eProjects Work Order Number: 1701821 Appropriation:
P-1538
SOF ARMORY
At the
MARSOC COMPLEX, STONE BAY, MARINE CORPS BASE
CAMP LEJEUNE, NC
DESIGNED BY:
MBF ARCHITECTS, P.A.
317-C POLLOCK ST.
NEW BERN, NC 28560
SPECIFICATION PREPARED BY:
Architectural: MBF Architects Civil: Stantec
Structural: Kaydos-Daniels Engineering Interior Design: Within Interior Design
Mechanical/Plumbing/Electrical: Crenshaw Consulting Eng.
Fire Prot.: Jensen Hughes
Audio Video: Thorburn
Specification: Darden J. Eure, III, MBF Architects
Date: 10 October 2024
SPECIFICATION APPROVED BY:
For Commander, NAVFAC MID-ATLANTIC:
Date:
10.8.2024
This page is intentionally left blank.
P-1538 SOF ARMORY eProjects Work Order: 1701821 MARSOC, Stone Bay, MCB Camp Lejeune, NC 8 October 2024
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/11, CHG 1: 08/14 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 04/22 SUMMARY OF WORK
01 14 00 04/22 WORK RESTRICTIONS (MCBL)
01 20 00 04/22 PRICE AND PAYMENT PROCEDURES (MCBCL)
01 30 00 01/23 ADMINISTRATIVE REQUIREMENTS
01 30 02.00 22 05/23 DESIGN, PROCUREMENT, AND INSTALLATION
OF AUDIOVISUAL EQUIPMENT
01 32 17.00 20 05/18, CHG 3: 08/20 COST-LOADED NETWORK ANALYSIS SCHEDULES NAS
SUBMITTAL REGISTER
01 33 00 04/22 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND REPORTING
HPSB CHECKLISTS
01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 29.13 11/15, CHG 1: 08/22 HEALTH, SAFETY, AND EMERGENCY RESPONSE
PROCEDURES FOR CONTAMINATED SITES
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23 QUALITY CONTROL
01 45 35 11/20 SPECIAL INSPECTIONS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 08/19, CHG 5: 08/22 PROJECT IDENTIFICATION
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 04/22 CLOSEOUT SUBMITTALS
01 78 23 04/22 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 03/23 FACILITY ELECTRONIC OPERATION AND
MAINTENANCE SUPPORT INFORMATION (eOMSI)
01 78 30.00 22 5/22 GIS DATA DELIVERABLES
01 91 00.15 05/23 BUILDING COMMISSIONING
01 91 19 05/23 BUILDING ENCLOSURE COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 4: 08/22 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY
DIVISION 05 - METALS
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 21 00 05/15, CHG 1: 08/18 STEEL JOIST FRAMING
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
05 51 00 02/17, CHG 1: 05/17 METAL STAIRS
05 52 00 02/18, CHG 1: 02/20 METAL RAILINGS
PROJECT TABLE OF CONTENTS Page 1
SCHEDULE OF FIRE PROTECTION SYSTEM INSPECTIONS
STATEMENT OF SPECIAL INSPECTIONS
SCHEDULE OF SPECIAL INSPECTIONS
PROJECT SIGN DETAILS
06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY
06 20 01 08/16, CHG 2: 11/18 CHAIR RAIL FINISH CARPENTRY
06 41 16.00 10 08/10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 08/19 PRESSURE TESTING AN AIR BARRIER SYSTEM
FOR AIR TIGHTNESS
07 21 13 02/16, CHG 2: 08/20 BOARD AND BLOCK INSULATION
07 21 16 11/11, CHG 4: 08/18 MINERAL FIBER BLANKET INSULATION
07 22 00 02/16, CHG 3: 11/18 ROOF AND DECK INSULATION
07 27 10.00 10 08/19, CHG 1: 02/20 BUILDING AIR BARRIER SYSTEM
07 27 19.01 05/17, CHG 2: 08/20 SELF-ADHERING AIR BARRIERS
07 27 26 05/17, CHG 2: 08/20 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 27 36 05/17, CHG 3: 02/23 SPRAY FOAM AIR BARRIERS
07 42 13 05/11, CHG 2: 02/18 METAL WALL PANELS
07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL
07 61 15.00 20 08 March 2021 CL ALUMINUM STANDING SEAM ROOFING
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 14 00 08/16, CHG 1: 08/18 WOOD DOORS
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 33 23 08/20, CHG 1: 02/22 STEEL OVERHEAD COILING DOORS
08 34 59 08/08, CHG 1: 11/12 VAULT DOORS AND DAY GATES
08 41 13 08/18, CHG 1: 08/18 ALUMINUM-FRAMED STOREFRONTS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 08/20 ALUMINUM METAL LOUVERS
DIVISION 09 - FINISHES
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
09 30 10 08/20 CERAMIC TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING
09 66 23 08/16, CHG 1: 08/18 RESINOUS MATRIX TERRAZZO FLOORING
09 68 00 11/17, CHG 2: 08/20 CARPET TILE
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE
10 14 00.20 08/20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 22 13 08/16, CHG 1: 08/18 WIRE MESH PARTITIONS
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 51 13 05/11 PLASTIC LOCKERS
DIVISION 12 - FURNISHINGS
PROJECT TABLE OF CONTENTS Page 2
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
12 00 01.00 20 02/23 FURNITURE, FIXTURES AND EQUIPMENT
(FF&E) PACKAGE
12 24 13 08/20 ROLLER WINDOW SHADES
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
DIVISION 22 - PLUMBING
22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48.19 05/18 SEISMIC BRACING FOR HVAC
23 05 93.00 22 09/19 TESTING, ADJUSTING, AND BALANCING FOR
MECHANICAL SYSTEMS
23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 08 00 05/23 COMMISSIONING OF MECHANICAL AND
PLUMBING SYSTEMS
23 09 23.13 08/24 BACnet DIRECT DIGITAL CONTROL SYSTEMS
FOR HVAC
23 11 20 05/20 FACILITY GAS PIPING
23 21 13.00 20 04/06, CHG 2: 11/19 LOW TEMPERATURE WATER (LTW) HEATING
SYSTEM
23 23 00 08/21 REFRIGERANT PIPING
23 25 00 05/21 CHEMICAL TREATMENT OF WATER FOR
MECHANICAL SYSTEMS
23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION
23 52 43.00 20 05/15 LOW PRESSURE WATER HEATING BOILERS
(UNDER 800,000 BTU/HR OUTPUT)
23 64 10 11/16 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 08/09, CHG 5: 11/19 CHILLED WATER PIPING SYSTEMS
23 81 00 05/18 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.00 09/22 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - ISOLATED SYSTEMS
DIVISION 26 - ELECTRICAL
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 12 19.10 05/19, CHG 1: 11/19 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED
TRANSFORMERS
26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM
26 27 14.00 20 02/21, CHG 1: 05/21 ELECTRICITY METERING
26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION
26 41 00 11/13 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 01/24 BUILDING TELECOMMUNICATIONS CABLING
PROJECT TABLE OF CONTENTS Page 3
SYSTEM (MCBCL)
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 08/23 EARTHWORK
31 11 00 11/18 CLEARING AND GRUBBING
31 31 16.13 08/22 CHEMICAL TERMITE CONTROL
31 32 19.16 02/21 GEOTEXTILE SOIL STABILIZATION
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 16.71 11/22 COLD MILLING ASPHALT PAVING
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
32 11 23 05/22 AGGREGATE BASE COURSE FOR FLEXIBLE
PAVING
32 12 13 05/17 BITUMINOUS TACK COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 31 13 11/21 CHAIN LINK FENCES AND GATES
32 92 23 04/06, CHG 1: 08/21 SODDING
DIVISION 33 - UTILITIES
33 05 07.13 02/24 UTILITY DIRECTIONAL DRILLING
33 11 00 02/18, CHG 2: 11/23 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 31 23.00 10 08/18 SANITARY SEWER FORCE MAIN PIPING
33 32 16 11/19, CHG 1: 11/23 PACKAGED UTILITY WASTEWATER PUMPING
STATIONS
33 40 00 11/21 STORMWATER UTILITIES
33 71 01 05/19, CHG 1: 11/19 OVERHEAD TRANSMISSION AND DISTRIBUTION
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 08/22 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4 eProjects Work Order Number: 1701821 Appropriation:
P-1538
SOF ARMORY
At the
MARSOC COMPLEX, STONE BAY, MARINE CORPS BASE
CAMP LEJEUNE, NC
DESIGNED BY:
MBF ARCHITECTS, P.A.
317-C POLLOCK ST.
NEW BERN, NC 28560
SPECIFICATION PREPARED BY:
Architectural: MBF Architects Civil: Stantec
Structural: Kaydos-Daniels Engineering Interior Design: Within Interior Design
Mechanical/Plumbing/Electrical: Crenshaw Consulting Eng.
Fire Prot.: Jensen Hughes
Audio Video: Thorburn
Specification: Darden J. Eure, III, MBF Architects
Date: 10 October 2024
SPECIFICATION APPROVED BY:
For Commander, NAVFAC MID-ATLANTIC:
Date:
VOLUME 1 of 2 Division 00 - 12
VOLUME 1 (Division 00-12)
TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/11, CHG 1: 08/14 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 04/22 SUMMARY OF WORK
01 14 00 04/22 WORK RESTRICTIONS (MCBL)
01 20 00 04/22 PRICE AND PAYMENT PROCEDURES (MCBCL)
01 30 00 01/23 ADMINISTRATIVE REQUIREMENTS
01 30 02.00 22 05/23 DESIGN, PROCUREMENT, AND INSTALLATION
OF AUDIOVISUAL EQUIPMENT
01 32 17.00 20 05/18, CHG 3: 08/20 COST-LOADED NETWORK ANALYSIS SCHEDULES NAS
SUBMITTAL REGISTER
01 33 00 04/22 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND REPORTING
HPSB CHECKLISTS
01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 29.13 11/15, CHG 1: 08/22 HEALTH, SAFETY, AND EMERGENCY RESPONSE
PROCEDURES FOR CONTAMINATED SITES
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23 QUALITY CONTROL
01 45 35 11/20 SPECIAL INSPECTIONS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 08/19, CHG 5: 08/22 PROJECT IDENTIFICATION
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 04/22 CLOSEOUT SUBMITTALS
01 78 23 04/22 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 03/23 FACILITY ELECTRONIC OPERATION AND
MAINTENANCE SUPPORT INFORMATION (eOMSI)
01 78 30.00 22 5/22 GIS DATA DELIVERABLES
01 91 00.15 05/23 BUILDING COMMISSIONING
01 91 19 05/23 BUILDING ENCLOSURE COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 4: 08/22 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY
DIVISION 05 - METALS
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 21 00 05/15, CHG 1: 08/18 STEEL JOIST FRAMING
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
05 51 00 02/17, CHG 1: 05/17 METAL STAIRS
05 52 00 02/18, CHG 1: 02/20 METAL RAILINGS
VOLUME 1 - TABLE OF CONTENTS Page 1
SCHEDULE OF FIRE PROTECTION SYSTEM INSPECTIONS
STATEMENT OF SPECIAL INSPECTIONS
SCHEDULE OF SPECIAL INSPECTIONS
PROJECT SIGN DETAILS
06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY
06 20 01 08/16, CHG 2: 11/18 CHAIR RAIL FINISH CARPENTRY
06 41 16.00 10 08/10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 08/19 PRESSURE TESTING AN AIR BARRIER SYSTEM
FOR AIR TIGHTNESS
07 21 13 02/16, CHG 2: 08/20 BOARD AND BLOCK INSULATION
07 21 16 11/11, CHG 4: 08/18 MINERAL FIBER BLANKET INSULATION
07 22 00 02/16, CHG 3: 11/18 ROOF AND DECK INSULATION
07 27 10.00 10 08/19, CHG 1: 02/20 BUILDING AIR BARRIER SYSTEM
07 27 19.01 05/17, CHG 2: 08/20 SELF-ADHERING AIR BARRIERS
07 27 26 05/17, CHG 2: 08/20 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 27 36 05/17, CHG 3: 02/23 SPRAY FOAM AIR BARRIERS
07 42 13 05/11, CHG 2: 02/18 METAL WALL PANELS
07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL
07 61 15.00 20 08 March 2021 CL ALUMINUM STANDING SEAM ROOFING
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 14 00 08/16, CHG 1: 08/18 WOOD DOORS
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 33 23 08/20, CHG 1: 02/22 STEEL OVERHEAD COILING DOORS
08 34 59 08/08, CHG 1: 11/12 VAULT DOORS AND DAY GATES
08 41 13 08/18, CHG 1: 08/18 ALUMINUM-FRAMED STOREFRONTS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 08/20 ALUMINUM METAL LOUVERS
DIVISION 09 - FINISHES
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
09 30 10 08/20 CERAMIC TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING
09 66 23 08/16, CHG 1: 08/18 RESINOUS MATRIX TERRAZZO FLOORING
09 68 00 11/17, CHG 2: 08/20 CARPET TILE
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE
10 14 00.20 08/20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 22 13 08/16, CHG 1: 08/18 WIRE MESH PARTITIONS
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 51 13 05/11 PLASTIC LOCKERS
VOLUME 1 - TABLE OF CONTENTS Page 2
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
12 00 01.00 20 02/23 FURNITURE, FIXTURES AND EQUIPMENT
(FF&E) PACKAGE
12 24 13 08/20 ROLLER WINDOW SHADES
VOLUME 1 - TABLE OF CONTENTS Page 3
DIVISION 12 - FURNISHINGS
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/11, CHG 1: 08/14
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
NAVFAC PLATE SHEET
NO NO TITLE
G GENERAL
12916882 G-001 TITLE SHEET
12916883 G-002 LOCATION MAPS AND GENERAL PROJECT NOTES
12916884 G-003 INDEX OF DRAWINGS
GI LIFE SAFETY
12916885 GI001 LIFE SAFETY GENERAL NOTES AND LEGEND
12916886 GI002 CODE COMPLIANCE SITE PLAN
12916887 GI101 LIFE SAFETY FLOOR PLAN
B GEOTECHNICAL
12916888 B-001 GEOTECHNICAL GENERAL NOTES
12916889 B-101 BORING LOG LOCATIONS
12916890 B -102 SPT AND CPT BORING LOGS
12916891 B-103 SPT AND CPT BORING LOGS
12916892 B-104 SPT AND CPT BORING LOGS
12916893 B-105 SPT AND CPT BORING LOGS
12916894 B-106 SPT AND CPT BORING LOGS
12916895 B-107 SUBSURFACE PROFILES
12916896 B-108 SUBSURFACE PROFILES
C CIVIL
12916897 C-001 CIVIL ABBREVIATIONS AND LEGENDS
12916898 VF001 SURVEY CONTROL POINTS, NOTES & LEGEND
12916899 VF100 OVERALL EXISTING CONDITIONS
12916900 VF101 EXISTING CONDITIONS - AREA 1
12916901 VF102 EXISTING CONDITIONS - AREAS 2 & 3
12916902 CD100 OVERALL DEMOLITION PLAN
12916903 CD101 DEMOLITION PLAN - AREA 1
12916904 CD102 DEMOLITION PLAN - AREAS 2 & 3
12916905 CS100 OVERALL SITE PLAN
12916906 CS101 SITE PLAN - AREA 1
12916907 CS102 SITE PLAN - AREAS 2 & 3
12916908 CG100 OVERALL GRADING PLAN
12916909 CG101 GRADING PLAN - AREA 1
12916910 CG102 GRADING PLAN - AREA 2 & 3
12916911 CG121 PARTIAL EROSION CONTROL PLAN - AREA 1 - PHASE 1
DOCUMENT 00 01 15 Page 1
NAVFAC PLATE SHEET
NO NO TITLE
12916912 CG122 PARTIAL EROSION CONTROL PLAN - AREA 2 & 3 - PHASE 1
12916913 CG123 PARTIAL EROSION CONTROL PLAN - AREA 1 - PHASE 2
12916914 CG124 PARTIAL EROSION CONTROL PLAN - AREA 2 & 3 - PHASE 2
12916915 CU100 OVERALL UTILITY PLAN
12916916 CU101 UTILITY PLAN - AREA 1
12916917 CU102 UTILITY PLAN - AREA 2 & 3
12916918 CU200 OVERALL UTILITY PLAN ALIGNMENT
12916919 CU201 GRAVITY SWER PROFILE
12916920 CU202 FORCE MAIN SWER PROFILE
12916921 CU203 WATER MAIN PROFILES
12916922 CU204 FIRE LINE PROFILE
12916923 CU205 FIRE LINE PROFILE
12916924 CU206 STORM DRAIN PROFILE
12916925 CU207 BORE PIT PLAN AND PROFILE
12916926 CU208 BORE PIT PLAN AND PROFILE
12916927 C-501 EROSION AND SEDIMENT CONTROL DETAILS
12916928 C-502 EROSION AND SEDIMENT CONTROL DETAILS
12916929 C-503 EROSION AND SEDIMENT CONTROL DETAILS
12916930 C-504 EROSION AND SEDIMENT CONTROL DETAILS
12916931 C-506 NCG01
12916932 C-507 NCG01
12916933 C-511 SITE DETAILS
12916934 C-512 SITE DETAILS
12916935 C-513 SITE DETAILS
12916936 C-514 SITE DETAILS
12916937 C-515 SITE DETAILS
12916938 C-521 SITE UTILITY DETAILS
12916939 C-522 SITE UTILITY DETAILS
12916940 C-523 SITE UTILITY DETAILS
12916941 C-524 SITE UTILITY DETAILS
12916942 C-525 SITE UTILITY DETAILS
12916943 C-526 SITE UTILITY DETAILS
12916944 C-527 SITE UTILITY DETAILS
12916945 C-528 SITE UTILITY DETAILS
S STRUCTURAL
12916946 S-001 COVER SHEET
12916947 S-002 STRUCTURAL NOTES
12916948 S-003 STRUCTURAL NOTES
12916949 S-101 FOUNDATION PLAN - OVERALL
12916950 S-102 PARTIAL FOUNDATION PLAN - AREA A
12916951 S-103 PARTIAL FOUNDATION PLAN - AREA B
12916952 S-104 PARTIAL FOUNDATION PLAN - AREA C
12916953 S-105 VAULT DECK FRAMING PLAN - OVERALL
12916954 S-106 PARTIAL VAULT DECK FRAMING PLAN - AREA A
12916955 S-107 PARTIAL VAULT DECK FRAMING PLAN - AREA B
12916956 S-108 PARTIAL VAULT DECK FRAMING PLAN - AREA C
12916957 S-109 ROOF FRAMING PLAN - OVERALL
12916958 S-110 PARTIAL ROOF FRAMING PLAN - AREA A
12916959 S-111 PARTIAL ROOF FRAMING PLAN - AREA B
12916960 S-112 PARTIAL ROOF FRAMING PLAN - AREA C
12916961 S-201 STRUCTURAL SECTIONS
12916962 S-202 STRUCTURAL SECTIONS
12916963 S-501 GENERAL CONSTRUCTION DETAILS
12916964 S-502 GENERAL CONSTRUCTION DETAILS
12916965 S-503 GENERAL CONSTRUCTION DETAILS
DOCUMENT 00 01 15 Page 2
NAVFAC PLATE SHEET
NO NO TITLE
A ARCHITECTURAL
12916966 A-001 SYMBOL LEGEND AND ABBREVIATIONS
12916967 AS501 DUMPSTER ENCLOSURE DETAILS
12916968 A-101 FLOOR PLAN - OVERALL
12916969 A-102 FLOOR PLAN - AREA A
12916970 A-103 FLOOR PLAN - AREA B
12916971 A-104 FLOOR PLAN - AREA C
12916972 A-105 REFLECTED CEILING PLAN - OVERALL
12916973 A-106 VAULT DECK PLAN - OVERALL
12916974 A-107 ROOF PLAN - OVERALL
12916975 A-108 AIR AND MOISTURE BARRIER PLAN, DETAILS AND NOTES
12916976 A-201 ELEVATIONS
12916977 A-301 BUILDING SECTIONS
12916978 A-302 BUILDING SECTIONS
12916979 A-303 WALL SECTIONS
12916980 A-304 WALL SECTIONS
12916981 A-401 CAGE PLAN
12916982 A-402 TYPICAL TOILET DETAILS AND ACCESSORIES LEGEND
12916983 A-403 ENLARGED TOILET PLANS
12916984 A-404 INTERIOR ELEVATIONS
12916985 A-405 INTERIOR ELEVATIONS
12916986 A-501 WALL TYPE DETAILS
12916987 A-502 MASONRY DETAILS
12916988 A-503 ROOFING DETAILS
12916989 A-504 MISCELLANEOUS DETAILS
12916990 A-505 STAIR DETAILS
12916991 A-506 RAILING DETAILS
12916992 A-507 MISCELLANEOUS DETAILS
12916993 A-508 MISCELLANEOUS DETAILS
12916994 A-509 WEAPONS ISSUE PORT DETAILS
12916995 A-601 DOOR AND FRAME SCHEDULE
12916996 A-602 DOOR AND FRAME DETAILS
12916997 A-603 WINDOW SCHEDULE AND DETAILS
12916998 A-604 SCHEDULE OF EXTERIOR MATERIALS
I INTERIOR DESIGN
12916999 I-101 FURNITURE PLAN - AREA A
12917000 I-102 FURNITURE PLAN - AREA B
12917001 I-103 FURNITURE PLAN - AREA C
12917002 I-111 FINISH PLAN - AREA A
12917003 I-112 FINISH PLAN - AREA B
12917004 I-113 FINISH PLAN - AREA C
12917005 I-121 SIGNAGE PLAN - AREA A
12917006 I-122 SIGNAGE PLAN - AREA B
12917007 I-123 SIGNAGE PLAN - AREA C
12917008 I-201 INTERIOR ELEVATIONS
12917009 I-301 CASEWORK SECTIONS
12917010 I-501 SIGNAGE DETAILS
12917011 I-502 INTERIOR DETAILS
12917012 I-601 SCHEDULES & LEGENDS
12917013 I-602 SCHEDULES & LEGENDS
F FIRE PROTECTION
12917014 FA001 FIRE ALARM GENERAL NOTES AND LEGEND
12917015 FA101 FIRE ALARM FLOOR PLAN - AREA A
12917016 FA102 FIRE ALARM FLOOR PLAN - AREA B
12917017 FA103 FIRE ALARM FLOOR PLAN - AREA C
DOCUMENT 00 01 15 Page 3
NAVFAC PLATE SHEET
NO NO TITLE
12917018 FA501 FIRE ALARM DETAILS
12917019 FA502 FIRE ALARM DETAILS
12917020 FA503 FIRE ALARM DETAILS
12917021 FX001 FIRE SUPPRESSION GENERAL NOTES AND LEGEND
12917022 FX101 FIRE SUPPRESSION FLOOR PLAN - AREA A
12917023 FX102 FIRE SUPPRESSION FLOOR PLAN - AREA B
12917024 FX103 FIRE SUPPRESSION FLOOR PLAN - AREA C
12917025 FX501 FIRE SUPPRESSION DETAILS
P PLUMBING
12917026 P-001 PLUMBING COVER SHEET
12917027 P-101 FLOOR PAN - OVERALL - WASTE AND VENT
12917028 P-102 FLOOR PLAN - AREA A - WASTE AND VENT
12917029 P-103 FLOOR PLAN - AREA B - WASTE AND VENT
12917030 P-104 FLOOR PLAN - AREA C - WASTE AND VENT
12917031 P-105 FLOOR PLAN - OVERAL - WATER & COMPRESSED AIR
12917032 P-106 FLOOR PLAN - AREA A - WATER & COMPRESSED AIR
12917033 P-107 FLOOR PLAN - AREA B - WATER & COMPRESSED AIR
12917034 P-108 FLOOR PLAN - AREA C - WATER & COMPRESSED AIR
12917035 P-501 PLUMBING DETAILS
12917036 P-502 PLUMBING DETAILS
12917037 P-601 PLUMBING SCHEDULES
12917038 P-701 RISER DIAGRAMS - WASTE AND VENT
12917039 P-702 RISER DIAGRAMS - WATER AND COMPRESSED AIR
12917040 P-703 RISER DIAGRAMS - WATER AND COMPRESSED AIR
M MECHANICAL
12917041 M-001 MECHANICAL COVER SHEET
12917042 MH101 FIRST FLOOR PLAN - MECHANICAL HVAC - OVERALL
12917043 MH102 FIRST FLOOR PLAN - MECHANICAL HVAC - AREA 'B'
12917044 MH103 FIRST FLOOR PLAN - MECHANICAL HVAC - AREA 'C'
12917045 MH104 VAULT DECK PLAN - MECHANICAL HVAC - AREAS 'A' & 'B'
12917046 MH105 VAULT DECK PLAN - MECHANICAL HVAC - AREA 'C'
12917047 MP101 FIRST FLOOR PLAN - MECHANICAL PIPING
12917048 MP102 FIRST FLOOR PLAN - MECHANICAL PIPING - AREA 'B'
12917049 MP103 FIRST FLOOR PLAN - MECHANICAL PIPING - AREA 'C'
12917050 M-301 MECHANICAL SECTION VIEWS
12917051 M-302 MECHANICAL SECTION VIEWS
12917052 MH401 ENLARGED FLOOR PLANS - MECHANICAL HVAC - AREA 'A'
12917053 MP401 ENLARGED FLOOR PLANS - MECHANICAL PIPING - AREA 'A'
12917054 M-501 MECHANICAL DETAILS
12917055 M-502 MECHANICAL DETAILS
12917056 M-503 MECHANICAL DETAILS
12917057 M-504 MECHANICAL DETAILS
12917058 M-505 MECHANICAL DETAILS
12917059 M-506 MECHANICAL DETAILS
12917060 M-507 MECHANICAL DETAILS
12917061 M-601 MECHANICAL SCHEDULES
12917062 M-602 MECHANICAL SCHEDULES
12917063 M-603 MECHANICAL SCHEDULES
12917064 M-604 MECHANICAL SCHEDULES
12917065 M-701 MECHANICAL CONTROLS
12917066 M-702 MECHANICAL CONTROLS
12917067 M-703 MECHANICAL CONTROLS
12917068 M-704 MECHANICAL CONTROLS
12917069 M-705 MECHANICAL CONTROLS
12917070 M-706 MECHANICAL CONTROLS
DOCUMENT 00 01 15 Page 4
NAVFAC PLATE SHEET
NO NO TITLE
12917071 M-707 MECHANICAL CONTROLS
12917072 M-708 MECHANICAL CONTROLS
12917073 M-801 CHILLED AND HOT WATER SYSTEM DIAGRAM
12917074 M-901 ISOMETRIC VIEWS - MECHANICAL ROOMS
ES ELECTRICAL SITE
12917075 ES001 SITE ELECTRICAL LEGEND
12917076 ES101 ELECTRICAL SITE PLAN
12917077 ES501 ELECTRICAL SITE DETAILS
12917078 ES502 ELECTRICAL SITE DETAILS
12917079 ES503 ELECTRICAL SITE DETAILS
12917080 ES504 ELECTRICAL SITE DETAILS
12917081 ES601 ELECTRICAL SITE SCHEDULES
E ELECTRICAL
12917082 E-001 ELECTRICAL NOTES AND LEGENDS
12917083 E-101 FLOOR PLAN - AREA 'A' - POWER
12917084 E-102 FLOOR PLAN - AREA 'B' - POWER
12917085 E-103 FLOOR PLAN - AREA 'C' - POWER
12917086 E-104 FLOOR PLAN - AREA 'A' - EQUIPMENT CONNECTIONS
12917087 E-105 FLOOR PLAN - AREA 'B' - EQUIPMENT CONNECTIONS
12917088 E-106 FLOOR PLAN - AREA 'C' - EQUIPMENT CONNECTIONS
12917089 E-107 FLOOR PLAN - AREA 'A' - LIGHTING
12917090 E-108 FLOOR PLAN - AREA 'B' - LIGHTING
12917091 E-109 FLOOR PLAN - AREA 'C' - LIGHTING
12917092 E-110 ROOF PLAN - LIGHTNING PROTECTION
12917093 E-401 ENLARGED PLANS - COMM ROOMS
12917094 E-501 ELECTRICAL DETAILS
12917095 E-502 ELECTRICAL DETAILS
12917096 E-503 ELECTRICAL DETAILS
12917097 E-504 ELECTRICAL DETAILS
12917098 E-505 ELECTRICAL DETAILS
12917099 E-601 ELECTRICAL SCHEDULES
12917100 E-602 ELECTRICAL SCHEDULES
12917101 E-603 ELECTRICAL SCHEDULES
12917102 E-604 ELECTRICAL SCHEDULES
12917103 E-605 ELECTRICAL SCHEDULES
12917104 E-701 ELECTRICAL RISER DIAGRAMS
T TELECOMMUNICATIONS
12917105 T-001 TELECOMMUNICATIONS NOTES AND LEGEND
12917106 T-101 FLOOR PLAN - AREA 'A' - TELECOMMUNICATIONS
12917107 T-102 FLOOR PLAN - AREA 'B' - TELECOMMUNICATIONS
12917108 T-103 FLOOR PLAN - AREA 'C' - TELECOMMUNICATIONS
12917109 T-104 FLOOR PLAN - AREA 'A' - SECURITY INFRASTRUCTURE
12917110 T-105 FLOOR PLAN - AREA 'B' - SECURITY INFRASTRUCTURE
12917111 T-106 FLOOR PLAN - AREA 'C' - SECURITY INFRASTRUCTURE
12917112 T-501 TELECOMMUNICATIONS DETAILS
12917113 T-502 TELECOMMUNICATIONS DETAILS
12917114 T-503 TELECOMMUNICATIONS DETAILS
12917115 T-504 TELECOMMUNICATIONS DETAILS
TA AUDIOVISUAL
12917116 TA001 SHEET INDEX AND NOTES
12917117 TA101 AV FLOOR PLAN - AREA A - SCHEMATIC
12917118 TA102 AV FLOOR PLAN - AREA B - SCHEMATIC
12917119 TA103 AV FLOOR PLAN - AREA C - SCHEMATIC
DOCUMENT 00 01 15 Page 5
NAVFAC PLATE SHEET
NO NO TITLE
12917120 TA601 AV EQUIPMENT SCHEDULE
12917121 TA602 FUNCTIONAL DRAWINGS
12917122 TA701 COORDINATION DETAILS
12917123 TA702 COORDINATION DETAILS
-- End of Document --
DOCUMENT 00 01 15 Page 6
SECTION 01 11 00
SUMMARY OF WORK
04/22
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work includes P-1538 an SOF Armory building, supporting site infrastructure extensions, distribution and improvements. Site infrastructure includes domestic water distribution, sanitary sewer distribution, and comm utility distribution. Site improvements include POV parking lots, tactical drives and aprons, Armory compound fencing and MARSOC installation fencing perimeter and incidental related work.
1.1.2 Location
The work shall be located within the Stone Bay, MARSOC campus aboard MCB Camp Lejeune. The exact location will be indicated by the Contracting Officer.
1.2 PHASED CONSTRUCTION SCHEDULE
Within the overall project schedule, commence and complete the work in phases as described in the attached project description.
1.3 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.4 LOCATION OF UNDERGROUND FACILITIES
The Contractor will be responsible for obtaining the services of a professional utility locator to scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
SECTION 01 11 00 Page 1
1.4.1 Notification Prior to Excavation
Notify the Contracting Officer 's Representative (COR) 48 hours prior to starting excavation work .
1.5 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
Government furnished material and equipment will be indicated on drawings and in scope of work if applicable.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 14 00
WORK RESTRICTIONS (MCBL)
04/22
PART 1 GENERAL
1.1 SUBMITTALS
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. The Contractor shall comply with all special scheduling requirements as described in the attached project description.
d. Permission to interrrupt any Station roads, railroads, and/or utility service shall be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Installation Access
Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html . No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
The following are specific details regarding contractor personnel
SECTION 01 14 00 Page 1 requirements. For the most up-to-date information regarding Base Access please visit https://www.lejeune.marines.mil/Base-Access/.
1.3.1.2.1 Registration for DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/om/dbids.html . Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/om/dbids.html .
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, fingerprints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.3.1.2.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.
The Government is the final authority.
1.3.1.2.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
SECTION 01 14 00 Page 2
1.3.1.2.4 One-Day Passes
Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.3.2 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.3 Working Hours
Regular working hours shall be 0730-1600, Monday through Friday, excluding Government holidays .
1.3.4 Work Outside Regular Hours
Work outside regular working hours requires COR approval. Provide written request at least 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the COR.
1.3.5 Utility Cutovers and Interruptions
a. The Contractor shall coordinate a minimum of 14 calendar days prior to any planned utility cutover / interruption. Make utility cutovers and interruptions during normal working hours.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air shall be considered utility cutovers. This time limit includes time for deactivation and reactivation.
d. Operation of Station Utilities: The Contractor shall not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor shall notify the Contracting Officer at least 15 days prior to such operation.
1.4 SECURITY REQUIREMENTS
Contract Clause "FAR 52.204-2, Security Requirements and Alternate II," "FAC 5252.236-9301, Special Working Conditions and Entry to Work Area," apply.
SECTION 01 14 00 Page 3
1.5 EMERGENCY UNEXPLODED ORDNANCE (UXO) RESPONSE
In the event that UXO, as defined in 40 CFR 260 is encountered during the construction activities that are deemed to be a threat to human health or the environment, Camp Lejeune Military Police and EOD professionals shall be immediately contacted to conduct an emergency response. Additionally, immediately contact the Contracting Officer if UXO is encountered. An evaluation of this scenario and procedures, with contract numbers, shall be included in the Health and Safety Plan (HASP) for the fieldwork.
1.5.1 3R TRAINING
All Contractor personnel performing ground disturbing activities must complete contractor awareness training related to recognizing UXO. This training (3R TRAINING) is available online at:
http://www.lejeune.marines.mil/OfficesStaff/EnvironmentalMgmt/TrainingVideo.aspx
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 4
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES (MCBCL)
04/22
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 1110-1-8 (2021) Engineering and Design -- Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Schedule of Prices ; G
1.3 SCHEDULE OF PRICES
1.3.1 Data Required
Within 15 calendar days of notice of award, prepare and deliver to COR a schedule of prices (construction contract). Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices therefor. Schedule of prices shall be separated by individual building numbers with subtotals for each building.
1.3.2 Payment Schedule Instructions
Payments will not be made until the Schedule of Prices has been submitted to and accepted by the Contracting Officer.
Additionally, the Schedule of Prices must be separated as follows:
a. Primary Facilities Cost Breakdown:
Defined as work on the primary facilities out to the 5 foot line.
Work out to the 5 foot line includes construction encompassed within a theoretical line 5 foot from the face of exterior walls and includes attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 foot line.
b. Supporting Facilities Cost Breakdown:
Defined as site work, including incidental work, outside the 5 foot line.
SECTION 01 20 00 Page 1
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates upon the applicable provisions of the
EP 1110-1-8 .
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies. The requests for payment shall include the documents listed below.
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 must include certification by Quality Control (QC) Manager as required by the Contract.
b. The Estimate for Voucher/ Contract Performance Statement on NAVFAC Form 4330/54 furnished by the Government. Use NAVFAC Form 4330, unless otherwise directed by the Contracting Officer, on NAVFAC Contracts when a Monthly Estimate for Voucher is required.
c. Contractor's Monthly Estimate for Voucher and Contractors Certification (NAVFAC Form 4330) with Subcontractor and supplier payment certification. Other documents, including but not limited to, that need to be received prior to processing payment include the following submittals as required. These items are still required monthly even when a pay voucher is not submitted.
d. Monthly Work-hour report.
e. Updated Construction Progress Schedule and tabular reports required by the contract.
f. Contractor Safety Self Evaluation Checklist.
g. Updated submittal register.
h. Solid Waste Disposal Report.
i. Certified payrolls.
j. Updated testing logs.
k. Other supporting documents as requested.
1.5.2 Submission of Invoices
If DFARS Clause 252.232-7006 Wide Area WorkFlow Payment Instructions is included in the Contract, provide the documents listed in above paragraph CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow
SECTION 01 20 00 Page 2
(WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction, provide it as instructed by the Contracting Officer.
Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.
1.5.3 Final Invoice
a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor must then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this Contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR
32.103 Progress Payments Under Construction Contracts:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this Contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to maintain accurate "as-built" or record drawings in
SECTION 01 20 00 Page 3 accordance with FAR 52.236.21.
1.6.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the Contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
c. Materials to be considered for progress payment prior to installation must be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Prices requirement of this Contract.
Requests for progress payment consideration for such items must be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price Construction Contracts have been met.
d. Materials are adequately insured and protected from theft and exposure.
e. Provide a written consent from the surety company with each payment request for offsite materials.
f. Materials to be considered for progress payments prior to installation must be stored either in Hawaii, Guam, Puerto Rico, or the Continental United States. Other locations are subject to written approval by the Contracting Officer.
g. Materials in transit to the job site or storage site are not acceptable for payment.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00 Page 4
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
01/23
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual
1.2 SUBMITTALS
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map
Progress and Completion Pictures
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.
Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.
Include a date designator in file names. Photographs provided are for unrestricted use by the Government.
1.5 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
SECTION 01 30 00 Page 1
1.6 ELECTRONIC MAIL (EMAIL)
a. The Contractor is required to establish and maintain electronic mail (email) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats.
b. Within 10 days after contract award; the Contractor shall provide the Contracting Officer a single (only one) email address for the ROICC office to send communications related to this contract correspondence. The ROICC office may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc.
c. Multiple email addresses are not authorized.
d. It is the Contractor's responsibility to make timely distribution of all ROICC email within its own organization, including field office(s).
e. The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to their email address.
1.7 SUPERVISION
1.7.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
1.7.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.7.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red
SECTION 01 30 00 Page 2
Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.7.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.8 PRECONSTRUCTION MEETING
Immediately after award , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting . The meeting must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
1.8.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.9 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)
Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client.