About this file

RFP 1442

View the file

Other files

File Type Posted
UAS_SATCOM_RELAY_PADS_AND_FACILITY_11005.docx DOCX document
AMENDMENT_0011_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
AMENDMENT_0010_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
AMENDMENT_009_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
AMENDMENT_008_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
AMENDMENT_007_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
1118648_SPC_03-09-2015.pdf PDF
1118648_DWG_03-09-2015.pdf PDF
AMENDMENT_006_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
1118648_Amendment_2_Continuation_Sheet_2015-03-06.doc DOC document
AMENDMENT_005_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
AMENDMENT_004_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
PPI_015__Response_Attachments.pdf PDF
AMENDMENT_003_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
AMENDMENT_002_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
N62470-09-R9034_Part10-FP.pdf PDF
N62470-09-R9034_Part03-CIV.pdf PDF
N62470-09-R9034_Part02-LS.pdf PDF
N62470-09-R9034_Part05-GEO.pdf PDF
11005R_SPECS_Final-EBS_04.13.12_Vol_1.pdf PDF
11005_SPECS_Final-EBS_04.13.12_Vol_2.pdf PDF
N62470-09-R9034_Part08-AR.pdf PDF
N62470-09-R9034_Part04-CIV_(CONT).pdf PDF
N62470-09-R9034_Part11-FP_(CONT).pdf PDF
N62470-09-R9034_Part09-IN.pdf PDF
N62470-09-R9034_Part06-LAND.pdf PDF
N62470-09-R9034_Part13-ME.pdf PDF
AMENDMENT_0001N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
N62470-09-R9034_Part14-EL.pdf PDF
N62470-09-R9034_Part07-ST.pdf PDF
N62470-09-R9034_Part12-PL.pdf PDF
N62470-09-R9034_Part01-GEN.pdf PDF
N62470-09-R9034_Part08-AR.pdf PDF
N62470-09-R9034_Part03-CIV-revised.pdf PDF
Contract_Risk_Assessment_and_QA_Responsibility_Spreadsheet-.pdf PDF
N62470-09-R9034_Part01-GEN.pdf PDF
N62470-09-R9034_Part04-CIV.pdf PDF
N62470-09-R9034_Part14-EL 1 .pdf PDF
11005R_SPECS_Final-EBS_04.13.12_Vol_1.pdf PDF
11005_SPECS_Final-EBS_04.13.12_Vol_2.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N33191-15-R-0802, Design-Bid-Build Firm Fix Price (FFP) Construction Contract, UAS SATCOM NAS II, SIGONELLA, ITALY

GENERAL DESCRIPTION: The w ork includes demolition and removal, site w ork for SATCOM relay structural pads and foundations w ith access roads, utilities and underground conduit connectivity to main facility, special security features such as perimeter fence, vehicle Sally Port, access control point pedestrian Sally Port and turnstile, reinforced concrete w all supported guardhouse w ith steel framed metal panel roofing system and bullet resistant w indow s, provisions for a single story reinforced concrete w all supported building w ith steel framed sloped metal panel roofing system, concrete slab, a continuous reinforced concrete foundation footing, interior f inishes, raised f looring system, f ire protection sprinkler and alarm system, HVAC, plumbing, electrical and incidental related w ork. This building shall qualify for LEED Silver Certif ication.

Duration of this contract is for 550 days

In accordance w ith FAR 36.204 and DFARS 236.204, the estimated price for this project is $10M a

GRACE E. MONTERO 081-568-6211

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

13-Jan-2015

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

X

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______15 calendar days and complete it w ithin ________550 calendar days after receiving aw ard, notice to proceed. This performance period is X mandatory, negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

NAVFAC EUROPE AFRICA SOUTHWEST ASIA

PSC 817 BOX 51

FPO AE 09622-0051

N33191

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

(hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

39 081 568 7750FAX:TEL: 39 081 568 7750 TEL: FAX:

N33191-15-R-0802 49

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued)

(Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

N33191-15-R-0802

Section 00010 - Solicitation Contract Form

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Lot

-UAS SATCOM, RELAY PADS, SIGONELLA, ITAL

FFP

The work includes demolition and removal, site work for SATCOM relay structural pads and foundations with access roads, utilities and underground conduit connectivity to main facility, special security features such as perimeter fence, vehicle Sally Port, access control point pedestrian Sally Port and turnstile, reinforced concrete wall supported guardhouse with steel framed metal panel roofing system and bullet resistant windows, provisions for a single story reinforced concrete wall supported building with steel framed sloped metal panel roofing system, concrete slab, a continuous reinforced concrete foundation footing, interior finishes, raised flooring system, fire protection sprinkler and alarm system, HVAC, plumbing, electrical and incidental related work. This building shall qualify for LEED Silver Certification.

FOB: Destination

NET AMT

0002 1 Lot

-BID OPTION #1 - FUEL CELL/GAS LINE

FFP

HVAC, SITE CIVIL/MECHANICAL UTILITIES, SITE ELECTRICAL

UTILITIES

0003 1 Lot

BID OPTION #2 - LID INFILTRATION

FFP

SITE PREPARATION, SITE CIVIL/MECHANICAL UTILITIES

0004 1 Lot

-BID OPTION #3 - LED SITE LIGHTING

FFP

SITE ELECTRICAL UTILITIES

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 N/A N/A N/A Government

0002 N/A N/A N/A Government

0003 N/A N/A N/A Government

0004 N/A N/A N/A Government

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC

0001 N/A N/A N/A N/A

0002 N/A N/A N/A N/A

0003 N/A N/A N/A N/A

0004 N/A N/A N/A N/A

CLAUSES INCORPORATED BY FULL TEXT

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

[Insert one or more Internet addresses]

(End of provision)

Section 00100 - Bidding Schedule/Instructions to Bidders

INSTRUCTIONS TO OFFERORS

DOCUMENT 00100

INSTRUCTIONS TO OFFERORS

1.1 GENERAL DESCRIPTION & SCOPE OF WORK

1.2 PRE-PROPOSAL CONFERENCE AND SITE VISIT

1.3 ENGLISH SPEAKING REPRESENTATIVE

1.4 JOINT VENTURES (JV), LIMITED LIABILITY COMPANIES (LLC), LIMITED PARTNERSHIPS

(LTD), ETC.

1.5 SYSTEM FOR AWARD MANAGEMENT

1.6 CAGE/NCAGE CODE

1.7 INSTRUCTIONS FOR THE SUBMISSION OF OFFERS

1.8 INSTRUCTIONS FOR SUBMITTING PRE-PROPOSAL INQUIRIES (PPI)

1.9 AMENDMENTS

1.10 PREAWARD SURVEY/RESPONSIBILITY DETERMINATION

1.11 CLASIFICACION DE EMPRESAS DE OBRAS CERTIFICATION

1.12 BONDS AND CERTIFICATES – PERFORMANCE GUARANTEE WITH LETTER SAMPLE

--End Document Table of Contents--

1.1 GENERAL DESCRIPTION & SCOPE OF WORK

(a) This procurement will result in the award of a Firm-Fixed Priced Design-Build Construction Contract. The contract will be procured using negotiated procedures, as it has been determined in accordance with FAR 6.401 to be the most appropriate method of contracting for the subject requirements. The tradeoff process on the best value source selection continuum, as described in FAR 15.101, will be used for this procurement.

(b) The purpose of this procurement is to provide a contract for the demolition and removal, site work for SATCOM relay structural pads and foundations. The work includes furnishing of all labor, management, supervision, tools, materials and equipment necessary to perform access roads, utilities and underground conduit connectivity to main facility, special security features such as perimeter fence, vehicle Sally Port, access control point pedestrian Sally

Port and turnstile, reinforced concrete wall supported guardhouse with steel framed metal panel roofing system and bullet resistant windows, provisions for a single story reinforced concrete wall supported building with steel framed sloped metal panel roofing system, concrete slab, a continuous reinforced concrete foundation footing, interior finishes, raised flooring system, fire protection sprinkler and alarm system, HVAC, plumbing, electrical and incidental related work. This building shall qualify for LEED Silver Certification. The estimated price rfor this project is $10M.

(c) The Request for Proposal (RFP) will include the following Contract Line Items (CLINS) for the basic contract:

BASE PERIOD

CLIN 0001

- UAS SATCOM

- GUARDHOUSE

- SUPPORTING FACILITIES

BID OPTIONS

CLIN 0002 BID OPTION 1

FUEL CELL/GAS LINE

CLIN 0003 BID OPTION 2

LID INFILTRATION

CLIN 0004 BID OPTION 3

LED SITE LIGHTING

Project completion date is anticipated to be 550 days with three (3) potential bid options for a total maximum duration of 60 months. Options will be exercised in accordance with FAR 17.208(g). The Government has the bid option to award any or all bid quantities at the time of award, contingent upon the price proposals received in comparison to the amount of funds available.

(d) The contract period of performance is anticipated to be 550 Calendar Days.

(e) This acquisition will be solicited on an unrestricted basis with full and open competition as authorized in the approved acquisition development plan.

1.2 PRE-PROPOSAL CONFERENCE AND SITE VISIT

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in the contract awarded as a result of this solicitation. Accordingly, offerors are urged and expected to inspect the site where the work will be performed.

(b) An organized Pre-Proposal Conference and Site Visit (a) A pre-proposal conference and site visit are schedule on Tuesday, January 27, 2015 from 1:00 p.m to 3:00 p.m at NAS II, Sigonella, Sicily.

Prospective Offerors will meet at the Public Works Building 618 FEAD Conference room for a briefing and then move to the actual project site. No Photography are allowed.

(b) Attendance is limited to a maximum or 4 personnel per Contractor.

Prospective Offerors are requested to provide the FEAD office with the names of personnel who will be attending, the companies they are from, e-mail and phone number. Personnel attending are to include copies of the "Carta D'Identita' (Italian Identification Card). This information is to be provided to Ms. Cristina Lauria at Cristina.lauria.it@eu.navy.mil No Later than January 20, 2015 by 4:00 p.m.

(c) The location for the site visit is as follows:

U.S. Naval Air Station, Sigonella, Bldg. 618 FEAD Conference Room Strada Statale 417 Catania - Gela

Contract Specialist Maria Arena, e-mail: maria.arena.it@eu.navy.mil Telephone: 011-39-380-702-4847 Conference will start promptly at 1300 and those not in attendance will not be allowed to participate.

1.3 ENGLISH SPEAKING REPRESENTATIVE

At all times when any performance of the work at the site is being conducted by an employee of the Contractor or his subcontractors, the contractor shall have a representative present on the site capable of explaining the work operations and receiving instructions in the English language. The Contracting Officer shall have the right to determine, without appeal of such decision, whether the proposed representative has sufficient technical and lingual capabilities, and the Contractor shall immediately replace any individual not acceptable to the Contracting Officer.

1.4 JOINT VENTURES (JV) AGREEMENTS

FOR THE PURPOSES OF THIS SOLICITATION, A JOINT VENTURE (JV) REFERS TO A U.S.-STYLED

FORMAL LEGAL ENTITY IN THE NATURE OF A PARTNERSHIP COMPRISED OF TWO OR MORE

PERSONS OR COMPANIES. EACH JOINT VENTURE MUST PROVIDE ONE (1) CAGE/NCAGE CODE,

ONE (1) DUNS NUMBER FOR THE JOINT VENTURE AND ONE (1) DUNS NUMBER FOR EACH MEMBER

COMPRISING THE JOINT VENTURE. EACH JOINT VENTURE MUST BE REGISTERED IN THE CCR

USING THE NAME OF THE JOINT VENTURE.

Joint Venture Offerors (JV) offerors, shall provide with their proposal a notarized legal document that establishes the

JV. The JV Agreement shall take effect upon the submission of the proposal and remain irrevocable until one (1) year after the work has been finally inspected and accepted by the Government. Submission of the notarized legal document that establishes the JV shall be furnished with the proposal in its original language version along with a certified English translation of the notarized JV document. The Joint Venture must be formed and valid at the time of submission of the proposal. The validated notarized legal document must include language that each member of the JV will be jointly and severally liable for the performance of the whole contract and will be incorporated into the contract award if award is made to the JV.

1. The Joint Venture Agreement shall include, at a minimum, the following:

(a) Name of firms that form the JV and the name of the JV.

(b) Name and title of the corporate officials signing on behalf of each party.

(c) Solicitation number.

(d) Description of the responsibilities in terms of work category for each member (for example: Firm A performing 100% of design).

(e) The statement "The composition and structure of the JV will remain unchanged from award to one (1) year after contract completion.”

(f) Date of issuance of the agreement and notarized signature of the corporate officials signing in behalf of each party.

(g) Statement under oath stating that the Joint Venture(JV) is in compliance at the time of proposal submission with all applicable laws, rules, and regulations. This statement must be signed under oath by all members comprising the Joint Venture.

The U.S. Government reserves the right to review the actual JV Agreement to determine its basis and compliance with the applicable laws. Any internal agreements affecting the internal composition of the existing JV and its potential liabilities in relation to the contract (performance guarantee, insurance, etc) will be sent to the Contracting

Officer to provide notice of the same. Any change in the composition of the JV will require the JV to formally request a Novation Agreement in accordance with FAR 42.12, which will be approved/disapproved at the discretion of the Contracting Officer.

1.5 SYSTEM FOR AWARD MANAGEMENT

1. System for Award Management (SAM) registration is required for all offerors, including Joint Venture (JV) offerors (registration must state the NAME of the JV). SAM registration can be accomplished at https://www.sam.gov. Offerors not registered in SAM shall obtain a DUN & Bradstreet (DUNS) number and a

CAGE or NCAGE prior to registering in SAM.

2. A DUNS number is required for all offerors, including JV offerors. In addition to the DUNS number required for

JV offerors, JV offerors must provide a DUNS number for each member comprising the JV. DUNS numbers can be obtained at http://fedgov.dnb.com/webform. The DUNS number is required in order to register in SAM.

3. Offerors must be registered in the SAM prior to the submission of proposals.

1.6 CAGE/NCAGE CODE

1. A CAGE/NGAGE Code is required for all offerors, including JV offerors. JV offerors must acquire a

CAGE/NCAGE Code registered in the JV name.

http://fedgov.dnb.com/webform

2. U.S. Offerors, including Joint Venture offerors: U.S. offerors must obtain a CAGE Code prior to registering in the SAM database, which is part of the SAM registration process.

3. Non-U.S. (foreign) Offerors ONLY: Non-U.S. offerors must obtain a NATO CAGE (NCAGE) Code instead of a CAGE Code prior to registering in the SAM database. NCAGE codes may be obtained at the NCAGE website http://www.dlis.dla.mil/Forms/Form_AC135.asp.

1.7 INSTRUCTIONS FOR THE SUBMISSION OF OFFERS

a. NON-PRICE PROPOSAL (FACTORS 1, 2, 3 AND 4): Submit the following via email to Grace Montero grace.montero@eu.navy.mil and Joseph Martinez at joseph.a.martinez@eu.navy.mil no later than Friday, 27

February 26th at 14:00 Central European Time (CET). Submit the Non-Price Proposal with the following subject line:

“SOLICITATION N33191-15-R-0802 UAS SATCOM RELAY PADS AND FACILITY”

1. Cover letter in accordance with FAR 52.215-1(c)(2), including Solicitation Number; name, address, telephone and email address of the Offeror; in case the Offeror is a JOINT VENTURE (JV), the name of the JV

MUST BE CLEARLY IDENTIFIED; Name, title, and signature of the person authorized to sign the proposal;

DUNS Number and CAGE or NCAGE Code of the Offeror, in case the Offeror is a JOINT VENTURE (JV), provide a DUNS Number for each member of the JV.

2. Completed (Blocks 14 through 20c), signed and dated Standard Form (SF) 1442, Solicitation, Offer, and

Award.

3. Acknowledgement of all amendments.

Multiple e-mails may need to be sent for any of the submissions, if your e-mail exceeds 5MB. The U.S. Navy computer server will only accept e-mails with attachments up to 5MB. If you need to submit more than one e-mail for the above submission, number them at the end of the e-mail subject title as “1 of ?”, “2 of ?”, etc.

Proposals not received at the above address on or before the hour and date set for the receipt of proposals shall be considered late, subject to the provisions of FAR Clause 52.215-1 Instructions to Offerors -- Competitive

Acquisition (JAN 2004).

The NON-PRICE PROPOSAL shall include the following:

(1) First page of the proposal shall be in accordance with FAR 52.215-1(c)(2)

(2) All information required by Factor 1, Experience

(3) All information required by Factor 2, Safety

(4) All information required by Factor 3, Schedule

(5) All information required by Factor 4, Past Performance on Recent, Relevant Projects

Non-Cost/Price Factors:

In making the best value award decision, the government will consider all non-price Factors and price.

The solicitation requires the evaluation of price and the following non-price factors:

Non-Price Evaluation Factors

Factor 1 – Experience

Factor 2 – Safety

Factor 3 – Schedule

Factor 4 – Past Performance http://www.dlis.dla.mil/Forms/Form_AC135.asp mailto:grace.montero@eu.navy.mil mailto:joseph.a.martinez@eu.navy.mil

The distinction between experience and past performance is that experience pertains to the types of work and volume of work completed by a contractor that are comparable to the types of work described under the definition of recent, relevant projects, in terms of size, scope, and complexity. Past performance pertains to both the relevance of recent efforts and how well a contractor has performed on the contracts.

The relative order of importance of the non-price evaluation factors is the technical factors (Factors 1, 2 and 3) are of equal importance to each other and, when combined are equal in importance to the past performance factor (Factor

4). When the proposal is evaluated as a whole, the technical factors and past performance factor combined (i.e., the non-price evaluation factors) are approximately equal to price.

The importance of price will increase if the Offerors’ non-price proposals are considered essentially equal in terms of overall quality, or if price is so high as to significantly diminish the value of a non-price proposal’s superiority to the

Government. Award will be made to the responsible Offeror(s) whose offer conforms to the solicitation and represents the best value to the Government, price and non-price factors considered.

3. Basis of Evaluation and Submittal Requirements for Each Factor

(a) Price:

(1) Solicitation Submittal Requirements:

Cover letter in accordance with FAR 52.215-1(c)(2), including Solicitation Number; name, address, telephone and email address of the Offeror; in case the Offeror is a JOINT VENTURE (JV), the name of the JV MUST BE

CLEARLY IDENTIFIED; Name, title, and signature of the person authorized to sign the proposal; DUNS Number and CAGE or NCAGE Code of the Offeror, in case the Offeror is a JOINT VENTURE (JV), provide a DUNS

Number for each member of the JV.

(2) Completed (Blocks 14 through 20c), signed and dated Standard Form (SF) 1442, Solicitation, Offer, and Award.

(3) Acknowledgement of all amendments;

(4) Certificate of Classification Requirement.

a. Societa' Organismi d' Attestazione (SOA) certification requirement. The following qualification standards shall be met by the offerors:

CATEGORY CLASSIFICATION PERCENTAGE OF WORK

The Prevailing Work Category OS30- Class IV BIS (43%)

Additional Category OG1 Class IV BIS (42%)

As per article 79 comma 16 of the DPR 207/2010, alternatively to the prevailing category OS30, the offerors OS30, the offerors possessing Category OG11 Class IV BIS can compete to this solicitation.

b. Submission of SOA Certification and Article 38 of the DL 163/06 (DeLise

Code). Offerors shall demonstrate that they meet the SOA certification requirements and demonstrate compliance with Article 38 of DL 163/06. An offeror shall submit the following as part of its proposal:

(1) An unexpired SOA Certificate (including joint venture partner, consortium partners or subcontractors that will be utilized to meet the qualification standard).

(2) Current self-certification documentation required by Article 38 of DL 163/06.

(3) If the potential offeror is a joint venture or a consortium, the offeror shall demonstrate how each member or partner meets the SOA certification requirements stated in paragraph (a) above. Include a description of the responsibilities in terms of work category for each member or partner (for example - Firm A performing 70% of OG-

1 and Firm B performing 30% of OS-30)

(4) An offeror's proposal will be rejected for failure to provide the current SOA certificates required under this solicitation. In the case of a Joint Venture (JV), each member of the JV must have at least one of the required SOA

Certifications. The JV member who has the SOA Certification must perform the majority of the work pertinent to the certification. In the case of a JV, certification submitted by a subcontractor will not be accepted.

2. Basis of Evaluation:

The Government will evaluate price based on the total price. Total price consists of the basic requirements and all option items (see Section B of the solicitation). The Government intends to evaluate all options and has included the provision FAR 52.217-5, Evaluation of Options (JUL 1990) in Section M of the solicitaiton. In accordance with

FAR 52.217-5, evaluation of options will not obligate the Government to exercise the option (s). A price, which is found to be unreasonably high, unrealistically low or unbalanced in relation to the proposed work and/or

Government estimate, may negatively impact the offeror’s evaluation and will result in a rating of Unacceptable. Price analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:

(i) Comparison of proposed prices received in response to the RFP;

(ii) Comparison of proposed prices with the IGE;

(iii) Comparison of proposed prices with available historical information; OR

(iv) Comparison of market survey results.

(v) The price proposals will be ranked from lowest to highest based on the evaluation criteria stated above.

(vi) The price proposal will initially be evaluated separately from the technical proposal. The

Government has the discretion of determining which offer is most advantageous to the Government considering price and technical quality of the proposal.

(1) Factor 1 – Experience:

(i) Solicitation Submittal Requirements:

The Offeror shall submit the following information:

(ii) Construction Experience:

Submit a minimum of three (3) projects and maximum of five (5) relevant construction projects for the Offeror that best demonstrates your experience on relevant projects that are similar in size, scope, and complexity to the RFP.

For purposes of this evaluation, a relevant project is further defined as the following: Offer may be given extra credit if all five (5) projects are relevant.

Similar in scope by providing for the construction of a facility that is a minimum of 800-Square Meters

(8,611-Square Feet) or larger.

Each relevant contract submitted must have a value of at least $6,000,000.

Projects submitted for the Offeror shall be completed within the past five (5) years of the date of issuance of this

RFP.

A project is defined as a construction project performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project;

rather Offerors shall submit the work performed under a task order as a project.

The attached Construction & Design Experience Project Data Sheet (Attachment D) is MANDATORY and SHALL be used to submit project information. Except as specifically requested, the Government will not consider information submitted in addition to this form. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed one (1) double-sided page (or two (2) single-sided pages).

For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP (i.e.: unique features, area, construction methods). In addition, the description should also address any sustainable features for the project, including specific descriptions of those features. Provide applicable documentation on projects that were validated and/or certified through U.S. Green

Building Council (USGBC) or the equivalent organization or process.

If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the

Joint Venture entity. If the Joint Venture does not have experience, at least one project shall be submitted for each

Joint Venture partner. Offerors are still limited to a total of five (5) projects combined.

If an Offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement in the performance of the contract.

The Offeror may utilize experience of a subcontractor that will perform major or critical aspects of the requirement to demonstrate construction experience under this evaluation factor. The Offer must provide a letter of commitment and an explanation of the meaningful involvement that the subcontractor will have in performance of this contract.

More weight may be given to the Offeror’s projects than to those submitted for subcontractors.

(iii) Basis of Evaluation:

The basis of evaluation will include the Offeror’s demonstrated experience and depth of experience in performing relevant construction projects as defined in the solicitation submittal requirements. The assessment of the Offeror’s relevant experience will be used as a means of evaluating the capability of the Offeror to successfully meet the requirements of the RFP. The Government will only review five projects for construction. Any projects submitted in excess of the five (5) for Construction Experience will not be considered.

Relevant projects that demonstrate experience with sustainable features may be considered more favorably than those that do not demonstrate experience with sustainable features.

Relevant projects that are also a SATCOM Relay Facility, Data Processing Center or Communications

Facility may be considered more favorably than a relevant project that is not one of these facility types.

Relevant projects that demonstrate experience with construction for the United States Government may be considered more favorably than those that do not demonstrate this experience.

Factor 2 – Safety

(i) Submittal Requirements:

The offeror shall submit the following information: (For a partnership or joint venture, the following shall address each contractor who is part of the partnership or joint venture; only one safety narrative is required.)

(1) Technical Approach for Safety:

Describe the Offeror’s technical approach to safety for its employees as well as the plan that the Offeror will implement to evaluate and measure safety performance of potential subcontractors as a part of the selection process for all levels of subcontractors. Also, describe any innovative methods that the Offeror will employ to ensure and monitor safe work practices at all subcontractor levels. The Safety Narrative shall be limited to three pages, 8 ½ x 11 page size, one (1) double-sided page and one (1) single-sided page (or three (3) single-sided pages). Any pages submitted in excess of the three (3) will not be considered.

(ii) Basis of Evaluation:

Technical Approach to Safety:

The Government is seeking to determine that the Offeror has consistently demonstrated a commitment to safety and that the Offeror plans to properly manage and implement safety procedures for itself and its subcontractors. The

Government will evaluate the Offeror’s overall safety record, the Offeror’s plan to select and monitor subcontractors, and any innovative safety methods that the Offeror plans to implement for this procurement. The Government’s sources of information for evaluating safety may include, but are not limited to, Government agencies, OSHA, NAVFAC’s Facility Accident and Incident Reporting (FAIR) and Contractor Incident Reporting System (CIRS) databases, and other related resources. While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete safety information regarding these submittal requirements rests with the Offeror. The evaluation will collectively consider the following:

- Offeror Technical Approach to Safety

- Other sources of information available to the Government

The Government will evaluate the narrative to determine the degree to which subcontractor safety performance will be considered in the selection of all levels of subcontractors on the upcoming project. The Government will also evaluate the narrative to determine the degree to which innovations are being proposed that may enhance safety on this procurement. Those Offerors whose plan demonstrates a commitment to hire subcontractors with a culture of safety and who propose innovative methods to enhance a safe working environment may be considered more favorably in the evaluation.

(2) Factor 3 –Schedule

Provide a contract schedule that includes all aspects of pre-construction activities, major HVAC and electrical procurement, construction and post-construction activities. The contract timeframe identified in the RFP defines the acceptable contract duration; a shorter contract duration is desirable.

For purpose of evaluation, the schedule shall be based on a 01 May 2015 Notice to Proceed (NTP), with construction durations in weeks/days in lieu of specific calendar dates. At a minimum the schedule shall address the following:

Pre-Construction (administration, PAK meeting, submittals, reviews & approvals)

Procurement of Major HVAC and Electrical equipment, and long lead items such as the Pre-Engineered

Metal Building (submittal preparation, submittal review and approval, fabrication and delivery).

Site Demolition/Preparation.

OSP/ISP Communication Duct Bank Construction

Antenna Foundation Construction.

Interior Build-Out and Finishes.

Start-Up, Testing & Commissioning.

Project Close-Out.

Provide a Narrative and a Project Schedule in CPM format that explains the proposed contract duration, construction and scheduling innovations and methods to provide realistic shorter contract duration. The Narrative shall not exceed four (4) (or eight (8) single-sided pages) double-sided 8-1/2”x11” pages. Provide the CPM format Project Schedule as a PDF file and source file, and the Summary Level, and Critical Path Schedule, documenting any multiple Critical

Paths in 11” x 17” pages, there is no page limit on the Summary Level and Critical Path (do not submit the printed copies of the entire CMP schedule).

The Government will evaluate a comparison of the contractor’s proposed contract duration to the overall contract duration provided in the RFP. The Government’s evaluation of the contractor’s proposed schedule is a means of determining whether the contractor understands the scope of work and approaches the tasks in a logical and effective manner.

The contractor may receive evaluative credit for realistic proposed contract duration that is shorter than the acceptable contract duration. The contractor’s proposed contract duration shall become an enforceable part of the contract and will be reflected in the awarded Contract Completion Dated (CCD) to the successful Offeror. Proposed schedules in excess of the contract duration provided in the RFP will be considered a material deficiency and will not be eligible for award.

(3) Factor 4 – Past Performance

IF A COMPLETED CONSTRUCTION CONTRACTOR APPRAISAL SUPPORT SYSTEM (CCASS)

EVALUATION IS AVAILABLE, IT SHALL BE SUBMITTED WITH THE PROPOSAL FOR EACH PROJECT

INCLUDED IN FACTOR 1 FOR CONSTRUCTION EXPERIENCE. IF THERE IS NOT A COMPLETED CCASS

EVALUATION THEN SUBMIT PAST PERFORMANCE QUESTIONNAIRES (ATTACHMENT E) FOR EACH

PROJECT INCLUDED IN FACTOR 1 FOR BOTH CONSTRUCTION EXPERIENCE. The Offeror should provide completed Past Performance Questionnaires (PPQ) in the proposal. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the

Government from utilizing previously submitted PPQ information in the past performance evaluation.

If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the

Offeror shall complete and submit with the proposal the first page of the PPQ, (Attachment E), which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, Offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Grace Montero at grace.montero@eu.navy.mil and Joe

Martinez at joseph.a.martinez@eu.navy.mil.

Offerors may provide any information on problems encountered and the corrective actions taken on projects submitted under Factor 1 – Experience. Offerors may also address any adverse past performance issues.

Explanations shall not exceed two (2) double-sided pages (or four (4) single-sided pages) in total.

The Government reserves the right to contact references for verification or additional information. The

Government’s inability to contact any of the Offeror’s references or the references unwillingness to provide the information requested may affect the Government’s evaluation of this factor.

Performance award or additional information submitted will not be considered.

This evaluation focuses on how well the Offeror performed on the relevant projects submitted under Factor 1 –

Experience and past performance on other projects currently documented in known sources. For purposes of the past performance evaluation, a relevant project is defined as building construction with a value of $6,000,000.00 or greater. In addition to the above, the Government reserves the right to obtain information for use in the evaluation of past performance from any and all sources including sources outside of the Government. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval

System (PPIRS) using all CAGE/DUNS numbers of Contractors who are part of a partnership or joint venture identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity

Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.

The Government will consider the currency and relevance of the information, the source of the information, context of the data, and general trends in the Contractor’s performance. This evaluation is separate and distinct from the

Contracting Officer’s responsibility determination. The assessment of the Offeror’s past performance will be used as a means of evaluating the Offeror’s probability to successfully meet the requirements of the RFP.

Offerors lacking relevant past performance history will not be evaluated favorably or unfavorably in past performance and will receive an Unknown Confidence rating.

1.8 INSTRUCTIONS FOR SUBMITTING PRE-PROPOSAL INQUIRIES (PPI)

Pre-Proposal Inquiries (PPI) regarding the solicitation shall be submitted in writing via electronic mail to Mrs Grace

Montero , Contract Officer, at grace.montero@eu.navy.mil and Mr. Joseph Martinez, Contract Specialist, at joseph.a.martinez@eu.navy.mil. Pre-Proposal Inquiries shall reference the drawing/detail and/or the specification section, including paragraph number. Verbal queries will not be entertained. Responses to the Pre-Proposal

Inquiries will be provided as an attachment to an amendment and will be posted on the Federal Business

Opportunities (FBO) website at https://www.fbo.gov. The Government may not respond to Pre-Proposal Inquiries submitted less than 10 days before the proposal receipt due date. The Pre-Proposal Inquiry (PPI) Template is provided as Attachment C, use this form for questions.

1.9 AMENDMENTS

Amendments will be posted to the FBO website https://www.fbo.gov. It is highly recommended that firms register on FBO as plan holders. It is the offeror’s responsibility to check the FBO website periodically for any amendments to the solicitation.

1.10 PREAWARD SURVEY/RESPONSIBILITY DETERMINATION

mailto:grace.montero@eu.navy.mil mailto:joseph.a.martinez@eu.navy.mil https://www.fbo.gov/ https://www.fbo.gov/

FAR §9.104 requires prospective contractors to demonstrate, among other things, that they have adequate financial resources to perform the contract or ability to obtain them, capability to comply with the required performance schedule, a satisfactory performance record, and be otherwise eligible to receive an award under applicable laws and regulations. The pre-award survey is not a part of the technical evaluation. The following information shall be submitted:

a. Annual Financial Balance Sheets for the past three years in English.

b. Financial resources available to perform the contract. Submit evidence of availability of working/operating capital that will be used for the performance of the contract in English. If the offeror plans to rely on financial support from other sources (i.e. independent financial institutions), identify the maximum lines of credit that will be available to include documentation to support the amounts. The maximum lines of credit should be based upon the inclusion of this contract effort.

For joint ventures, discuss the financial responsibilities among companies and provide the same information for each partner.

1.11 ANTI-MAFIA LAW:

Offeror is responsible for complying with Italian Anti-Mafia laws with respect to its subcontractors, including, but not limited to, obtaining subcontractor C.C.I.A.A. certificates inclusive of the anti-mafia "nulla osta" statement in accordance with Art. 67 of Legislative Decree no. 159/2011; and, if necessary, requesting additional information regarding attempts of mafia infiltration from a competent Prefect (Prefetto). Offeror agrees to provide Government appropriate documentation showing results of any Prefect (Prefetto) investigations. If after award, a competent

Prefect (Prefetto) determines that mafia infiltration attempts have occurred with a subcontractor, then Offeror agrees to promptly terminate the subject subcontract and replace the mafia-colluded subcontractor at its own cost with a compliant company.

Pre-Award Effect of Anti-Mafia Procedures: In asmuch as the work of this solicitation is to be performed on land owned by the Italian State, the prospective contractor will be subject to Italian legislation concerning anti-mafia documentation, including, without limitation: Legislative Decree no. 159 of September 6, 2011, Decree of the

President of the Republic no. 252 of June 3, 1998, Legislative Decree no. 490 of August 8, 1994 and Law Decree

no. 629 of September 6, 1982, and subsequent integrations and amendments. Only firms that submit the requested documentation will be considered for award. In the event that prior to award any mafia infiltration attempt is determined by the competent Prefect (Prefetto) against an offeror, pursuant to Art. 4 of Legislative Decree no.

490/1994 and Art. 10 of Decree of the President of the Republic no. 252/1998, no award will be made to said offeror. Furthermore, in the event that prior to award any additional information against an offeror is provided by the competent Prefect (Prefetto) pursuant to Art. 1, Section 7 of Law decree 629/1982 and Art. 10, paragraph 9, of

Decree of the President of the Republic no. 252/1998, the Government may decide, at its sole discretion, that no award will be made to said offeror.

Termination Under Decree of the President of the Republic no. 252/1998: If during the life of this contract, any mafia infiltration attempt is determined by the Prefect (Prefetto) against any component of the Contractor or any

Subcontractor, pursuant to Art 4 of Legislative Decree no. 490/1994 and Art. 10 of Decree of the President of the

Republic no. 252/1998, the Government will consider this a failure to execute the work and terminate the contractor's right to proceed with the work under the "Default" clause of this contract. If during the life of this contract, any additional information is provided by the Prefect (Prefetto) pursuant to Art. 1, Section 7 of Law

Decree 629/1982 and Art. 10, paragraph 9, of Decree of the President of the Republic no. 252/1998, against any component of the Contractor or any subcontractor, the Government at its sole discretion may consider this a failure to execute the work and terminate the contractor’s right to proceed with the work under the “Default” clause of this contract.

Documentation Requirements, Contractor shall submit the following:

If available, include the Certificate di Iscrizione alia Camera di Commercia - Original, unexpired and not older than SIX (6) months old from the date of proposal submission from the Chamber of Commerce Certificate of

Membership (Certificato di Iscrizione alla Camera di Commercio) inclusive of the antimafia nulla osta statement reading: "Nulla osta ai fini dell'articolo 67 del Decreto legislativo n. 159 del 6 settembre 2011 (gia Art. 10 della legge 31 maggion 1965, n 575) e successive modificazioni. La presente certificazione e emessa dalla C.C.I.A.A.

utilzzando il collegamento telematico con il sistema informativo utilizzato dall prefettura di Roma.

If contractor has attempted and is unable to obtain the certificate from the Chamber of Commerce please include an explanation why not, along with official correspondence from the Chamber of Commerce if available.

This documentation is to be included in your Price Proposal.

1.12 Societa' Organismi d' Attestazione (SOA) certification requirement. The following qualification standards shall be met by the offerors:

CATEGORY CLASSIFICATION PERCENTAGE OF WORK

The Prevailing Work Category OS30- Class IV BIS (43%)

Additional Category OG1 Class IV BIS (42%)

As per article 79 comma 16 of the DPR 207/2010, alternatively to the prevailing category OS30, the offerors OS30, the offerors possessing Category OG11 Class IV BIS can compete to this solicitation.

b. Submission of SOA Certification and Article 38 of the DL 163/06 (DeLise

Code). Offerors shall demonstrate that they meet the SOA certification requirements and demonstrate compliance with Article 38 of DL 163/06. An offeror shall submit the following as part of its proposal:

(1) An unexpired SOA Certificate (including joint venture partner, consortium partners or subcontractors that will be utilized to meet the qualification standard).

(2) Current self-certification documentation required by Article 38 of DL 163/06.

(3) If the potential offeror is a joint venture or a consortium, the offeror shall demonstrate how each member or partner meets the SOA certification requirements stated in paragraph (a) above. Include a description of the responsibilities in terms of work category for each member or partner (for example - Firm A performing 70% of OG-

1 and Firm B performing 30% of OS-30)

(4) An offeror's proposal will be rejected for failure to provide the current SOA certificates required under this solicitation. In the case of a Joint Venture (JV), each member of the JV must have at least one of the required SOA

Certifications. The JV member who has the SOA Certification must perform the majority of the work pertinent to the certification. In the case of a JV, certification submitted by a subcontractor will not be accepted.

1.13 PERFORMANCE GUARANTEE OR BOND REQUIREMENTS

The Contractor shall provide a notarized Performance Guarantee letter within ten (10) days after award or as required by the Contracting Officer. In lieu of the 10% Performance Guarantee requirement, the Offeror may provide Performance and Payment Bonds, pursuant to FAR Clause 52.228-15, through an approved surety under the

United States Treasury Department Circular 570. If the Offeror fails to provide a Performance Guarantee letter or

Performance and Payment Bonds within ten (10) days, the task order may be terminated for default. In such event, Offeror shall be liable for any cost of re-procuring the work which exceeds the amount of his offer.

This Performance Guarantee replaces NFAS 5252.228-9306.

The Performance Guarantee letter shall be accompanied by a notarized document authenticating the financial institution's authority to sign the letter. An English translation of the Performance Guarantee letter shall be submitted at the same time.

Performance Guarantee: An amount equal to ten percent (10%) of the amount of the contract shall be deposited into a properly certified banking institution, which will then issue an irrevocable letter guaranteeing the payment of the amount deposited plus any applicable interest, to the United States Government, upon demand by the Contracting

Officer. Demand will be made if the Contractor fails to comply with the terms and conditions of the contract, or does not fulfill its undertaking in whole or in part. Payment to the Contracting Officer will be by check made payable to the "United States of America by the U.S. Department of the Navy, Naval Facilities Engineering Command, Europe, Africa, Southwest Asia."

The Performance Guarantee shall take effect upon the date of signature of the Performance Guarantee letter and shall remain valid and irrevocable until one (1) year after the work has been finally inspected and accepted by the

Government."

SAMPLE OF PERFORMANCE GUARANTEE ISSUED BY A BANK

This sample meets the material requirements of clause NFAS 5252.228-9306, “Performance Guarantee.” The

Government will accept as valid a Performance Guarantee conforming to these requirements.

BANK LETTERHEAD

To: United States of America

U.S. Department of Navy

Naval Facilities Engineering Command, Europe Africa Southwest Asia

Viale Porto, Box 51

Aeroporto Capodichino

80144, Napoli, Italia

Attention: Contracting Officer

Date _____________

Bank Letter of Performance Guarantee No. ____

I/We, the undersigned, acting as the duly authorized representative(s) of the Bank, declare that the Bank hereby guarantees and is jointly and severally liable as guarantor with the Contractor named below to effect payment to the

Contracting Office that issued the contract stated below, by check made payable to the “United States of America by the U.S.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .