ATTACHMENT D REVISED - Price Proposal Form.docx

DOCX document 37 KB Posted

Attached to
P325 HUMAN PERFORMANCE TRAINING CENTER
Solicitation number
N4008525R2563
Issued by

About this file

This document is a Price Proposal Form for the P325 Human Performance Training Center project, issued by the Department of the Navy Naval Facilities Engineering Command. The solicitation is restricted to Multiple Award Construction Contract (MACC) holders and includes a base price and seven optional line items covering various aspects of the project, such as design, construction, sitework, foundation piling, asbestos removal, turf field, site lighting, building demolition, parking lot, electronic security systems, audio-visual equipment, and furniture, fixtures, and equipment (FF&E).

The pricing structure allows bidders to provide unit prices for specific line items, with a total bid encompassing the base price and optional items. The government reserves the right to award optional line items within 60 calendar days after contract award, with the total proposed price for all line items serving as the basis for evaluation. Bidders can propose a Handling and Administration Rate (HAR) up to 5% for electronic security systems, FF&E, and audio-visual equipment, which will be a fixed rate applied to vendor/supplier costs. The estimated government price for FF&E is $3,307,966, with additional estimated prices for electronic security systems ($182,486.44) and audio-visual equipment ($529,240.85).

View the file

Other files

Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICE SCHEDULE

Provide line item prices, where indicated by blank underlines, for the following items:

Line Item
Description
Quantity
Unit
Unit Price
Sub-Total
Total Price
0001
BASE PRICE: Total Price for sub line items 0001A-0001E, the entire work for Project P325 – Human Performance Training Center in accordance with the RFP, complete, but excluding work provided in another Priced line Item.
1
EA
0001A
Subtotal of Base Price for the entire work for P325 - Human Performance Training Center complete to the 5-foot line outside of the building in accordance with the RFP, but excluding work provided in another line item
1
EA
0001B
Subtotal of Base Price for the entire project sitework, outside the facility 5-foot line, for P325 - Human Performance Training Center complete in accordance with the RFP, but excluding work described in another line Item.
1
EA
0001C
Subtotal of Base Price for entire Design of the Project, complete, but excluding work provided in another line item, and excluding the Design associated with Option Item No. 1, Option Item No. 2, Option Item No. 3, and Option Item No. 4.
1
EA
0001D
Unit Price for providing Foundation Piling complete in accordance with the RFP, but excluding work provided in another line item.
24,000
LF
$_____
$_____
0001E
Unit Price for removal and disposal of asbestos containing floor tile complete in accordance with the RFP, but excluding work provided in another line item.
4,500
SF
$_____
$_____
0002
Option Item No. 1: Price for providing all work in connection with design and demolish of the existing turf field, and construction of the playing field complete in accordance with the RFP, but excluding work provided in another Priced line item.
1
EA
0003
Option Item No.2: Price for providing all work (Design and Construction) in connection Site Lighting at the turf field complete in accordance with the RFP, but excluding work provided in another Priced line item. If CLIN 0002, Option Item No. 1 is not awarded, then CLIN 0003, Bid Item No. will not be awarded.
1
EA
0004
Option Item No.3: Price for providing all work (design and construction) in connection with demolition of Bldg 3812 complete in accordance with the RFP, but excluding work provided in another Priced line item.
1
EA
0005
Option Item No.4: Price for providing all work (design and construction) in connection with the parking lot complete in accordance with the RFP, but excluding work provided in another Priced line item.
1
EA
0006
Option Item No. 5: Price for providing Electronic Security System (ESS) equipment, testing, and associated training, but excluding work provided in another Priced line item. The ESS includes, but is not limited to, Intrusion Detection System (IDS), Access Control System (ACS), and Video Systems complete in accordance with the RFP. Equipment includes items such as Premise Control Units (PCU), central processing units, field panels, sensors, card readers, keypads, cameras, switches, video recorders, workstations, and the communication cabling connecting these devices together.

Include the price for supporting, permanent infrastructure under the Base Price. Interior supporting infrastructure includes items such as conduit, junction boxes, electronic door strikes, door-hardware, mounting hardware, and power connections. Exterior supporting infrastructure includes items such as exterior duct banks, manholes, utility poles, utility connections, and power connections.

$182,486.44
HAR Percent (NTE 5%)

HAR Subtotal Total FF&E Estimated Price

0007
Option Item No. 6: Price for providing Audio Visual System (A/V) Equipment, testing, and associated training in accordance with the RFP, but excluding work provided in another Priced line item. Equipment includes, but is not limited to, items such as flat panel monitors, projectors, wall input boxes, touch screens, push button control panels, video teleconferencing codecs, microphones, speakers and the communication cabling connecting these devices together.

Include the price for supporting, permanent infrastructure under the Base Price. Interior supporting infrastructure includes items such as conduit, junction boxes, mounting hardware, and power connections.

$529,240.85
HAR Percent (NTE 5%)

HAR Subtotal Total FF&E Estimated Price

0008
Option Item No. 7: Price for providing work in connection with labor, material, equipment, transportation and supervision required for the Furniture, Fixtures, and Equipment (FF&E), complete in accordance with the [drawings and specifications][RFP], but excluding work provided in another Priced line item.
Government Estimated Price:

$3,307,966 HAR Percent (NTE 5%)

HAR Subtotal Total FF&E Estimated Price

Total for base bid and all options
$_____

GENERAL BID NOTES

a. Award will be made on the total proposed price for Line Items 0001-0008; Base Price and the sum of all Options.

b. The Government reserves the unilateral right to award Line Items 0002-0005 to the Contractor at the proposed price within 60 calendar days after the contract award, and in accordance with all bid notes.

c. Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR 17.206 (b) not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for the Option(s), Line Items 0002 -0008 to the total price for the Base Bid, Line Item 0001. Evaluation of options will not obligate the Government to exercise the Option(s). (FAR 52.217-5).

d. In accordance with FAR 52.217-7; Option for Increased Quantity-Separately Priced Line Item (Mar 1989), the Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

e. The Government may reject an offer as non-responsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.

f. Failure to enter a price for any Line Item will result in a proposal being rejected.

g. If Line Items 0002-0008 are exercised, additional bonding and consent of surety is required. Consequently, the Performance Bond must reflect 100 percent of the aggregate amount of all items.

BID NOTES FOR ESS, FF&E and A/V (Line items 0006-0008)

a. The estimated amount for ESS, FF&E, and A/V has been supplied by the Government, to provide Offerors with the projected magnitude of effort. The estimated amount includes the actual cost of the ESS, FF&E and A/V including freight and installation charges. The Government ESS, FF&E and A/V Estimate is only an estimated amount.

b. If awarded, line items will be funded separately after completion of ESS, FF&E, and A/V design package review by the Government, and receipt of appropriate funding by the Government. Requirements and details are provided in D503005 SECURITY SYSTEMS, E20, FURNISHINGS and E10, EQUIPMENT.

c. Bonding,

1. Bonding is not required for the design, procurement and installation of ESS, FF&E and A/V equipment at time of Construction Contract Award.

FAR 28.102-1(a) requires that performance and payment bonds be included in all construction contracts exceeding the SAT, except under the conditions listed. Since the ESS, FF&E Option Item is not part of the original contract award, the Construction Contractor must not be required to secure bond for the FF&E at the time the basic contract is awarded.

2. Additional Bond at FF&E Option Item Award FAR 28.102-2(d) requires the Government to secure additional bond from the Construction Contractor for any contract price increases. Therefore, an increase to the original contract bond is required at the time of the FF&E Option Item award, to protect the Government against the Construction Contractor not providing FF&E ordered and to ensure that the FF&E vendor(s) receive payment if the Construction Contractor goes out of business. The increased cost of the bond must come from the FF&E funding source and is not a part of the Construction Contractor’s HAR.

3. Bonds Required by the Construction Contractor If the Construction Contractor requires bonding from the FF&E subcontractor(s), the cost must be covered in the Construction Contractor’s HAR.

d. Offerors may propose a Handling and Administration Rate (HAR) for the ESS, FF&E and A/V not to exceed 5 percent. This fee will account for all administrative costs, overhead, bonding fees, administration of subcontracts, profit, and any other costs associated with and related to the coordination and processing of the procurement and installation of ESS, FF&E, and A/V. The proposed HAR percentage will be incorporated into the contract award and will not be adjusted regardless of fluctuations from the estimate amount for the ESS, FF&E and A/V. The proposed HAR is a fixed rate.

e. The Government is not obligated to award the Option line item(s) 0006-0008. Should the Government choose to award the ESS, FFE and AV, the line item will be awarded as a negotiated option to the contract/task order. The Contractor's proposed HAR will be applied to all vendor/supplier costs for the ESS, FF&E and AV.

f. If awarded, the ESS, FF&E and AV modification will be awarded at least six months prior to the contract completion date. A minimum of six months is required for the Contractor to purchase, deliver and install the ESS, FF&E and AV without impacting the overall completion date of the project. The Contractor's schedule must assume the award of the ESS, FF&E and AV as an option. No schedule extensions will be granted if the option is awarded at least six months prior to the contract completion date. If the Government decides to negotiate and award the furniture modification with less than six months prior to the contact completion date, the Contractor may be entitled to a contract extension and extended field overhead. A contract extension and extended field overhead will only be granted in those cases where the Contractor demonstrates that an accepted Final ESS, FF&E and AV packages were submitted within the approved schedule deadlines and sufficient lead time for the ESS, FF&E and AV is not available and the Government's award of the option is in the last six months of the contract.

Attachment D Page 5 of 5

File details come from the government source that posted it. Updated .