About this file

This is an Amendment of Solicitation for a Design-Build/Design-Bid-Build (DB/DBB) Indefinite Delivery/Indefinite Quantity (IDIQ) Multiple Award Construction Contract for General Construction Services to serve NAVFAC Mid-Atlantic's Marine Corps Installations East Area of Responsibility, specifically for Project P-1538 SOF Armory at Marine Corps Base Camp Lejeune, North Carolina. The project involves constructing a SOF Armory building with supporting site infrastructure, including domestic water, sanitary sewer, and communications utility distributions, along with parking lots, tactical drives, compound fencing, and related improvements.

The solicitation includes several Contract Line Items (CLINs): a base price for the entire project, optional items for Audio Visual System equipment, Furniture/Fixtures/Equipment, geotechnical soil work, surplus soil handling, and demolition of unforeseen buried debris. The estimated budget ranges between $10-25 million, with a desired completion time of 835 calendar days. Contractors must use the updated Wage Determination (NC20260010) dated 01/02/2026, and the proposal due date is 28 January 2026. Liquidated damages are set at $2,457.95 per calendar day of delay, and contractors must submit past performance projects completed within the past seven years.

View the file

Other files

File Type Posted
N4008525R2507 Amendment 0013.pdf PDF
N4008525R2507 Amendment 0012.pdf PDF
N4008525R2507 Amendment 0011.pdf PDF
N4008525R2507 Amendment 0010.pdf PDF
N4008525R2507 Amendment 0009.pdf PDF
P-1219PackageSewageLiftStationInfo.pdf PDF
Civil revisions narrative.docx DOCX document
Civil Dwg - Revised_v2.pdf PDF
N4008525R2507 Amendment 0007.pdf PDF
N4008525R2507 Amendment 0006.pdf PDF
N4008525R2507 Amendment 0005.pdf PDF
2025 NEW UTILITIES RATES.pdf PDF
BLDG P1538-1701821-C-523-REV02.pdf PDF
BLDG P1538-1701821-B-109-REV02.pdf PDF
Amendment 0004 SPC Revisions.pdf PDF
BLDG P1538-1701821-CG123-REV03.pdf PDF
Amendment 0004 - Revisions Narrative.pdf PDF
N4008525R2507 Amendment 0004.pdf PDF
Technical Amendment 0003 DWG.pdf PDF
Technical Amendment 0003 SPC.pdf PDF
Technical Amendment 0003 - Revisions Narrative.pdf PDF
N4008525R2507 Amendment 0003.pdf PDF
Attachment J - Price Proposal Form Rev1.docx DOCX document
N4008525R2507 Amendment 0002.pdf PDF
25R2507 (P1538 Seed Project) Site Visit Log.pdf PDF
Technical Amendment 0001.pdf PDF
N4008525R2507 Amendment 0001.pdf PDF
MARSOC - Site Visit Contractor Access Roster.xlsx XLSX spreadsheet
Attachment I - P1538 DWG 4 of 6.pdf PDF
Attachment F - Small Business Participation Commitment Document (SBPCD).docx DOCX document
Attachment C - Construction and Design Experience Project Data Sheet.docx DOCX document
Attachment B - PIEE Vendor Access Instructions.pdf PDF
Attachment J - Price Proposal Form.docx DOCX document
Attachment I - P1538 DWG 6 of 6.pdf PDF
Attachment I - P1538 DWG 5 of 6.pdf PDF
Attachment D - Past Performance Questionnaire.docx DOCX document
N4008525R2507.pdf PDF
Attachment I - P1538 DWG 3 of 6.pdf PDF
Attachment G - Small Business Subcontracting Plan (SBSP) Template.docx DOCX document
Attachment I - P1538 DWG 2 of 6.pdf PDF
Attachment I - P1538 DWG 1 of 6.pdf PDF
Attachment H - P1538 SPECS.pdf PDF
Attachment E - Historical Small Business Utilization.docx DOCX document
Attachment A - PPI Log Template.xlsx XLSX spreadsheet
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Block 14 (Description of Amendment/Modification): Design-Build/Design-Bid-Build (DB/DBB), Indefinite Delivery/Indefinite Quantity (IDIQ) Multiple Award Construction Contract (MACC) for General Construction Services to Serve NAVFAC Mid-Atlantic's Marine Corps Installations (MCI) East AOR Including North Carolina and South Carolina

The proposal due date of 28 January 2026 NLT 2:00 PM EST has not been extended.

The Amendment is issued to incorporate the following:

1. Provide revised Wage Determination, General Decision Number NC20260010 dated 02 January 2026.

2. Provide revised PPI responses.

(End of Summary of Changes)

Section 00 73 00 - Supplementary Conditions

Miscellaneous text in this section has been modified to:

This Contract (or Purchase Order) contains rated order quantities certified for national defense use, and you are required to follow all the provisions of the DPAS regulation (DPAS Regulation - 15 CFR Part 700.12) only as it pertains to the rated quantities.

PGI PAYMENT INSTRUCTIONS

The Procedures, Guidance and Information (PGI), Section 204.7108 link provides a standard set of payment instructions (in table format) that defines how payments should be made based on the payment request type and the service being acquired.

The link to the PGI table is as follows: https://www.acq.osd.mil/dpap/dars/pgi/pgi_htm/current/PGI204_71.htm#payment_instructions

SUPPLEMENTAL LANGUAGE

AUTHORITY

1. No person other than the Contracting Officer has authority to bind the Government with respect to this contract.

2. No action or omission of any government employee or representative other than the Contracting Officer shall increase or decrease the scope of this contract or shall otherwise modify the terms and conditions of this contract.

3. In no event shall any of the following be effective or binding on the Government or imputed to the Contracting Officer with respect to this contract:

(a) An understanding or agreement between the Contractor and anyone other than the Contracting Officer;

(b) A purported modification or change order issued by anyone other than the Contracting Officer;

(c) A promise by anyone other than the Contracting Officer to provide additional funding or make payments; or

(d) An order, direction, consent, or permission from anyone other than the Contracting Officer to:

(i) Incur costs in excess of a specified estimated cost, allotment of funds, or other ceiling; or

(ii) Expend hours in excess of a specified level of effort.

(End of language)

NOTICE OF BONDING REQUIREMENTS

Within 10 days after receipt of award, the offeror to whom the award is made shall furnish the bonds required by FAR Clause 52.228-15.

Offerors are hereby notified that the contract time for purposes of fixing the completion date, default, and liquidated damages will be as stated in FAR Clause 52.211-10 Commencement, Prosecution, and Completion of Work, regardless of when performance and payment bonds or deposits in lieu of surety are executed.

(End of language)

N4008525R25070008 https://www.acq.osd.mil/dpap/dars/pgi/pgi_htm/current/PGI204_71.htm#payment_instructions

UTILITIES FOR CONSTRUCTION AND TESTING

The Contractor shall be responsible for obtaining, either from available Government sources or local utility companies, all utilities required for construction and testing. The Contractor shall provide these utilities at his expense, paid for at the current utility rate delivered to the job site. The Contractor shall provide and maintain all temporary utility connections and distribution lines, and all meters required to measure the amount of each utility used.

(End of language)

MINIMUM INSURANCE REQUIREMENTS

In accordance with FAR 28.307-2, the coverage specified below is the minimum insurance required for this contract:

(a) Workers' compensation and employer's liability. Contractors are required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers. (See 28.305(c) for treatment of contracts subject to the Defense Base Act.)

(b) General liability.

(1) The contracting officer shall require bodily injury liability insurance coverage written on the comprehensive form of policy of at least $500,000 per occurrence.

(2) Property damage liability insurance shall be required only in special circumstances as determined by the agency.

(c) Automobile liability. The contracting officer shall require automobile liability insurance written on the comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.

(d) Aircraft public and passenger liability. When aircraft are used in connection with performing the contract, the contracting officer shall require aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger liability, and $200,000 per occurrence for property damage. Coverage for passenger liability bodily injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

(e) Vessel liability. When contract performance involves use of vessels, the contracting officer shall require, as determined by the agency, vessel collision liability and protection and indemnity liability insurance. The certificate shall contain an endorsement to the effect that cancellation or any material change in the policies adversely affecting the interests of the Government in such insurance shall not be effective until 30 days after written notice thereof to the Contracting Officer.

(End of language)

CONTRACTOR PERFORMANCE INFORMATION

Contractor Performance Information: Contractor's performance will be evaluated using the respective contractor performance evaluation report entry system located on the website http://www.cpars.gov/. Prior to commencement of work, the contractor is required to provide the government with the name, phone number, and email address of the "Contractor's Representative" that will be responsible for receipt and review of draft performance evaluations prepared by the government in the appropriated system. It is the contractor's responsibility to keep this contract information current.

(End of language)

DEFINITIZATION OF EQUITABLE ADJUSTMENTS FOR CHANGE ORDERS UNDER CONSTRUCTION CONTRACTS

1. No data is available regarding the timely definitization of equitable adjustments for change orders under construction contracts.

2. The REA definitization information referenced in Navy Marine Corps Acquisition Regulation Supplement (NMCARS) 5236.211(b)(2), should not be utilized.

3. There are no agency-specific policies and procedures that apply to the definitization of equitable adjustments for change orders under construction contracts.

(End of language)

GENERAL REQUIREMENTS

GENERAL REQUIREMENTS FOR THE SEED PROJECT

N4008525R25070008

NAVFAC Solicitation No.: N4008525R2507

Title: P-1538 SOF Armory

Location of the Work: MARSOC Complex, Stone Bay, Marine Corps Base (MCB) Camp Lejeune, NC

Description of the Work: This project provides the Construction of an SOF Armory building, supporting site infrastructure extensions, and distribution and improvements. Site infrastructure includes domestic water distribution, sanitary sewer distribution, and communications utility distribution. Site improvements include POV parking lots, tactical drives and aprons, Armory compound fencing and MARSOC installation fencing perimeter, and incidental related work.

See drawings and specifications for full description.

The following CLINs will be included in the solicitation:

CLIN 0001 - Base Price - Total Price for the entire work for Project P-1538 SOF Armory in accordance with the drawings and specifications, complete, but excluding work provided in another Priced line Item.

CLIN 0002 - Option Item No. 1 - Price for providing Audio Visual System (A/V) Equipment, testing, and associated training in accordance with the drawings and specifications, but excluding work provided in another Priced line item.. Equipment includes, but is not limited to, items such as flat panel monitors, projectors, wall input boxes, touch screens, push button control panels, video teleconferencing codecs, microphones, speakers and the communication cabling connecting these devices together.

CLIN 0003 - Option Item No. 2 - Price for providing work in connection with labor, material, equipment, transportation and supervision required for the Furniture, Fixtures, and Equipment (FF&E), complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.

CLIN 0004 - Option Item No. 3 - Unit Price for undercut and temporary stockpiling of additional geotechnically unsuitable subgrade soils and replacement with imported structural fill material or with NCDOT #57 crushed stone, complete in accordance with the drawings and specifications, but excluding work provided in another Line Item. Disposal of impacted surplus media will be covered under a separate CLIN.

CLIN 0005 - Option Item No. 4 - Unit Price for handling, storage, sampling, and analysis of non-hazardous impacted surplus soil media including but limited to PFAS, petroleum, VOC's and metals for treatment and disposal at a licensed facility, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item.

CLIN 0006 - Option Item No. 5 - Unit Price for demolition, removal and disposal of unforeseen buried debris, structures, pipes and concrete below grade 1/2 CY and larger in size encountered within the planned excavation limits complete in accordance with the drawings and specifications, but excluding work provided in another line item.

Estimated Budget Amount or Price Range: In accordance with DFARS 236.204, the magnitude of construction for the seed project is between $10,000,000 and $25,000,000.

Time for Completion: In accordance with FAR 52.211-10 Commencement, Prosecution, and Completion of Work, the Government desires completion of construction within 835 calendar days after award (includes fifteen (15) calendar days for submission and approval of bonds and insurance).

Wage Determination: Department of Labor (DoL) General Decision Number NC20250010 01/03/2025 applies to this work. Should this wage determination be modified by DOL prior to award, the most current wage determination will be incorporated at the time of award.

Liquidated Damages: In accordance with FAR 52.211-12 Liquidated Damages, if the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $2,457.95 for each calendar day of delay until the work is completed or accepted.

Utilities: In accordance with FAR 52.236-14 Availability and Use of Utility Services, the Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. Unless otherwise provided in the contract, the amount of each utility service consumed shall be charged to or paid for by the Contractor at prevailing rates charged to the Government or, where the utility is produced by the Government, at reasonable rates determined by the Contracting Officer. The Contractor shall carefully conserve any utilities furnished without charge.

Record Shop Drawings: In accordance with FAR 52.236-21 Specifications and Drawings for Construction, record shop drawings are required.

Reproducible copies of these record drawings are also required.

Bond Requirements: In accordance with FAR 52.228-1 Bid Guarantee, each offeror shall submit with its offer a guarantee bond (Standard Form 24) in a penal sum equal to at least 20 percent of the offer price or $3,000,000, whichever is less.

Proposal Acceptance Period: Proposal acceptance period shall be 120 days from receipt of offers.

Pursuant to FAR 52.232-18, Availability of Funds, the Government's obligation under this solicitation, or any task order or contract that might result from the solicitation is entirely subject to, and contingent upon, the availability of appropriated funds. Should the Government be unable to award the seed project, the Government guarantees an award in the amount of $5,000 to each successful offeror upon award of the Multiple Award Construction Contracts. This minimum guarantee is over the full term of the contract, including option years. No legal liability on the part of the Government shall arise until funds are made available to the Contracting Officer and a task order or contract is awarded by the Contracting Officer. Any offeror proposing on this solicitation does so at its own cost and with the full knowledge that a task order for the seed project, might not result from this solicitation.

Evaluation Factors for Award: Refer to Section 00 21 00 - Instructions to Offerors of the SF1442, 4. Evaluation Factors for Award

Site Visit: Refer to Section 00 21 00 - Instruction to Offerors of the SF1442, 5. Proposal Requirements, 5.1 Site Visit

Pre-Proposal Inquiries (PPIs): Submit in accordance with Section 00 21 00, Instruction to Offerors of the SF1442, 5. Proposal Requirements, 5.3 Pre-Proposal Inquiries (PPIs).

Please submit in accordance with Section 00 21 00 INSTRUCTIONS TO OFFERORS of the SF1442, 5. PROPOSAL REQUIREMENTS, 5.2

PROPOSAL SUBMISSION INSTRUCTIONS

Attachments:

ATTACHMENT H - P1538 SPECS

ATTACHMENT I - P1538 DWG

ATTACHMENT J - PRICE PROPOSAL FORM

WAGE DETERMINATION

"General Decision Number: NC20260010 01/02/2026

Superseded General Decision Number: NC20250010

State: North Carolina

Construction Type: Building

County: Onslow County in North Carolina.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Modification Number Publication Date 0 01/02/2026

IRON0848-003 07/01/2025

Rates Fringes

IRONWORKER..............................................$ 29.75 18.00

PLUM0421-006 07/01/2023

Rates Fringes

PIPEFITTER...................................................$ 33.96 13.48

SUNC2018-010 08/08/2023

Rates Fringes

BRICKLAYER.................................................$ 19.13 0.00

CARPENTER, Excludes Form Work............$ 18.11 2.63

CEMENT MASON/CONCRETE FINISHER....$ 16.72 0.00

ELECTRICIAN................................................$ 22.15 5.93

FORM WORKER...........................................$ 14.51 1.88

LABORER: Common or General................$ 11.98 0.81

LABORER: Mason Tender - Brick...............$ 13.17 0.00

LABORER: Mason Tender - Cement/Concrete........................................$ 15.26 0.00

LABORER: Pipelayer....................................$ 16.33 3.11

OPERATOR:

Backhoe/Excavator/Trackhoe...................$ 21.00 2.89

OPERATOR: Bulldozer.................................$ 17.54 2.63

OPERATOR: Forklift.....................................$ 16.75 0.00

OPERATOR: Grader/Blade..........................$ 22.68 3.27

OPERATOR: Roller.......................................$ 15.31 1.46

PAINTER.......................................................$ 15.55 1.05

PLUMBER.....................................................$ 23.11 0.00

ROOFER........................................................$ 18.26 4.38

SHEET METAL WORKER..............................$ 19.67 13.27

TRUCK DRIVER: Dump Truck.....................$ 15.98 2.93

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded.

If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.30 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in 2025. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.

Union Rate Identifiers

A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.

0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.

Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.

Union Average Rate Identifiers

The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:

UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.

The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.

A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.

Survey Rate Identifiers

The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.

?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).

State Adopted Rate Identifiers

The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.

The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.

WAGE DETERMINATION APPEALS PROCESS

1) Has there been an initial decision in the matter? This can be:

a) a survey underlying a wage determination

b) an existing published wage determination

c) an initial WHD letter setting forth a position on a wage determination matter

d) an initial conformance (additional classification and rate) determination

On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:

Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.

Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).

Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210.

END OF GENERAL DECISION"

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

2. Revised PPI Responses (changes denoted in red below):

Date

Submitted

Reference

Question Government Response

Page Section Para.

8/21/25 10 of 62 SF1442 In SF1442, the past performance projects must be completed within

5 years of the date of issuance of this RFP. It is requested to revise the project completion from the date of issuance of the RFP to the date of submission of proposals.

This will allow for evaluation of the most recent contractor project experiences by providing a more up-to-date and accurate presentation of contractor capabilities and performance history. It may also help the

Government mitigate the risk of awarding contracts based on potentially outdated or less relevant project experiences.

Lastly, it will also enhance competition by attracting a wider pool of qualified firms.

Please bid per RFP. Projects submitted for the offeror shall have been completed within the past seven (7) years of the date of issuance of this RFP.

09/09/25 General For planning the preliminary project schedule, what is the anticipated award date?

Use an estimated contract award date of 30 APRIL 2026.

Please note, this is an estimated date for proposal purposes only and not dispositive of an anticipated/actual award date.

(End of Summary of Changes)

IDCode: J
Page: 1
Pages: 9
AmendNo: 0008
EffDate: 06 Jan 2026
ReqNo: See Continuation Sheet
ProjNo: WON 1814107
IssCode: N40085
AdmCode:
IssuedBy: NAVFACSYSCOM MID-ATLANTIC

9324 VIRGINIA AVENUE, NORFOLK VA 23511-0395

NORFOLK, VA 23511-0395

UNITED STATES

James Godwin, Email: james.a.godwin41.civ@us.navy.mil Telephone: 7573411999 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: N4008525R2507
SolDate: 06 Aug 2025
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: See Section 00 70 00 - Conditions of the Contract
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: See Schedule
ContNameTitle:
CoNameTitle: JAMES A. GODWIN
ContDate:
CODate: 06 Jan 2026

File details come from the government source that posted it. Updated .