YFNX-20 Errata 5.pdf
PDF 301 KB Posted
- Attached to
- U. S. NAVY BARGE YFNX-20 NPTU SOLICITATION
- Solicitation number
- N40027-23-R-0010
About this file
This document package includes a federal contract opportunity solicitation and related technical specifications for ship repair and upgrade work. The solicitation seeks proposals to perform maintenance, inspection, and system replacement efforts aboard the Navy barge YFNX-20, including underwater hull repair, fire alarm and HVAC upgrades, and refurbishment of interior spaces. Technical specifications provide detailed requirements and references for tasks such as hull blasting and coating, detection system installation, duct cleaning and air conditioning replacement. Responses to the solicitation are due on November 15th, 2023 to the Naval Sea Systems Command. The overall work will refurbish various systems and components on the barge to support its training vessel mission.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THIS PERMANENT CHANGE UPDATES THE SPECIFICATION BID PACKAGE.
SHIP: YFNX-20 (RMC 22747)
SERM-024-24
ERRATA NUMBER:
SPECIFICATION NUMBER:
THE FOLLOWING ITEMS ARE REPLACED:
110-11-001
436-11-001
514-11-001
631-11-001
635-11-001
DATED: 9/28/2023 6:36:06PMPage 1 of 1
SHIP: YFNX-20 (RMC 22747) ITEM NO: 110-11-001 (E5)
COAR: 28 PCN: SERM-L001
HULL-L001
CSWT FILE NO: 110-004 (DDG 51) CMP: NONE
REVISED: 02 OCT 2022 PLANNER: CORNWELL, RICHARD
BENNETT, KEITH
BRIDGER, WRAY
SSP: SERM-024-24 1 of 3 ITEM NO: 110-11-001
ERRATA NO. 5
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Underwater Hull, Freeboard and Voids; inspect and repair
1.2 Location of Work:
1.2.1 Underwater Hull, including Freeboard up to Main Deck, Frame 0- 50, Port and Starboard
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Standard Items
2.2 S9086-DA-STM-010 Rev 3, Hull Structures
2.3 Hull S9086-CQ-STM-010/081 Structures Rev 6, Waterborne Underwater Hull Cleaning of Navy Ships
(E1)
2.4 T9074-AS-GIB-010/271 Rev 1, Requirements for Nondesructive Testing Methods
2.5 MIL-STD-2035A, Nondestructive Testing Acceptance Criteria
2.6 633-8337791 Rev A, Modification to Anodes
2.7 803-921865 Rev P,R, Cathodic Protection Hull Zinc Anodes (E1)
3. REQUIREMENTS:
3.1 Clean the underwater hull to prepare each surface for visual and ultrasonic inspection using 2.2 and 2.3 for guidance.
3.2 Accomplish a visual inspection of the Underwater Hull and interior of voids, including Freeboard up to Main Deck for structural integrity, deterioration, pitting, cracking, and each area of damaged or distortion in each location listed in 1.2, using 2.2 and 2.3 for guidance.
3.2.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.2 with sketches listing the type, amount and location of structural damage and deterioration to the SUPERVISOR
3.3 Accomplish an ultrasonic thickness survey of each underwater hull area, in accordance with 2.4, using 2.2 and 2.3 for guidance. The accept or reject criteria must be in accordance with 2.5.
3.3.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements
SSP: SERM-024-24 2 of 3 ITEM NO: 110-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
of 3.3 to the SUPERVISOR.
3.3.1.1 List in one column the design thickness of plate
inspected, using 2.5 for guidance.
3.3.1.2 List in another column, next to the design thickness, each actual thickness reading taken.
3.3.1.3 List specific location with respect to frame, strake, or measurement from each suitable reference point.
3.4 Accomplish the following repairs as determined by the visual inspection in 3.2 and ultrasonic result of 3.3 in the location listed 1.2, as designated by the SUPERVISOR, using 2.2 and 2.3 for guidance.
3.4.1 Vee-out and weld a total of 2 linear feet of splitting, cracking, deteriorated and damaged weld.
3.4.2 Accomplish base metal repair for a total of 144 square inches of deteriorated and damaged shell plating.
3.4.2.1 Each surface must be ground to sound metal prior to base metal repair.
3.4.2.2 Fill each local pit and groove with weld metal prior to the application of each principal build-up layer.
3.4.2.3 Each surface of completed base metal repair need not be ground smooth if not greater than 1/8 inch above plating surface.
3.4.3 Remove existing and install new a total of 2 square feet of deteriorated and damaged shell plating.
3.4.4 Remove existing and install new a total of 2 linear feet of adjacent support structure.
3.4.5 Remove existing and install new 20 EA Zinc mounting stud.
3.4.6 Chip and grind each surface flush in way of each repair.
3.4.7 Template exact size, configuration, and location from existing shipboard condition.
3.5 Accomplish the requirements of 009-12 of 2.1, including Table 3, Column A, Lines One through 7.
3.6 Accomplish the requirements of 009-25 of 2.1 for an air hose or water hose test of each new insert and weld seam. Allowable leakage:
None.
3.7 Accomplish the requirements of 009-32 of 2.1, including Table One, Line 5, for each surface listed in 1.2.
3.8 Accomplish the requirements of 009-32 of 2.1, including Table 2, Lines One, 1A, 2, 3 or 4, Columns A, B and G for each surface listed in 1.2.
(E5)
3.9 Remove existing and install new a total of 60 EA exterior zinc anode, using 2.6 for guidance, as designated by the SUPERVISOR.
(E5)
3.9.1 Torque each zinc anode retaining nut to 35 to 40 foot-pounds in accordance with 2.7.
(E5)
SSP: SERM-024-24 3 of 3 ITEM NO: 110-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
3.9.2 Test each zinc anode to verify electrical resistance between anode and hull structure is less than 0.1 Ohm.
(E5)
3.10 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
(E5)
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.
SHIP: YFNX-20 (RMC 22747) ITEM NO: 436-11-001 (E5)
COAR: 28 PCN: SERM-L009
CSWT FILE NO: 436-007 (CG 47) CMP: NONE
REVISED: 25 SEP 2022 PLANNER: NEWSOME, TERRY
BENNETT, KEITH
BRIDGER, WRAY
KRIMMER, DAVID
SSP: SERM-024-24 1 of 3 ITEM NO: 436-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Fire and Flooding Alarm and Warning System Assessment and Upgrade; accomplish
1.2 Location of Work:
1.2.1 Throughout the Barge
1.3 Identification:
1.3.1 Quantity (One EA), Control Panel, Honeywell Fire-Lite or equivalent
(E5)
1.3.2 Quantity (20 EA), Detector, Thermal Fire, Model DT-135CS or equivalent
(E5)
1.3.3 Quantity (6 EA), Liquid Level Switch, Type IC/R1-U or
equivalent
(E5)
1.3.4 Quantity (4 EA), Horn, Model HDC-24 or equivalent (E5)
1.3.5 Quantity (4 EA), Bell, Model MBDC-6 or equivalent (E5)
1.3.6 Quantity (1,000 FT), Cable, Type: LSDCOP 1-1/2, Item No. 22, as Shown on Sheet One of 2.2, NSN: 6145-01-202-2776 or equivalent
(E5)
2. REFERENCES:
2.1 Standard Items
2.2 7029583,401-7029583, Fire and Flooding Alarms (E1)
2.3 7029582 302-7029582 Rev B, YFNX-20, Power Distribution and Lighting (E1)
2.4 MIL-STD-2003B, Electric Plant Installation Standard Methods for Surface Ships and Submarines
2.5 MIL-STD-1310H, Shipboard Bonding, Grounding, and Other Techniques for Electromagnetic Compatibility, Electromagnetic Pulse (EMP) Mitigation, and Safety
2.6 605-2540769 Rev D, Label Plate Standards
3. REQUIREMENTS:
3.1 Accomplish the requirements of 009-90 of 2.1 for the services of an authorized original equipment manufacturer (OEM) service provider to remove, disassemble, inspect, repair, install, reassemble, test, adjust, and provide each special tool and drawing for each equipment listed in
1.3 and located in 1.2.
(E5)
3.2 Remove existing and install new the equipment listed in 1.3, using
SSP: SERM-024-24 2 of 3 ITEM NO: 436-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
2.2 through 2.5 for guidance, as designated by the SUPERVISOR.
3.2.1 Install new an additional 2 EA Thermal Fire Detector, one EA Horn, and one EA Bell (for a total of 12 EA Thermal Fire Detector, 6 EA Horn, and 6 EA Bell) for each void.
3.2.2 Ensure each Liquid Level Switch is installed in accordance wiht General Note 10 of 2.2.
3.2.3 Remove existing and install new One EA smoke detector (for a total of 6 EA) for each void.
3.2.3.1 Ensure each smoke detector is powered (hardwired) from power distribution system.
3.2.4 Template exact size, configuration, and location from each existing shipboard condition.
3.2.5 Accomplish the requirements of 009-12 of 2.1, including Table 2, Columns A and D, Lines One through 7.
3.2.6 Electrical equipment and cable removal and installation must conform to the requirements of 2.4.
3.2.7 Bond and ground equipment in accordance with 2.5.
3.2.8 Remove each unused clip, hanger, electrical button, and stud from overhead, deck and each bulkhead.
3.2.9 Chip and grind each surface flush in way of removals.
3.2.10 Accomplish the requirements of 009-25 of 2.2, for a air hose test of each new and disturbed penetration. Allowable leakage: None.
3.3 Provide 5 mandays of labor and 1,000 dollars of material to accomplish work not previously identified in the Work Item, as directed by the SUPERVISOR. If the total costs are less than the authorized manday and dollar amounts, remaining funds will be subject to recoupment.
The contractor is not authorized to exceed these limits.
(Q)(G) "OPERATIONAL TEST"
3.4 Accomplish an operational test the fire and flooding detection system, and each smoke detector, to ensure the operation and functionality of the alarm monitoring panel, associated circuitry, each audible and visual alarm indicator, and sensor function as designed, using 2.3 and 2.4 for guidance.
3.5 Install each new label plate for each component, in accordance with
2.2 through 2.4, using 2.6 for guidance.
3.6 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
SSP: SERM-024-24 3 of 3 ITEM NO: 436-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. None.
5.2 PUSH MATERIAL:
1. None.
SHIP: YFNX-20 (RMC 22747) ITEM NO: 514-11-001 (E5)
COAR: 28 PCN: SERM-L015
SERM-L002
BWST FILE NO: 000-001 CMP: NONE
REVISED: 05 APR 2019 PLANNER: KRIMMER, DAVID
BENNETT, KEITH
BRIDGER, WRAY
SSP: SERM-024-24 1 of 4 ITEM NO: 514-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Heating, Ventilation, Air Conditioning (HVAC) System Replacement; accomplish
1.2 Location of Work:
1.2.1 Throughout the Barge
1.3 Identification:
1.3.1 Quantity (3 EA), Fan, Vaneaxial, MIL-18593, Size A1/2A4W6, 500 CFM, Piece No. One of 2.2, NSN 4140-00-554-8203
1.3.2 Quantity (One EA), Air Conditioning Unit, 7.5 Ton Capacity, Weight: 690 LB, Mfr: Trane, Mfr Model: WSC090A4R0A0V0 or Equivalent, Serial No: 934100759L, Service: Main Deck, Located Aft of Deckhouse, Shown on 2.3
(E5)
1.3.3 Quantity (One EA), Air Conditioning Unit, 4 Ton Capacity, Weight: 500 LB, Mfr: Trane, Mfr Model: WSC048E4R0A0R0 or Equivalent, Serial No: 93310007L, Service: Second Deck, Located Aft of Deckhouse, Shown on 2.3
(E5)
1.3.4 Quantity (One EA), Air Conditioning Unit, Service: Second Deck Conference Room, Mfr: Trane, Mfr Model: 2JJA3030A4000AA or Equivalent, Serial No: 6422PL93F, Located Second Deck Port Exterior Walkway, Shown on Zone 53-F, Sheet 7 of 2.4
(E5)
1.3.5 Quantity (170 LF), Ventilation Ducting, Service: Main Deck Served by 7.5 Ton Air Conditioning Unit, From Air Conditioning Unit To Each Branch Termination, Shown on 2.3
1.3.6 Quantity (100 LF), Ventilation Ducting, Service: Second Deck Served by 4 Ton Air Conditioning Unit, From Air Conditioning Unit To Each Branch Termination, Shown on 2.2
1.3.7 Quantity (100 LF), Ventilation Ducting, Service: Void
Ventilation, To Include Each Vent Fan Bellmouth, Shown on 2.3
2. REFERENCES:
2.1 Standard Items
2.2 601-5911038 Rev B, YFNX 20 Barge Void Ventilation Modifications
2.3 4-P-8826, Comet III 25'-7"x80'-10 1/8"x25'-0 3/4" 2 Story Building for YFNX-20 Barge at CSNY, 5C (Sheet 4)
2.4 302-7029582 Rev B, YFNX-20 Power Distribution and Lighting
2.5 S9086-RQ-STM-010/CH-510 Rev 7, Heating, Ventilating, and Air Conditioning Systems for Surface Ships
SSP: SERM-024-24 2 of 4 ITEM NO: 514-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
2.6 S9AA0-AB-GOS-010 Rev 10, General Specifications for Overhaul of Surface Ships (GSO)
3. REQUIREMENTS:
3.1 Accomplish a preliminary operational test of each fan listed in 1.3.1, using 2.2 for guidance.
3.1.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.1 to the SUPERVISOR.
3.2 Remove the equipment listed in 1.3.2 through 1.3.5,6, using 2.2 through 2.4 for guidance.
(E1)
3.3 Accomplish a visual inspection of each foundation for the equipment listed in 1.3, for structural integrity, deterioration, pitting, each crack, and each area of damage or distortion.
3.3.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.3 to the SUPERVISOR.
3.4 Accomplish the requirements of 009-32 of 2.1, including Table 2, Line One, 1A, 2, 3, or 4, for the foundation of each equipment listed in
1.3.2 through 1.3.4.
3.5 Install new the equipment listed in 1.3.2 through 1.3.5,6, in accordance with 2.2 and 2.3, using 2.4 through 2.6 for guidance.
(E1)
3.5.1 Relocate existing disconnect switch for the equipment listed in 1.3.4 to accessible location on second level exterior, as designated by the SUPERVISOR.
3.5.2 Locate each thermostat control for the equipment listed in
1.3.2 and 1.3.3 in each location designated by the SUPERVISOR.
3.5.3 Template exact size, configuration, and location from each existing onboard condition.
3.5.4 Accomplish the requirements of 009-12 of 2.1, including Table One, Column B, Lines One through 10.
3.5.5 Accomplish the requirements of 009-12 of 2.1, including Table 3, Columns A, C, and D, Lines One through 7.
3.6 Accomplish cleaning of the ventilation system listed in 1.3.6 7 from each weather opening to each terminal end, in accordance with 2.5, using
2.2 for guidance.
(E1)
3.6.1 Matchmark, remove and clean each wire mesh screen, damper, diverting/balancing plate, orifice plate and access plate. Retain for reuse.
3.6.2 Clean interior of ducting free of rust, dirt, grease, lint and other contaminate.
3.6.3 Accomplish a visual inspection of each cleaned interior surface of each ventilation branch for ventilation listed in 1.3.6 7
(E1)
SSP: SERM-024-24 3 of 4 ITEM NO: 514-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
for cleanliness and completion of work prior to installation of each wire mesh screen, damper, orifice plate and access plate. Allowable foreign matter or debris: None.
3.6.3.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.6.3 to the SUPERVISOR.
3.6.4 Install each ventilation piece, including each wire mesh screen, damper, diverting/balancing plate, orifice plate and access plate removed in 3.6.1, using 2.2 and 2.5 for guidance.
3.7 Accomplish the requirements of 009-25 of 2.1 for an air hose test of each new and disturbed penetration. Allowable leakage: None.
3.8 Accomplish the requirements of 009-71 of 2.1 for new and disturbed piping.
(V)(G) "OPERATIONAL TEST"
3.9 Energize with shore power and accomplish operational testing of the equipment listed in 1.3 to ensure equipment functions to designed sequence of operation, in accordance with each manufacturer's instruction supplied with equipment. Allowable leakage: None.
3.9.1 Verify 73 (plus 5 / minus 5) degrees at each compartment serviced by the equipment listed in 1.3.2 through 1.3.4, in accordance with manufacturer's instructions.
(V)(G) "BALANCING VERIFICATION"
3.10 Accomplish testing and balancing for each system installed new, and modified and disturbed portion of each existing system, to ensure minimum delivery of designed air quantities in accordance with 2.3, using 2.5 and
2.6 for guidance.
3.11 Accomplish the requirements of 009-11 of 2.1, for new ducting.
3.11.1 Accomplish the requirements of 009-32 of 2.1 for each surface to be insulated with the exception of non-ferrous and corrosion resistant steel (CRES) piping, plating, and vent ducting.
3.11.2 Accomplish the requirements of 009-32 of 2.1 for new
insulation, lagging, and each reusable cover to match each surrounding area.
3.12 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
5.2 PUSH MATERIAL:
SSP: SERM-024-24 4 of 4 ITEM NO: 514-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. None.
SHIP: YFNX-20 (RMC 22747) ITEM NO: 631-11-001 (E5)
COAR: 28 PCN: SERM-L018
CSWT FILE NO: 631-063 (DDG 51) CMP: NONE
REVISED: 02 OCT 2022 PLANNER: CORNWELL, RICHARD
BRIDGER, WRAY
SSP: SERM-024-24 1 of 1 ITEM NO: 631-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Deck House Interior Bulkhead; preserve (OPTION ITEM)
1.2 Location of Work:
1.2.1 First Deck, Frame 3-13, Port and Starboard
1.2.2 Second Deck, Frame 3-13, Port and Starboard
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Standard Items
3. REQUIREMENTS:
3.1 Accomplish the requirements of 009-32 of 2.1, including Table 3, Lines Line 25,31, 26, or 27, Columns A, B, and D, for preservation of the bulkhead surface, in each location listed in 1.2.
(E5)
3.2 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SHIP: YFNX-20 (RMC 22747) ITEM NO: 635-11-001 (E5)
COAR: 28 PCN: SERM-L008
SWT FILE NO: 635-083 CMP: NONE
REVISED: 02 OCT 2022 PLANNER: KRIMMER, DAVID
BRIDGER, WRAY
CORNWELL, RICHARD
SSP: SERM-024-24 1 of 2 ITEM NO: 635-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Insulation and Ceiling Tile Replacement; accomplish
1.2 Location of Work:
1.2.1 Second Deck (01 Level)
1.2.2 Main Deck
1.3 Identification:
1.3.1 Quantity (1,900 SF), Ceiling Tile System, For the Location Listed in 1.2.1
1.3.2 Quantity (2,000 SF), Ceiling Tile System, For the Location Listed in 1.2.2
1.3.3 Quantity (1,825 SF), Thermal Fibrous Glass Overhead
Insulation, MIL-DTL-32585, Type I, MIL-I-742,Form 2, For the Location Listed in 1.2.1
(E5)
1.3.4 Quantity (2,000 SF), Thermal Fibrous Glass Overhead
Insulation, MIL-DTL-32585, Type I, MIL-I-742,Form 2, For the Location Listed in 1.2.2
(E5)
2. REFERENCES:
2.1 Standard Items
2.2 4-P-8826, Comet III 25'-7"x80'-10 1/8"x25'-0 3/4" 2 Story Building for YFNX-20 Barge at CSNY, 5C (Sheet 2)
2.3 551-5911033 Rev A, Moored Training Ship YFNX 20 Deckhouse Modifications
2.4 302-7029582 Rev B, YFNX-20 Power Distribution and Lighting
3. REQUIREMENTS:
3.1 Remove and dispose of existing ceiling tile system, insulation and lagging from each overhead of each location listed in 1.2, as designated by the SUPERVISOR.
3.2 Accomplish the requirements of 009-11 of 2.1 for installation of new insulation and lagging in the overhead of each location listed in 1.2, in accordance with 2.2.
3.2.1 Accomplish the requirements of 009-12 of 2.1 for each new stud to support insulation and lagging.
3.2.2 Accomplish the requirements of 009-32 of 2.1 for each surface to be insulated with the exception of non-ferrous and corrosion resistant steel (CRES) piping, plating, and vent ducting.
3.2.3 Accomplish the requirements of 009-32 of 2.1 for new
SSP: SERM-024-24 2 of 2 ITEM NO: 635-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
insulation, lagging, and each reusable cover to match each surrounding area.
3.3 Install new each ceiling tile system listed in 1.3 and located in 1.2, using 2.2 through 2.4 for guidance.
3.3.1 Relocate each light, fixture, equipment, pipe, cable, and wire in way of new installation. New installation must be template to suit each existing shipboard condition and offset around each interference not feasible to relocate.
3.3.2 Accomplish the requirements of 009-12 of 2.1, including Table 2,3, Columns A, C, and D, Lines One through 7.
(E2)
(V)(G) "OPERATIONAL TEST"
3.4 Accomplish an operational test of each equipment relocated, using
2.2 through 2.4 for guidance. Verify proper operation.
3.5 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.