J-2 Execution Milestone and Key Event Dates REV1.pdf

PDF 78 KB Posted

Attached to
U. S. NAVY BARGE YFNX-20 NPTU SOLICITATION
Solicitation number
N40027-23-R-0010
Issued by

About this file

This document outlines key milestones and event dates for the YFNX-20 barge overhaul solicited by the Department of the Navy Naval Sea Systems Command. The schedule includes start and completion dates for availability, towing, docking, conferences to review progress at 20%, 25%, 50%, 75% completion, undocking, work completion, and towing back to the naval shipyard. Responses to solicitation N40027-23-R-0010 are due for the overhaul work of the U.S. Navy barge YFNX-20 at the Naval Ship Repair Training Unit to be performed according to the milestone schedule.

View the file

Other files

File Type Posted
CONFORMED RFP N4002723R00100005.pdf PDF
AMENDMENT 0005 RFP N4002723R0010 USN BARGE NPTU SERM-024-24.pdf PDF
CONFORMED RFP N4002723R00100004.pdf PDF
YFNX-20 Errata 6.pdf PDF
AMENDMENT 0004 RFP N4002723R0010 USN BARGE NPTU SERM-024-24.pdf PDF
CONFORMED RFP N4002723R00100003.pdf PDF
J-3 ERL SERM_024-24 YFNX 20 REV 2.pdf PDF
YFNX-20 Errata 5.pdf PDF
YFNX-20 Errata 4.pdf PDF
AMENDMENT 0003 RFP N4002723R0010 USN BARGE NPTU SERM-024-24.pdf PDF
YFNX-20 ERRATA Three.pdf PDF
YFNX-20 ERRATA Two.pdf PDF
CONFORMED RFP N4002723R00100002.pdf PDF
AMENDMENT 0002 RFP N4002723R0010 USN BARGE NPTU SERM-024-24.pdf PDF
YFNX-20 Addendum One.pdf PDF
J-3 ERL SERM_024-24 YFNX 20 REV1.pdf PDF
YFNX-20 ERRATA One.pdf PDF
J-1 Specification Package SSP SERM 024-24 REV1.pdf PDF
S-2 Cost Data Break Down YFNX-20 SERM-024-24 Rev 1.xlsx XLSX spreadsheet
N4002723R00100001.pdf PDF
N4002723R00100001 CONFORMED.pdf PDF
N4002723R0010 RFP.pdf PDF
J-4 Small Business Subcontracting Plan.doc DOC document
S-1 Request for Specification Clarification.doc DOC document
Exhibit A CDRL DD 1423-2 NPTU YFNX-20 SSP_024-24.pdf PDF
J-1 Specification Package SSP SERM 024-24.pdf PDF
S-2 Cost Data Break Down YFNX-20 SERM-024-24.xlsx XLSX spreadsheet
J-3 ERL SERM_024-24 YFNX 20.xls.pdf PDF
J-2 Execution Milestone and Key Event Dates.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

YFNX-20 DOCKING OVERHAUL

KEY EVENT/MILESTONE WORKSHEET

EVENT START DATE COMPLETE DATE

Start of Availability (Key Event) 27 Nov 2023

Tow prep/Tow (Key Event) 28 NOV 2023 7 December 2023

DOCK (Milestone)

8 DEC 2023

20% OPEN/INSPEC COMPLETE

(ALL) (Milestone)

29 Dec 2023

25% CONFERENCE (Milestone)

5 Jan 2024

50% CONFERENCE (Milestone)

16 Feb 2023

Fleeting

18 Mar 2024

75% CONFERENCE (Milestone)

22 Mar 2023

UNDOCK (Milestone)

22 Mar 2023

(WC) - WORK COMPLETE (Key Event)

19 April 2024

Tow to NPTU (key Event) 19 April 2024 25 Apr 2024

Complete Availability (Key Event)

26 Apr 2024