

42 01 32 17.00

1.10.1.9.1 Buildings 1245 & 1246: Under the section it

states "The value of commissioning, testing and closeout WBS section may not be less than 10 percent of the total costs for procurement and construction activities." Please confirm that this

10% value only pertains to 1. Subcontracted scope values and 2. MEP scope of work. It is 10% of all procurement and construction activities. In other words

10% of the total contract value.

43 N/A Buildings 1245 & 1246: Is a project sign required for this project as there is no spec for this? If required, 1 per building or 1 total? No monument sign is required. The contractor project sign with site safety information, etc.

44 N/A Buildings 1245 & 1246: Is there a Knox box requirement for this project? If so where and how many? No, the Knox Box should already be on the buildings.

45 N/A Buildings 1245 & 1246: Is there a AED requirement for this project? If so where and how many? Yes, per the EM-385. See the EM-385 for how many.

46 N/A Buildings 1245 & 1246: Is there a requirement to clean the exterior masonry facade for these projects? We could not locate this in the specifications or drawings but it appeared the adjacent project under construction was cleaned at some point. Yes, this is stated in the general notes on the drawings.

47 N/A Buildings 1245 & 1246: Is there are requirement to refurbish, replace or otherwise any of the exterior façade components including the EGA's, building signage or any other signage features?

The exterior of these buildings will be being cleaned and any existing expansion/control joints or damaged wall spots will to be sealed repaired/replaced as needed. the joints at the floor/wall edge is to be removed before floor finish is applied and reinstalled after the floor finish is completed.

48 N/A Buildings 1245 & 1246: Please confirm that there is no exterior window scope associated with this project to include cleaning or recaulking of the windows.

No repairs are required but perimeter caulking before painting is required.

Aslo the contractor must document the exisitng conditions prior to construction and will be responsible for any damage to the windows during construction, and cleaning all paint, drywll mud, dirt, ect. that is on the windows at the end of the project.

49 I-001 and

AD901

Please confirm all bathroom accessories including; toilet paper dispenser, towel hook, towel bar, medicine cabinets as indicated on

AD901 are to be stored, reinstalled and that there is not a requirement for purchasing replacements of any of these items. All fixtures (mirrors, medicine cabinets, robe hooks, towel bars, ect. are to be evaluated and either replaced if damaged or cleaned and reinstalled.

50 AD901 DA21 Buildings 1245 & 1246: This detail states

"CONTRACTOR TO REPLACE NOT LESS

THAN 16 SF OF WATER DAMAGED GYP BD

AT CERAMIC WALL BASE LOCATIONS IN

EACH BATHROOM. CONTRACTOR TO

FIELD VERIFY QUANTITY AND LOCATION

IN EACH BATHROOM." Is this 16SF in addition to the CLIN breakouts provided in CLIN

05 (Option 2), CLIN 06 (Option 3), CLIN 06

(Option 4), CLIN 07 (Option 5)?

Per the adendum there will be more gypsum required to be removed due to lessons learned in the first phase of construction.

51 C-501B 01 50 00 Detail 6 Buildings 1245 & 1246: For the temp fence can the government confirm that barbed wire is required for the install.

The site security is the contractor's responsibility. Recommend installing the fencing per the design.

52 C-501B 01 50 00 Detail 6 Buildings 1245 & 1246: For the temp fence can the government confirm that no blackout cloth is required for this install. Provide per the design.

53 CD101B, C-

501B

Detail 5 Buildings 1245: Is the tree protection

(DC10/CD101B) to be provided only for the trees indicated on CD101B or are others to be accounted for? Some trees are inside of the fence line and do not have this tag nor are to be removed.

Protect all trees within the site that can be contaminated by construction/stormwater runoff

54 CD101C, C-

501B

Detail 5 Buildings 1246: Is the tree protection

(DC10/CD101C) to be provided only for the trees indicated on CD101B or are others to be accounted for? Some trees are inside of the fence line and do not have this tag nor are to be removed.

Protect all trees within the site that can be contaminated by construction/stormwater runoff

55 A/R Buildings 1245 & 1246: Are components of the design team excluded from providing 3rd party special inspections such as Materials Testing or

FPQE? Yes

56 AD401,

AD901 & A-

Buildings 1245 & 1246: Reference Closets A &

B, Please confirm contractors scope for coat hooks mounted on the inside of the closet doors.

Assuming these doors require repainting? Coat hooks to be removed, cleaned, and reinstalled. Damaged or missing hooks to be replaced.

57 AD401,

AD901 & A-

Buildings 1245 & 1246: Reference Closets A &

B, Please confirm contractors scope for mirrors mounted on the outside of the closet doors.

Assuming these doors require repainting? Mirrors to be removed, cleaned, and reinstalled. Damaged or missing mirrors to be replaced.

58 AD401,

AD901 & A-

Buildings 1245 & 1246: Reference Closets A &

B, Please confirm contractors scope for shelving inside of the closets. Assuming these closets require repainting?

All assessories to be removed, cleaned, and reinstalled. Damaged or missing accessories to be replaced.

59 N/A Buildings 1245 & 1246: What components (if any) of this project need to be coordinated with

Beaufort Jasper Water & Sewer Authority?

All water supply piping and sanitary sewer sitework.

60 N/A Buildings 1245 & 1246: Is the contractor responsible for any fees or subcontracting components with Beaufort Jasper Water & Sewer

Authority? Yes.

61 AD102B &

AD103C,

A102B &

A102C, A-301

CLINS 0010 &

Buildings 1245 & 1246: Options 07 & 08: States to provide a unit price for replacing metal roof deck, per current structural (hurricane and seismic) code, and install rigid insulation on top of the roof deck, complete in accordance with the drawings and specifications, but excluding work provided in another Line Item.. This will require the new fascia size to increase by 6”. It is understood that the metal decking may need to be replaced if damaged panels are observed, however what is the purpose of the insulation as it relates to the scope included in base bid scopes, where there is no insulation shown to be added

(A-301) nor demolished (AD-102B/C). Is it possible the government chooses to replace metal decking and exclude insulation? Or add insulation and not replace decking?

This is an optoin to this construction contract. Because this is an option to the construction contract it will be the contractor's responsibility to provide the design to replace the roof deck in its entirity. the design will be reviewed by MCAS Beaufort Public Works Engineering Department.

62 S-302, Others CLINS 0013 &

Buildings 1245 & 1246: Options 09 & 10: Repair offsite in ceiling from misaligned pre-tensioned concrete attic floor slabs. Can the government please provide additional information to what is being asked to be repaired and by what means?

There are no specific indicators in the drawings that differentiates or explains this scope that we can find.

The pre-tensioned concrete roof panels are not flush along the perimeter of the 3rd floor exterior wall. The outter panel is slightly higher where it abutts to the next panel. The original contractor infilled this with drywall and mud to make it flush. this condition has failed over the years and needs to be addressed and made smooth before painting the ceiling.

63 A-601, I-001 CLINS 0014 &

Buildings 1245 & 1246: Options 11 & 12: States to provide a unit price for 14Ga metal frames to the 72 door frames with new exterior slabs, complete in accordance with the drawings and specifications, but excluding work provided in another Line Item. Is there a process to how replacement will be determined to include whether door frames need to be replaced, repaired or left as is. For example in the base bid does the contractor own field measuring these openings or other inspection means to include mock-ups to determine the frames condition?

Again, this is in the amendment and is not reflected on the original design drawings. Exterior doors and frames are to be replaced.

64 CS101B &

CS101C, C-

503B & C-

504B

Detail 7 Buildings 1245 & 1246: Options 17 & 18: States to restripe approximately 7,500 LF. Can the government please confirm that thermoplastic is required in all locations even if striping basketball courts as indicated in Detail 7.

Yes, all striping on site.

65 CS101B, C-

503B

Detail 5 Building 1245, Option 17; States to Mill 1” of paving on the parking lots and basketball court area (500SY), install 1” thick of new wearing course (500SY), restripe approximately 7,500

LF. Can the government please provide a plan or indicator to where these parking areas and/or basketball courts are so that we can gauge the logistical impacts to include traffic control, restoration of areas surrounded by green area and other general requirements. Is this the parking lot area to the East of the building to where the new

RCP crossing is at and the basketball court to the

West near building 1248?

Mill Parking only, the Basketball court is to be restriped only.

66 CS101C, C-

503C

Detail 5 Building 1246, Option 18; States to Mill 1” of paving on the parking lots and basketball court area (500SY), install 1” thick of new wearing course (500SY), restripe approximately 7,500

LF. Can the government please provide a plan or indicator to where these parking areas and/or basketball courts are so that we can gauge the logistical impacts to include traffic control, restoration of areas surrounded by green area and other general requirements. Is this the parking lot area to the West of the building to where the new

RCP crossing is at and the basketball court to the

East near building 1244?

Mill Parking only, the Basketball court is to be restriped only.

67 AD401 DA41 Buildings 1245 & 1246: The drawings lack a

DFH schedule and there are also no specifications for door hardware. Please clarify the scope of work to be provided by the contractor for all doors to be replaced on this project. It is unclear what is to be provided in terms of closers, weather seals, hinges, thresholds, etc.

The amendment calls for replacing all the entry doors, therefore new hardware is required and it is stated that this hardware match the existing

(hinges, closers, kickplate, etc.

The original design called for the original exterior door locksets to be removed with batteries removed and placed in individual boxes that are marked with the room number they came from. These locks are to be reinstalled on the door they came from when construction is completed.

All interior doors will be addressed as stated in the original design.

68 AD401 DA41 Buildings 1245 & 1246: When disassembling the existing card swap door hardware/handles, what is the expectation by the government to catalogue and document the current condition of these. For instance it is likely that parts will be missing, broken or in poor shape when dissambeling these and an understanding of the process to replace these parts / components will be necessary for reinstallation. There is no spec or drawing notes stating this guidance. Thank you.

The original design called for the original exterior door locksets to be removed with batteries removed and placed in individual boxes that are marked with the room number they came from. These locks are to be reinstalled on the door they came form when construction is completed.

Catalog:

Remove lockset, remove batteries, place each lockeset, and all srews, strickplates, etc. into an individual box, bag, bin, etc., and mark the container with the room number from the room the lock came from. Store all these locks in a secure, conditioned space and re-install at the end of construction on the door of the room they were originally on.

69 AD401 DA41 Buildings 1245 & 1246: From the site visit it appears that room signage is installed to each door slated to be demolished. There also appears to be no notes or indicated scope to provide guidance on replacement signage (no signage schedule or spec included). What is the governments intent for replacement of these? Provide new room signage on the new doors. Coordinate with Base

Signage Department.

70 E-101B & E-

101C, E-501

Buildings 1245 & 1246: Is the triangle with an X indicating replacements for Exit lighting or something else? The sheet notes on these pages do not indicate replacement however they are shown on E-501. Please clarify if all exit lights are to be replaced.

Refer to the Amendment. The fire alarm control panel will be upgraded per MCAS Fire Protection contractor and replace all alarm/notification components. The work will require the installer to perform programming, testing and approval from NAVFAC's FPE wil be required before the work is complete.

71 E-101B & E-

101C, E-501

Buildings 1245 & 1246: It is hard to discern the scope required on the exterior walkways as it pertains to the Wall Pack lighting. The sheet notes on these pages do not indicate replacement however they may be shown on E-501. Please clarify if any of the wall pack lights are to be replaced. Replace wall pack lighting.

72 01 31 19.05 20 Building 332: With the documents being developed to at least a 40% solution does the government plan to hold a CDW and the associated processes and deliverables leading up to and after the CDW? If this is not a requirement, the government stands to save travel costs and time (schedule) associated with this process.

CDW required

73 01 33 10.05 20 1.7 Building 332: Considering that the design has been completed to or beyond a Preliminary

Design can the government clearly state the design deliverables they are expecting to receive for this project?

Full design required from bidder. A 65% design, 98% design and Final design milestone are all required. This is listed out in the RFP

74 01 35 13 Building 332: Please confirm/deny that specification 01 35 13 does or does not apply to this project.

This section does not apply.

75 01 30 00, 01 35 26, 01 45 00

Building 332: Staffing requirements. For clarity purposes, please confirm that a dedicated

Superintendent, SSHO and QCM is required for building 332 and also cannot be simultaneous coverage associated with the 1245 and 1246 buildings.

Confirmed, a dedicated Superintendent, SSHO, and QCM is required and cannot be the same as the invdidivudals associated with 1245 and 1246

UNLESS the projects do not occur simultaniously. AKA, a dedicated team is required for each project while it is actively under construction

76 01 32 17.00

1.10.1.10.1 Building 332: Under the section (d.) it states

"The value of commissioning, testing and closeout WBS section may not be less than 10 percent of the total costs for procurement and construction activities." Please confirm that this

10% value only pertains to 1. Subcontracted scope values and 2. MEP scope of work.

No. The requirement states the value must not be less than 10 percent of the total costs for procurement and construction activities. This 10% minimum applies to the total aggregate cost of all construction and procurement activities across the entire project, inclusive of all disciplines

(Architectural, Civil, Structural, MEP, etc.) and regardless of whether the work is self-performed or subcontracted

77 01 50 00 2.3 Building 332: Does MCRD Parris Island have a requirement for Temporary Chain link fencing for this project? The specification opens it up for

Polyethylene Mesh Safety Fencing to be used.

Follow specs.

78 01 50 00 3.6.2 Building 332: Is there an area designated for contractor laydown for these buildings? The areas within the temp fence lines will not allow for this necessary means. Please also clarify if this area requires temporary fencing.

Site laydown will be available for KTR use. Exact location TBD and will be discussed during design.

79 01 50 00 3.6 Building 332:: Is there an area designated for contractor trailer for these buildings? The areas within the temp fence lines will not allow for this necessary means. Please also clarify if this area requires temporary fencing.

Site laydown will be available for KTR use. Exact location TBD and will be discussed during design.

80 01 50 00 3.2 Building 332: Along with the PPI for the proposed trailer location, what temporary utilities may be used to support the project trailer including water, sewer and electrical.

Utilities will be dependent on trailer location. If available, utilities will be provided.

81 01 50 00 3.1 Building 332: Is there an area designated for contractor parking for these buildings?

Parking will be available for KTR use. Exact location TBD and will be discussed during design.

82 N/A Building 332: Is a project sign required for this project as there is no spec for this?

Yes

83 N/A Building 332: Is there a AED requirement for this project? If so where and how many?

All FF&E items including AED machines, along with their required quantities and locations for this facility, must be confirmed during the

CDW.

84 CD/CS/CG/C

U 101 (Part 6)

Part 3 RFP G2040 Site

Development

What guidance can the government provide for the contractor in terms of trimming back over growth from the oak trees surrounding the building. Several limbs on some of the larger oaks will impede work on EIFS, Windows and roof work.

Add requirement for the DB KTR to provide an Arborist to review trees adjacent to build, confirm pruning activites and identify tree protection zones.

85 CD/CS/CG/C

U 101 (Part 6)

Part 3 RFP G2050

LANDSCAPING

Building 332: Please clarify landscaping requirements for this project. Does the contractor only provide sod to replace disturbed areas from construction operations? Please note there are many areas around large trees void of grass.

This conceptual design includes sod to replace disturbed areas. No additional landscaping is is included. Verify at the CDW.

86 CD/CS/CG/C

U 101 (Part 6)

Part 3 RFP G2050

LANDSCAPING

Building 332: Please clarify landscaping requirements for this project. Are there any planting requirements outside of sod as it relates to trees, shrubbery or planting beds?

This conceptual design includes sod to replace disturbed areas. No additional landscaping is is included. Verify at the CDW.

87 CD/CS/CG/C

U 101 (Part 6)

Part 3 RFP G2050

LANDSCAPING

Building 332: Please clarify site amenity requirements for this project. Is the contractor to provide any benches, trash receptacles or replace existing grills found on site?

No new site furnishings are included in the conceptual design (benches, trash receptacles or etc.)

88 CD/CS/CG/C

U 101 (Part 6)

Part 4 RFP G204090 1.1

DUMPSTER PADS

AND ENCLOSURES

Building 332: Please confirm that there is no new or renovation work under this contract at the dumpster enclosures found onsite.

No new or renovation work is proposed at the dumpster enclosures.

89 CD/CS 101

(Part 6)

Part 3 RFP G2030

PEDESTRIAN

PAVING

Building 332: Please clarify the amount of sidewalks to be replaced on site as it relates to the replacements shown on CD101 and CS101.

The condition of the sidewalk that wraps around the building is in poor shape and will likely need to come up in order to properly grade wash outs and provide a 3:1 slope.

replace all sidewalks within 40 feet of the building's perimeter. This may exceed the 8,000 sqft disturbance threshold and therefore stormwater permits may be required.

90 Part 3 RFP G4020 SITE

LIGHTING

Building 332: Confirming that the existing site lighting provided on site is sufficient for turnover of the new project. Do lighting studies under our design need to be performed to verify this?

Site lighting is existing to remain.

91 CU101 (Part

6)

Part Six -

Attachments

Building 332: What is the MVT designation on the plans and for what purpose? These are a type of vault, 1 on each side of the building.

These are existing metal vault for the foundation drain system (lift station with PVC forcemain). It appears to be connected to storm drain inside the building. These are proposed to remain unchanged.

92 CD/CS/CG/C

U 101 (Part 6)

Part Six -

Attachments

Building 332: The concrete extension with vent

(typical) depicted on the plans. Are these just under slab vents or do they serve another purpose? Is work to be done on these as it relates to EIFS work shown on A-201 or grading work indicated on the Civil plans?

Correct, under the slab vents. These are proposed to remain unchanged.

93 CE101 Part Six -

Attachments

Building 332: Reference Keynote #2 which lists to install a new sidewalk section across the front of the building (Specifically the Noth/Front side of the building). Does this make sense considering it is a small section of green area that also requires new grading at a 3:1 slope?

Essentially this newly graded area will have a ledge or the sidewalk will need to be slanted.

Recommend that the existing sidewalk that is right next to this section be repurposed and utilized.

New sidewalk provides ADA accessible path, the existing sidewalk does not.

94 CS101 Building 332: Reference Keynote #1 which lists to maintain/install temporary portable toilet.

What is the purpose of this? Is this for government use outside of contractors field use?

The temporary portable toilet is intended for DB KTR use.

95 S-101 (Part 6) Building 332: For the typical scour areas under the building perimeter it is clear what needs to be done to reinforce the slab and backfill against the new reinforcement; however what is the expectation under the existing slab where washout has occurred around the pipe chases.

Will further excavation and backfill need to occur underneath these areas? If so what is that scope of work entail?

Yes excavation and backfill will be required to provide proper slopes and drainage away from the building.

96 Part 4 RFP E201002 WINDOW

TREATMENTS

Building 332: Confirming no window treatments, blinds, curtains or otherwise are part of the base bid contract as they are not listed in Part 3 but were part of the previous building to be demolished.

Interior window coverings are required by Part 4, Section E20, paragraph

E201002 WINDOW TREATMENTS, which requires functional window coverings at each exterior window and at interior windows where privacy is required. Roller shades are the basis of design; see the room finish schedule on Sheet I-601 (Finish Schedule Notes #4 and #5), finish legend

WS-1 and WS-2, and details C2 and C3 on Sheet I-502 in Part 6.

97 BJWSA

Development Policy

(Part 6)

Building 332: Is the contractor responsible for any fees or subcontracting components with

Beaufort Jasper Water & Sewer Authority?

The DB KTR is responsible for any fees or subcontracted components with BJWSA.

98 RFP Drawings Part Six -

Attachments

Building 332: Are the drawings provided in Part

6 of the RFP to be further developed from these designs or are these drawings for suggested/optional use? For example, a minor example of this can be found on A4/A-302 where it depicts wood trim above HVAC systems on the

Typical Wall Section, however other areas of the

RFP do not reference this scope.

The drawings provided in part 6 are preliminary and must be fully developed by the DB KTR.

99 RFP Drawings Part Six -

Attachments

Building 332: For scope found in the Part 6 drawings but not listed in Part 3 of the RFP; are those components found in the drawings contractual requirements? Please note that Part 3 references the following multiple times "Provide

XXXX as indicated in the drawings."

The drawings provided in part 6 are preliminary and must be fully developed by the DB KTR.

100 Part 3 RFP C103012

FIRESTOPPING

PENETRATIONS

Building 332: This section lists: "See attachment

07 84 00.00 22 Firestopping in Part 6. Contractor must contact MIDLANT FPE for the edits required for UFGS Section 07 84 00.00 22

Firestopping." This information should be provided during the proposal period so that the contractor can proper account for all scope needed.

Contractor must contact MIDLANT FPE for Specsintact file to be edited during design.

101 Part 3 RFP D503004

TELEVISION

SYSTEMS

Building 332: Please confirm that there is no expectation for any Audio-Visual scope to include wall mounted outlets, mounts or other

A/V infrastructure outside of what is being asked for with D503001 TELECOMMUNICATIONS

SYSTEMS.

There were not any A/V requirements relayed to DOR during RFP development. Confirm during CDW.

102 PD101 Part Six -

Attachments

Building 332: For plumbing components listed on PD101, notes 1 & 2that are installed under slab or through slab can these items be filled or abandoned in place in order to not demo out slabs for access to these?

plumbing components specifically under slab can be abandoned in place

103 Part 4 RFP Z10 1.3

MATERIALS AND

EQUIPMENT

REQUIREMENTS

IDENTIFICATION

Building 332: Please identify any government furnished equipment, either GFCI or GFGI as part 3 is silent on this.

There is no Government Furnished Contractor Installed (GFCI) equipment identified for this project. Government/station furnished and installed

(GFGI) items include all FF&E and collateral equipment, including AED units, which will be specified and provided by the station. The DB KTR is responsible for providing all supporting rough-in, blocking, power, and data required to serve these items. Confirm at CDW.

104 01 33 00.05 20 1.4.3 Submittals

Reserved for

Government

Approval

Building 332: Please confirm that the list provided in this section is a substantiated list of government required approved submittals. We have ran into issues where our design team has pulled down SpecsIntact templated specs and not allowed to edit sections based on this guidance.

Design Build team to verify.

105 01 33 10.05 20 2.2.5 Design and

Submittal Review

Schedule

Building 332: Has the guidance in table 2 been reviewed against the projects Time for completion of 734 days? Thus, if following this schedule of 282 days, this only allows for a build schedule of 452 days which is not enough time considering the Cx and Acceptance process.

Yes, the guidance in Table 2 was reviewed prior to RFP solicitation and is aligned with the overall 734-day Period of Performance (POP). The 734-day timeline is considered sufficient for a project of this scope.

It is the Contractor's responsibility to develop an integrated project schedule that overlaps design phases, submittal reviews, and procurement with early-stage site work and demolition. Commissioning (Cx) and

Acceptance activities must be integrated concurrently throughout the construction phase, rather than treated as a linear, consecutive block of time at the very end of the project. The 734-day schedule remains unchanged

106 01 33 10.05 20 2.2.5 Design and

Submittal Review

Schedule

Building 332: At what stage will demolition be allowed to occur? Does this need to wait until

IFCs are published or can this be planned to be

Finish to Start sequenced with the IFC deliverable?

it can be planned to be finish-to-Start sequenced with a dedicated, early-release Demolition & Site Prep IFC Package, rather than waiting for the entire project's final design IFC.

107 01 33 10.05 20 1.6 DESIGN

QUALITY

CONTROL

Building 332: Please confirm that the Design

Quality Control Manager is not necessarily full time, dedicated to this project and that this is a as needed role per the scope, timeline and complexity of the contract.

as needed, but should be a primary POC for design related questions during design

108 01 45 00

QUALITY

CONTROL

Building 332: At what point is the Full-time

Quality Control Manager (QCM) required to be onsite? We have ran into issues where other sections of the specifications are misinterpreted such as 01 20 00 Price and Payment Procedures and the contractor is told to mobilize the QCM well ahead of construction in order to have an invoice paid or have submittals processed. This has a significant impact to General Conditions during design so please respond accordingly. We recommend by the start of construction or the

PreCon/kick-off (PAK) meetings.

QCM should be identified in the quality control plan submitted to the government prior to mobilization. The QCM should be reviewing the quality control plan. This normally happens between final design acceptance and the PRECON

109 01 35 26

GOVERNMENTAL

SAFETY

REQUIREMENTS

Building 332: At what point is the Full-time

Safety Manager (SSHO) required to be onsite?

We have ran into issues where other sections of the specifications are misinterpreted such as 01

20 00 Price and Payment Procedures and the contractor is told to mobilize the SSHO well ahead of construction in order to have an invoice paid or have submittals processed. This has a significant impact to General Conditions during design so please respond accordingly. We recommend by the start of construction or the

PreCon/kick-off (PAK) meetings.

SSHO should be identified in the safety plans/AHAs submitted to the government prior to mobilization. The SSHO should be reviewing the safety plans/AHAs. This normally happens between final design acceptance and the PRECON

110 01 30 00

ADMINISTRATIV

E

REQUIREMENTS

Building 332: At what point is a trailer and onsite personnel required to be onsite? We have ran into issues where we have been told this needs to be coordinated and in place while conducting design investigations to include abatement surveys? We recommend by the start of construction or the

PreCon/kick-off (PAK) meetings.

On site trailer and personnel are not required until job site mobilization, but the sourcing and placing of the trailer should not detrimentally impact the project schedule in any way

111 Part 3 RFP D301002 GAS

SUPPLY SYSTEM

Building 332: D301002 GAS SUPPLY SYSTEM

States " Coordinate with the natural gas utility provider to determine if existing gas connection and meter is sufficient for new building systems.

Provide any applications and permits and provide the complete natural gas system from the load side of the utility meter to the heating equipment.

Contract with the local natural gas utility provider for installation of any new piping and appurtenances up to the load side of the meter.

Tie meter into the new Building Automation

System (BAS). Is the contractor responsible for paying any fees associated with the disconnection or reconnection of the meter for this process?

Yes. The Contractor is responsible for all costs and fees associated with utility coordination, including disconnection, reconnection, and metering, to provide a complete and usable system

112 Part 3 RFP D301002 GAS

SUPPLY SYSTEM

Building 332: D301002 GAS SUPPLY SYSTEM

States " Coordinate with the natural gas utility provider to determine if existing gas connection and meter is sufficient for new building systems.

Provide any applications and permits and provide the complete natural gas system from the load side of the utility meter to the heating equipment.

Contract with the local natural gas utility provider for installation of any new piping and appurtenances up to the load side of the meter.

Tie meter into the new Building Automation

System (BAS). If the supply side is found to be insufficient, is the contractor responsible for paying any fees associated with any install of insufficient sized systems?

Yes. The RFP explicitly requires the Contractor to 'Contract with the local natural gas utility provider for installation of any new piping and appurtenances up to the load side of the meter.' This includes paying the utility provider for any required system upgrades or tap fees to ensure sufficient gas supply to the building

113 Part 3 RFP D301002 GAS

SUPPLY SYSTEM

Building 332: D301002 GAS SUPPLY SYSTEM

States " Coordinate with the natural gas utility provider to determine if existing gas connection and meter is sufficient for new building systems.

Provide any applications and permits and provide the complete natural gas system from the load side of the utility meter to the heating equipment.

Contract with the local natural gas utility provider for installation of any new piping and appurtenances up to the load side of the meter.

Please provide further detail on the application and permit process.

The application and permitting process is dictated by the local privatized natural gas utility provider, not the Government. The Contractor is responsible for coordinating directly with the provider to determine their specific administrative requirements.

114 Part 3 RFP D301002 GAS

SUPPLY SYSTEM

Building 332: D301002 GAS SUPPLY SYSTEM

States " Coordinate with the natural gas utility provider to determine if existing gas connection and meter is sufficient for new building systems.

Provide any applications and permits and provide the complete natural gas system from the load side of the utility meter to the heating equipment.

Contract with the local natural gas utility provider for installation of any new piping and appurtenances up to the load side of the meter.

Please provide contact information for the gas company associated with this work.

The privatized natural gas utility provider for MCRD Parris Island is

Dominion Energy South Carolina. The Contractor is responsible for initiating contact with their commercial/builder services division for coordination. Formal contact information can be discussed after award.

115 361 Part 3, Ch 6 G4020 Building 332: Paragraph states existing site lighting to be connected to new panels with new controls. Will the existing site lighting remain or will it need to be replaced with new?

Existing site lighting (ex. pole lights) is to remain, but it is being reconnected to the building's new electrical and control panel(s). Building mounted exterior lights are to be new and included in scope.

116 278 Part 3, Ch 3 3.1.2 - Permits Building 332: Paragraph states that site disturbance is less than 8,000 SF and no stormwater permitting is anticipated. The Civil

BOD (page 835) also lists that the project proposes to disturb less than 8,000 SF. However, the Civil Drawings in Part 6 - Attachments

(pages 699 - 707) list a disturbance area of

11,260 SF. Please confirm that the intent is to keep the disturbance below 8,000 SF.

The intent is for land disturbance to be less than 8,000 SF. [ADC] Revised civil drawings correcting the disturbance area will be issued by amendment. The DB KTR remains responsible for verifying the final limits of disturbance based on its completed design and for obtaining any permits required.

117 269 Part 3, Ch 1 1 Building 332: Please confirm the existing roof diaphragm, including the connections of the diaphragm to roof framing members and the roof-to-wall connections, are not required to be evaluated in accordance with the applicable provisions of the IEBC, per 3-4.2 of UFC 3-301-

01.

The DB KTR is required to evaluate structural system and apply their own judgment as to what is required when following the UFC requirements.

118 319 Part 3, Ch 6 B10 Building 332: Per 4-5.2.6 of 1-300-09N, please provide the seismic site class to be used in design.

Site Class is "D" was a presumptive classifications for preliminary design.

Actual Site Class to be determined by DB KTR.

119 944 Part 6, Ch 6 Seismic Calc Building 332: The Tier 1 Seismic Assessment included in the RFP identifies a significant deficiency in the existing shear walls required to resist the required lateral forces. Please clarify whether additional seismic evaluations in accordance with ASCE 41 (e.g., Tier 2 or Tier 3) have been completed. Is retrofit of the seismic deficiency identified required as part of this project scope? Per government direction DB KTR to evaluate if seismic retro fit is required per current UFC.

120 944 Part 6, Ch 6 Seismic Calc Building 332: The Tier 1 Seismic Assessment uses M factors from ASCE 41 Table 4-9 for unreinforced masonry, but the RFP record drawings indicate the masonry shear walls are reinforced. Please identify any locations of unreinforced masonry and provide supporting information on the existing wall construction to justify the use of unreinforced masonry M factors. If reinforced M factors are acceptable, please provide updated Tier 1 calculations for use.

DB KTR to use Record Drawings to and their own judgment as to what is required when following the UFC requirements .

121 944 Part 6, Ch 6 Seismic Calc Building 332: Please confirm whether demonstrating compliance of the structural performance objectives through a Tier 1 Seismic

Assessment is sufficient to establish compliance of the existing lateral force-resisting system with the current building code, or whether additional evaluation, analysis, and retrofit is required for compliance with the new building code where required by the IEBC.

DB KTR is required to evaluate structural system and apply their own judgment as to what is required when following the UFC requirements.

122 319 Part 3, Ch 6 B10 Building 332: The RFP specifies seismic design category D to be used for design. The existing building’s lateral force resisting system is a legacy system and not permitted for Seismic

Design Category D per the current ASCE 7, Table 12.2-1. Please confirm, that if required by the IEBC/UFC, the existing structure is required to be upgraded to comply with current code requirements.

Site Class is "D" was a presumptive classifications for preliminary design.

DB KTR is required to evaluate structural system and apply their own judgment as to what is required when following the UFC requirements .

123 724 Part 6, Ch 1 A-101 Building 332: Please confirm that the first-floor kitchen, mini mart and Storage, and laundry areas are required to be designed for the following minimum design live loads based on their intended occupancy/use: 250 psf for the kitchen, 125 psf for the mini mart and storage, and 150 psf for the laundry. DB KTR is required to evaluate structural system and apply their own judgment as to what is required when following the UFC requirements.

124 724 Part 6, Ch 1 A-101 Building 332: Please identify and provide information on equipment and anticipated heavy loads (pallets of product, etc.) within the mini-mart.

All collateral equipment items are to be specified and provided by station.

125 1423 Part 6, Ch 18 S-12 Building 332: Please provide all structural record drawings for Building B332, including but not limited to structural general notes, floor framing plans, sections, and typical details.

We will provide all drawings after award

126 272 Part 3, Ch 2 2.3.6 Building 332: Please confirm that disproportionate collapse is applicable to this building. Please confirm that a collapse resistant design category "A" per ASCE 7-23 should be used for bidding purposes.

DB KTR to follow UFC requirements to determine applicability of disproportionate collapse requirements.

127 317 Part 3, Ch 6 A10 Building 332: Please confirm that a geotechnical report is not required as part of the project scope and that this requirement may be waived in accordance with UFC 3-220-01.

The geotechnical report is not required, as the scope is limited and specifically no new or modifications to existing foundation are proposed.

[ADC] The DB KTR may elect to perform subsurface investigation at its own discretion if needed to support its design.

128 317 Part 3, Ch 6 A10 Building 332: Please confirm whether the proposed alterations to existing Building B332 constitute a substantial improvement as defined by the International Existing Building Code

(IEBC). If so, please confirm that the existing building will be required to comply with the applicable flood-resistant design requirements of

ASCE 24.

The site is in Flood Zone AE with a BFE of 7'. Final determination of

IEBC and ASCE 24 applicability must be determined by the DB KTR.

129 317 Part 3, Ch 6 A10 Building 332: Please confirm whether the project location is classified as a High Risk Flood

Hazard Area in accordance with Chapter 3 of

ASCE 24. If applicable, please identify the hazard type(s) requiring the High Risk Flood

Hazard classification.

The site is in Flood Zone AE with a BFE of 7'. Final determination of

IEBC and ASCE 24 applicability must be determined by the DB KTR.

130 281 Part 3, Ch 4 4.1 Building 332: This RFP specifies 20 SF for a telecom closet on the first floor at the duty desk and no further telecommunications room space on any other floors. In UFC 3-580-01, the minimum telecom room size is specified as 10'6" x 9' for buildings above 5,000 SF. Additionally, UFC 3-580-01 requires a minimum of one telecom room per floor for multi-story buildings.

Please confirm if we should follow UFC requirements or if a waiver of these requirements has been granted.

We were directed to reuse existing telecomm spaces during RFP development. Confirm during CDW.

131 806 Building 332: The drawings included with this

RFP specify Category 6 cabling for telecommunications outlets. UFC 3-580-01 requires the use of CAT6A. Please confirm if we should follow the UFC requirements or if a waiver of these requirements has been granted.

Follow current UFC requirements.

132 347 Part 3, Ch 6 D503005 Building 332: This paragraph says to provide empty conduits, outlet boxes, cover plates, and power for an Access Control System. In an apparent contradiction this paragraph also says that the system must be provided as part of this contract but no further mention or specifications of an Access Control System can be found in the

RFP. Please confirm if the contractor is responsible for providing access control design, wiring, and devices or empty conduits, backboxes, cover plates, and power only.

Provide Access control system design, wiring and devices for hotel sytle card-key system.

133 326 Part 3, Ch 6 C102091 Building 332: This paragraph states that sleeping room doors must include hotel style card-key access control. Will these RFID readers be tied into base-wide access control systems or is this a stand alone system?

This is a stand alone system.

134 724 Part 6, Ch 1 Building 332: No space has been designated in the floor plan for electronic security head end equipment. Where are access control panels intended to be located?

Confirm at CDW. System can be located within a common core area utility space.

135 278 Part 3, Ch 3 3.1.2 Building 332: Are the accessible parking spaces in the southwest corner of the parking lot to remain? If so, how many additional accessible parking spaces are requested?