This is a Request for Proposals (RFP) from Naval Facilities Engineering Command Mid-Atlantic for a Design-Build project to construct a new two-story, 40,000 GSF Human Performance Training Center at JEB Little Creek-Fort Story in Virginia Beach, VA. The project includes demolition of three buildings (3812, 3855A, and 3855D) totaling 27,900 SF and construction of a new facility with CMU construction, pile foundation, single-ply roof, and built-in equipment including a passenger/freight elevator. The facility will support Naval Special Warfare with sports medicine, injury prevention, rehabilitation, testing and evaluation, strength conditioning, nutrition, research and development, and sports psychology services.

The solicitation (N4008525R2563) is restricted to eight specific MACC holders under contract numbers N4008521D0079-0086. The estimated price range is $25-100 million with a completion time of 859 calendar days from award. Proposals are due April 22, 2025 at 2:00 PM ET and must be submitted electronically via PIEE. Award will be made on a Lowest Price Technically Acceptable (LPTA) basis, with technical factors and past performance being approximately equal to price in importance. A site visit is scheduled for March 20, 2025 at 10:00 AM. Liquidated damages are set at $3,992 per calendar day of delay. The project requires adherence to DoD sustainable building requirements and includes Low Impact Development features.

View the file

Other files

Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NAVAL FACILITIES ENGINEERING COMMAND, MID-ATLANTIC

9324 VIRGINIA AVE, BLDG Z-140

NAVAL STATION NORFOLK, NORFOLK, VA 23511

POC: Angie Clifton, 757-341-0692, angela.j.clifton2.civ@us.navy.mil

INDEFINITE-DELIVERY/INDEFINITE QUANTITY (IDIQ) MULTIPLE AWARD

CONSTRUCTION CONTRACT (MACC) FOR LARGE GENERAL CONSTRUCTION

PROJECTS PRIMARILY IN THE HAMPTON ROADS AREA OF RESPONSIBILITY (HR

AOR), VIRGINIA

SOLICITION NUMBER:

N40085-25-R-2563

P325 HUMAN PERFORMANCE TRAINING CENTER, JEB LITTLE CREEK-FORT STORY,

VIRGINIA BEACH, VIRGINIA

DATE OF SOLICITATION:

05 March 2025

HR LP MACC CONTRACT HOLDERS:

N4008521D0079

AMERESCO

4006 Victory Blvd, Suite J909 Portsmouth, VA 23701 POC: Nicole Bulgarino Email: nbulgarino@ameresco.com;

Emily.chapin@ameresco.com

N4008521D0080 Harkins 10490 Little Patuxent Parkway, Suite 400 Columbia, MD21044 POC: Ben Nichols Email: bnichols@harkinsbuilders.com;

ekrick@harkinsbuilders.com; rtirocchi@harkinsbuilders.com

N4008521D0081 RQ Construction, LLC 1620 Faraday Ave Carlsbad, CA 92008 POC: Travis Nichols, George Rogers Email: TNichols@rqconstruction.com;

GRogers@rqconstruction.com

N4008521D0082 Sauer 9728 Florida Mining Blvd. W, Suite Jacksonville, FL 32257 POC: Gary Weeks Email: sauerjaxestimating@sauer-inc.com; kalvers@sauer-inc.com

N4008521D0083 SB Ballard 2828 Shipps Corner Rd Virginia Beach, VA 23453 POC: Candy Hennig Email: chennig@sbballard.com

N4008521D0084 Walsh 929 West Adams St Chicago, IL 60607 POC: Brian McGinty, Anthony DeCarlo Email: adecarlo@walshgroup.com;

bmcginty@walshgroup.com

N4008521D0085 Whiting Turner 6305 Ivy Lane, Suite 800 Greenbelt, MD 20770 POC: Sam Abutaleb, Nathan Leonard Email: sam.abutaleb@whiting-turner.com;

nathan.leonard@whiting-turner.com;

tara.schlichtig@whiting-turner.com;

michael.thomas@whiting-turner.com

N4008521D0086 WM Jordan 11010 Jefferson Avenue Newport News, VA 23601 POC: Michael Daniels Email: mdaniels@wmjordan.com;

estimating@wmjordan.com

P-325 Human Performance Training Center Solicitation N4008525R2563 JEB Little Creek-Fort Story, Virginia Beach, VA Work Order 1602585

General Requirements

All terms and conditions of N40085-21-D-0079/0080/0081/0082/0083/0084/0085/0086 Indefinite Delivery Quantity Contract apply to this solicitation. Please review your MACC award document for guidance on contract clauses and requirements that may pertain to this order. All contract clauses in the Basic Contract by reference or full text remain in effect unless superseded by this task order. You are responsible to adhere to all applicable clauses, even if they are not stated in this RFP package or the Task Order award document. For clarification on any clause or other contractual issues, please contact Angie Clifton at angela.j.clifton2.civ@us.navy.mil.

Amendments will be posted to PIEE, SAM.gov, and sent directly to MACC Holders. It is ultimately the responsibility of MACC Holders to monitor SAM.gov for any updates.

NAVFAC Solicitation No.: N4008525R2563

NAVFAC Specification/Drawings: WON 1602585

Title: P-325 Human Performance Training Center, JEB Little Creek-Fort Story

Location of the Work: Virginia Beach, VA

Description of the Work:

The P-325 Human Performance Training Center project aboard JEB Little Creek-Fort Story, Virginia Beach, VA is a Design-Build project that is for the design/construction of a new two-story, 40,000 GSF Human Performance Training Center to support Naval Special Warfare. It includes demolition of three buildings 3812, 3855A, and 3855D, approximately 27,900 SF. The facility co-locates sports medicine and human performance and will support special operator injury prevention, rehabilitation, testing and evaluation, strength and conditioning, nutrition, research and development, and sports psychology.

Construction consists of Concrete Masonry Unit (CMU) with a pile foundation, slab on grade and a single ply roof. Special costs include conduit for Physical Security Equipment (PSE). Built-in equipment includes a passenger/freight elevator. This project includes all pertinent site preparations and site improvements, mechanical and electrical utilities, telecommunications, emergency generator, landscaping, irrigation, drainage, parking and exterior lighting. Department of Defense principles for high performance and sustainable building requirements will be included in the design and construction of the project in accordance with federal laws and Executive Orders. Low Impact Development features will be included in the design and construction of this project as appropriate.

Estimated Price Range: In accordance with DFARS 236.204(ii), Disclosure of the Magnitude of Construction Projects, the estimated price range for this project is between $25,000,000 and $100,000,000.

Time for Completion: In accordance with FAR 52.211-10 Commencement, Prosecution, and Completion of Work, the deadline for completion of this task order (including Bid Options) shall be 859 calendar days from date of award (includes 15 calendar days for submission and approval of bonds and insurance). Consistent with FAR 52.211-10, completion of the entire work ready for use must occur prior to the aforementioned date. The time stated for completion shall include final cleanup of the premises.

Wage Determination: Department of Labor (DoL) General Decision Number VA20250167 applies to this work (Attachment B). The wage determination version in effect at the time of award shall apply to the work performed under this contract.

JEB Little Creek-Fort Story, Virginia Beach, VA Work Order 1602585

Liquidated Damages: In accordance with FAR 52.211-12 Liquidated Damages, if the Contractor fails to complete the work within the time specified in the task order, the Contractor shall pay liquidated damages to the Government for each calendar day of delay until the work is completed or accepted. See associated liquidated damages per phase below:

Phase Number of Days Liquidated Damages

Base Bid + Bid Options 1-7 859 calendar days after award $3,992 per calendar day

Utilities: The Contractor shall be responsible for obtaining all utilities required for construction and testing. The Contractor shall provide these utilities at his expense, paid for at the current utility rate delivered to the job site. The Contractor shall provide and maintain all temporary utility connections and distribution lines, and all meters required to measure the amount of each utility used.

Record Shop Drawings: In accordance with FAR 52.236-21 Specifications and Drawings for Construction, record shop drawings are required. Reproducible copies of these record drawings are required to be provided to the Government as deliverables under the task order.

Bond Requirements: In accordance with FAR 52.228-1, Bid Guarantees, each offeror shall submit with its offer a guarantee bond (Standard Form 24) in a penal sum equal to at least 20 percent of the offer price or $3,000,000, whichever is less.

Performance and Payment Bonds are required from the contract task order awardee no later than ten (10) calendar days after date of award.

Proposal Acceptance Period: Proposal acceptance period shall be 120 calendar days from the deadline for receipt of offers.

Definitization Of Equitable Adjustments for Change Orders Under Construction Contracts: No data is available regarding the timely definitization of equitable adjustments for change orders under construction contracts. The REA definitization information referenced in Navy Marine Corps Acquisition Regulation Supplement (NMCARS) 5236.211(b)(2), should not be utilized. There are no agency-specific policies and procedures that apply to the definitization of equitable adjustments for change orders under construction contracts. This Contract contains rated order quantities certified for national defense use, and you are required to follow all the provisions of the DPAS regulation (DPAS Regulation - 15 CFR Part 700.12) only as it pertains to the rated quantities.

Pre-Proposal Inquiries (PPIs): Offerors who determine that the technical and or contractual requirements of this RFP require clarification(s) in order to permit submittal of a responsive proposal shall submit all questions in writing. All inquiries shall be submitted via email to Angie Clifton at angela.j.clifton2.civ@us.navy.mil no later than ten (10) calendar days prior to proposal due date.

Additionally, all inquiries shall be submitted using the Pre-Proposal Inquiry (PPI) form (Attachment C).

Do not submit the same inquiry more than once. Please verify that inquiries submitted by you on behalf of your subcontractors are not duplicates. A response will be published via an amendment by email to MACC holders.

Site Visit: All MACC holders are invited to attend the Site Visit for the project. Firms participating in the site visit will not be directly compensated for their participation.

JEB Little Creek-Fort Story, Virginia Beach, VA Work Order 1602585

Date: Thursday, 20 March, 2025 Time: 1000 Meeting Location: 1300 Helicopter Drive Virginia Beach, VA 23459 Building B3854

Parking is available at the meeting location.

All participants must meet outside the main entrance to Building B3854 on time. We will walk to the site from Building B3854. Late arrival of participants will not be able to participate as the buildings are secured and additional personnel will not be available to escort to the reminder of the group.

THE FOLLOWING NEEDS TO BE COMPLETED FOR ALL ATTENDEES THAT NEED BASE

ACCESS:

CONTRACTOR ACCESS:

1. All Base Access requests must be submitted through the Little Creek Access email address at NAVFACML_PWDLittleCreek-Access@navy.mil. Additionally, Cc Angie Clifton @ angela.j.clifton2.civ@us.navy.mil. It is the responsibility of the Prime Contractor to submit requests. Review all documents yourself for accuracy prior to sending to our office for processing. Complete all information to ensure your forms are processed. REQUESTS ARE

DUE BY TUESDAY, 11 MARCH 2025 @ 1200 ET.

2. The SECNAV 5512 form (Attachment H) and One Day Pass (ODP) excel spreadsheet (Attachment I) must be completely filled out and submitted to the email addresses above.

a. SECNAV 5512 must be completely filled out. An incomplete form will result in the form being rejected and returned for resubmission. Please label your forms last name, first name (ONLY) when submitting; a separate document must be submitted for each individual.

b. The ODP spreadsheet should have all highlighted columns completed. The company name is how you will be listed on the CNIC website. Please list your individuals in alphabetical order on your spreadsheet. Label your spreadsheet as ODP – <Company Name>

c. Sponsor will be the Construction Manager, Thomas Witherspoon, thomas.l.witherspoon3.civ@us.navy.mil, 757-462-1022, for the project.

2. On the email subject line put “ONE DAY PASS”, in the body of the email please state the company name, Title of Project, Solicitation number, and the start /end dates for requested access. Please list your start and end date as the date of the site visit.

3. If someone is denied clearance, the procurement technician (PT) will be notified and an email with the findings will be sent to you. For follow-up or questions, please contact NAVFACML_PWDLittleCreek-Access@navy.mil. Please check the below CNIC website for approval / clearance before sending an inquiry email. NOTE: Website is updated by the Regional Office as individuals are cleared.

https://www.cnic.navy.mil/regions/cnrma/om/contractor_verification_system.html

JEB Little Creek-Fort Story, Virginia Beach, VA Work Order 1602585

4. After receiving clearance, direct individuals to the Pass and ID office with the proper identification (two forms of ID and a copy of the SECNAV 5512). For vehicles, please make sure you have your vehicle registration and proof of insurance.

Contractors ARE NOT ALLOWED to use any cameras, tape recorders, or other recording devices during the site visit unless approved by appropriate NAVFAC personnel.

Please see additional information regarding the site visit:

All firms wishing to attend the site visit MUST email Angie Clifton at angela.j.clifton2.civ@us.navy.mil a list of names with their associated companies that will attend the site visit.

Each attendee is required to wear protective safety shoes (steel toe) and safety vests. Attendees must supply their own PPE.

A briefing of the camera policy will occur at the site. No cameras with Bluetooth or Internet connectivity are allowed. Only cameras that will be allowed are standard digital cameras with no wireless connectivity.

Site Visit POCs:

Sam Russo: (email) samuel.v.russo5.civ@us.navy.mil; (phone) 757-341-2056 Tennille Wade: (email) tennille.b.wade.civ@us.navy.mil; (phone) 757-341-2055 Angie Clifton: (email) angela.j.clifton2.civ@us.navy.mil; (phone) 757-341-0692 Thomas Witherspoon: (email) thomas.l.witherspoon3.civ@us.navy.mil; (phone) 757-462-1022

Proposal Due Date: Tuesday, 22 April 2025 at 02:00PM ET. LATE PROPOSALS WILL BE HANDLED IN ACCORDANCE WITH FAR 15.208(b).

Proposal Submission Instructions: In response to this request for proposal, the complete proposal shall include the Price Proposal and the Non-Price Factors Proposal, submitted in accordance with the Basis of Evaluation and Submittal Requirements for Each Factor. The Offeror shall submit an electronic copy of the proposal in accordance with the instructions below by the proposal due date.

Electronic Copies: Only The Procurement Integrated Enterprise Environment (PIEE) Solicitation Module is authorized for the submission of electronic proposals (.pdf format) in response to this solicitation. Electronic proposal submissions should be no larger than 1.9 GB per file. Offerors shall ensure that the Government has received the electronic proposal prior to the date and time specified. PIEE Solicitation Vendor Access Instructions are provided via Attachment E. Emailed, mailed and hand-delivered submissions will not be accepted.

Offerors shall allow adequate time to upload files which may be slower for non-DoD users and to avoid other technical difficulties that may be encountered. Offerors are also responsible for submitting files in the format specified and consistent with requirements stated elsewhere in this solicitation. Files that cannot be opened, or are otherwise missing the required content are the responsibility of the Offeror.

The PIEE system will record the date and time of package receipt. Upon successful receipt of the proposal through PIEE, the Offeror should receive an email confirmation. Please keep this for your records. The date and time of package receipt recorded in PIEE shall govern the timeliness of any proposal submission.

Late responses will be handled in accordance with FAR 15.208(b).

Basis for Award: This task order will be awarded on a fair opportunity basis pursuant to FAR 16.505 ordering procedures. The proposed task order will be awarded to the responsible offeror, offering the best

JEB Little Creek-Fort Story, Virginia Beach, VA Work Order 1602585 value to the Government. For this task order, to make a determination of best value, tradeoff selection procedures are selected. The relative order of importance of the non-cost/price evaluation factors is the technical factor (Factor 1 – Technical Solutions) is of equal importance to the performance confidence assessment (Factor 2 – Past Performance). The combined non-cost/price factors are approximately equal to price.

Evaluation Factors for Award

The Proposed Task/Delivery Order will be awarded to the responsible offeror offering the lowest price technically acceptable (LPTA) to the Government.

Factor 1 – Technical Solutions Factor 2 – Past Performance

An overall non-price factors rating must be at least “ACCEPTABLE” in order to be eligible for award.

An “UNACCEPTABLE” rating in any factor results in the overall non-price factors proposal being rated “UNACCEPTABLE” unless corrected through discussions.

Non-cost/Price Evaluation Factors

The offeror shall submit one (1) original, marked “Original”, via PIEE of the solicitation submittal requirements identified below. All submissions shall include the following:

Cover page with solicitation number, solicitation title, offeror name, address, phone number, fax number, Unique Entity Identifier in SAM, Cage Code, Point of Contact (POC), POC phone number, and POC email address

Price information contained in the non-price/technical proposal will not be considered. Likewise, non-price/technical information contained in the price proposal will not be considered

Factor 1 – Technical Solution:

(i) Solicitation Submittal Requirements:

a) The Offeror shall provide a “Technical Approach Narrative” describing the technical solution to the project that meets the requirements of the RFP and that demonstrates the Offeror's ability to successfully perform this project in Joint Expeditionary Base (JEB) Little Creek, Virginia Beach, VA.

The narrative shall address major elements of work and demonstrate understanding of the scope, all phases and major milestones, technical complexities, and construction schedule required to achieve the work as identified in the solicitation. Identify activities that may affect the project timeline, including other/off site work activities. In addition, the plan shall address the following technical complexities:

1. Provide narrative discussing overall management and coordination of simultaneous construction activities with multiple disciplines.

2. Provide narrative addressing construction strategy for working in a confined site.

3. Provide narrative strategy in avoiding project schedule slippage due to material/equipment procurement or delivery delays.

JEB Little Creek-Fort Story, Virginia Beach, VA Work Order 1602585

b) Provide a “Labor Force Narrative” describing how the needed skilled labor forces will be provided and maintained throughout the duration of this construction contract for all labor forces at Joint Expeditionary Base Little Creek, Virginia Beach, VA. The narrative shall address at a minimum:

1. Securing the required non-skilled workforce/skilled work force to work the project and maintaining the workforce as needed.

2. Design Team, including a Human Performance Center / Gymnasium equipment Subject Matter Expert (SME). The SME shall have a minimum of five years of experience in equipment layouts for similar size and type of facilities. SME’s responsibilities shall include:

a. Provide appropriate equipment layouts on floor plans for optimal workout and traffic flow including required spacing around equipment for safe, effective use.

b. Provide location and layout of Electrical infrastructure for equipment. Review placement of TV monitors and equipment for optimal ergonomics, user comfort, and viewing.

c. Provide 3D visualization images of the facility.

3. Construction subcontractors (civil, structural, mechanical, and electrical) and their ability to provide skilled labor.

Both the Technical Approach Narrative and the Labor Force Narrative shall not exceed eight (8) single-sided pages combined. Up to four (4) drawings on separate sheets or separate PDF files can be provided to supplement the narratives and will not count towards the page limit.

c) Provide an overall Critical Path Method (CPM) schedule showing the timeline of the proposed designs and construction. There are no page restrictions on the CPM schedule.

(ii) Basis of Evaluation:

The Offerors will be evaluated to determine whether they demonstrate both a clear understanding of the requirements of the RFP and a realistic plan for performing the necessary work within the permitted time period. An Offeror whose schedule fails to propose a realistic and feasible contract duration compliant with the RFP may be rated unacceptable.

The basis of evaluation will also include a determination as to whether the Offeror’s narratives and CPM schedule demonstrate a realistic plan for handling the complexity of the actual construction work. The assessment of the Offeror’s narrative and CPM schedule will be used as a means of evaluating the capability of the Offeror to successfully meet the requirements of the RFP.

NOTE: If a realistic contract duration is proposed that is shorter than specified in the RFP, the proposed duration will be incorporated into any resultant contract.

Factor 2 – Past Performance:

(i) Solicitation Submittal Requirements:

Offerors do not need to provide any information under this factor as the Government will base the evaluation on known past performance on task orders awarded under this Multiple Award Construction Contract (MACC). However, Offerors may provide any information on problems encountered and the corrective actions taken on task orders under this MACC. Offerors may also address any adverse past

JEB Little Creek-Fort Story, Virginia Beach, VA Work Order 1602585 performance issues under this MACC. Explanations shall not exceed two (2) double-sided pages (or four

(4) single-sided pages) in total.

(ii) Basis of Evaluation:

This evaluation focuses on how well the Offeror performed on projects under this Multiple Award Construction Contract. More emphasis will be placed on task orders that are more similar to the RFP. The Government reserves the right to obtain information for use in the evaluation of past performance other than projects performed under this Multiple Award Construction Contract from any and all sources including sources outside of the Government. Other sources may include, but are not limited to, past performance information retrieved through the Contractor Performance Assessment Rating System (CPARS), inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.

The Government will consider the currency and relevance of the information, the source of the information, context of the data, and general trends in the Contractor’s performance. This evaluation is separate and distinct from the Contracting Officer’s responsibility determination. The assessment of the Offeror’s past performance will be used as a means of evaluating the Offeror’s ability to successfully meet the requirements of the RFP.

Offerors lacking past performance information on other task orders under this Multiple Award Construction Contract will not be evaluated favorably or unfavorably in past performance and will receive a Neutral Confidence rating, which equates to an Acceptable rating in this LPTA procurement.

Price

i) Solicitation Submittal Requirements:

Price shall be submitted on the Price Proposal Form included in the solicitation. The offeror shall submit one (1) electronic original, with the following:

Cover page with solicitation number, solicitation title, offeror name, address, phone number, Employer Identification Number (EIN),Unique Entity Identifier (UEI) in SAM, CAGE code, Federal Tax ID number, Point of Contact (POC), POC phone number, and POC email address;

All amendments acknowledged;

Price Proposal Form;

Copy of Representation and Certifications and proof of registration in System for Award

Management (SAM);

Confirmation of filing of Veterans’ Employment and Training (VETS) VETS-4212 for the

2023/2024 filing cycle;

Bid Guarantee in accordance with FAR Clause 52.228-1, Bid Guarantee. Amount shall be at least

20 percent of the proposed price, but shall not exceed $3 million; and

The offeror is required to submit a complete Price Proposal Form that includes completion of all contract line items numbers (CLINs). All required proposal documents shall be submitted in accordance with FAR 15.208.

The price proposal shall be submitted separately, but at the same time as the technical proposal.

Furthermore, technical information contained in the price proposal will not be considered. Likewise, price information contained in the technical proposal will not be considered.

(ii) Basis of Evaluation: The Government will evaluate price based on the total lump sum price. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:

JEB Little Creek-Fort Story, Virginia Beach, VA Work Order 1602585

a. Comparison of proposed prices received in response to the RFP.

b. Comparison of proposed prices with the Independent Government Cost Estimate (IGCE).

c. Comparison of proposed prices with available historical information.

d. Comparison of market survey results.

VI. EVALUATION

This task order will be awarded on a fair opportunity basis pursuant to FAR 16.505 ordering procedures.

The proposed task order will be awarded to the responsible offeror offering the best value to the Government. To make a determination of best value, the LPTA process is selected as appropriate for this acquisition because the best value is expected to result from selection of the technically acceptable proposal with the lowest evaluated price.

The Government reserves the right to eliminate from consideration for award any or all offers at any time prior to award of the task order; to negotiate with offerors in the competitive range; and to award the task order to the offeror submitting the lowest priced, technically acceptable offer.

The Government intends to evaluate proposals and award a task order without discussions with offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

In order to permit efficient competition, the Navy will utilize the following methodology. Proposals will initially be screened for price and placed in order (lowest price to highest price). The Navy will then evaluate the technical factors of the lowest priced proposal. In the event the proposal is deemed Unacceptable, the process described will be conducted again as many times as necessary, until such time as the Government identifies a technically acceptable proposal. The Navy will make award to the lowest priced technically acceptable proposal from among the lowest priced proposals. However, the Navy, at its sole discretion, reserves the right to increase the number of proposals it will review under this methodology. Accordingly, under this methodology, the technical factors of some proposals may not be evaluated by the Navy. If discussions are deemed necessary by the Contracting Officer, all proposals will be evaluated (both technical and price) for the purpose of establishing a competitive range.

An overall non-price factors rating must be at least “ACCEPTABLE” in order to be eligible for award.

An “UNACCEPTABLE” rating in any factor results in the overall non-price factors proposal being rated “UNACCEPTABLE” unless corrected through discussions. An overall non-price factors rating of “UNACCEPTABLE” makes a proposal ineligible for award.

Any proposal found to have a Deficiency in meeting the stated solicitation requirements or performance objectives will be considered ineligible for award, unless the Deficiency is corrected through discussions (if held). Proposals may be found to have either a Significant Weakness or multiple Weaknesses that impact either the individual factor rating or the overall rating for the proposal.

JEB Little Creek-Fort Story, Virginia Beach, VA Work Order 1602585

Attachments:

ATTACHMENT A1: Specifications Vol I of II ATTACHMENT A2: Specifications Vol II of II ATTACHMENT A3: USSOCOM Project Sign ATTACHMENT B: Wage Determination VA20250167 ATTACHMENT C: Pre-Proposal Inquiry Form ATTACHMENT D: Price Proposal Form ATTACHMENT E: PIEE Vendor Access Instructions ATTACHMENT F: JA ML-23-26 Class Fire Alarm Reporting

ATTACHMENT G: CJA ML-25-01 ALC FRCS

ATTACHMENT H: SECNAV 5512

ATTACHMENT I: ODP Spreadsheet