J-2 Execution Milestone and Key Event Dates.pdf

PDF 291 KB Posted

Attached to
U. S. NAVY BARGE YFNX-20 NPTU SOLICITATION
Solicitation number
N40027-23-R-0010
Issued by

About this file

This document outlines key milestones and event dates for the execution of a federal contract to perform docking overhaul work on the U.S. Navy barge YFNX-20 located at the Nuclear Power Training Unit in Charleston, South Carolina. The contract start date is scheduled for November 27, 2023 with work to be complete by April 26, 2024. Key milestones and events include towing the barge on November 28, 2023, dry docking on December 8, 2023, conferences at 20%, 50%, and 75% completion, undocking on March 22, 2023, production completion on April 19, 2024, towing the barge back to the Nuclear Power Training Unit on April 19, 2024, and fully completing the availability by April 26, 2024. The document also lists optional items that may be included and controlling work items to be accomplished under the contract.

View the file

Other files

File Type Posted
CONFORMED RFP N4002723R00100005.pdf PDF
AMENDMENT 0005 RFP N4002723R0010 USN BARGE NPTU SERM-024-24.pdf PDF
CONFORMED RFP N4002723R00100004.pdf PDF
YFNX-20 Errata 6.pdf PDF
AMENDMENT 0004 RFP N4002723R0010 USN BARGE NPTU SERM-024-24.pdf PDF
CONFORMED RFP N4002723R00100003.pdf PDF
J-3 ERL SERM_024-24 YFNX 20 REV 2.pdf PDF
YFNX-20 Errata 5.pdf PDF
YFNX-20 Errata 4.pdf PDF
AMENDMENT 0003 RFP N4002723R0010 USN BARGE NPTU SERM-024-24.pdf PDF
YFNX-20 ERRATA Three.pdf PDF
YFNX-20 ERRATA Two.pdf PDF
J-2 Execution Milestone and Key Event Dates REV1.pdf PDF
CONFORMED RFP N4002723R00100002.pdf PDF
AMENDMENT 0002 RFP N4002723R0010 USN BARGE NPTU SERM-024-24.pdf PDF
YFNX-20 Addendum One.pdf PDF
J-3 ERL SERM_024-24 YFNX 20 REV1.pdf PDF
YFNX-20 ERRATA One.pdf PDF
J-1 Specification Package SSP SERM 024-24 REV1.pdf PDF
S-2 Cost Data Break Down YFNX-20 SERM-024-24 Rev 1.xlsx XLSX spreadsheet
N4002723R00100001.pdf PDF
N4002723R00100001 CONFORMED.pdf PDF
N4002723R0010 RFP.pdf PDF
J-4 Small Business Subcontracting Plan.doc DOC document
S-1 Request for Specification Clarification.doc DOC document
Exhibit A CDRL DD 1423-2 NPTU YFNX-20 SSP_024-24.pdf PDF
J-1 Specification Package SSP SERM 024-24.pdf PDF
S-2 Cost Data Break Down YFNX-20 SERM-024-24.xlsx XLSX spreadsheet
J-3 ERL SERM_024-24 YFNX 20.xls.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXECUTION MILESTONE and KEY EVENT DATES WORKSHEET

• MILESTONES

• LIST OF OPTION ITEMS

• LIST OF CONTROLLING WORK ITEMS

• EXECUTION KEY EVENT/MILESTONES FOR SOLICITATION

• KEY EVENT READINESS LIST BY MILESTONE

The following contracting milestones apply.

MILESTONE SKED DATE COMMENTS/REMARKS

CONTRACTOR SHIPCHECK 8/2/2022

Ship is available 9/6/2023 through 9/28/23. Ship is located at Nuclear Power Training Unit, Charleston SC.

CUTOFF FOR BIDDERS

QUESTIONS 9/28/2023

RECEIVE PROPOSALS 10/6/2023

RECEIVE AWARD FUNDS 11/6/2023

AWARD CONTRACT 11/7/2023

START AVAILABILITY 11/27/2023

END AVAILABILITY 4/26/2024

YFNX-20 DOCKING OVERHAUL

OPTION ITEMS

ITEM NO.

SHORT TITLE

COAR

EXERCISE

NLT

522-10-001 Sprinkling System; install

(OPTION ITEM 28 A+3

992-11-003 Barge Towing Service; provide

(OPTION ITEM) 90 A+3

992-11-004 Barge Inland Waterway Tow;

provide (OPTION ITEM) 90 A+3

YFNX-20 DOCKING OVERHAUL

CONTROLLING WORK ITEMS

WORK ITEM

NUMBER

WORK ITEM TITLE

110-11-001 Underwater Hull Survey; accomplish

514-11-001 Heating, Ventilation, Air Conditioning (HVAC) System Replacement; accomplish 522-10-001 Sprinkling System; install 997-11-001 Dry-docking and Undocking; accomplish

YFNX-20 DOCKING OVERHAUL

KEY EVENT/MILESTONE WORKSHEET

EVENT START DATE COMPLETE DATE

Start of Availability (Key Event) 27 Nov 2023

Tow prep/Tow (Key Event) 28 NOV 2023 7 December 2023

DOCK (Milestone) 8 DEC 2023

20% OPEN/INSPEC COMPLETE

(ALL) (Milestone) 29 Dec 2023

25% CONFERENCE (Milestone) 5 Jan 2024

50% CONFERENCE (Milestone) 16 Feb 2023

Fleeting 18 Mar 2024

75% CONFERENCE (Milestone) 22 Mar 2023

UNDOCK (Milestone) 22 Mar 2023

(PCD) - PRODUCTION COMPLETION

DATE (Key Event) 19 April 2024

(WC) - WORK COMPLETE (Key Event) 19 April 2024

Tow to NPTU (key Event) 19 April 2024 25 Apr 2024

Complete Availability (Key Event) 26 Apr 2024

OPTION ITEMS
EVENT