This document is a PPI (Preliminary Project Information) Revision Narratives document for the P-1538 SOF Armory project at MCB Camp Lejeune, NC. The document details extensive revisions to multiple drawing sheets and specifications across various disciplines including architectural, plumbing, mechanical, electrical, telecommunications, and civil engineering. Key modifications include adding compressed air drops, updating security bar requirements, adjusting gate and turnstile locations, adding AV backboxes and infrastructure details, and making numerous specification changes such as removing PVC shower pans, updating earthwork sections, and adding options for virtual meetings. The revisions appear to be part of a comprehensive design update for a military facility, with changes spanning from technical details like beam grades and concrete jointing to infrastructure elements like vehicle gates and fence grounding.

View the file

Other files

File Type Posted
N4008525R2507 Amendment 0013.pdf PDF
N4008525R2507 Amendment 0012.pdf PDF
N4008525R2507 Amendment 0011.pdf PDF
N4008525R2507 Amendment 0010.pdf PDF
N4008525R2507 Amendment 0009.pdf PDF
N4008525R2507 Amendment 0008.pdf PDF
P-1219PackageSewageLiftStationInfo.pdf PDF
Civil revisions narrative.docx DOCX document
Civil Dwg - Revised_v2.pdf PDF
N4008525R2507 Amendment 0007.pdf PDF
N4008525R2507 Amendment 0006.pdf PDF
N4008525R2507 Amendment 0005.pdf PDF
BLDG P1538-1701821-B-109-REV02.pdf PDF
2025 NEW UTILITIES RATES.pdf PDF
BLDG P1538-1701821-C-523-REV02.pdf PDF
Amendment 0004 SPC Revisions.pdf PDF
BLDG P1538-1701821-CG123-REV03.pdf PDF
Amendment 0004 - Revisions Narrative.pdf PDF
N4008525R2507 Amendment 0004.pdf PDF
Technical Amendment 0003 DWG.pdf PDF
Technical Amendment 0003 SPC.pdf PDF
N4008525R2507 Amendment 0003.pdf PDF
Attachment J - Price Proposal Form Rev1.docx DOCX document
N4008525R2507 Amendment 0002.pdf PDF
25R2507 (P1538 Seed Project) Site Visit Log.pdf PDF
MARSOC - Site Visit Contractor Access Roster.xlsx XLSX spreadsheet
Technical Amendment 0001.pdf PDF
N4008525R2507 Amendment 0001.pdf PDF
Attachment J - Price Proposal Form.docx DOCX document
Attachment I - P1538 DWG 6 of 6.pdf PDF
Attachment I - P1538 DWG 5 of 6.pdf PDF
Attachment D - Past Performance Questionnaire.docx DOCX document
N4008525R2507.pdf PDF
Attachment I - P1538 DWG 4 of 6.pdf PDF
Attachment F - Small Business Participation Commitment Document (SBPCD).docx DOCX document
Attachment C - Construction and Design Experience Project Data Sheet.docx DOCX document
Attachment B - PIEE Vendor Access Instructions.pdf PDF
Attachment I - P1538 DWG 3 of 6.pdf PDF
Attachment G - Small Business Subcontracting Plan (SBSP) Template.docx DOCX document
Attachment I - P1538 DWG 2 of 6.pdf PDF
Attachment I - P1538 DWG 1 of 6.pdf PDF
Attachment H - P1538 SPECS.pdf PDF
Attachment E - Historical Small Business Utilization.docx DOCX document
Attachment A - PPI Log Template.xlsx XLSX spreadsheet
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P‐1538 SOF Armory MCB Camp Lejeune, NC MBFA No: 2202

PPI Revision Narratives Date: September 19, 2025

Drawings

Sheet CD100: Added additional demolition note #11

Sheet CD101: Updated keynote #8 to demolish the existing power pole and guy wires

Sheet CS101: Moved the turnstile and concrete sidewalk far enough from the sliding gate plan west of them so that there is sufficient clearance for the gate to open

Sheet CS103: Add jointing plan

Sheet CG101: Updated the 24’ contour and sidewalk spot elevations

Sheet CG123: Added keynote #15 and layer controlled to show the gravel filter strip

Sheet CU101: Corrected keynotes #1 and #2; Deleted keynotes #19 and #26 and associated blocks in the model file

Sheet CU207: Corrected profiles A1 and A4

Sheet CU208: Corrected profile A2

Sheet C‐511: Deleted detail C2, Asphalt Pavement Patch

Sheet C‐512: Added Card Reader and Card Reader Pedestal details

Sheet C‐513: Added NCDEQ Permanent Seeding detail

Sheet C‐516: Added concrete jointing details

Sheet S‐003: Wide flange beam grade updated to A992 & deck primer requirement removed

Sheet A‐105: Tagged Bulkhead keynotes and tagged vault head ceilings

Sheet A‐304: Deleted insulation at entry roof and corrected slope tag

Sheet A‐403: Added locker tags

Sheet A‐503: Added bulkhead at stair

Sheet A‐505: Added “T” seam detail

Sheet I‐101: CFCI schedule updated to show dimensions

Sheet I‐102: CFCI schedule updated to show dimensions

Sheet I‐103: CFCI schedule updated to show dimensions

Sheet I‐601: Room finish schedule corrected; painted ceilings updated to PNT‐5

Sheet I‐602: Sealed Concrete MFG and info added

Sheet I‐602: WS‐2 Blackout Roller shade added

Sheet P‐107: A3/P‐107 – FLOOR PLAN – AREA B – WATER & COMPRESSED AIR: Added plan note #1 to include the additional ¾” Compressed air drops to hose reels

Sheet P‐501: C4/P‐501 – PLUMBING DETAILS: Removed the seismic bracing detail because it is not applicable for this project

Sheet MH401: Revised note #4 from ‘PROVIDE SECURITY BARS IN DUCT PENETRATION OF MECHANICAL

ROOM. PROVIDE ACCESS DOOR ON SECURE SIDE OF WALL.’ To ‘PROVIDE SECURITY BARS IN ANY DUCT

PENETRATION OF VAULT ASSEMBLY THAT EXCEEDS 96 SQUARE INCHES. PROVIDE ACCESS DOOR ON

SECURE SIDE OF WALL.’

Sheet M‐507: Added detail C1/M‐507 ‘BURIED PREINSULATED CHILLED WATER PIPING DETAIL’

Sheet ES101: Added vehicle gate infrastructure and adjusted turnstile location.

Sheet ES503: Added vehicle gate and turnstile details.

Sheet ES504: Added gate and fence grounding details.

Sheet E‐101: Added receptacles for AV backboxes and racks in Floor Plan Area ‘A’ ‐ Power.

Sheet E‐102: Added duplex receptacles for AV backboxes in Floor Plan Area ‘B’ ‐ Power.

Sheet E‐602: Updated panel schedule for panel ‘P1B’.

Sheet T‐001: Added AV symbols and descriptions to legend.

Sheet T‐101: Added AV backboxes, wall inputs, and ceiling speakers in Floor Plan Area ‘A’ ‐

Telecommunications.

Sheet T‐102: Added AV backboxes and wall inputs in Floor Plan Area ‘B’ ‐ Telecommunications.

Specifications

Tabel of Contents: Revised

Submittal Register: Revised

03 30 00, 3.10.2: Slab FF/FL requirements for industrial construction removed

03 30 00, 3.5.8: Note revised to allow field bending of reinforcing bars up to #5

10 11 00: added to the project

10 51 13: Revised Section to eliminate single tier lockers and add locker benches

12 00 01.00 20: 3.1.2.8 – Added the option for a virtual OTS meeting

22 00 00: Deleted PVC shower pans.

31 00 00: Sections 3.3.3, 3.4.3, 3.4.5, 3.6.2, 3.6.6.1, and 3.6.6.2 have been updated

32 01 16.71: has been removed

32 12 13: has been removed

32 12 16.16: has been removed

32 16 19: Spec has been edited to remove all items related to curb and gutter

33 05 07.13: Spec has been removed.

33 05 23: has been added

33 40 00: Section 2.4.1 and 3.8.1 have been removed