This document is Amendment 0009 to Solicitation N4008525R2563 for the P325 Human Performance Training Center Design-Build project at Joint Expeditionary Base Little Creek in Virginia Beach, VA. The amendment extends the proposal due date from May 9, 2025 to May 21, 2025 at 2:00 pm local time and incorporates several key revisions, including: updated Pre-Proposal Inquiry (PPI) responses, changes to work restrictions, modifications to technical requirements for exterior windows and glazing, updates to exhaust systems specifications, and revisions to the Factor 1 Technical Solution submittal requirements. The contract duration has been lengthened by 120 calendar days, and the amendment includes updates to Attachments P and Q, with specific changes to submittal requirements for the Design Team and Subject Matter Expert qualifications.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
Amendment 0009
The purpose of this amendment is to:
1. Incorporate PPI responses
2. Incorporate PPI revisions
3. Incorporate RFP revisions
4. Revised Factor 1 – Technical Solution
5. Incorporate Attachment P – CJA ML023-80-ML AMI
6. Incorporate Attachment Q – Revised Price Proposal Form
7. Extend proposal due date from 09 May 2025 to 21 May 2025
1. Incorporate PPI Responses
PPI
Date Submit
Reference Question Government Response
Page Section Para
4/29/25
PPI 14
Bid Due
Date
PPI 14 requested that the Proposal Due Date be extended to May 28, 2025.
Amendment 0006 extended the due date to May 9, 2025, however, there are still an excessive amount of PPIs unanswered including critical PPIs regarding the phasing and sequencing of construction along with the Period of Performance for this new construction project. Please considered complying with this original request and extend the Proposal Due Date to May 28, 2025 to allow for the proper time to incorporate responses from outstranding PPIs.
RFP will be extended to Wednesday, 21 May 2025 at 2:00 pm local time. The PPI cutoff date will not be extended.
205 4/25/25 Amendment
PPI 42
PPI 42 response states "DPR". Please confirm this is to be "DOR"?
Confirmed
206 4/9/25 108 Part 2 1.4.4
Spec section 01 33 29 05 20 requires "Third Party Certification or Validation." The High Performance and Sustainable Building Checklist indicates "GBI Guiding Principles Compliance." Please confirm that Third Party Certification is not required and GBI Guiding Principles
Provide Third Party Certification in accordance with Part 2, Section 01 33 29 05 20.
207 4/25/25 Amendment
007 PPI 63
Response is acknowledged. Are any of the PPI responses that to no answer the specific question going to be changed?
See Amendment 0009 PPI 63 revised response
208 4/25/25 PPI 63
PPI 63 pointed out the numerous instances (8) where the government's response was "Bid Per RFP" for valid PPI's asking for clarification to ambiguous or conflicting direction in the RFP. Similarly, the government has now responded to an additional (39) PPI's with, "The offeror’s DOR is responsible for the design." The purpose of the Pre-Proposal Inquiry process is to clarify or define ambiguous or conflicting scope items so all Offeror's can more responsibly propose on this Solicitation and provide the government with competitive pricing and solutions for this project. We respectfully ask that the government consider providing responses to these PPI's actually answering these questions to better aide both the offeror's and the government in this process.
See Amendment 0009 PPI 63 revised response
209 4/29/25 PPI 63
PPI
Responses to date
PPI 63 requested that the government please reconsider responding to PPIs with "Bid Per RFP" and the response was "Acknowledge." At that time, 25% of PPI responses had been "Bid Per RFP". Moving forward, the government started responding to PPIs with "The Offeror's DOR is responsible for the design." This response does not aide us in our efforts to provide the government with responsible competitive solutions from all MACC Participants. Through Amendment 0008, we have recieved the response of "Bid Per RFP" or "DOR is Responsible" over 75 times, equating to 40% of the PPI responses to date. Please consider returning to these responses and amending the answers to help our teams responsibly respond to this RFP.
See Amendment 0009 PPI 63 revised response
210 4/9/25
3.0 Site
Analysis 3.2.16
3.2.16 Construction Laydown Area.
Please provide haul routes, laydown areas, trailer area, and construction parking area for pricing?
See Amendment 0009 RFP revisions
211 4/25/25 Amendment
006 PPI 43
PPI 43 response states to bid per B202009. We do not see B202009.
Please clarify?
See Amendment 0009 PPI 43 revised response
212 4/11/25 RFP Gen. Req.
We have evaluated the period of performance and confirmed with our designers and subcontractors that the 859 calendar days is too short for this project, even with fast tracking the demo, sitework and foundation design.
Please add 3 months (90 calendar days) to the current period of performance allowing 949 calendar days to meet the project requirements.
See Amendment 0009.
The contract duration is lengthened by 120 calendar days.
213 4/29/25 Amendment
Period of
Performance
A PPI was previously submitted stating the current period of performance was not adequate for the project, and requests an additional 3 months be added. Please provide a response adding 3 months to the period of performance to allow us to bid the project.
See Amendment 0009.
The contract duration is lengthened by 120 calendar days.
214 4/10/25 12 D30 D304008
Other sections speaks to packaged VAV rooftop units; however, this section speaks to vapor tight marine lighting system in each access section of the AHU with switch outside of each section. Please confirm that there are a minimum of 3 DX vendors that have this as standard or is the intent to use a custom style unit?
A custom unit is not required. Per D304008 “Provide a vapor tight marine lighting system in each access section of the air handling units with switch outside of each access door.”
215 4/10/25 n/a D30 n/a
Per UFC, a Life Cycle Cost Analysis (LCCA) needs to be completed.
Typically, an LCCA is completed prior to 35% design. In the case of this project, the RFP is very descriptive with the HVAC system types and this is a competitive bid RFP. Please confirm that AE1 did a LCCA and AE2 does not have to perform one.
No LCCA was done for this DB RFP. The offeror’s DOR is responsible for providing LCCA as required in Part 2, General Requirements, Section 01 33 29.05 20 Design Submittal requirements.
216 4/10/25 11 D30 Diffusers
This section speaks to having linear slot diffusers in areas with ACT.
Please confirm this is for all ACT ceilings and not just conference room ACTs.
See revised Part 3, Chapter 6 ESER, D20
HVAC, D304001,
Amendment 0009
217 4/10/25
Part 6, Attachment
K, AE101
214-Combative Training and 215- Cardio Mezzanine are required per 5.0 Room Requirements to have CMU wall finishes. Per the AE101 Partition Types Legend, the shared partition with C201-Corridor is indicated to be CMU with furring with gypsum wallboard on one side (Type CF). The
5.0 Room Requirements for C201-
Corridor allow for both CMU and gypsum wallboard finishes. Please confirm that the furring with gypsum board is required at the C201-Corridor.
Confirmed. Corridor C201 requires gypsum wall board and furring on the CMU walls.
218 4/10/25 V-101 Appendix K -
Drawings
The topographic survey shows that the existing storm drain from structure 103 to catch basin 105 flows in the reverse direction. The proposed storm drain will tie in upstream of this 'backflow' condition. Please verify that this replacement of the existing storm drain is not part of this contract.
Part 3, Chapter 3 Site Analysis Paragraphs 3.2 Site Development Requirements and 3.2.3 New Site Work notes the contractor is required to analyze the existing site conditions and the requirements must be incorporated into the site design that satisfies the
RFP.
219 4/9/25
6.
Engineering
System Reqmts
G10
G10 Site Preparation, page 2 paragraph 3 states the Contractor must reasonable anticipate that excavations will encounter materials beyond what are specifically indicated on the test boring records. This is too subjective and cannot be priced since it is a unforeseen condition. Please delete this section from this paragraph, or provide an allowance for Contractors to carry for this unforeseen condition?
See Amendment 0008 Attachment O for Building 3812 As-Built drawings, in addition to Part 6, Attachment K, and Drawing V-101.
220 4/10/25
Part 6, Attachment
K, AE201
Key Note 4 indicates "translucent window panel system" at the North, East, and West Exterior Elevations.
However, a "translucent window panel system" is not included in Part 3, 5.0 Room Requirements for rooms 115, 116, 117, or 118 nor in Part 3, 6.0 Engineering System Requirements (ESR) B2020 Exterior Window.
1. Please confirm that a "translucent window panel system" is required as shown in the AE201 Exterior Elevations.
2. If a "translucent window panel system" is required as shown in the
Provide translucent polycarbonate window panel system in locations shown on Part 6 Drawings.
AE201 Exterior Elevations, please provide Engineering System Requirements (ESR).
221 4/29/25 Amendment
006 PPI 43
PPI 43 response states to bid per B202009. We do not see B202009.
Please clarify?
See Amendment 0009 PPI 43 revised response
222 4/25/25 Room 104
In PPI 48, the following questions was asked, "Room 104 PT Open Office has acoustics being STC 50. This is an open area, please clarify how to achieve STC 50 for this space?" In PPI 49, the question was, "There are numerous rooms requiring STC 50 acoustics. Please confirm this high STC rating is required for all rooms STC 50 is designated for?" In PPI 50, the question was, "Room 215 Cardio Mezzanine is required to have STC 50 acoustics. The mezzanine is an open space to below. Please clarify how this open room can meet any acoustics requirements?" The government's response for PPI 48, 49, and 50 was, "Offeror's DOR is responsible to the design per the RFP." This response is not sufficient to responsibly bid these items. If the open mezzanine area is to be rated to STC 50, then the entire first floor open gym area has to be STC 50 to the exterior walls, glazing, etc.
Please confirm the open mezzanine area does not need to meet STC 50.
Please also confirm the areas, rooms, and spaces to be designed to STC 50.
See Amendment 0009 for revised PPI responses for PPIs 48, 49, and 50.
223 4/29/25
PART 3 -
CHAPTER 5
Room 215
Cardio Mezzanine
STC 50 Requirements: Room 215 – Cardio Mezzanine. Please confirm that at rating of STC 50 applies to the Type CF and Type C walls as indicated on AE102 and that the guard rails at the open edge of the mezzanine (C201090) do not necessitate an STC rating.
Confirmed. Open edge of the mezzanine does not require SCT 50.
224 4/25/25
007 PPI 119
PPI 119 response states that the Contractor is responsible for evaluating the existing sanitary system has adequate capacity and providing improvements as necessary. This existing condition is not known and not provided in the RFP documents so cannot be defined to price. For bidding purposes, can we assume the existing sanitary system is in good working condition and has adequate capacity for this project?
No. The offeror is required to provide a sanitary system per their DOR’s sanitary design.
The existing systems will require modifications.
225 4/25/25 Amendment
PPI 52 and
PPI response 52 and 53 do not answer the specific questions. Please provide a response that specifically answers the questions in order to price?
See Amendment 0009 for PPI 52 and 53 revised responses.
226 4/9/25 Part 3 Ch-6 C301090
Clarify locations for wall guards (Plate Wall Protection) finish. Was not defined in the Room Requirements section.
See Part 3, Chapter 6, ESR, Paragraph C30 Interior Finishes, C301090 Other Wall Finishes, Wall Protection and Corner Guards, and Wall Guards for the required.
227 4/9/25 Part 3 Ch-6
C301090
Wall Protection: Clarify the height extent of the wall protection wainscot system and material type/thickness.
Per Part 3, Chapter 6, ESR, Paragraph C30 Interior Finishes, C301090 Other Wall Finishes, Corner Guards, and Wall Guards the offeror's DOR is responsible to set the height of the wainscot, and the height must be consistent throughout the facility and coordinated with built-in or wall mounted furnishings.
228 4/10/25 12 01 14 00 1.3.1.2.2
In section 01 14 00 – Work Restrictions in paragraph 1.3.1.2.2 Finish Work, it states “Finish Work within the secure annex area must be accomplished by U.S. TOP SECRET-cleared personnel.” Please clarify if this will be required of work in this project during construction as the facility is unoccupied.
Top Secret –cleared personnel are not required. See Amendment 0009 for revised specifications.
229 4/25/25
Per Section 01 14 00, page 2, items
1.3.1.2.2 (Finish Work) and 1.3.1.2.3 (Electronic Security Systems Equipment), we seek clarification regarding the intent of the government.
Specifically, is it the government's intention to require contractors and subcontractors working on the P-325 SOF Human Performance Center to possess a Top Secret clearance?
If so, this requirement could significantly reduce the available subcontractor pool, potentially limiting competition and resulting in increased project costs to the government. We respectfully request further guidance on this matter to ensure proper planning and compliance.
Top Secret –cleared personnel are not required. See Amendment 0009 for revised specifications.
230 4/25/25 Amendment
006 PPI 51
PPI 51 response is not reasonable for this project. Awarding, procuring and installing this project's FFE package of over $3 million in 6 months cannot occur as confirmed with the FFE and equipment vendors. The project has liquidated damages for delays and it is unreasonable to include a 6 month time frame that cannot be reasonably met.
And by not meeting the completion date, the Contractor runs the risk of obtaining an unsatisfactory CPAR that would jeopardize future Federal work.
Also this 6 month award period has been questioned by several other Contractors in other PPIs. Please extend the award period from 6 months to 9 months prior to contract completion so that Contractors can meet the project period of performance?
See Amendment 0009, Attachment Q for revised FF&E package submission date.
231 4/25/25 PPI 51
BID NOTES
FOR ESS,
FF&E and A/V (Line items 0006- 0008) Item f.
Bid Pricing Form
PPI 51 expressed concern about the 6 month period for planned modifications in CLINs 0006 - 0008.
We have since discovered that the lead time for the hydrotherapy pools alone is 10 - 12 months. Please consider extending this award period to twelve months prior to contract completion.
See Amendment 0009, Attachment Q for revised FF&E package submission date.
232 4/29/25
Bid Pricing
Form
Amendment 008 and the latest Pricing Form does not address this issue. The FFE / AV / ESS Options have up to 6 months of project completion to be awarded. Due to the significant size and scope of this FFE package and long lead time for equipment, as confirmed with vendors, 6 months cannot be acheived. The hydrotherapy pool vendor has confirmed a 10 month lead time from approval. It is unreasonable for the Government to include a FFE / AV / ESS award date that cannot be acheived especially when the project has liquidated damages. Please change the award date from 6 months to 12 months from CCD in order for us to comply with RFP period of perfromance.
See Amendment 0009, Attachment Q for revised FF&E package submission date.
233 4/25/25 PPI 66
PPI 66 requested the following, "D30 HVAC section did not see any requirements for outside HVAC equipment corrosive resistance requirements. Please provide." The government's response was, "The offeror’s DOR is responsible for the design per applicable UFCs." This is not typical for JBLCFS. Typically, all rooftop or exterior HVAC equipment has to meet the 3,000 hour sea salt spray requirements among other stringent corrosive resistance criteria.
Please confirm these requirement's beyond the typical UFC are not required.
See Amendment 0009 PPI 66 revised response
234 4/25/25 Amendment
006 PPI 48
PPI 48 response is a generic response that DOR is responsible for design per the RFP however this does not specifically answer the STC 50 requirement for an open space (Room 104 PT Open Office). Please provide a specific response in order to price?
See Amendment 0009 PPI 48 revised response
235 4/25/25 Amendment
006 PPI 50
PPI 50 response is a generic response that DOR is responsible for design per the RFP however this does not specifically answer the STC 50 requirement for an open space (Room 215 Cardio Mezzanine). Please
See Amendment 0009 PPI 50 revised response provide a specific response in order to price?
236 4/29/25 Page 363
PART 3 -
CHAPTER 5
Room 104 PT Open office
STC 50 requirements: Room 104 – PT Open Office. Please confirm that a rating of STC 50 applies to all types of partition types indicated on AE101.
Specifically, Type G: Storefront, Section 101066.
Confirmed. See Amendment 0009 For C101006 Revision.
237 4/29/25 ESR B20
PART 3 -
CHAPTER 6
Exterior Glazing
STC Ratings
ESR B20 does not specify a requirement for STC Rated Glazing for this project. Please confirm that exterior windows and glazing are standard and are not required to meet the STC Rating of the global room requirments.
See Amendment 0009 for revisions to B2020 Exterior Windows.
238 4/29/25 ESR B20
PART 3 -
CHAPTER 6
Interior Glazing
STC Ratings
ESR B20 does not specify a requirement for STC Rated Glazing for this project. Please confirm that interior windows and glazing are standard and are not required to meet the STC Rating of the global room requirments.
See Amendment 0009 for revisions to B2020 Exterior Windows.
239 4/29/25 ESR C10
PART 3 -
CHAPTER 6
Glazed Partitions and Storefronts
C101006 does not call for an STC Rating for interior Glazed Partitions.
Please confirm that the interior glazed partitions on the first floor are not required to meet the global STC specified in the room requirments.
See Amendment 0009 for revisions to B2020 Exterior Windows.
240 4/29/25 ESR C10
PART 3 -
CHAPTER 6
Glazed Partitions and Storefronts
If the Glazed Partitions are required to be STC Rated, please confirm that all glazed partitions will be STC 35 and not STC 50. The cost difference and the wall thickness required for STC 50 will increase the cost of the interior glazed partitions exponentially and could jepardize the stated project budget.
See Amendment 0009 for revisions to C101006 Glazed Partitions
241 4/9/25 347 Part 3 3.2.1
Please confirm that if the bid alternative is not selected, then the quonset hut adjacent to the existing field is also to remain.
Per Part 1 - Mission Summary, demolition of Building 3855D (quonset hut) is an RFP requirement. Building 3855D is next to the existing turf. The demolition of Building 3855D is not part of Option Item No.1. Turf Field.
242 4/25/25 PPI 39
6.
Engineering
System Reqmts
A1010
In PPI 39, the following confirmation was requested. A1010 Standard Foundations state structure(s) can be supported by a shallow foundation system, but other areas state to use deep foundation system. Please confirm deep foundations is a prescriptive requirement for P325 building? The government's response was The Offeror's DOR is responsible for the foundation design. The Geotechnical Report in the RFP clearly states that shallow foundations are no suitable for this project site. To ensure all Offeror's are responsibly proposing on similar foundation, please confirm shallow foundations are not acceptable for this facility.
See PPI response 158.
Please consult your Structural Engineer and Geotechnical Engineer for professional guidance on foundations design, they are the offeror’s responsible parties. As noted in PPI 158 Part 3, Chapter 6 ESR, A10 Foundation, Paragraph System Description notes “building and superstructure and ground floor slabs must be supported on a deep foundation system …".
243 4/8/25 543 of
RFP G204007
Is there any special lighting requirements for the Synthetic turf field for night time or low light use?
No.
244 4/9/25
Please advise if duct and pipe risers are permitted to be exposed in the open gym area to go between floors.
Yes.
245 4/10/25 12 D30 D304008
Other sections speaks to packaged VAV rooftop units; however, this section speaks to access door labeling and resets which are not standard for some vendors. Please confirm that there are a minimum of 3 DX vendors that have this as standard or is the intent to use a custom style unit?
Intent is not to use custom units.
246 4/10/25 13 D30 D3060
Other sections speaks to packaged VAV rooftop units; however, this section speaks control elements and points that are not available with standard equipment for some vendors.
Please confirm that there are a minimum of 3 DX vendors that have this as standard or is the intent to use a custom style unit?
Intent is not to use custom units.
247 4/9/25
3.0 Site
Analysis 3.2.3
3.2.3 New Site Work section
references decorative paving. Please clarify if there is any decorative paving, and if so, please provide where and what?
See Part 3, Chapter 6, Paragraph G20 Site Improvements, G2030 Pedestrian paving for locations. Decorative Paving is not shown on the Part 6 Attachments, Attachment K drawings
248 4/25/25 RFP
AE101 &
AE102
Drawings AE101 and AE102 have lines in the Partition Types for Wire Mesh but no annotations on the drawings themselves for wire mesh partitions. Please confirm no wire mesh walls or cages are required for this project.
See Part 3, Chapter 5 Room Requirements, wall types
249 4/9/25
Please advise if duct and pipe risers are permitted to be exposed in the open gym area to go between floors.
Yes.
250 4/9/25 409 Part 5 207
Room Requirements for 207 - Sports Psychologist includes C101005 Interior Windows. Part 6 - Drawings do not include interior or exterior windows for this space. Please clarify if a window will be needed.
Yes. See Amendment 0009 RFP revisions
251 4/11/25 488 ESR D30 D303001
Section D303001 - Chilled Water Systems indicates that it is not used.
There is a requirement for a polar plunge pool that we would anticipate requires cooling. Is this system to be conditioned by a DX condenser or a remote chiller? If the requirement or option is a remote chiller, please confirm there are no prescriptive requirements for chilled water piping and chilled water system insulation.
Chillers for pools will be provided with the pool in accordance with the manufacturer's recommendations and meet applicable building codes.
252 4/9/25 RFP Factor 1
The Non-Price Factor 1 allows for 8 pages of narrative and 4 pages of drawings. Due to the RFP required information to be provided, please consider increasing the narrative to 10 pages, and the drawings limit to 8 pages of 11x17 drawings.
See Amendment 0009 Revised Factor 1 language
253 4/9/25 7 Gen Req Factor 1
The requirements for the technical narrative state, "provide location and layout of Electrical infrastructure for equipment." This implies drawing(s) are required. Only four drawings are allowed. Is this intended to include electrical drawings?
See Amendment 0009 Revised Factor 1 language
254 4/9/25 7 Gen Req Factor 1
The requirements for the technical narrative state, "provide location and layout of Electrical infrastructure for equipment." Is this intended to include both interior and exterior electrical infrastructure?
See Amendment 0009 Revised Factor 1 language
255 4/16/25 7 General
Requirements
Factor 1 Technical
Solution, b) Labor Force
Narrative
Factor 1 Technical Solution, b) Labor Force Narrative requires the Offeror to “discuss at a minimum” the “Design Team, including a Human Performance Center / Gymnasium equipment SME.”
(a) Please confirm that Offerors are not required to specifically name in their proposal the Design Team firm names including all disciplines and the SME.
(b) Please confirm that Offerors only need to provide information which displays understanding of the necessary team members and team structure as required per the RFP.
See Amendment 0009 Revised Factor 1 language
256 4/29/25 Amendment
Factor 1
Technical Solution
Amendment 008 still has not increased the page count for Factor 1 as requested in previous PPI still not answered. In order for us to provide adequate responses to all of the information requested in Factor 1, please increase the page count from 8 pages to 10 pages?
See Amendment 0009 Revised Factor 1 language
257 4/9/25 127-132 01 33 29.05
The NAVFAC HPSB Checklist, included with spec section 01 33 29.05 20, implies that a LCCA has been performed. Moreover, the RFP prescriptively lists the equipment types and systems that must be used in the building. As such, there is no room for comparing multiple proposed designs.
In lieu of performing a LCCA, is it acceptable to compare a single proposed design to the ASHRAE 90.1 Baseline to demonstrate the proposed design achieves the minimum required energy savings?
Final sustainability goals and HPSB Checklist to be developed by DOR.
See Amendment 0005, PPI 21
258 4/9/25
3.0 Site
Analysis 3.2.5
3.2.5 Electrical and Mechanical
Equipment Pad Elevations provides an elevation of 9.0' NAV88 or above, but then has a Note to NAVFAC reviewer that elevations may be adjusted.
Please clarify?
See Amendment 0009 RFP revisions
259 4/9/25 339 Part 3, Ch.1,
1.0 2
The RFP states, "the roof will have a screened mechanical equipment area."
Is all of the rooftop mechanical equipment required to be contained within a single screened area, or will multiple screened areas be permitted?
Are exhaust fans required to be contained within the screened area(s)?
The offeror's DOR will determine roof equipment screening to compliment the building architecture. It can be one or more areas.
260 4/9/25 105 1.1 GBI
This project is a "GBI Guiding Pricinples compliant" facility. There is no indication of a recycle area on the plan. Is there a preferred location for a recycle area or recycle room?
The offeror's DOR is responsible for compliance with the GBI Guiding Principles.
2. Incorporate revised PPI responses
PPI
Date Submitted
Reference Question Government Response
Page Section Para
22 04/2/25 477 of
RFP Part
D202001
Domestic piping lists specifically Type K copper only for all aboveground piping. Typically Type L is used, please confirm pipe material.
Type L is not acceptable.
Pre Part 3, Chapter 6 ESR, D20 Plumbing, G20, D202001, “Piping must be Type K …”
23 04/2/25 19 of 24 Drawing s sheet
IF101C
Drawings call out G87 (large air compressor) but no compressed air listed in RFP D20 section. It appears the compressor may be for resistance training equipment. Its assumed the compressor is owner furnished and installed and only pathways for the pneumatic tubing would be provided, please confirm.
Per Part 6 – Attachment A FF&E Movable Furniture Summary, and Part 6, Attachment K, Drawing IF101C, the G87 Large Air Compressor is part of the FF&E, and is CFCI.
24 04/2/25 479 of
RFP Part
D203001 Sanitary piping materials are stated to be hub and spigot underground. Can underground sanitary be PVC?
No. Per Part 3 Chapter 6 ESR, Paragraph D20 Plumbing, D203001 Waste Pipe & Fittings:
“Provide cast iron hub less pipe and fittings
25 4/2/25 478 of
RFP Part
D202003
Section calls for two gas fired water heaters sized for 66% as well as a triplex booster pump. UFC 3-420-01 states that water heaters are not required to have redundancy for this type building and the booster pump shall be duplex if not mission critical.
Is there a reason for the redundancy?
Per Part 3, Chapter 6 ESR, D20 Plumbing, D202003 two gas fired water heaters required.
Provide two gas fired water heaters
26 4/2/25 593 of
RFP
Attachm ent B
The body of the RFP directs us to us the flow test located in Attachment B .
The date of the fire flow test is 3/20/19.
This is well outside of the time frame required by UFC 3-600-01. Is there a more current flow test?
Utilize the flow test in the RFP
43 4/9/2025
6.
Engineer ing System Reqmts
B201009
B201009 Exterior Painting and Coatings states that even if metals are galvanized, they must receive a prime coat and two finish coats. This is not standard industry practice. Please confirm/clarify this requirement?
Follow the B201009 requirements:
“Coatings on ferrous and galvanized metal surfaces must be a prime coat and not less than two finish coats.”
48 4/9/2025 Room 104
Room 104 PT Open Office has acoustics being STC 50. This is an open area, please clarify how to achieve STC 50 for this space?
Per Part 3, Part 5 Room requirements room 104 Open Office is not open, it has one SCT50 Glazed Storefront Partition.
49 04/09/25 Acoustics
There are numerous rooms requiring STC 50 acoustics. Please confirm this high STC rating is required for all rooms STC 50 is designated for?
Yes. Comply with the STC 50 requirements
50 04/09/25 Room 215
Room 215 Cardio Mezzanine is required to have STC 50 acoustics.
The mezzanine is an open space to below. Please clarify how this open room can meet any acoustics requirements?
The STC 50 rating is required on the three walls to achieve STC in the adjacent rooms and corridor.
52 4/9/2025 361
P3, 5- Room
Require ments, 104 PT
Open Office
C103008, C103010
5 lft of counters and base cabinets are noted on room requirement table for
104. On both AE101 and IF101A, the furniture layout shown does not provide space for this casework and it is note shown. Confirm if casework is still required in 104 PT open office.
Yes, counters and case work are required.
53 4/9/2025 Part 3, Ch-6, Pg 2
C301004
A porcelain tile wall system is described detailing multiple tile types with a combination of 12x24 porcelain tile, designer decorative strips and pre-fabricated mosaic accent border. Can the breakdown of the two accent tiles be defined after 5'AFF? Are they equal parts 50/50?
The offeror’s DOR shall determine the tile wall design during the design process.
63 4/11/2025 Amend-ment PPIs
Amendments 0001 thru 0005 have been issued to date for this Solicitation.
There have been 28 PPI responses provided thus far with PPIs 1, 14, 22, 23, 24, 25, 26, (25% of the responses provided) having the response of "Bid per RFP." Please consider revisiting these PPIs and providing more definitive clarifying responses that better assist all MACC partners in accurately and responsibly providing a proposal for this Solicitation. We respectfully ask that evaluators please refrain from using this response for future PPIs as it provides no benefit in our proposal preparation efforts.
Many of the offeror’s PPIs ask for information that is provided in the DB RFP documents.
When the information is in the RFP documents, the Government will direct the offeror to the location in the RFP in lieu of addressing a question that could change the RFP contract requirements. When a PPI requires an architectural/engineering design decision – solution, the offeror should consult their DOR to provide the design – solution for competitive pricing.
66 4/9/2025
6.
Engineer ing System Reqmts
D30
D30 HVAC section did not see any requirements for outside HVAC equipment corrosive resistance requirements. Please provide.
See Part 3, Chapter 6 ESR, D30 HVAC for corrosive resistance. Page 6 specifies several corrosion resistance requirements. D304001, page 11 also addresses corrosion.
3. Incorporate Revised RFP requirements
Part 2 General Requirements 01 14 00 Work Restriction, Section 1.3.1.2.2 Finish Work
Change:
“Finish Work within the secure annex area must be accomplished by U.S. TOP SECRET-cleared personnel. Finish Work includes construction activities such as insulation, floor/partition/ceiling systems, cabinet work, conveyor systems, specialties, building furnishings/ fixtures/equipment, mechanical/electrical services and equipment including those specialized for fire protection, security, communication, control, energy conservation, safety, comfort, convenience, and similar purposes.”
To:
“Finish Work within the secure annex area must be accomplished by U.S. Citizen. Finish Work includes construction activities such as insulation, floor/partition/ceiling systems, cabinet work, conveyor systems, specialties, building furnishings/ fixtures/equipment, mechanical/electrical services and equipment including those specialized for fire protection, security, communication, control, energy conservation, safety, comfort, convenience, and similar purposes.”
Part 3 Chapter 3 Site Analysis, Paragraph 3.2.5 Electrical & Mechanical Equipment Pad Elevations, delete
Delete third paragraph in its entirety:
“(Note to NAVFAC reviewer: The top of electrical and mechanical equipment pad elevations may be Revised after the topographic survey is received.)”
Part 3 - Chapter 6 ESR, C101006 Glazed Partitions & Storefronts
Change:
“Provide glazed storefront system with a finish to match that of exterior system. Storefront system must be full height unless otherwise noted.”
To:
“Provide glazed storefront system with a finish to match that of exterior system. Storefront system must be full height unless otherwise noted. Where Chapter 5 Room Requirements require STC 50 Acoustics, provide a SCT 50 glazed storefront system.”
Part 3 – Chapter 6 ESR, Paragraph E20 Furnishings, page 2, last paragraph
Change:
The FF&E and A/V packages must be fully integrated into the design and construction schedule for the building. All submittal due dates for the SID, A/V and FF&E must be reflected in the Contractor’s construction schedule. The Contractor and the Contractor’s Interior Designer must strictly adhere the FF&E submittal schedule defined prior to the 35% design development to ensure that the final FF&E package is submitted no later than 9 months prior to building completion. Requests to change the SID or FF&E schedule must be submitted to the NAVFAC Interior Designer for review/recommendation and approved by the NAVFAC Contracting Officer
To:
The FF&E and A/V packages must be fully integrated into the design and construction schedule for the building. All submittal due dates for the SID, A/V and FF&E must be reflected in the Contractor’s construction schedule. The Contractor and the Contractor’s Interior Designer must strictly adhere the FF&E submittal schedule defined prior to the 35% design development to ensure that the final FF&E package is submitted no later than fifteen (15) months prior to building completion. Requests to change the SID or FF&E schedule must be submitted to the NAVFAC Interior Designer for review/recommendation and approved by the NAVFAC Contracting Officer
Part 3 – Chapter 6 ESR, B20 Exterior Closures, B202 Exterior Windows
Change:
“Provide windows in each area of the building that is regularly occupied, to enhance the working environment, without compromising visual acuity and comfort. Natural daylighting is preferred. Exterior windows must be prefinished aluminum. Windows must meet Antiterrorism requirements.”
To:
“Provide windows in each area of the building that is regularly occupied, to enhance the working environment, without compromising visual acuity and comfort. Natural daylighting is preferred. Exterior windows must be prefinished aluminum. If the Chapter 5, Room Requirements require STC 50, the windows must be STC50. Windows must meet Antiterrorism requirements.”
Part 2, Division 1 General Requirements, Section 01 31 19.05 20 Post Award Meetings, Paragraph 1.3.5.1 CDW General Requirements
Change:
“Contractor's Design Team. The primary functions of the Design Team will be to investigate, develop and present alternate design solutions. The entire Design Team must participate in all phases of the Concept Design Workshop effort and provide assistance to the Facilitator in development of the Concept Design Workshop Report, including most of the required documentation. Contractor shall retain the services of a Human Performance Center / Gymnasium equipment Subject Matter Expert (SME) to aid the design team for the equipment layout. SME shall have a minimum of five year's experience in equipment layouts for similar size and type facilities.
Responsibilities shall include:”
To:
“Contractor's Design Team. The primary functions of the Design Team will be to investigate, develop and present alternate design solutions. The entire Design Team must participate in all phases of the Concept Design Workshop effort and provide assistance to the Facilitator in development of the Concept Design Workshop Report, including most of the required documentation. Contractor shall retain the services of a Human Performance Center / Gymnasium equipment Subject Matter Expert (SME) to aid the design team for the equipment layout. SME shall have a minimum of five years of experience in equipment layouts for similar size and type facilities. Provide a two page SME resume seven (7) calendar before the PAK Meeting to the Contracting Officer for Government review.
Responsibilities shall include:”
Part 3, Chapter 6 ESR, Paragraph D30 HVAC, D304007 EXHAUST SYSTEMS
Change:
“Provide a type 316L stainless steel residential type hood (Type 2) over the teaching cooktop. Provide a variable speed direct drive roof mounted exhaust fan / ventilation system for the exhaust hood in the kitchen. Provide make-up air via transfer grille(s) to maintain the kitchen at slightly negative pressure with respect to adjacent spaces
To:
“Provide a type 316L stainless steel residential type hood over the teaching cooktop (Type 2) and the student cooktops (Type 1). Provide a variable speed direct drive roof mounted exhaust fan / ventilation system for the exhaust hood in the kitchen. Provide make-up air via transfer grille(s) to maintain the kitchen at slightly negative pressure with respect to adjacent spaces
Change:
“Provide double-wall casing construction with minimum R-13 insulation. Provide a weather resistant sloped roof. Provide closed cell foam gaskets between sections, providing thermal and acoustical break.”
To:
“Provide double-wall casing construction with minimum R-13 insulation. Provide a weather resistant roof. Provide closed cell foam gaskets between sections, providing thermal and acoustical break.”
Part 3 – Chapter 5 Room Requirements, Room 201 Kitchen
Change:
“D304007 Exhaust Systems 1 Exhaust hood over teaching cooktop”
To:
“D304007 Exhaust Systems 5 Exhaust hood over teaching and student cooktops”
Add:
C101005 Interior Window - Solid Surface Sills
4. Revised Factor 1 – Technical Solution
Factor 1 – Technical Solution:
From:
(i) Solicitation Submittal Requirements:
a) The Offeror shall provide a “Technical Approach Narrative” describing the technical solution to the project that meets the requirements of the RFP and that demonstrates the Offeror's ability to successfully perform this project in Joint Expeditionary Base (JEB) Little Creek, Virginia Beach, VA.
The narrative shall address major elements of work and demonstrate understanding of the scope, all phases and major milestones, technical complexities, and construction schedule required to achieve the work as identified in the solicitation. Identify activities that may affect the project timeline, including other/off site work activities. In addition, the plan shall address the following technical complexities:
1. Provide narrative discussing overall management and coordination of simultaneous construction activities with multiple disciplines.
2. Provide narrative addressing construction strategy for working in a confined site.
3. Provide narrative strategy in avoiding project schedule slippage due to material/equipment procurement or delivery delays.
b) Provide a “Labor Force Narrative” describing how the needed skilled labor forces will be provided and maintained throughout the duration of this construction contract for all labor forces at Joint Expeditionary Base Little Creek, Virginia Beach, VA. The narrative shall address at a minimum:
1. Securing the required non-skilled workforce/skilled work force to work the project and maintaining the workforce as needed.
2. Design Team, including a Human Performance Center / Gymnasium equipment Subject Matter Expert (SME). The SME shall have a minimum of five years of experience in equipment layouts for similar size and type of facilities. SME’s responsibilities shall include:
a. Provide appropriate equipment layouts on floor plans for optimal workout and traffic flow including required spacing around equipment for safe, effective use.
b. Provide location and layout of Electrical infrastructure for equipment. Review placement of TV monitors and equipment for optimal ergonomics, user comfort, and viewing.
c. Provide 3D visualization images of the facility.
3. Construction subcontractors (civil, structural, mechanical, and electrical) and their ability to provide skilled labor.
Both the Technical Approach Narrative and the Labor Force Narrative shall not exceed eight (8) single-sided pages combined. Up to four (4) drawings on separate sheets or separate PDF files can be provided to supplement the narratives and will not count towards the page limit.
c) Provide an overall Critical Path Method (CPM) schedule showing the timeline of the proposed designs and construction. There are no page restrictions on the CPM schedule.
TO:
(i) Solicitation Submittal Requirements:
a) The Offeror shall provide a “Technical Approach Narrative” describing the technical solution to the project that meets the requirements of the RFP and that demonstrates the Offeror's ability to successfully perform this project in Joint Expeditionary Base (JEB) Little Creek, Virginia Beach, VA.
The narrative shall address major elements of work and demonstrate understanding of the scope, all phases and major milestones, technical complexities, and construction schedule required to achieve the work as identified in the solicitation. Identify activities that may affect the project timeline, including other/off site work activities. In addition, the plan shall address the following technical complexities:
1. Provide narrative discussing overall management and coordination of simultaneous construction activities with multiple disciplines.
2. Provide narrative addressing construction strategy for working in a confined site.
3. Provide narrative strategy in avoiding project schedule slippage due to material/equipment procurement or delivery delays.
b) Provide a “Labor Force Narrative” describing how the needed skilled labor forces will be provided and maintained throughout the duration of this construction contract for all labor forces at Joint Expeditionary Base Little Creek, Virginia Beach, VA. The narrative shall address at a minimum:
1. Securing the required non-skilled workforce/skilled work force to work the project and maintaining the workforce as needed.
2. Construction subcontractors (civil, structural, mechanical, and electrical) and their ability to provide skilled labor.
Both the Technical Approach Narrative and the Labor Force Narrative shall not exceed ten (10) single-sided pages combined. Up to eight (8) drawings on separate sheets or separate PDF files can be provided to supplement the narratives and will not count towards the page limit.
c) Provide an overall Critical Path Method (CPM) schedule showing the timeline of the proposed designs and construction. There are no page restrictions on the CPM schedule.
5. Incorporate Attachment P – CJA ML-23-80-ML AMI
Attachment P is attached separately
6. Incorporate Attachment Q – Revised Price Proposal Form
Attachment Q is attached separately
7. Extend proposal due date from 09 May 2025 to 21 May 2025
The proposal due date is extended from 09 May 2025 to 21 May 2025 at 2:00 pm local time. The PPI cut off date will not be extended.
| 23R2656 Amendment 0001 |
| 23R2656 Amendment 0004 |
| Pages from 23R2541 Amendment 0003-2 |
Amendment 0001 continuation page
| topmostSubform[0]: |
| Page1[0]: |
| AmendmentNo[0]: 0009 |
| Code[0]: N40085 |
| Code[1]: |
| AccountingData[0]: |
| A13[0]: |
| C13[0]: |
| D13[0]: |
| NameandTitleSigner[0]: |
| NameandTitleOfficer[0]: |
| Description[0]: N40085-25-R-2563, Design-Build (DB), P 325 Human Performance Training Center, JEB Little Creek Fort Story, Virginia Beach, Virginia |
SEE SF 30 BLOCK 14 CONTINUATION PAGE
Contract POC: Angie Clifton, angela.j.clifton2.civ@us.navy.mil
| FacilityCode[0]: |
| Code[2]: |
| IssuedBy[0]: NAVFACYSCOM MID-ATLANTIC |
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK, VA 23511-3095
| NameandAddress[0]: |
| AdministeredBy[0]: See Item 6 |
| ContractIDCode[0]: |
| ReqNumber[0]: |
| AmendmentNo[1]: N4008525R2563 |
| ModificationNo[0]: |
| ProjectNo[0]: |
| Page[0]: 1 |
| Pages[0]: 21 |
| EffectiveDate[0]: 05/02/2025 |
| Dated9B[0]: 03/05/2025 |
| Dated10B[0]: |
| CheckBox9[0]: 1 |
| CheckBox10[0]: Off |
| CheckBox11[0]: 1 |
| CheckBox13A[0]: Off |
| CheckBox13B[0]: Off |
| CheckBox13C[0]: Off |
| CheckBox13D[0]: Off |
| IsNot[0]: Off |
| Is[0]: 1 |
| Extended[0]: 1 |
| NotExtended[0]: Off |
| DateSigned[0]: |
| DateSigned[1]: |
| Copies[0]: 1 |
| CopiesReturned[0]: 1 |