This is a Continuation Sheet for Revisions to solicitation PI2501M for the repair of Building 332, dated August 25, 2026.

The document outlines ten drawing revisions and two RFP text revisions. Drawing revisions include: revised Limits of Disturbance areas on drawings CD101, CS101, CG101, CU101, CE101, and CE102; elimination of Keynotes with indicated Manual Pull station locations on drawings FA101, FA102, and FA103; and a revised detail on drawing FA502 to show the Fire Alarm Reporting and Monitoring system. RFP revisions address updates to Part 3, Chapter 5 of the solicitation: elimination of the floor drain requirement for sleeping units (Pages 2-7) and modification of entry porch requirements to mandate a concrete ramp for the north (front) entry porch only (Page 31).

View the file

Other files

File Type Posted
Amendment 0011 PPI response.pdf PDF
Amendment 0011.pdf PDF
Amendment 0010.pdf PDF
Amendment 0009 PPI Responses.pdf PDF
Amendment 0009.pdf PDF
2501 2026.08.25 Revised Documents for PPIs.pdf PDF
Amendment 0008.pdf PDF
Amendment 0007.pdf PDF
PI B332 RFP - Revised FP Sheets.pdf PDF
_CIVIL.B332 RFP Revised.pdf PDF
Amendment 0006 PPI Responses.pdf PDF
Amendment 0006.pdf PDF
Amendment 0005.pdf PDF
Amendment 0005 PPI Responses.pdf PDF
Beaufort Site Visit Sheet 1245 and 1246.pdf PDF
Amendment 0004.pdf PDF
Parris Island B332 Site Visit Sheet.pdf PDF
Amendment 0003 Revised Price Proposal Schedule.pdf PDF
Amendment 0003.pdf PDF
Amendment 0002 Revised Price Proposal Schedule.pdf PDF
Amendment 0002.pdf PDF
Attachment K - PI2501M Bldg 332.pdf PDF
Attachment J6 - 18918-18954.pdf PDF
Attachment J5 - 18619-18954-ASBUILT.pdf PDF
Attachment J7 - Bldg 1244-1248 Fl-Dim-Evac.pdf PDF
Amendment 0001.pdf PDF
Attachment J2 - Drawings 1245.pdf PDF
Attachment J3 - 13943-14077Part1.pdf PDF
Attachment J4 - 13943-14077Part2.pdf PDF
Attachment J1 - Drawings 1246.pdf PDF
Attachment I - MCRD VISIT REQUEST.xlsx XLSX spreadsheet
N4008526R0187 General Requirements.pdf PDF
Attachment D - Davis-Bacon Act WD SC20260008.pdf PDF
Attachment G - Contractor Base Access Request Form Bldg 1245 and 1246.docx DOCX document
Attachment A - Drawings and Specs Bldg 1245 and 1246.pdf PDF
Attachment B - SOW Bldg 1245 and 1246.pdf PDF
Attachment F - PIEE Vendor Access Instructions.pdf PDF
Attachment E - Pre-Proposal Inquiry Log.xlsx XLSX spreadsheet
Attachment H - SECNAV 5512.pdf PDF
Attachment C - Price Proposal Schedule.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PI2501M Repair Building 332

Continuation Sheet for Revisions

August 25, 2026

Drawings

1. CD101: Revised Limits of Disturbance area.

2. CS101: Revised Limits of Disturbance area.

3. CG101: Revised Limits of Disturbance area.

4. CU101: Revised Limits of Disturbance area.

5. CE101: Revised Limits of Disturbance area.

6. CE102: Revised Limits of Disturbance area.

7. FA101: Eliminated Keynotes and indicated Manual Pull station locations

8. FA102: Eliminated Keynotes and indicated Manual Pull station locations

9. FA103: Eliminated Keynotes and indicated Manual Pull station locations

10. FA502: Revised detail to show Fire Alarm Reporting and Monitoring system

RFP

1. Part 3 - Chapter 5 - Pages 2-7: Updates to sleeping units with floor drain requirement eliminated.

2. Part 3 - Chapter 5 - Page 31: Update to entry porch with concrete ramp requirement required for the north (front) entry porch only.