This document is a Pre-Proposal Inquiry (PPI) Responses summary for a federal contract opportunity related to construction of Bachelor Enlisted Quarters (BEQs) at Marine Corps Air Station (MCAS) Cherry Point in North Carolina. The document addresses 215 numbered inquiries submitted by potential bidders regarding the Request for Proposal (RFP), with government responses indicating either completed answers or "PENDING RESPONSE" status.

Key contract details include three standalone four-story BEQ buildings designed to house 480 occupants each (1,440 total), with design-build delivery and life-cycle cost analysis (LCCA) requirements for multiple building systems. The Phase II proposal due date was extended to July 14, 2026 via Amendment 0007. Critical technical issues addressed include conflicting requirements for HVAC systems (specifically A2L refrigerant restrictions versus PTHP prescriptive specifications), foundation system specifications (pile versus shallow foundations determined by Designer of Record), pavement design criteria (NCDOT versus UFC 3-250-01), and site utility infrastructure documentation. Outstanding pending responses concern fire truck accommodation specifications, mechanical/electrical system routing, contaminated soil management protocols, dewatering effluent treatment standards, exterior sun control device requirements, and clarifications on ASHRAE standard versions for ventilation and energy efficiency. The RFP requires compliance with multiple UFC (Unified Facilities Criteria) standards, NFPA codes, and site-specific MCAS Cherry Point policies. Contractors must address unreliable power supply implications, emergency generator requirements, demolition scope clarity, and comprehensive utility mapping for electrical, water, sewer, storm drainage, and telecommunications systems across the project site.

View the file

Other files

File Type Posted
N4008526R0053 Site Visit Log.pdf PDF
Amendment 0010.pdf PDF
AMENDMENT 0009.pdf PDF
Amendment 0008 - D16 - Ladder 251 - Pierce Turning Performance Analysis.pdf PDF
AMENDMENT 0008.pdf PDF
Amendment 0008 - C9 - Storm Drain Replacement Exhibit.pdf PDF
Amendment 0008 - C8 - Cherry Point Site 1 Sanitary Plan.pdf PDF
Amendment 0008 - D15 - ITG A2L Refrigerants For Navy and MC Facilities.pdf PDF
Amendment 0008 PPI Responses.pdf PDF
AMENDMENT 0007.pdf PDF
Amendment 0006 PPI Responses.pdf PDF
AMENDMENT 0006.pdf PDF
AMENDMENT 0005.pdf PDF
Amendment 0005 B2 Hazardous Materials Report Bldgs 4201 4294 4295 4296 4312.pdf PDF
Amendment 0005 Wage Determination NC20260018 05 18 26.pdf PDF
Amendment 0005 D14 - Excerpt from Cherry Point Area Development Plan.pdf PDF
AMENDMENT 0004.pdf PDF
AMENDMENT 0003.pdf PDF
AMENDMENT 0002.pdf PDF
Attachment H - 1895345 MCAS CP DBRFP VOL3of4.pdf PDF
Attachment F - Small Business Participation Commitment Document (SBPCD).docx DOCX document
CJA ML-25-03 Class FRCS Cherry Point - Redacted.pdf PDF
Attach H - MCASCP Sites Subsurface Soil Geotech Report.pdf PDF
Attachment H - 1895345 MCAS CP DBRFP VOL1of4.pdf PDF
Attachment G - SBSP.docx DOCX document
Attachment E - Historical Small Business Utilization.docx DOCX document
Attachment I - Price Proposal Schedule.xlsx XLSX spreadsheet
Attachment H - 1895345 MCAS CP DBRFP VOL4of4.pdf PDF
Attachment H - 1895345 MCAS CP DBRFP VOL2of4.pdf PDF
AMENDMENT 0001.pdf PDF
AMENDMENT 0001 Attachment C - Experience Project Data Sheet.docx DOCX document
AMENDMENT 0001 Pre-Proposal Inquiries.pdf PDF
Attachment C - Construction and Design Experience Project Data Sheet.docx DOCX document
N4008526R0053.pdf PDF
Attachment D - Past Performance Questionnaire.pdf PDF
Attachment B - PIEE Vendor Access Instructions.pdf PDF
Attachment A - Pre-Proposal Inquiry Log Template.xlsx XLSX spreadsheet
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2. PRE-PROPOSAL INQUIRY RESPONSES:

Question

Reference

Question Government Response Page Section

Paragrap h

14 Survey Please provide a copy of the CAD files for the Survey/Civil Scopes

CAD Files will be provided via DoD Safe.

RFP

3.2.1.2

Provide the fire truck model of the

Cherry Point Ladder 251. Or provide its dimensions and wheelbase.

PENDING RESPONSE

RFP

3.2.1.4

Provide sizing information on the drying areas and the number of separate sections noted in this paragraph. The FC 4-721-10N is referenced. Under FC 4-471-10N 5-

3.5 Exterior wash areas the drying

area section does not give any area requirement or give a number of required separate sections.

Electrical

Service

POC - A3-

A4

Changes -

AFTER

DEMO

Attachme nts C.7

Confirm that splices of existing MV cable in manholes following demolition of building transformers is allowed as indicated in attachment C.7

28 1

Part 3

Chapter 6

ESR B10

Superstruc ture

The RFP mentions "Precast concrete tilt-up construction is not allowed."

Please confirm that non-structural concrete precast is allowed.

30 2

Part 3B

Chapter 6

ESR

A101002

Deep

Foundatio ns

RFP Part 3A states "For east coast sites refer to specific requirements in chapter 3B." RFP Part 3B is labeled as

Part Three "A". Please confirm the bookmarked Part 3B ESR A10 takes precedence which states, "The building and first floor slab must be entirely supported by a pile foundation system consisting of either precast pre-stressed concrete piles or auger cast piles. "

35 1

Part 6

Attachme nts

C.1

Existing

Condition s Plan

Volume 4 Part 6 notes that CADD files and Survey notes are provided via separate attachment. Please send these documents.

Files provided via DoDSafe with Amendment 0007.

With the current plans, it is unclear exactly what is included in the demolition scope outside of the building footprint. Should demolition contractors assume demolition of the structure and all improvements within five (5) feet of the building, or is removal of additional pavement, sidewalks, curb and gutter, utilities, or other site improvements required?

Do the mechanical/power brick enclosures associated with each structure (housing HVAC equipment, electrical equipment, and other mechanical systems) fall within the demolition scope, or are they to remain in place?

53 Part 3 "A" Chapter 6 D4020

D4020 notes Camp Lejeune and

MCAS New River do not have reliable power. If a fire pump is determined to be required in a facility with unreliable primary power, an emergency backup generator must be provided for the fire pump as a secondary power sources. D509002 then notes Camp Lejeune and MCAS

Cherry Point site do not have reliable power. Please confirm MCAS Cherry

Point does not have reliable power and generator is required.

Part 3B, 3.2.1.8.1

Section states to replace sewer mains to C Street, but survey does not extend that far. Please provide utility maps showing sewer line and manholes beyond survey limits

PENDING RESPONSE

Part 3B, 3.2.1.8.1

Section states to replace sewer mains to manholes in E street. The survey does not show manholes in the street.

If there are not existing manholes, do they have to be added? Or can work start at existing manholes southeast of

E street?

Part 3B, 3.1.2.1

Section states that we are replacing the storm drainage under the northeast parking lot. However, no survey was provided in that area. Please provide utility maps showing existing storm drainage in the parking lot.

Attachment

H; Vol 1 of

4, Page 536 of 605

3.0 Site

Analysis 3.2.1.8.1

Can the sanitary sewer replacement route, that is located off-site to C

Street, be provided, as discussed in

Sec. 3.2.1.8.1?

PENDING RESPONSE

Attachment

H; Vol 1 of

Chapter 6.

Engineeri

A101002

Deep

Part Three A Chapter 6 section

A101002 Deep Foundations states

4, Page 547 of 605 ng

Systems

Requirem ents

Foundatio ns

“The building and first floor slab must be entirely supported by a pile foundation system consisting of either precast pre-stressed concrete piles or auger cast piles”, will the government allow alternative foundation systems?

Attachment

H; Vol 1 of

4, Page 600 of 605

Section

23 81 00 2.3.1.6.1

UFC 4-721-01, part 3-12 does not allow A2L refrigerants in the occupied space. All PTACs and PTHPs come with A2L refrigerants. Does this preclude PTACs and PTHPs from the project?

67 Solicitation Due Date

Please provide a 4 week bid extension to allow adequate time for design based on the level of bridging documents provided and for subsequent subcontractor pricing efforts.

The Phase II proposal due date has been extended to 14 July

2026 NLT 2:00 P.M. EDT via

Amendment 0007.

76 2

Chapter 6

ESR

A101002

Deep

Foundatio ns

RFP Part 3A states "For east coast sites refer to specific requirements in chapter 3B." RFP Part 3B is labels as

Part Three "A". Please confirm the bookmarked Part 3B ESR A10 takes precedence which states, "The building and first floor slab must be entirely supported by a pile foundation system consisting of either precast pre-stressed concrete piles or auger cast piles. "

81 1

Part 6

Attachme nts

C.1

Existing

Condition s Plan

Volume 4 Part 6 notes that CADD files and Survey notes are provided via separate attachment. Please send these documents.

See response to PPI #35.

Existing

Site

Condition s

General Question: If contaminated soils are discovered do they need to be removed from the limits of construction or can they be capped by the slab with an air/vapor barrier under the slab?

Petroleum impacted soils must be removed per State Law. Bid per RFP for all other requirements.

Existing

Site

Condition s

General Question: Do contaminated soils need to be taken off the base or if there is available storage for them on the base?

Propose per RFP; all contaminated soils must be disposed offsite at a permitted landfill that will accept the soils.

Amendme nt #5

Attachme nt Figure

5.1

Assuming that Figure 5.1 issued with

Amendment 5 does now apply to this

Project please advise if all parts of

Figure 5.1 now apply, and if not, advise which parts are intended to apply?

nt #5

Attachme nt Figure

5.1

AM 005 states that Figure 5.1 is an excerpt from the "Cherry Point Area

Development Plan". Assuming Figure

5.1 now applies, at least in part, to this project will the GOVT be issuing the full/complete "Cherry Point Area

Development Plan" via Amendment and if so advising which parts of the document will be made a part of this

Project.

PENDING RESPONSE

Section 23

81 00

A2L

Refrigeran t

Section 23 81 00 cites ASHRAE 15 and 34 (2022) but does not specify an acceptable refrigerant for PTHPs.

AIM Act phasedown has effectively eliminated new R-410A PTHP production. A2L PTHPs (e.g., R-32) serving sleeping quarters are high-probability systems under ASHRAE

15, requiring refrigerant leak detection and occupant notification not addressed in the current spec.

Confirm: (1) A2L PTHPs are acceptable; (2) whether ASHRAE

15.2 compliance is required; (3) whether refrigerant leak detection integrated with MNS/fire alarm is in the DB contractor scope.

PENDING RESPONSE

Section 23

81 00

A2L

Refrigeran t -

ASHRAE

15.2

Applicabil ity

Section 23 81 00 cites ASHRAE 15 and 34 (2022) but does not cite

ASHRAE 15.2 (2022). A2L PTHPs serving occupied sleeping rooms are high-probability systems under

ASHRAE 15.2, which imposes refrigerant leak detection and occupant notification requirements not addressed in the current specification.

Confirm whether ASHRAE 15.2

(2022) compliance is required for plan unit PTHPs.

PENDING RESPONSE

Section 23

81 00

A2L

Refrigeran t - Leak

Detection and MNS

Integratio n Scope

ASHRAE 15.2 (2022), applicable to high-probability A2L systems in occupied sleeping spaces, requires refrigerant leak detection and occupant notification. At 720 plan units, integration with the MNS/fire alarm system may be required. Section

23 81 00 does not address this scope.

Confirm whether refrigerant leak detection and MNS integration for

A2L plan unit PTHPs is included in the DB contractor scope.

UFC 4-

721-01

§3-12

Revised

UFC 4-721-01 Change 1 (12 March

2026) was issued prior to this solicitation. The prescriptive PTHP requirement in Section 23 81 00

Prescripti ve

Specificati on for

Plan Units appears to conflict with §3-12 of that change. Confirm whether the government will issue a revised prescriptive specification for plan unit

HVAC that resolves this conflict.

UFC 4-

721-01

§3-17

FC 4-721-

10N §3-

14.5 -

Emergenc y Power

D50 ESR states MCAS Cherry Point does not have reliable power and implies a standby generator requirement where driven by code.

UFC 4-721-01 Section 3-17 states emergency power is not authorized in

UH. FC 4-721-10N Section 3-14.5 states emergency power is not required in UH. These criteria appear to conflict with the unreliable power statement in D50. Confirm: (1) whether a standby generator is required for this project notwithstanding the UFC/FC prohibition; and (2) how utility unreliability is to be addressed for fire pump reliability (NFPA 20) and elevator recall.

PENDING RESPONSE

UFC 4-

721-01

§3-17

Unreliable

Power

Fire Pump and

Elevator

Recall

NFPA 20 requires 120 minutes of backup power for fire pump rooms, and building code requires elevator recall power. UFC 4-721-01 Section

3-17 states emergency power is not authorized in UH. Confirm the acceptable means of achieving fire pump reliability and elevator recall at

MCAS Cherry Point given these conflicting requirements.

PENDING RESPONSE

Part 3B

Chapter 6

D30

Cherry

Point DX

Prohibitio n

Section 23 81 00 prescribes PTHPs for plan units. UFC 4-721-01 Change 1

(12 March 2026) Section 3-12 requires A2L refrigerant containment vessels to remain exterior to occupied spaces; all current PTHP production uses A2L refrigerant. The Part 3B

Chapter 6 D30 Cherry Point supplement prohibits DX packaged or split systems, VRF, and DX VAV at this installation, eliminating the common system alternatives. Confirm:

(1) what HVAC system type is acceptable for plan units at Cherry

Point that satisfies UFC 4-721-01 §3-

12, ASHRAE 15.2, and the Cherry

Point DX prohibition simultaneously;

(2) whether chilled water fan coils for plan units are the intended solution;

and (3) whether the government will issue a revised prescriptive specification for plan unit HVAC.

D30

Cherry

Point Plan

Unit

System

Chilled

Water Fan

Coil

If the acceptable plan unit HVAC system at Cherry Point is a chilled water system, confirm whether chilled water fan coils in plan units are the government's intended solution, and confirm whether the prescriptive

Section 23 81 00 PTHP requirement is superseded for Cherry Point.

PENDING RESPONSE

Part 3B

D30

Cherry

Point Plan

Unit

System

Revised

Prescripti ve Spec

Required

Section 23 81 00 is a prescriptive specification that locks the system type for plan unit HVAC. The combination of UFC 4-721-01 §3-12 and the Cherry Point DX system prohibition renders the prescribed system non-procurable. Confirm whether the government will issue a revised prescriptive specification for plan unit HVAC at MCAS Cherry

Point prior to proposal submission.

PENDING RESPONSE

Part 3B

D303002

IT Room

Ductless

Split vs

Cherry

Point DX

Prohibitio

Part 3B Chapter 6, Section D30 states that DX packaged or split systems are not acceptable at Cherry Point.

Section D303002 of the same supplement requires a direct expansion ductless split cooling-only unit for the

Telecommunications/Data/NMCI room. These requirements are contradictory within the same document section. Additionally, the required ductless split unit has its indoor coil (containment vessel) inside the IT room, which conflicts with

UFC 4-721-01 Change 1 (12 March

2026) Section 3-12 for A2L refrigerant systems. Confirm: (1) whether the IT room ductless split is exempt from the

Cherry Point DX prohibition; (2) whether a chilled water cooling solution is acceptable for the IT room as an alternative; and (3) the compliant refrigerant and system configuration for the IT room.

PENDING RESPONSE

Part 3B

D303002

IT Room

A2L UFC

§3-12

Complian ce Path

The ductless DX split unit required by

D303002 for the IT room has its indoor coil (A2L refrigerant containment vessel) inside the occupied equipment space. UFC 4-

721-01 Change 1 (12 March 2026)

Section 3-12 requires A2L containment vessels to remain exterior to occupied spaces. Confirm the compliant A2L refrigerant compliance path for the IT room cooling unit.

D303002

IT Room

Chilled

Water

Alternativ e

If the DX ductless split required by

D303002 for the

Telecommunications/Data/NMCI room conflicts with the Cherry Point

DX system prohibition, confirm whether a chilled water cooling solution is an acceptable alternative for the IT room.

PENDING RESPONSE

115 General

The RFP establishes a Pre-Proposal

Inquiry (PPI) submission deadline of

June 23, 2026, and a proposal due date of July 7, 2026. Given the number and scope of outstanding PPIs— particularly those affecting site conditions, utilities, and environmental requirements—the time between the PPI deadline and proposal due date is not sufficient to allow for:

1. Review and incorporation of

Government PPI responses, 2.

Coordination with subcontractors and suppliers, 3. Development and validation of pricing, and 4.

Completion of internal proposal reviews. As currently scheduled, Offerors may be required to carry additional assumptions and contingencies due to unresolved scope elements. Request the Government consider extending the proposal due date by 4 weeks to allow adequate time for evaluation of PPI responses and development of a complete and coordinated proposal. This will support more accurate and competitive pricing aligned with the Government’s intent.

The Phase II proposal due date has been extended to 14 July

2026 NLT 2:00 P.M. EDT via

Amendment 0007.

Mechanic al

RFP calls for PTAC units in the rooms. PTAC units typically do not come with covers to minimize/eliminate access to the controls of the unit and to help prevent damage to the unit. These are offered by some manufacturers at an added cost. Can we assume the Government does not want the covers as there is no reference made to them in the RFP?

PENDING RESPONSE

117 RFP Schedule

Please confirm advance notice timing required for the resident marines that will be moving into the 1st Barracks.

What length of advance notice is required prior to full or limited BOD?

PENDING RESPONSE

118 RFP Vol 4 of 4

Volume 4 of 4 references a Base

Utility Map and CAD Files being available. These documents would be

Base Utility Map and CAD files provided via DoDSafe to the GC’s in Phase II.

very helpful to the bidding process, when will they be made available?

23 05

48.19

23 05 48.19: Please verify ATFP

Bracing is only required for mechanical equipment over 31lbs hung from structure, not piping and duct distribution systems.

Confirmed, AT bracing requirement is found in UFC

4-010-01 Standard 19, Section

3-20. (KAD 06/23/2026)

Vol 1 of 4, 23 05 93

B201011

Sun

Control

Devices

The site location will requirement buildings that are orientated like the adjacent barracks at apx. A 45 degree angle from North. This creates very difficult shading geometries since each window has some amount of East and West orientation. With the high performance glazing and the window shading systems the rooms will already have significant solar control.

Suggest removing the exterior sun control devices.

PENDING RESPONSE

Vol 1 of 4, 23 05 93

23 05 93-3.2.14.1.2 Sample Strategy notes DALT is to be 25% of ductwork lengths. Please verify this is correct and not to be 100% ductwork DALT.

PENDING RESPONSE

Part 3B, Ch. 6 /

ESR G20

/ Section

G2020

Parking

Lots

2nd paragraph

This section states that pavements are to be designed "based on the anticipated daily traffic over the life of the project (25 years)" and that the

"Designer of Record will need to coordinate with facility users to determine anticipated traffic patterns."

Please provide the anticipated traffic patterns, including the design vehicles

(e.g. passenger cars, pick-up trucks, fire trucks/emergency vehicles, etc.)

and the anticipated daily traffic volume for each vehicle and for each pavement type (light duty and heavy duty).

PENDING RESPONSE

Part 3B, Ch. 3 /

Section

3.2.1.2

Service

Access

3rd paragraph

This section states the site is to be designed "to accommodate the largest vehicle used by the Fire Department that can be reasonably expected to respond to an incident at the BEQs

(Cherry Point Ladder 251)." With respect to pavement design, please provide the appropriate design vehicle(s) and anticipated traffic volume (number of passes over design life) to use in PCASE analysis.

PENDING RESPONSE

124 2

Part 3B, Ch. 6 /

ESR G10

Governme nt

Provided

3rd paragraph

This section states that a geotechnical report is to be prepared including recommendations for pavement design as specified and in accordance with

UFC 3-201-01, Civil Engineering. In

UFC 3-201-01, Chapter 4 Pavements, Section 4-1 (first paragraph), it states

It is NCDOT.

Geotechni cal

Informatio n

"Use pavement design criteria and procedures recognized by the DOT in the state in which the project is located or UFC 3-250-01. When state design criteria and procedures are used, the entire pavement section must conform in every detail to the applicable state criteria and materials must conform to the DOT material specifications." Please confirm the appropriate design criteria to use for pavement design on this project. Is it

UFC 3-250-01 or NCDOT (since the project is in North Carolina)?

125 23 81 00 2.3.1.10

23 81 00-2.3.1.10: PTAC Unit

Controls notes the function and temperature controls must be integral to unit. We understand this to be a built in thermostat only. If a wall mounted thermostat is desired, please clarify.

PENDING RESPONSE

126 Pg.2-5 nt 0002

Subject: Clarification of Scope

Allocation Between Base CLIN and

Option CLINs for Contaminated Soils and Dewatering Effluent

The RFP indicates that contaminated soil handling and dewatering effluent management are included within the base scope (CLIN 0001). However, these same elements are also identified as separate Option CLINs

(0003–0007).

This creates ambiguity regarding the intended allocation of scope between the base bid and option pricing.

Please clarify the following:

1. Confirm whether CLIN 0001 is intended to include all contaminated soil handling and dewatering effluent management required for the project, or only a baseline level consistent with anticipated site conditions. Currently these items are called out as options please advise as your intentions are unclear.

2. Confirm whether Option CLINs

0003–0007 represent additional scope beyond the base condition (e.g., higher contamination levels, additional quantities, offsite disposal, treatment requirements, or unforeseen conditions).

3. Define the limits of responsibility for each Option CLIN to clearly distinguish what work is included in the base bid versus option pricing.

PROPOSE AS SPECIFIED

4. Provide guidance to ensure Offerors do not duplicate or omit scope between CLIN 0001 and Option

CLINs.

127 Pg.2-5

Can the Government provide a revised bid Form in Excel format.

No. The format provided is consistent with the FC and

UFC.

128 Pg.2-5

Option CLINs 0008 and 0009 for removal of asbestos containing material are identified as unit-priced items for removal and disposal of asbestos-containing material (ACM) pipe insulation and buried utilities.

However, the bid schedule and associated RFP documents do not provide defined quantities (e.g., linear feet or number of occurrences) for these items. In order to minimize the potential of Contractors pricing in risk for this large unknown can the Govt provide the estimated quantities (e.g., LF, EA, or other applicable unit) for

Option CLINs 0008 and 0009 to allow development of extended pricing.

Quantities are provided in F20 for CLIN 0001 and other

CLIN's have quantities provided in the bid schedule.

129 1 01 91

00.15 22 1.1

Per paragraph 1.1, "the Government has hired an independent

Commissioning Firm." Please confirm if the following are in the Government

Commissioning Firm's Scope of

Work:

1. Lead Commissioning Specialist

2. Commissioning Specialists

3. Building Envelope Commissioning

Professional?

Propose per RFP.

130 25 01 57 19 3.3.1

Per paragraph 3.3.1 "All construction dewatering effluent must be treated prior to discharge." For bidding purposes, please provide an anticipated flow rate to appropriately size the treatment system.

This cannot be provided without defining means and methods of construction. This determination is the responsibility of the contractor.

131 1 J&A 3

Per J&A, only JCI Metasys brand products are required for all CPFRCS

DDC projects at Cherry Point. The

Metasys product line is only available to JCI branches. Per the J&A, "there are several known sources who can provide such services." Please provide the several known sources other than the JCI Wilmington, NC branch who can provide JCI Metasys brand controllers, software and licenses.

JCI is required; J&A does not limit to Wilmington branch.

132 Part 6 Section C

Request for Complete Existing Utility

Information and Points of Connection

– Barracks Phase II The RFP references existing utility information under Part 6, Section C, including the

All existing utility information has been provided.

Existing Conditions Plan (C.1) and supporting documents. However, the provided information does not appear to include complete or clearly defined utility mapping, routing, or verified locations for existing underground utilities within the project areas, including Site.

Please provide the following:

1. Complete and accurate existing utility drawings or mapping (including civil, electrical, mechanical, and steam systems) for all project sites, including

Site 1 V 106.

2. Available record drawings, GIS data, or as-built utility information that defines: - Utility type and size -

Horizontal and vertical routing -

Depths and elevations (if available) -

Identification of abandoned or inactive utilities

3. Clearly defined points of connection for all required utilities serving the new barracks buildings, including but not limited to: -

Electrical - Water - Sewer - Storm drainage - Steam / thermal systems -

Telecommunications

4. Clarification on whether the

Existing Conditions Plan (C.1) is intended to represent complete and accurate utility information for bidding purposes.

133 25 01 57 19 3.3.1

Please confirm the sampling frequency required for treated construction dewatering effluent.

Sampling frequency required is defined by NCDEQ discharge permit requirements.

134 14 01 57 19 1.5.1.1.1.5

Subject: Contaminated Soil

Management. Per the 01 57 19 spec, "once the work is completed or a proper amount is collected for disposal shipment, then the contractor will select a laboratory to conduct soil analytical testing." Please confirm the frequency of soil samples to be tested

(i.e., every 250 cubic yards?).

For bidding purposes, assume petroleum impacted soils must be tested for TPH DRO and

TPH GRO every 250 CY. All other waste characterization analysis must be conducted for every 1,000 CY. Sample analysis must meet the definition of representative under RCRA, be provided by the contractor within the

Waste Management Plan and approved by EAD in addition to meeting the requirements of the contractor selected offsite permitted landfill that will receive the waste generated from construction.

135 14 01 57 19 1.5.1.1.1.5 Subject: Contaminated Soil

Management. Per the 01 57 19 spec, Full TCLP is a standard term.

TCLP includes a standard list

"the tests to be conducted are Gasoline

Range Organics (GRO), Diesel Range

Organics (DRO), Oil & Grease with a silica gel wash, and Full TCLP."

Please provide the contaminants required to be tested in the "Full

TCLP."

of metals, VOCs, SVOCs, PCBs, pesticides/herbicides.

Additionally, all waste must be tested for RCRA characteristics including ignitability, corrosivity, and reactivity).

136 14 01 57 19 1.5.1.1.1.5

Subject: Contaminated Soil

Management. Does a soil sample need to be collected for PFAS analysis?

Bid per the RFP and the requirements for the contractors selected permitted landfill requirements.

137 25 01 57 19 3.3.1

Subject: Cofferdams, Diversions, and

Dewatering. "Do not discharge excavation ground water to the sanitary sewer, storm drains, or to surface waters without prior specific authorization in writing from EAD or

Contracting Officer. "Please confirm who is responsible for discharge permits? Please also confirm if the dewatering effluent can be discharged to sanitary sewer or storm drains once it has been treated to discharge levels.

The contractor is responsible for applying, receiving, and complying with all requirements of the discharge permit received from the State

(with Installation approval).

The contractor may discharge treated effluent in accordance with the discharge permit.

138 7 Amendme nt 0002 3.3.1

Subject: Cofferdam, Diversions and

Dewatering. Will treated effluent activities be subject to MCAS Cherry

Point's Defense Environmental

Restoration Program (DERP) policies?

No; however, the contractor is responsible for eliminating the migration of contaminants from the construction site.

139 25 01 57 19 3.3.1

Subject: Cofferdams, Diversions, and

Dewatering. Please confirm if the dewatering effluent can be discharged to sanitary sewer and/or storm drains once it has been treated to discharge levels.

The contractor is responsible for applying, receiving, and complying with all requirements of the discharge permit received from the State

(with Installation approval).

The contractor may discharge treated effluent in accordance with the discharge permit.

140 7 Amendme nt 0002 3.3.1

Subject: Cofferdam, Diversions and

Dewatering. The subject section requires dewatering effluent to be treated to "non-detect". It is not reasonable to achieve "non-detect" for dissolved metals or TPH contaminants. Should "non-detect" be changed to "the approved discharge criteria"?

The non-detect is intended for

PFAS treatment utilizing EPA

Method 1633. All other contaminants must meet the

State permitted discharge criteria in the permit the contractor is responsible for applying and receiving prior to mobilization of dewatering treatment system components.

141 7 Amendme nt 0002 3.3.1

Subject: Cofferdam, Diversions and

Dewatering. Will the Contractor be responsible for appropriate NCDEQ

NPDES permits and notifications for discharge of treated dewatering effluent?

Yes

142 7 nt 0002 1.5.1.1.1.5

Subject: Contaminated Soil

Management. Will soil excavation activities be subject to MCAS Cherry

Point's Defense Environmental

Restoration Program (DERP) policies?

No

143 7 Amendme nt 0002 1.5.1.1.1.5

Subject: Contaminated Soil

Management. Since contaminated soil media are ubiquitous at the site based on the Attachment H (Site

Characterization Report), will OSHA

1910.120 (HAZWOPER)

certifications be required for all site personnel?

Safety of workers is the contractor’s responsibility.

144 7 Amendme nt 0002 1.5.1.1.1.5

Subject: Contaminated Soil

Management. Since contaminated soil media are ubiquitous at the site based on the Attachment H (Site

Characterization Report), will breathing zone monitoring be required for site workers?

Safety of workers is the contractor’s responsibility.

145 7 Amendme nt 0002 1.5.1.1.1.5

Subject: Contaminated Soil

Management. Since contaminated soil media are ubiquitous at the site based on the Attachment H (Site

Characterization Report), will perimeter air monitoring be required?

Safety of workers and downgradient receptors (that may be affected by the selected means and methods of construction) is the contractors responsibility.

146 7 Amendme nt 0002 1.5.1.1.1.5

RFP states the following "Anticipate that all surplus soil media is contaminant impacted (including but not limited to PFAS/PFOA, petroleum, metals, VOC's, and PAH's) and must be disposed of at a licensed, permitted facility that accepts PFAS impacted soil media. Subject:

Contaminated Soil Management. May the Contractor reuse any excavated contaminated soil media onsite as backfill where appropriate?

Petroleum impacted soils may not be reused onsite. Reuse of contaminant impacted soil is driven by Installation policies, bid in accordance with RFP requirements.

147 126

Attachme nt H - Site

Characteri zation

Report

Table -

Summary of

Composit e Soil

Sample

Results

The subject table includes "PSRG" criteria for Residential, Commercial/Industrial and Protection of GW. Please define PSRG and how the criteria were derived.

In North Carolina, PSRG stands for Preliminary Soil

Remediation Goals. These are risk-based screening levels established by the NC

Department of Environmental

Quality (DEQ) to dictate how much hazardous chemical can safely remain in soil at contaminated sites before cleanup or land-use restrictions are required. See the NCDEQ website for derivation of these values.

148 126

Attachme nt H -

Site

Table -

Summary of

The subject table includes "PSRG" criteria for Residential, Commercial/Industrial and Protection

Yes, these screening levels are helpful to identify soils available for reuse from a

Characteri zation

Report

Composit e Soil

Sample

Results of GW. Should the Contractor use these criteria for waste management decisions of any excess soil or water media?

contaminant perspective only.

additional factors must be utilized to determine suitable fill for structures (see LA, geotechnical, and civil requirements). PSRGs are not applicable to water.

149 Page 277

Attachme nt H Vol 4 of 4 section

3.1.8

Plaza and

Courtyard

Materials

Please confirm exterior finishes are intended to reflect 'informal spaces' and are not required to contain premium features representative of

'formal spaces', as defined within the

BEAP on page 18 and elsewhere.

Exterior finishes are to reflect informal and formal spaces as defined in the BEAP.

CAD Site

Documents

- Cherry

Point

CAD site plan documents were referenced as an attachment to the

RFP but were not found to be attached. Can these CAD site plan documents be issued for use?

CAD files will be provided via

DOD SAFE

RFP -

General

Confirm which FAR 52.229 clause is required and clarify contractor responsibility for state and local taxes.

FAR clauses 52.229-2, FAR

52.229-3 apply to this contract. FAR 52.229-1 does not apply and has been removed.

Existing

Conditions/

Demolition

Attachme nt I Price

Schedule

Confirm if the existing building(s) to be demolished will have all FF&E

(furniture fixtures and equipment) removed prior to mobilization of the contractor.

See RFP Part 3B, Chapter 6, ESR F20, F201008 Equipment

& Furnishings provides requirements for demolition.

153 Factor 5

Would NAVFAC consider revising

Factor 5 to include a section for proposed betterments that are included in the proposed price? If betterments are desired, would NAVFAC provide a higher technical rating for inclusion of betterments?

Propose per RFP.

Attachme nt H, Vol.

4, V-106

Can the location of manhole MH57L be confirmed? The location noted on the site plan V-106 doesn't seem accurate. This looks more like a low-voltage handhole serving the secondary conductors to 4201.

PENDING RESPONSE

Attachme nt H, Vol.

4, V-106

If an alternate or more optimal tie-in location for medium-voltage power can be identified and implemented without causing outages to other buildings, is the government open to considering alternate tie-in locations?

PENDING RESPONSE

Attachme nt H, Vol

1, G40

This section mentions that generally manholes aren't permitted for medium-voltage extensions and that above-ground tap-boxes are preferred for radial feeds. The RFP also states to maintain loop-feed capability through all new transformers. Being able to pull multiple sets of MV conductors through shared manholes to allow for loop-feed topologies is much simpler and requires significantly fewer structures than installing tap-boxes at all UFC 3-550-01 driven locations.

Can manholes be utilized for this project in addition to tap-boxes?

Attachme

1, G4030

Its noted 4199, 4201, 4312, 4294, and

4295 are supplied from underground infrastructure in the area supplied from 4197 and it may need demolition. Does the underground infrastructure in the campus area serve any other buildings beyond the 5 mentioned above? The same section mentioned "primary feeder" - does this pass through or near the campus?

PENDING RESPONSE

Attachme nt H, Vol

4, V-series drawings

Can any additional existing site telecommunications documentation be provided? Things pertaining to duct bank sizes, cable quantities in given segments for duct banks, manhole numbering/naming, telecom survey information that extends further from the campus than what is provided in this drawings series? As its shown right now, it's difficult to determine exactly what telecommunications lines pass through or near this campus that need to be rerouted in lieu of demolished.

PENDING RESPONSE

Attachme

1, G4010

Its mentioned that there's a MV switch at MH57A, however it appears to just be a manhole. Confirm this is only a manhole.

PENDING RESPONSE

Attachme

1, G40

Its mentioned that underground medium-voltage splices are not permitted, however to remove the existing BEQ transformers and re-establish the loop connection with the

A3/A4 MV feeder, underground splicing in the manholes around the campus is the much more cost-effective approach rather than pulling new MV cables from the next upstream and downstream transformers/switches on a given segment of the MV loop. Can medium-voltage splicing be utilized for this project?

PENDING RESPONSE

Attachme nt H, Vol

1, G403002

Can the exterior CATV connection point be identified at this time?

No. DOR to coordinate during design.

162 Factor 5

Is there a page limit for the project schedule which is outside of the narrative page limit?

Per the RFP, there is no page limitation the schedule.

163 Part 3A D202001

D202001 says to provide copper tubing and fitting for above ground and buried piping. Part 6, D.8 MCAS

CP Mech Policies Updated 30 Aug

2023, #59, says "utilize Type L copper piping for all above ground piping

(hydronic and domestic). RFP and

Mech Policies does not designate type of copper for underground domestic piping. Typically, Cherry Point has required type L hard copper above ground, and type K soft copper. What type of piping will be required for above ground and underground domestic water systems?

Refer to Part 4, Performance

Technical Specifications, of the RFP for domestic water pipe material.

164 Part 3A D202003

D202003 states to provide a domestic hot water storage tank in addition to the high-efficiency domestic hot water heaters. Historically, the barracks renovations have specified the use of large storage-type domestic hot water heaters with integral storage tanks

(such as those by PVI). Will this project require the use of large integral storage type domestic hot water heaters, or is it acceptable to provide water heaters and separate hot water storage tanks?

Refer to Part 2, spec section

01 33 29, domestic water heater type to be determined through life cycle cost analysis.

165 Part 3A D203001

PVC piping allowed for above ground installations when provided with effective noise reduction insulation.

What is effective noise reduction insulation?

PENDING RESPONSE

166 Part 3A D304003

D304003 says to "provide insulated type "K" copper hot water supply and return piping to serve the HVAC equipment throughout the facility.

Refer to site specific guidelines in Part

6 for additional specific material requirements." Part 6, D.8 MCAS CP

Mech Policies Updated 30 Aug 2023

#59, says "utilize Type L copper piping for all above ground piping

(hydronic and domestic). Do we use

Type "K" copper piping per D304003, or Type "L" copper piping per Part 6, D.8 MCAS CP Mech Policies?

Follow RFP section D304003 requirements; type "L" authorized per part 6.

167 Part 3A D304006

D304006 says "For exterior buried chilled water distribution systems, coordinate with Section G30, Site

Civil/Mechanical Utilities." Part 3B, G3050 Cooling Distribution, says "not used". Typically for exterior buried chilled water piping, Cherry Point has required a pre-insulated piping system consisting of type K copper piping, with a HDPE jacket; sticks and kits system. What will be required for the underground chilled water piping systems?

168 Part 3A D304006

D304006 says to "provide insulated type "K" copper hot water supply and return piping to serve the HVAC equipment throughout the facility.

Refer to site specific guidelines in Part

6 for additional specific material requirements. If no guidance is given, either steel or copper piping may be provided." Part 6, D.8 MCAS CP

Mech Policies Updated 30 Aug 2023, #59, says "utilize Type L copper piping for all above ground piping

(hydronic and domestic). Do we use

Type "K" copper piping per D304003, or Type "L" copper piping per Part 6, D.8 MCAS CP Mech Policies?

Follow RFP section D304006 requirements; type "L" is acceptable per part 6.

169 Part 3A D304006

D304006 says to "provide insulated type "K" copper hot water supply and return piping to serve the HVAC equipment throughout the facility.

Refer to site specific guidelines in Part

6 for additional specific material requirements. If no guidance is given, either steel or copper piping may be provided." Part 6, D.8 MCAS CP

Mech Policies Updated 30 Aug 2023, #59, says "utilize Type L copper piping for all above ground piping

(hydronic and domestic). Typically, if given an option to use copper or steel piping, Cherry Point has used copper piping for 4" and smaller, and the options for steel or copper for piping larger than 4". If given the choice to use copper or steel piping, will we be required to use copper for pipe sizes

4" and smaller, and copper or steel for sizes larger than 4"?

Correct, Follow RFP section

D304006 requirements; type

"L" is acceptable per part 6;

above 4" steel is acceptable;

4" and below is copper.

170 Part 5 Section 23

81 00

Specification Section 2.3.1.7 Cabinet

Construction states that the

PTAC/PTHP enclosure shall be 18 gauge steel with removable face panels, access to controls, and adjustable louvers. Historically, the barracks renovations which utilized

PTACs have specified the installation of a full ligature-proof cover with stationary louvers to protect the unit from damage and prevent access by room occupants. Will ligature-proof covers for the PTAC/PTHP units be required on this project?

171 Part 3A D3030

D3030 Cooling Generating Systems states to provide a single air-cooled chiller utilizing a primary/secondary pumping system. This pumping configuration is typically used with systems utilizing multiple chillers.

Since there will only be one chiller, would it be acceptable to use a primary-only pumping system with 3-way chilled water valves and constant flow through the chiller?

No. Provide chiller system per

RFP requirements.

172 Part 3A

5.0 Room

Requirem ents

Section 5.0 Room Requirements and the 4.2 Space Relationships diagram only show one main mechanical room

(114 - Main Mechanical Room) on the first floor. Will we be required to

"split" this main mechanical room into two separate rooms to provide one space for the "hot" equipment

(boilers/water heaters/HW pumps) and one space for the "cold" equipment

(air handlers/DOAS/CHW pumps)?

Mechanical room designs must follow the requirements indicated in UFC 3-401-01, 3-

410-01 and UFS 3-410-01 and as indicated in the RFP.

Bubble diagram in 4.2 Space relationships is included to show intended spatial adjacencies.

173 Part 3A D30

HVAC

D30 HVAC General System

Requirements state the summer design conditions for Cherry Point to be

90Fdb/77Fwb (high ambient) and

87Fdb/79Fwb (high humidity). Part 6

D.8 MCAS CP Mech Policies

Updated 30Aug2023 #46 calls for summer design conditions to be

90Fdb/78Fwb. Which summer design condition should be used for sizing the cooling loads?

PENDING RESPONSE

174 Part 3A D30

HVAC

D30 HVAC General System

Requirements state the winter design condition for Cherry Point to be 27F.

Part 6 D.8 MCAS CP Mech Policies

Updated 30Aug2023 #46 calls for the winter design condition to be 24F.

Which winter design condition should be used for sizing the heating load?

PENDING RESPONSE

175 Part 3A D30

HVAC

D30 HVAC System Description states to comply with the latest edition of

ASHRAE 62.1, Ventilation for

Acceptable Indoor Air Quality - 2016 edition. Part 6 D.8 MCAS CP Mech

Policies Updated 30Aug2023 #1 states to use the latest revision of ASHRAE

62 for guidance on indoor air quality

(currently Standard 62.1-2025).

Which version of ASHRAE 62.1 should be used on this project - 2016 or 2025?

176 Part 3A D30

HVAC

D30 HVAC makes multiple references to ASHRAE 90.1, but does not specify which version to utilize for this project. The NAVFAC High

Performance and Sustainable Building

Checklist makes reference to both

ASHRAE 90.1-2013 and ASHRAE

90.1-2016, while Section 01 91 00.15

22 Total Building Commissioning makes reference to ASHRAE 90.1-

2019. Which version of ASHRAE

Standard 90.1 shall be used for this project?

PENDING RESPONSE

177 1 Part 3A

1.0

Project

Descriptio n

The RFP references multiple other sites including but not limited to

Camp Lejeune, New River, and Camp

Pendleton. Please confirm any and all requirements to bases other than

Cherry Point shall be removed from the RFP and contract.

Refer to RFP Organization

Outline Note which indicates

"In sections where there are site specific requirements indicated, only those requirements that are associated with the project location are applicable. "

178 2 Part 3A

A101002

DEEP

FOUNDA

TIONS

RFP Part 3A A101002 DEEP

FOUNDATIONS states "The building and first floor slab must be entirely supported by a pile foundation system consisting of either precast pre-stressed concrete piles or auger cast piles. "RFP Part 3B A101001

SHALLOW FOUNDATIONS states

"The Building and First Floor slab may be supported on shallow foundations if used in conjunction with the requirements of A1020

Special Foundations." Additionally the RFP Section A10 repeatable states

"As determined by the Designer of

Record". Please confirm the foundations shall be determined by the

Designer of Record and in accordance with applicable UFCs.

PENDING RESPONSE

179 6 Part 3B

3.1.2.13

AICUZ /

Explosive

Arcs /

HERO

Permits

The RFP states "The project site is located in a 65-70 dB Day-Night

Average Sound Level (DNL) zone.

Comply with noise mitigation measures listed in UFC 3-101-01

Architecture, Section 3-8 Acoustics as required. Contractor will need to consider increased noise levels when selecting materials." Additionally the

RFP states D30 HVAC states to provide "Provide package terminal heat pumps (PTHP) " Please confirm

PTHP units must mitigate sound per the requirements within this RFP section.

See response to PPI#92.

180 8

Part 2

Section 01

33 29

1.6.5

The RFP states "1.6.5 On-Site

Renewable Energy Generation, For the submittal documentation below, demonstrate compliance with UFC 1-

200-02." Please advise if renewable energy generation is required or per

LCCA analysis.

Renewable energy generation only required if life cycle cost effective.

181 8

Part 2

Section 01

33 29

1.6.5

The RFP states "1.6.6 Solar Domestic

Hot Water (SDHW) for the submittal documentation below, demonstrate compliance with UFC 1-200-02."

Please advise if renewable energy generation is required or per LCCA analysis.

Renewable energy generation only required if life cycle cost effective.

182 6 Part 3B

3.1.2.13

AICUZ /

Explosive

Arcs /

HERO

Permits

The RFP states "The project site is located in a 65-70 dB Day-Night

Average Sound Level (DNL) zone.

Comply with noise mitigation measures listed in UFC 3-101-01

Architecture, Section 3-8 Acoustics as required. Contractor will need to consider increased noise levels when selecting materials." Please confirm windows and storefront shall comply with this standard.

Comply with UFC requirement for all applicable building envelope elements per RFP.

183 6 Part 3A B202001

The RFP states "Provide a minimum of 30% window to wall ratio for each space on an exterior wall, excluding building support spaces. Windows are to be similar in size and scale across the exterior face of the building."

Please confirm storefronts and windows are included in the ratio.

Confirmed, storefront and windows included in window to wall ratio requirement per

Part 3A, Chapter 6, ESR

Section B2020.

184 6 Part 3A

B201011

SUN

CONTRO

L

DEVICES

(EXTERI

OR)

The RFP states "Provide fixed horizontal sunshades on the southern face of the building and fixed vertical sunshades on the east and west faces of the building." The 2+0 Room sheet does not list this requirement. Please confirm sunshades shall be provided on windows at the 2+0 units.

PENDING RESPONSE

185 2 Part 3A B202001

The RFP states "Provide operable aluminum windows with integral insect screens and locks." but does not state a location. Please confirm this applies to the all windows within the

2+0 Rooms.

Confirmed, requirement applies to all rooms with windows per Part 3A, Chapter

6, ESR B202001.

186 2 Part 3A B202001

The RFP states "Determine the construction of security windows by evaluating the project program security requirements, using the

Military Handbook (MIL-HDBK)

1013/1A, Design Guidance for

Physical Security of Facilities, to define window requirements." This

MIL-HDBK lists multiple sensors that are tied into an intrusion detection section. Additionally, the request on the contractor is unreasonable since coordinating with base security on project specific requirements. Please provide specific direction on window sensors, intrusion decition, and window physical security requirements.

187 1 Part 3A

C101001

Fixed

Partitions

The RFP states to provide extreme abuse resistant gypsum wall board per

"ASTM C1629, Level III" however it doesn't state to what extent. Please confirm this applies to the 2+0

Rooms.

This applies to the 2+0 rooms also.

188 3 Part 3B 3.1.1.7

The RFP states to "PFAS contaminant impacted soil and groundwater conditions are present on the project sites." Is a report available to quantify contaminants?

The Basewide PFAS SI Report is publicly available at https://administrative-records.navfac.navy.mil/Public

_Documents/MID_ATLANTI

C/CHERRY_POINT_MCAS/

M00146_006447.pdf

189 3 Part 3B 3.1.2.1

The RFP states "Fire truck and emergency/maintenance vehicle access is provided to the site via paved

12-foot-wide lanes off E Street and D

Street. D" The minimum fire lane width is 20 feet per the Fire Protection

UFC. Please confirm new fire lanes compliant with the UFC must be provided.

Section 3.1.2.1 are existing conditions. Site Development requirements are in Section

3.2.1.2 "Provide fire department access to the new

BEQs in accordance with UFC

3-600-01 Fire Protection

Engineering for Facilities and

Cherry Point regulations.

190 14 of 15

Factor 5

Technical

Solution

Narrative

The Factor 5: Technical Solution instructions for Narrative states, "Provide a narrative not to exceed eight (8) pages that address at a minimum...:" For (1) Design

Methodology this includes nine (9) design elements; For (2) Construction

Methodology this includes three (3) construction elements; For

Management Team this includes 3 management elements, as well as an

Organization Chart and a "a brief synopsis of the names, education, training and experience of key individuals based on the proposed management structure".

We request that NAVFAC allow four

(4) additional pages for a total twelve

(12) pages for the narrative, and also that the Org Chart can be submitted on an 11x17 page and not be included in overall 12-page count.

PENDING RESPONSE

191 RFP SF1442

As of this submission, NAVFAC has not released PPI responses for any submitted PPIs to date and the

The Phase II proposal due date has been extended to 14 July

2026 NLT 2:00 P.M. EDT via proposal due date is only eight (8) working days away, with a long 3-day holiday weekend. To allow NAVFAC sufficient time to prepare and release responses for all submitted PPIs, and

Contractors sufficient time to review and implement those responses into our proposal solutions, we request an extension of the proposal due to at least three (3) weeks after receipt of all PPI responses to allow sufficient time to finalize our best technical and price solutions for the Government.

Amendment 0007. There will not be a three-week extension.

Section

G4030

Section G4030 includes a requirement for (3) 4” concrete conduits to each

EF for each new building. The work described related to OSP is extensive and will require a significant amount of phasing and coordination. The manholes were not identified and the survey plans provided seem to show more than that (8) in the limit of work area. There could also be manholes or handholes that were not captured by the survey team. The downstream facilities that will need to have service maintained were not identified, also the routing to these facilities from the connection point was not identified.

Propose per RFP.

Section

D503001

Section D503001 states that the

“layout of devices in the BEQ resident rooms must match room layouts in the

Appendices.” This layout for the data devices was not found. The quantity of outlets per room is provided but we will need to confirm this matches the referenced layout.

PENDING RESPONSE

Part 3A -

1.0

Project

Descriptio

The RFP states "4 story BEQ to house

1,440 total occupants: three buildings of (480) occupants each"

Should the three buildings be standalone buildings with respect to utilities and mechanical central plants?

Yes

Part 3A -

6.

Engineeri ng System

Requirem ents

Please confirm these requirements are for each individual building and not for the combined three buildings.

Confirmed, requirements are given per individual BEQ, unless otherwise stated in the

RFP.

Part 3A -

6.

Engineeri ng System

Requirem ents - D30

HVAC -

The RFP states to “Provide mechanical equipment rooms on each floor and, if necessary, in each wing, For mechanical rooms on each floor, provide a clear path to a freight elevator or other means to remove and replace the equipment with

Freight elevators are not required, per Part 3A, Chapter

6, ESR D10. Exterior doors will be provided for ground floor mechanical rooms, per

Part 3A, Chapter 5, Room

Requirements sheet 114 -

System

Descriptio n ease, Additionally, provide exterior access in accordance with UFC 3 401-

01 or as directed by local design guidance.” Are the buildings required to have freight elevators?

Also a 60" wide corridor is not wide enough for a DOAS unit. Should the corridors be made wider or will exterior doors be required?

Main Mechanical Room. 60" width is designated in the RFP as circulation corridor minimum, final width to be determined by DOR during design. Exterior access on upper-level mechanical rooms is still required, as per mechanical UFC.