About this file

Amendment 004 file was corrupt this is Amendment 004 that goes with the drawings that were attached previously

View the file

Other files

File Type Posted
UAS_SATCOM_RELAY_PADS_AND_FACILITY_11005.docx DOCX document
AMENDMENT_0011_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
AMENDMENT_0010_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
AMENDMENT_009_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
AMENDMENT_008_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
AMENDMENT_007_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
1118648_SPC_03-09-2015.pdf PDF
1118648_DWG_03-09-2015.pdf PDF
AMENDMENT_006_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
1118648_Amendment_2_Continuation_Sheet_2015-03-06.doc DOC document
AMENDMENT_005_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
PPI_015__Response_Attachments.pdf PDF
AMENDMENT_003_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
AMENDMENT_002_N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
N62470-09-R9034_Part10-FP.pdf PDF
N62470-09-R9034_Part03-CIV.pdf PDF
N62470-09-R9034_Part02-LS.pdf PDF
N62470-09-R9034_Part05-GEO.pdf PDF
11005R_SPECS_Final-EBS_04.13.12_Vol_1.pdf PDF
11005_SPECS_Final-EBS_04.13.12_Vol_2.pdf PDF
N62470-09-R9034_Part08-AR.pdf PDF
N62470-09-R9034_Part04-CIV_(CONT).pdf PDF
N62470-09-R9034_Part11-FP_(CONT).pdf PDF
N62470-09-R9034_Part09-IN.pdf PDF
N62470-09-R9034_Part06-LAND.pdf PDF
N62470-09-R9034_Part13-ME.pdf PDF
AMENDMENT_0001N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
N62470-09-R9034_Part14-EL.pdf PDF
N62470-09-R9034_Part07-ST.pdf PDF
N62470-09-R9034_Part12-PL.pdf PDF
N62470-09-R9034_Part01-GEN.pdf PDF
N62470-09-R9034_Part08-AR.pdf PDF
N62470-09-R9034_Part03-CIV-revised.pdf PDF
Contract_Risk_Assessment_and_QA_Responsibility_Spreadsheet-.pdf PDF
N62470-09-R9034_Part01-GEN.pdf PDF
N33191-15-R-0802_SATCOM_Relay_Pads.pdf PDF
N62470-09-R9034_Part04-CIV.pdf PDF
N62470-09-R9034_Part14-EL 1 .pdf PDF
11005R_SPECS_Final-EBS_04.13.12_Vol_1.pdf PDF
11005_SPECS_Final-EBS_04.13.12_Vol_2.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment 004 to Change Schedule, and answ er PPI's

1. CONTRACT ID CODE PAGE OF PAGES

J 1 9

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 25-Feb-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N33191-15-R-0802

X 9B. DATED (SEE ITEM 11)

13-Jan-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

25-Feb-2015

CODE

NAVFAC EUROPE AFRICA SOUTHWEST ASIA

PSC 817 BOX 51

FPO AE 09622-0001

N33191 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N33191-15-R-0802

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

SUMMARY OF CHANGES

AMENDMENT 004

AMENDMENT 004 is issued to incorporate the following changes and answer PPI questions:

The proposal due date will be changed from March 9th; to March 19, 2015 there will be another follow on Amendment to answer questions not yet obtained.

Question: FUEL CELLS RE. Specification Section 48 18 13.0050 We have noticed an inconsistency in the specification: Section 1.6.3 describes a product with 300 kW output, but section 2.3.4 describes a 400 kW system. 2. Paragraph 1.3 reads: “The powerplant system shall operate on natural gas and anaerobic digester gas as the fuel source” Does it mean we will blend the gas?

Answer: 1. Provide fuel cell with 400 kW output. 2. Fuel cell shall operate on natural gas only.

Anaerobic digester gas operation is not required.

Question: (Include RFP Section, page number, and paragraph if applicable)

In Specs Vol 1- SECTION 01 32 17.00 20 Part 1.4 Page 2 it is stated that:

Project schedules must be prepared and maintained using Primavera P3, Primavera SureTrak or current mandated scheduling program.

Please clarify if at the proposal phase it is allowed to use different scheduling software as MSP (Microsoft Project) and provide USG with the required source file document in .mpp, accordingly.

Answer:

Microsoft Project will not be acceptable. Please use Primavera as specified in SECTION 01 32

17.00 20; Part 1.4; Page 2.

Question: (Include RFP Section, page number, and paragraph if applicable)

In regards to the LEED documentation, paragraph 1.3.1 of section 01 33 29 states that the US Government will register the project with the USGBC, but who is responsible for collecting, downloading, and submitting all documentation to the USGBC through LEED Online, including all associated submittal fees?

Answer: The contractor is responsible for collecting, downloading, and submitting all documentation for Construction Credits, which are all credits included in the LEED construction submittal, to the USGBC through LEED Online. But there are other parties responsible for uploading some data in these credits as well, the Commissioning for example. All LEED Review fees will be paid by the Government.

Question: (Include RFP Section, page number, and paragraph if applicable)

In paragraph 1.3 of Section 01 33 29, it states that no variation to the LEED Scorecard nominated as “Table 1” in the LEED documentation specification is to be allowed. What if the Contractor notes an error in the attempted credits noted in the scorecard? Is the Contractor allowed to suggest additional credits (either design or construction) that were not previously considered or believed to be unachievable?

Answer:

Contractor is responsible for corrections only to Construction Credits. The Contractor may suggest additional credits not previously considered, but may not remove or delete any Construction Credits already designated to be achieved.

Question: (Include RFP Section, page number, and paragraph if applicable)

The LEED Scorecard in Section 01 33 29, indicates that Enhanced Commissioning will be attempted. Does this imply that the Contractor is not responsible in providing the Commissioning Authority for the construction phase? That is, that the government has already nominated a Commissioning Authority during the design phase that will be used throughout the construction phase as well?

Answer:

Correct, while the Contractor is responsible for achieving the required Commissioning utilizing a Commissioning Manager who is hired by the contractor, the contractor is not responsible for providing the Commissioning Authority. The Government will provide the Commissioning Authority which may or may not be the same as the Commissioning Authority used during Design.

Question: What field experience and expertise does the SSHO person have to have?

Answer:

SSHO Experience is defined by EM 38511 and all its sub paragraphs:

01.A.17 Site Safety and Health Officer (SSHO). The Contractor shall employ a minimum of one Competent Person at each project site to function as the SSHO, depending on job complexity, size and any other pertinent factors.

a. The SSHO shall be a fulltime responsibility unless specified differently in the contract. The SSHO shall report to a senior project (or corporate) official.

b. The SSHO(s), as a minimum, must have completed the 30hour OSHA Construction safety class or as an equivalent, 30 hours of formal construction safety and health training covering the subjects of the OSHA 30hour course (see Appendix A, paragraph 4.b) applicable to the work to be performed and given by qualified instructors. > The SSHO is also required to have five (5) years of construction industry safety experience or three (3) years if he possesses a Certified Safety Professional (CSP) or safety and health degree. c. An SSHO (or a Designated Representative, as identified in the APP/AHA and as deemed appropriate/equivalent to SSHO by the GDA) shall be onsite at all times when work is being performed.

d. The SSHO shall be responsible for managing, implementing and enforcing the Contractor’s Safety and Health Program in accordance with the accepted APP.

e. SSHOs shall maintain this competency through 24 hours of formal safety and health related coursework every four (4) years. For limited service contracts, for example, mowing (only), park attendants, rest room cleaning, the contracting Officer and Safety Office may modify SSHO requirements and waive the more stringent elements of this section. See Appendix A, paragraphs 4 and 11. For complex or high hazard projects, the SSHO shall have a minimum of ten (10) years of safety related work with at least five (5) years’ experience on similar type projects

Question: Within the structural drawings, it is unclear how the eaves are to be anchored to the walls. Please clarify or provide details.

Answer: The connections between the prefabricated roof panel system and the building structure shall be the responsibility of the panel system manufacturer. In accordance with the project specifications, 07 41 63, 1.5.1.a, the contractor is responsible for providing, but is not limited to, signed and sealed layout drawings as well as the connections of the roof panel system to the structure

Question: In it unclear in the drawings how the base pads for the mechanical equipment need to be constructed. Please clarify or provide details.

Answer: Reference attached sheets.

Question Drwg. No. 224 / 14024874 ES101 ELECTRICAL SITE PLAN Drwg. No. 265 / 14024915 EP601 SINGLE LINE DIAGRAM

On the drawings above specified is not identified the type and the square millimetres of medium voltage cable that connects:

EXISTING SF6 PAD MOUNTED SWITCH 693 with SWITCH STATION 1 SWITCH STATION 1 with SUBSTATION SS-1 SWITCH STATION 1 with SWITCH STATION 2 SWITCH STATION 2 with SUBSTATION SS-1

Answer: See legend on EG001 for duct bank section symbol. The definition for this symbol states that numbers indicate cables, and references EP701 for the duct bank cable schedule.

Drawing ES101 includes the number "1" in each of the duct bank section markers for the cables in question. These cables are noted as "3x95 (20KV)" on the DUCT BANK CABLE SCHEDULE on sheet EP701.

Question:

Section 20 10 00.00 42 STRUCTURED TELECOMMUNICATION CABLING AND

PATWAY SYSTEM FOR THIS SYSTEM WE MUST PROVIDE ONLY THE WAY CABLE ?

WE DON’T MUST PROVIDE CABLES ; CABINETS ; OUTLETS AND ACCESSORIES ?

Answer: Only provide items specified in 20 10 00.00 42 and shown on the drawings which is limited to the pathway system and grounding system. All cables, termination equipment, jacks, cabinets, and racks are Government Furnished, Government Installed and are not part of this construction contract.

Question: DOCUMENT 00100 INSTRUCTIONS TO OFFERORS 1.7 INSTRUCTIONS FOR THE SUBMISSION OF OFFERS Non-Cost/Price Factors

3.Basis of Evaluation and Submittal Requirements for Each Factor

We received the amendment No. 3 and I demand more simply regarding a permanent Consortium

EXAMPLE

The permanent Consortium includes 5 Companies :

Company “A” Does not have the requirement requested in the solicitation (He has not done no. 3 similar projects required of $. 6,000,000.00 in the last 7 years and has not the SOA for categories and amount required)

Company “B” Does not have the requirement requested in the solicitation (He has not done no. 3 similar projects required of $. 6,000,000.00 in the last 7 years and has not the SOA for categories and amount required)

Company “C” Does not have the requirement requested in the solicitation (He has not done no. 3 similar projects required of $. 6,000,000.00 in the last 7 years and has not the SOA for categories and amount required)

Company “D” HAS THE REQUESTED REQUIREMENTS

Company “E” Does not have the requirement requested in the solicitation (He has not done no. 3 similar projects required of $. 6,000,000.00 in the last 7 years and has not the SOA for categories and amount required)

The permanent Consortium designates companies “A” and “B” to do the job indicates in this Solicitation BUT The companies “A” and “B” does not have the necessary requirements requested in the Solicitation (They have not performed no. 3 similar project required of $. 6,000,000.00 in the last 7 years and have not the SOA for categories and/or amount required)

The Company “D” , that have the requirement requested decides to participate alone OUTSIDE

THE PERMANENT CONSORTIUM.

THE PERMANENT CONSORTIUM MAY PARTECIPATE WITH DESIGNATED

COMPANIES “A” AND “B” WHO DO NOT HAVE THE REQUIREMENT

REQUESTED IN THE SOLICITATION ?

THE PERMANENT CONSORTIUM MAY PARTECIPATE IF THE ONLY COMPANY

(COMPANY “D”) , THAT HAVE THE REQUIREMENT REQUESTED, PARTECIPATES

ALONE OUTSIDE AND NOT IN THE PERMANENT CONSORTIUM AT THE SAME

SOLICITATION ?

Please clarify

Answer: If Company D wants to participate with designated companies A and B and A and B do not have the qualifications of the solicitation then this would be a deficiency and not be eligible for award. The Consortium doesn't qualify to bid if the sum of all the qualifications held by each individual company of the Consortium doesn't equal the amount required by the solicitation in a peculiar work category.

Government Changes to the below On the CONTINUATION SHEET

Solicitation Section 00100 – Bidding Schedule/Instructions to Bidders

1.7 INSTRUCTIONS FOR THE SUBMISSION OF OFFERS

a. NON-PRICE PROPOSAL (FACTORS 1, 2, 3 AND 4); Page 14 of 50; Factor 3 – Schedule

Is amended as follows, FROM:

(2) Factor 3 –Schedule

(i) Solicitation Submittal Requirements:

Provide a contract schedule that includes all aspects of pre-construction activities, major HVAC and electrical procurement, construction and post-construction activities. The contract timeframe identified in the RFP defines the acceptable contract duration; a shorter contract duration is desirable.

For purpose of evaluation, the schedule shall be based on a 01 May 2015 Notice to Proceed (NTP), with construction durations in weeks/days in lieu of specific calendar dates. At a minimum the schedule shall address the following:

• Pre-Construction (administration, PAK meeting, submittals, reviews & approvals)

• Procurement of Major HVAC and Electrical equipment, and long lead items such as the Pre-Engineered Metal Building (submittal preparation, submittal review and approval, fabrication and delivery).

• Site Demolition/Preparation.

• OSP/ISP Communication Duct Bank Construction

• Antenna Foundation Construction.

• Interior Build-Out and Finishes.

• Start-Up, Testing & Commissioning.

• Project Close-Out.

Provide a Narrative and a Project Schedule in CPM format that explains the proposed contract duration, construction and scheduling innovations and methods to provide realistic shorter contract duration. The Narrative shall not exceed four (4) (or eight (8) single-sided pages) double-sided 8-1/2”x11” pages. Provide the CPM format Project Schedule as a PDF file and source file, and the Summary Level, and Critical Path Schedule, documenting any multiple Critical Paths in 11” x 17” pages, there is no page limit on the Summary Level and Critical Path (do not submit the printed copies of the entire CMP schedule).

(ii) Basis of Evaluation:

The Government will evaluate a comparison of the contractor’s proposed contract duration to the overall contract duration provided in the RFP. The Government’s evaluation of the contractor’s proposed schedule is a means of determining whether the contractor understands the scope of work and approaches the tasks in a logical and effective manner.

The contractor may receive evaluative credit for realistic proposed contract duration that is shorter than the acceptable contract duration. The contractor’s proposed contract duration shall become an enforceable part of the contract and will be reflected in the awarded Contract Completion Dated (CCD) to the successful Offeror. Proposed schedules in excess of the contract duration provided in the RFP will be considered a material deficiency and will not be eligible for award.”

TO:

(2) Factor 3 –Schedule

(i) Solicitation Submittal Requirements:

Provide a contract schedule that includes all aspects of pre-construction activities, major HVAC and electrical procurement, construction and post-construction activities. The contract timeframe identified in the RFP defines the acceptable contract duration; a shorter contract duration is desirable.

For purpose of evaluation, the schedule shall be based on a 01 July 2015 Notice to Proceed (NTP), with construction durations in weeks/days in lieu of specific calendar dates. At a minimum the schedule shall address the following:

• Pre-Construction (administration, PAK meeting, submittals, reviews & approvals)

• Procurement of Major HVAC and Electrical equipment, and long lead items such as the Pre-Engineered Metal Building (submittal preparation, submittal review and approval, fabrication and delivery).

• Site Demolition/Preparation.

• OSP/ISP Communication Duct Bank Construction

• Antenna Foundation Construction.

• Interior Build-Out and Finishes.

• Start-Up, Testing & Commissioning.

• Project Close-Out.

Additionally, the proposed construction schedule shall accommodate the following milestones:

1) All underground electrical and communications conduit, duct-banks, manholes and other associated appurtenances shall be complete and in-place by October 1st, 2016.

2) All antenna foundations shall be complete and in-place including concrete ring walls (already having a 30-day curing period), underground conduit with stub-ups, electrical panels and all other associated antenna foundation appurtenances no later than October 1, 2016 allowing government access to site in order to begin placement of antennas on October 1, 2016.

Provide a Narrative and a Project Schedule in CPM format that explains the proposed contract duration, construction and scheduling innovations and methods to provide realistic shorter contract duration. The Narrative shall not exceed four (4) (or eight (8) single-sided pages) double-sided 8-1/2”x11” pages. Provide the CPM format Project Schedule as a PDF file and source file, and the Summary Level, and Critical Path Schedule, documenting any multiple Critical Paths in 11” x 17” pages, there is no page limit on the Summary Level and Critical Path (do not submit the printed copies of the entire CMP schedule).

(ii) Basis of Evaluation:

The Government will evaluate a comparison of the contractor’s proposed contract duration to the overall contract duration provided in the RFP. The Government’s evaluation of the contractor’s proposed schedule is a means of determining whether the contractor understands the scope of work and approaches the tasks in a logical and effective manner.

This evaluation will consider how the construction incorporates the above milestones.

The contractor may receive evaluative credit for realistic proposed contract duration that is shorter than the acceptable contract duration. The contractor’s proposed contract duration shall become an enforceable part of the contract and will be reflected in the awarded Contract Completion Dated (CCD) to the successful Offeror. Proposed schedules in excess of the contract duration provided in the RFP will be considered a material deficiency and will not be eligible for award.”

SECTION 01 11 00 SUMMARY OF WORK; 1.2.2 Project Description;

After this paragraph, ADD the following:

“The work requires phased completion dates that will allow government access to antenna foundations and underground electrical/communication conduit no later than Oct 1, 2016 while other work continues to completion as required. On October 1, 2016, the government will begin installation of antennas on completed foundations and the government will also begin pulling cabling within OSP/ISP conduit to nearest manhole of building within projects perimeter fence-line.”

B. ALL OTHER ITEMS:

Proposal due date changed from March 9th, 2015 to March 19th 2015 1400 Central European Time

PLEASE REMEMBER TO ACKNOWLEDGE THIS AMENDMENT ON YOUR BID

SCHEDULE

(End of Summary of Changes)