25R2563 Amendment 0012.pdf
PDF 413 KB Posted
- Attached to
- P325 HUMAN PERFORMANCE TRAINING CENTER
- Solicitation number
- N4008525R2563
About this file
This document is a Standard Form 30 Amendment (Amendment 0012) for a Design-Build contract for the P-325 Human Performance Training Center at JEB Little Creek-Fort Story, Virginia Beach, VA. The amendment modifies two key aspects of the contract: Liquidated Damages and Time for Completion.
The changes extend the project timeline from 881 to 919 calendar days for Phase A and from 90 to 150 calendar days for Phase B demolition, with a total project duration of 1,069 calendar days after contract award. Corresponding liquidated damages have been adjusted, with Phase A damages remaining at $3,468 per calendar day, while Phase B damages are reduced from $213 to $128 per calendar day. The amendment maintains the requirement for final cleanup and completion of the entire work within the specified timeframe, and includes 15 calendar days for submission and approval of bonds and insurance.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
Amendment 0012
The purpose of this amendment is to:
1. Revise General Requirements: Liquidated Damages
2. Revise General Requirements: Time for Completion
1. Revise Liquidated Damages
From:
Liquidated Damages: In accordance with FAR 52.211-12 Liquidated Damages, if the Contractor fails to complete the work within the time specified in the task order, the Contractor shall pay liquidated damages to the Government for each calendar day of delay until the work is completed or accepted. See associated liquidated damages per phase below:
Phase Number of Days Liquidated Damages
Phase A - Entire Project, except demolition of buildings 3855A and 3855D
881 calendar days after award $3,468 per calendar day
Phase B - Demolition of buildings 3855A and 3855D
90 calendar days after completion of Phase A
$213 per calendar day
To:
Liquidated Damages: In accordance with FAR 52.211-12 Liquidated Damages, if the Contractor fails to complete the work within the time specified in the task order, the Contractor shall pay liquidated damages to the Government for each calendar day of delay until the work is completed or accepted. See associated liquidated damages per phase below:
Phase Number of Days Liquidated Damages
Phase A - Entire Project, except demolition of buildings 3855A and 3855D
919 calendar days after award $3,468 per calendar day
Phase B - Demolition of buildings 3855A and 3855D
150 calendar days after completion of Phase A
$128 per calendar day
Phase A + Phase B 1,069 days after award
2. Revise General Requirements: Time for Completion
From:
Time for Completion: In accordance with FAR 52.211-10 Commencement, Prosecution, and Completion of Work, the deadline for completion of this task order (including Bid Options) shall be 859 calendar days from date of award (includes 15 calendar days for submission and approval of bonds and insurance). Consistent with FAR 52.211-10, completion of the entire work ready for use must occur prior to the aforementioned date. The time stated for completion shall include final cleanup of the premises.
To:
Time for Completion: In accordance with FAR 52.211-10 Commencement, Prosecution, and Completion of Work, the deadline for completion of this task order (including Bid Options) shall be 919 calendar days for Phase A and 150 calendar days for Phase B for a total of 1,069 calendars days after contract award (includes 15 calendar days for submission and approval of bonds and insurance). Consistent with FAR 52.211-10, completion of the entire work ready for use must occur prior to the aforementioned date. The time stated for completion shall include final cleanup of the premises.
Please see chart below:
Phase Number of Days
Phase A - Entire Project, except demolition of buildings 3855A and 3855D
919 calendar days after award
Phase B - Demolition of buildings 3855A and 3855D
150 calendar days after completion of Phase A
Phase A + Phase B 1,069 days after award
| 23R2656 Amendment 0001 |
| 23R2656 Amendment 0004 |
| Pages from 23R2541 Amendment 0003-2 |
Amendment 0001 continuation page
| topmostSubform[0]: |
| Page1[0]: |
| AmendmentNo[0]: 0012 |
| Code[0]: N40085 |
| Code[1]: |
| AccountingData[0]: |
| A13[0]: |
| C13[0]: |
| D13[0]: |
| NameandTitleSigner[0]: |
| NameandTitleOfficer[0]: |
| Description[0]: N40085-25-R-2563, Design-Build (DB), P-325 Human Performance Training Center, JEB Little Creek-Fort Story, Virginia Beach, VA |
SEE SF 30 BLOCK 14 CONTINUATION PAGE
Contract POC: Angie Clifton, angela.j.clifton2.civ@us.navy.mil
| FacilityCode[0]: |
| Code[2]: |
| IssuedBy[0]: NAVFACYSCOM MID-ATLANTIC |
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK, VA 23511-3095
| NameandAddress[0]: |
| AdministeredBy[0]: See Item 6 |
| ContractIDCode[0]: |
| ReqNumber[0]: |
| AmendmentNo[1]: N4008525R2563 |
| ModificationNo[0]: |
| ProjectNo[0]: |
| Page[0]: 1 |
| Pages[0]: 3 |
| EffectiveDate[0]: 05/20/2025 |
| Dated9B[0]: 03/05/2025 |
| Dated10B[0]: |
| CheckBox9[0]: 1 |
| CheckBox10[0]: Off |
| CheckBox11[0]: 1 |
| CheckBox13A[0]: Off |
| CheckBox13B[0]: Off |
| CheckBox13C[0]: Off |
| CheckBox13D[0]: Off |
| IsNot[0]: Off |
| Is[0]: 1 |
| Extended[0]: Off |
| NotExtended[0]: 1 |
| DateSigned[0]: |
| DateSigned[1]: |
| Copies[0]: 1 |
| CopiesReturned[0]: 1 |
File details come from the government source that posted it. Updated .