25R2563 Amendment 0005.pdf

PDF 220 KB Posted

Attached to
P325 HUMAN PERFORMANCE TRAINING CENTER
Solicitation number
N4008525R2563
Issued by

About this file

This document is Amendment 0005 for the P325 Human Performance Training Center solicitation (N4008525R2563), issued by the Department of the Navy Naval Facilities Engineering Core. The amendment serves two primary purposes: 1) incorporating Pre-Proposal Inquiry (PPI) responses and 2) incorporating revised specifications. The PPIs address technical clarifications across multiple areas including HVAC systems, facility references, pool equipment specifications, sustainability requirements, piping materials, and equipment details. Key revisions include updating a facility code reference from FC 4-740-02N to UFC 4-740-02, modifying basement construction specifications, and replacing Part 5 Prescriptive Specifications entirely with a new attachment (Attachment M). The amendment provides detailed government responses to 28 specific contractor questions, offering guidance on design interpretations, equipment specifications, and technical requirements for the human performance training center project.

View the file

Other files

Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

N40085

N40085-24-R-2608, Design-Build (DB), P 325 Human Performance Training Center, JEB Little Creek-Fort Story, Virginia Beach, VA

SEE SF 30 BLOCK 14 CONTINUATION PAGE

Contract POC: Angie Clifton, angela.j.clifton2.civ@us.navy.mil

NAVFACYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK, VA 23511-3095

See Item 6

N4008525R2563

1 5

04/09/2025

03/05/2025

Amendment 0005

The purpose of this amendment is to:

1. Incorporate PPI responses

2. Incorporate Revised Specification

1. Incorporate PPI Responses

PPI # Date Submitted

Reference Question Government Response

Page Section Para

15 3/28/2025 342 Part 3 2.4

RFP references compliance with FC 4- 740-02N. It appears this FC has been canceled and replaced with UFC 4- 740-02. Should the reference to FC 4- 740-02N be replaced with UFC 4-740- 02 in its entirety?

Yes. UFC 4-740-02 is the correct reference, and the RFP is revised with this amendment.

16 3/28/2025 483 Part 3 D30

Under "Dedicated air conditioning system for high humidity spaces" header, it states the pool space dehumidification units call for a heat recovery loop. Is it correct that this is referring to a heat recovery loop with the pool water? The various pools indicated in Part 5 are described as being pre-fabricated / pre-packaged pools with integral heaters and chillers.

Since the pools are pre-fabricated, please confirm the requirement for heat recovery loops between the pool dehumidification units and the pools.

The Offeror’s Designer of Record (DOR) is responsible for the design of the heat recovery loop.

The DOR can design the heat recovery loop to be a runaround coil to recover heat with the exhaust airstream; design the heat recovery loop to provide heat to the pool water; or design solution.

Coordinate with provided pool manufacturer.

17 3/28/2025 483 Part 3 D30

Under "Cooled, Heated and Mechanically Ventilated (VAV System" header, it states each thermal zone must be provided with a VAV terminal unit with hydronic reheat. The RFP also states the open gym area must be on its own system. Is it acceptable to provide a Single Zone Variable Air Volume Rooftop Unit (RTU) to serve the open gym in lieu of a Multizone RTU serving multiple VAV terminal units?

The Offeror’s DOR is responsible for the design. A single zone is an acceptable design solution; however, it is the Offeror’s DOR responsibility to determine proper zoning and to determine if the gym area that includes warm up, cool down, equipment area and running lanes can be maintained as one thermal zone with proper air distribution.

18 3/28/2025 483/5 77 Part 3

Part 3 D30/Part 5

Hydro therapy

Equipment

Under the "Dedicated air conditioning system for high humidity spaces" header, it states the Isopod Room must be conditioned by a pool room dehumidification HVAC system.

Unlike the prescriptive specifications for the Hydrotherapy Pools, there are no specifications for the Hydropod in the Isopod Room. Please provide specifications, water temperature, etc.

for the Hydropod to support sizing of the dehumidification unit.

Selection of the hydro pod unit is the responsibility of the Offeror. Refer to the hydro pod unit manufacturer for operational requirements.

19 3/31/2025 Part 5 Prescriptive

Specifications Hydro therapy

Equipment

Part 5 Prescriptive Specifications provides information for the three Hydrotherapy Equipment Items;

Hydrotherapy Pool, Polar Plunge Pool, and Thermal Plunge Pool, however, G204006 Fountains and Pools states, "Not used." Please clarify and confirm if the costs for these three equipment items are to be included in CLIN 0001A as construction costs or if they are already included in CLIN 0008 Option Item No. 7 for FF&E?

Part 3, Chapter 6 Engineering Systems Requirements, G20 Site Improvements, paragraph G204006 Fountains and Pools “Not Used”. There are no fountains or pools required with the P325 Site Improvements. For the Hydrotherapy Pool, Polar Plunge Pool, and Thermal Plunge Pool Equipment see Part 3, Chapter 4 Building Requirements, Part 6 Engineering System Requirements, and Part 5 Prescriptive Specifications, Hydrotherapy Equipment. The hydrotherapy equipment is built-in equipment and are included to be included in CLIN 0001.

20 04/02/2025

Part 3 D20 D30 and other sections

The RFP documents are dated 21 July 2023. 1 March 2024 the Department of NAVY issued ITG FY24-01 Electrification of Navy Facilities.

Multiple places in the RFP reference Natural Gas fired systems and energy supply. Is the ITG FY24-01 Electrification to be applied to this project?

No, electrification is not required.

21 04/02/25 of

RFP -

Sustainability checklist states harvesting rainwater is in compliance however there are no provided calculations for an LCCA. This is not mentioned anywhere else in the RFP.

Equipment rooms, exterior tanks, etc.

cannot be found for harvested rainwater use. Is the checklist in error?

If not, what is the water savings goal and what is the water being used for?

Final sustainability goals and HPSB Checklist to be developed by DOR.

22 04/02/25 of

RFP Part 3 D202001

Domestic piping lists specifically Type K copper only for all aboveground piping. Typically Type L is used, please confirm pipe material.

Bid per RFP.

2325 04/02/25 19 of

Drawings sheet IF101C -

Drawings call out G87 (large air compressor) but no compressed air listed in RFP D20 section. It appears the compressor may be for resistance training equipment. Its assumed the compressor is owner furnished and installed and only pathways for the pneumatic tubing would be provided, please confirm.

Bid per RFP.

24 04/02/25 of

RFP Part 3 D203001

Sanitary piping materials are stated to be hub and spigot underground. Can underground sanitary be PVC?

Bid per RFP.

25 04/02/25 of

RFP Part 3 D202003

Section calls for two gas fired water heaters sized for 66% as well as a triplex booster pump. UFC 3-420-01 states that water heaters are not required to have redundancy for this type building and the booster pump shall be duplex if not mission critical.

Is there a reason for the redundancy?

Bid per RFP.

26 04/02/25 of

RFP

Attachment B

The body of the RFP directs us to us the flow test located in Attachment B .

The date of the fire flow test is 3/20/19. This is well outside of the time frame required by UFC 3-600-01.

Is there a more current flow test?

Bid per RFP.

27 3/31/25 AE10

Concept Drawings Keynote 2

Can the Government provide additional specifications for the Climbing wall in the in equipment room 114? For Example: what are the desired dimensions for the climbing wall? Is this to be a boulder wall, or full climbing rope? If climbing rope, See Attachment M for Part 5 - Prescriptive Specifications, Climbing Wall.

please specify how many lines and if Autobelays are required.

28 3/28/25 577 Part 3 Hydro therapy

Equipment

Please provide pool water temperatures to support sizing of the pool dehumidification units.

See Attachment M for Revise Part 5 - Prescriptive Specification, Hydrotherapy Equipment.

2. Incorporate Revised Specifications

PART 3 – Project Program, Chapter 2 Project Objectives, 2.4 Appropriate Design

Change: “FC 4-740-02N”

To: “UFC 4-740-02”

PART 3 – Project Program, Chapter 6. Engineering Systems Requirements, A20 Basement Construction, A2020 Basement Walls

Change:

“Basement walls include exterior walls below the ground floor level of the building, including walls that are below grade, elevator pits and other pits. Provide basement walls constructed of cast-in-place concrete.

Provide waterproofing and insulation of basement walls.”

To:

“Basements/pits (walls/floors/structural foundations) are below the finish floor elevation. Basements are required for the elevator, Hydrotherapy Pool, Polar Plunge Pool, Thermal Plunge Pool and other pits required. Depth and size of the basements to be determined by the Designer of Record. The basement/pit walls and slab constructed of cast-in-place concrete supported by the deep pile foundation. Provide waterproofing and insulation of basement/pit walls and floors.”

PART 5 - Prescriptive Specifications, is replaced in its entirety. SSee Attachment M