This is a Questions and Answers (Q&A) document from NAVFAC addressing inquiries about a federal services contract solicitation. The document contains 24 numbered questions with corresponding government responses addressing clarifications on contract requirements, subcontracting opportunities, proposal submission procedures, and technical specifications.

Key clarifications include: the Government cannot anticipate subcontracting opportunities or incumbent contractor pursuit; a site visit was scheduled for July 23, 2026, with no additional industry days or networking events planned; the minimum yearly contract value for corporate experience is clarified in Amendment 0002 as $4,900,000 for recurring services; Responsibility Determination information must be submitted with the Price proposal; staffing contingencies for facility investment and pest control are required, with references to Annex 1503060 Pavement Clearance corrected to Annex 1503020 Pest Control via Amendment 0002; Emergency Services and Emergency Work requirements are specified in Annex 1700000 Spec Item 3.4-3.5 per Amendment 0004; and the RFP due date has been extended via amendments to accommodate proposal complexity. Additional key requirements include: CMMC Level 2 (Self) certification remains required at contract award; JV members must identify all CMMC Unique Identifiers (UIDs) for processing Federal Contract Information or Controlled Unclassified Information; the anticipated contract term is 12 months with performance beginning 90 days after award; questions must be submitted at least 10 days before proposal deadline per Section B.18 and L.3; contractor responsibility for all inventory items is specified in Annex 1502000; and contractors must develop pricing based on professional experience as no historical workload data is available for this new procurement.

View the file

Other files

File Type Posted
Solicitation N4008526R0033 Amendment 0009.pdf PDF
J-0200000-11 ELIN Amd 0009.xlsx XLSX spreadsheet
Solicitation N4008526R0033 Amendment 0008.pdf PDF
J-0200000-11 ELIN Amd 0008.xlsx XLSX spreadsheet
N4008526R0033 Section C Annexes Amd 0007.pdf PDF
Solicitation N4008526R0033 Amendment 0007.pdf PDF
1502000 J Facility Investment Amd 0007.pdf PDF
J-0200000-11 ELIN Amd 0007.xlsx XLSX spreadsheet
0200000 J Management and Administration Amd 0007.pdf PDF
J-1502000-04 - J-1502000-40 Facilities Investment Inventory Amd 0007.xlsx XLSX spreadsheet
1700000 J BSVE Inventory Amd 0007.xlsx XLSX spreadsheet
N4008526R0033 PPIs for Amendment 0006.pdf PDF
Solicitation N4008526R0033 Amendment 0005.pdf PDF
N4008526R0033 PPIs for Amendment 0005.pdf PDF
J-0200000-06-01 - J-0200000-06-05 Amd 0005.xlsx XLSX spreadsheet
J-1502000-04 - J-1502000-40 Facilities Investment Inventory Amd 0005.xlsx XLSX spreadsheet
N4008526R0033 Section C Annexes Amd 0004.pdf PDF
0200000 J Management and Administration.pdf PDF
Solicitation N4008526R0033 Amendment 0003.pdf PDF
RFP N4008526R0033 Site Visit Sign-in Sheet.pdf PDF
Solicitation Amendment N4008526R00330002 SF 30.pdf PDF
J-1502000-17-01 Tank Farm A Inventory.pdf PDF
J-0200000-22 CBA-2026-360.pdf PDF
J-0200000-21 PIEE Solicitation Vendor Access Instructions.pdf PDF
J-1502000-41 HERO System.pdf PDF
J-1502000-02 Historical Maintenance Spill Boil Equipment.pdf PDF
J-0200000-14 - ASSET INFORMATION.xlsx XLSX spreadsheet
J-0200000-04 INVOICE FORM.pdf PDF
1700000 J BSVE Inventory.xlsx XLSX spreadsheet
1503020 J Pest Control.pdf PDF
1602000 J Electrical.pdf PDF
J-1502000-21-03 Air Quality Inspections.pdf PDF
J-0200000-13 - SERVICE PROVIDER INFORMATION.xlsx XLSX spreadsheet
0200000 J Management and Administration.pdf PDF
J-0200000-12 FRCS Cybersecurity Program.pdf PDF
1700000 J Base Support Vehicle Equipment.pdf PDF
J-0200000-06-01 - J-0200000-06-05 Furnished Inventory.xlsx XLSX spreadsheet
J-1502000-04- J-1502000-40 Facilities Investment Inventory.xlsx XLSX spreadsheet
J-1502000-16 Lightning Arrestors and Grounding Devices Inventory.xlsx XLSX spreadsheet
J-1502000-21-04 Daily HVAC Report.xlsx XLSX spreadsheet
J-0200000-18 - CHARACTERISTIC METER READING INFORMATION.xlsx XLSX spreadsheet
J-0200000-12-01 FRCS Roles and Responsiblities.xlsx XLSX spreadsheet
N4008526R0033 SECTION F ANNEX.pdf PDF
Solicitation - N4008526R0033.pdf PDF
1502000 J Facility Investment.pdf PDF
J-0200000-03-01 Destructive Weather Operations.pdf PDF
J-0200000-11 ELINs.xlsx XLSX spreadsheet
1602000 J Electrical Inventory.xlsx XLSX spreadsheet
J-0200000-15 - ASSET SPECIFICATION.xlsx XLSX spreadsheet
N4008526R0033 Section C Annexes.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question No. Question Government Response Page Section Paragraph

1 Does NAVFAC anticipate transportation, vehicle operations, material handling, or logistics functions being subcontracted under this contract?

The Government cannot anticipate what services, if any, a contractor will subcontract.

2 Is the current BOS contractor expected to pursue the follow-on contract, and if so, are subcontracting opportunities anticipated for qualified small businesses?

The Government cannot anticipate if the incumbent will pursue this RFP and cannot anticipate what subcontracting opportunities may exist.

3 L L.6 Will there be an Industry Day, pre-proposal conference, or networking opportunity for interested subcontractors and teaming partners?

A site visit was scheduled for July23, 2026, via Amendment 0001. There are no plans for any other meetings/events of this type.

4 Are there additional transportation or logistics-related requirements at MCAS Laurel Bay or Townsend Bombing Range to monitor for future opportunities?

We cannot anticipate the needs of MCAS Laurel Bay or Townsend Bombing Range.

5 2 J Annex, J-0200000-19

In Section L, Factor 2, Corporate Experience, the Solicitation states, "Size: A contract with a yearly value of at least $5,000,000 for recurring services." However, page 2 of the Corporate Experience Data Sheet states, "7. The Relevancy Size requirement for this solicitation is a contract with a yearly value of at least $4,900,000 for recurring services." Will the Government please clarify the minimum yearly value for recurring services required for contracts submitted under Corporate Experience?

See Amendment 0002, revised Corporate Experience Data Sheet.

6 Does the Government want the Responsibility Determination information in the same file as the Price document or in a separate file entirely?

The information is required to be submitted with the Price proposal.

7 7 of 17 and

M In the following, the Solicitation asks for staffing contingencies during surges to provide services in Annex 1502000 Facility Investment, Annex 1503060 Pavement Clearance, and 1700000 BSVE.

Annex 1503060 Pavement Clearance is not noted in this Solicitation. Please verify and confirm.

Section M is revised, see Amendment 0002.

8 C Annex 1700000, Spec

Item 3.4

Emergency Services - Please identify the contractor's limit of liability for Emergency Service.

See Amendment 0004 and Annex 1700000, Spec Item 3.4.

Reference

9 C Annex 1700000, Spec

Item 3.4

Emergency Services - Please provide the historical annual workload for Emergency Services so the offeror can accurately price the requirement.

This is a new procurement with no available historical workload data.

Offerors shall develop their price proposal based on their professional experience and the requirements detailed in PWS Annex 1700000, Spec Item 3.4.

10 C Annex 1700000, Spec

Item 3.5

Emergency Work - Please identify the contractor's limit of liability for Emergency Work.

See Amendment 0004 and Annex 1700000, Spec Item 3.4.

11 C Annex 1700000, Spec

Item 3.5

Emergency Work - Please provide the historical annual workload for Emergency Work so the offeror can accurately price the requirement.

This is a new procurement with no available historical workload data.

Offerors shall develop their price proposal based on their professional experience and the requirements detailed in PWS Annex 1700000, Spec Item 3.5.

12 7 of 17 and

M Please confirm whether this reference is intentional. If Annex 1503060 is not applicable to this procurement, will the Government revise the solicitation accordingly?

This has been corrected to remove reference to Annex 1503060 Pavement Clearance and include reference to Annex 1503020 Pest Control. See Section M of Amendment 0002.

13 Given the scope and complexity of the solicitation, as well as the recent amendment and pending site visit, would the Government consider extending the proposal due date to 11 August 2026?

The RFP has been extended, see amendments.

14 J Annex, J-1502000-11

Attachment J-1502000-11:

Please identify which items in the attachment require seasonal start-up and shut-down.

This is a Performance-Based Service Contract. The Government does not provide a prescriptive list identifying which specific items in Attachment J-1502000-11 require seasonal start-up and shut-down.

The Contractor is solely responsible for operating and maintaining all heating systems to meet the seasonal temperature and operational readiness requirements specified throughout the Performance Work Statement (PWS). The Contractor shall use its professional expertise to determine which specific boilers and associated equipment must be seasonally started-up or shut-down to ensure all performance objectives are met.

15 5 of 70 and

B,B.18 and L, L.3

Will the government allow additional questions to be submitted via email after the 23 July 2026 site visit?

Questions should be submitted at least 10 days before proposals are due, Section B, B.18 and Section L, L.3.

16 RFIs are due before the site visit, will the government extend the due date for RFIs to provide Offerors time to submit additional questions? Also would the government consider extending the proposal due date 2 weeks since the due date is two business days after the site visit.

The RFP due date has been changed, see amendments.

Section F.2 states performance begins 90 days after award.

Section B.15 warns the base period may be less than one year. - Considering that some aspects of this contract require items of a fixed cost nature, will NAVFAC confirm whether the base period will be a full 12 months?

The contract term is anticipated to be 12 months, though this remains subject to final confirmation which NAVFAC cannot provide at this time.

18 C, E, F, and H FAR 52.246-4 (Deviations 2026-00035) Inspection of Services - Fixed Price, section E. please define the scope and scale of the inspections. What mitigation methods will be in place before this clause is used?

See Section C, E, F and H.

Also, the contractor is required to submit a Quality Management Plan, see Section C, Annex 0200000.

19 4 of 70 B, B12 Section F.2 provides a 90-day phase-in period. A successful Phase-In where the contractor does not start the program financially burdened is the hallmark to a successful long-term program. Since there is no phase-in specific CLIN, and the Base period has the potential to be shorter than a full year (Per B.15), what guarantees are there for the offeror to be able to recover their full Phase-In Costs? Will NAVFAC include a CLIN for Phase-In?

See Section B, B12. No separate Phase-In Costs ELIN will be included.

20 C Annex, 0200000, Spec Item 2.4

Responsibility for Missing, Damaged, or Unserviceable GFIs - The tool room inventory includes items with QTY HI/QTY LO, implying shortages. If GFIs are missing, damaged, or below minimum quantities, is the contractor responsible for replenishment, or will NAVFAC restore GFI inventories to the listed quantities at NTP?

See 1502000 Inventory, all items are the responsibility of the contractor. See Annex 0200000, Spec Item 2.4.

21 I In the solicitation it states that the CMMC Level required for this bid in CMMC Level 2 (Self). Is this still the case with the temporary hold and review the government is doing concerning CMMC.

CMMC Level 2 (Self) is still applicable.

22 I If a bidder is a Mentor Protege JV, do both parties within the JV have to be CMMC Level 2 self-certified? Or does only the managing member of the JV need to be CMMC Level 2 self-certified?

Offerors, including JVs, must identify all CMMC Unique Identifiers (UIDs) in their proposal that will be used to process, store, or transmit Federal Contract Information (FCI) or Controlled Unclassified Information (CUI) during contract performance. All processing, storing, or transmitting of FCI and CUI must be limited to the CMMC UIDs identified in the proposal.

The identified CMMC UIDs may apply to individual JV members or to the JV itself, if the JV operates using systems and networks that serve multiple members. In either case, the CMMC UIDs must represent the scope of the systems and networks used during contract performance.

23 I If both members of a JV are required to have CMMC Level 2 (Self), and one is not, can the firm that is not at CMMC Level 2 (self) submit a Plan of Action and Milestones (POAM) in place of its Level 2 (Self)

CMMC UID?

CMMC level stated in the RFP must be available at time of contract award.

24 I It states in DFARS 252.204- 7025 that the appropriate CMMC level is required prior to award. That said, if we are not at Level 2 (self) at time of proposal submittal but instead provide a POAM showing the path to Level 2 (Self) prior to award, is that acceptable?

CMMC level stated in the RFP must be available at time of contract award.