AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
AMENDMENT 003 TO ANSWER PPI QUESTIONS AND EXTEND THE PROPOSAL DUE DATE.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N33191-15-R-0802
X 9B. DATED (SEE ITEM 11)
13-Jan-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
U0003
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Feb-2015
CODE
NAVFAC EUROPE AFRICA SOUTHWEST ASIA
PSC 817 BOX 51
FPO AE 09622-0001
N33191 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N33191-15-R-0802
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following have been added by full text:
AMENDMENT 003
AMENDMENT 003 is issued to incorporate the following changes and answer PPI questions:
The proposal due date will be extended to March 9 th
; there will be another follow on
Amendment to answer questions not yet obtained.
Question: RE. Dwg. MH 801 – MH 804
1) WATER CHILLER
The schedule on Dwg MH 801 shows the Base Bid Air Cooled Water Chiller with 210 KW capacity.
The schedule on Dwg MH 804 shows the Bid Option 1 alternate Water Chiller for the absorption Chilled water system, with 2049 KW nominal capacity. Please confirm this requirement, taking into consideration that, according to the same schedule, the resulting capacity at the evaporator should be 228 KW.
2) COOLING TOWER
The schedule on Dwg MH 804 shows the Closed-Circuit Cooling Tower with 340 KW Nominal Capacity. Please confirm this requirement, taking into consideration that, according to the same schedule, the resulting capacity should be 2615 KW.
Answer: The water chiller on MH804 for Bid Option 1 should have a nominal capacity of 228 KW. The cooling tower capacity of 340 KW indicated on the “Closed Circuit Cooling Tower Schedule” on the same sheet is correct.
Question: (Include RFP Section, page number, and paragraph if applicable)
2. Is the Contractor responsible for the credits that are considered a part of the Design Phase? That is, is the
Contractor to collect all of the design credit documentation? Paragraph 1.3.2 of Section 01 33 29 states that no further documentation needs to be completed; however, if changes or corrections are to be made during the construction phase either to the actual design or only for the documentation paperwork, whose responsibility is it to be carried out? For instance, energy modeling and other similar design calculations that often changes through the course of a construction site? And, during the GBCI review phases?
Answer: No the contractor is not responsible for Design Credits. Contractor is fully responsible for achieving the Construction Credits, including changes and corrections.
Question: (Include RFP Section, page number, and paragraph if applicable)
3. Paragraph 2.1 of Section 01 33 29 states that the Contractor is to provide and install the LEED plaque. The plaque is no longer a gratuity with the certification of the building. Please confirm that it will be the Contractor’s responsibility to provide these services.
Answer: Yes, it is the Contractor’s responsibility to provide and install the LEED Plaque
Question: According to the specifications attached to the solicitation, the only personnel that is required to be onsite at all times are the following: Project Superintendent, QC Manager, and Site Safety Health Officer (SSHO).
Please confirm.
Answer: Per the Specifications the contractor personnel required to be on site at all times are:
00 73 04, 1.4 English Speaking Representative
01 35 26, 1.6.1.1 SSHO
Question: It specifically states in the specifications that the QC Manager cannot be any other managerial position;
however, it does not specify anything regarding the SSHO. Can the SSHO per the same person as the Project
Superintendent?
Answer: Yes, the SSHO can be the same person as the Project Superintendent.
Question: On Sheet MH804, please confirm and clarify the data indicated in the “Water Chiller Schedule CH/1”.
Discrepancies are found between the potential and the water flows.
Answer: The nominal capacity for the chiller should be 228 KW. This should clear up the discrepancy between the potential and the water flows.
Additionally the “Water Chiller Schedule CH/1” should reflect the following:
Maximum Power = 5 Kw/ton
Evaporator pressure Drop =17.7 KPa
Electrical Total KW = 5.2 KW
Question: On Sheet MH802, please confirm and clarify the power supply for the Cooling Coil – Dx (25 kW)
CAC/1,2,3 and the power supply for the Condensing Unit (73.4 kW) CU/1,2,3.
Answer: The Capacity of the cooling coils on sheet MH802 for the “Computer Room Air Conditioning Units” should be 70 KW for CAC/1, CAC/2, and CAC/3. Additionally the total capacity of the condensing units is also 70
KW.
Question: Please confirm that a screed does not need to be installed prior to the installation of the box shower in the bathrooms.
Answer All mortar needs to be screeded. The membrane is under the mortar. Assume the term "Box Shower" means the shower membrane.
Question In regards to the Engine Generator Set: specification Section 26 32 13.00 50 paragraph 2.1.1.1 indicates
1800rpm (60Hz), whereas, on the single-line diagram it states 50Hz. Please clarify which is to be used.
Answer: The drawings indicate the correct frequency. Generators shall be 50Hz.
Question In regards to the Engine Generator Set: The generators indicated require 3x350 kW; but in the tests
(specification Section 26 32 13.00 50 paragraph 3.5.3 g combinations), it requires the application of a single step of
900 kW in pairs of two groups. This is not possible with 350 kW generators and it is not possible to provide an immediate power supply of 400kW on a single generator. Please clarify this testing procedure.
Answer: Paragraph 3.5.3, g. 2. requires one step to 900kW, but after generators have been paralleled and load divided proportionally between the sets for 15 minutes (3.5.3, g.1). The total capacity with all three generators operating in parallel is 1050 kW, so increasing load to 900kW is possible. Provide this test as specified. Paragraph
3.5.3, g.6 requires to transfer 400kW to each set. This load should be 300kW to each set.
Question Are the four (4) foundations nominated as “future extension” on Sheets CS101 and CS102 or as “future relax pad” on Sheet AS100 to be installed under this contract? Please clarify the requirements for these four Radar pads.
Answer: The "Future Relay Pads" are shown for planning purposes only, and are not a part of the construction scope, and NOT installed under this contract.
Question Drwg. No. 10 / 14024660 C-001 CIVIL LEGEND AND ABBREVIATION
The line UNDERGROUND NATURAL GAS (100 mm. UG) is indicated on the drawing above specified but is non shown on the SITE UTILITY PLANS
Please clarify
Answer: Existing gas line is located south of the project limits within the area surveyed for the project and is not within the area included within the drawing limits.
Question A permanent Consortium (art. 36 of Decree Law No. 163-2006 ) designate one or more consortium company for the performance of this contract but this designate company has not the requirement requested in the solicitation (No. 3 similar project of $ 6,000,000.00 ).
The only company of the consortium that have the requirements requested in the solicitation participates alone and not with the consortium. In these conditions, the consortium can participate for this solicitation ?
Please clarify
Answer: If the Consortium does not have the required requirements that the RFP state, then they cannot participate for this solicitation.
Question The specifications state that the Contractor is only to provide a Commissioning Manager who will support and follow the commissioning activities of the project. Please confirm that the Contractor is not required to provide a CxA in accordance with the LEED regulations.
Answer: Correct, while the Contractor is responsible for achieving the required Commissioning utilizing a
Commissioning Manager who is hired by the contractor, the contractor is not responsible for providing the
Commissioning Authority. The Government will provide the Commissioning Authority which may or may not be the same as the Commissioning Authority used during Design.
Question On Sheet MH804, please confirm and clarify the data indicated in the “Closed-Circuit Cooling Tower
Schedule CT/1”. Discrepancies are found in the potential indicated between the power supply and the water flows.
Answer: The water flow indicated in the “Closed Circuit Cooling Tower Schedule CT/1” should be 18.6
L/s.
Question Re: Section 00100 Bidding Schedule/Instructions to Bidders.
1) Please clarify whether the bid for subject solicitation shall be expressed in Euro or U.S. Dollars.
In case a bid in U.S. Dollars is required, can you provide the Euro/U.S. Dollar reate of exchange?
2) Re paragraph 1.1. General description & Scope of work. Please clarify the sentence “Project completion date is anticipated to be 550 days with three (3) potential bid options for a total maximum duration of 60 months. “
Does the “maximum duration of 60 months” refer to performance of the Bid Options?
Answer: The solicitation will be awarded in local currency euros. The base bid is for 550 days. Bid Options if any or all of the options are awarded the total maximum duration will be 60 months.
B. ALL OTHER ITEMS:
Proposal due date changed from February 27 th
, 2015 to March 9 th
2015.
PLEASE REMEMBER TO ACKNOWLEDGE THIS AMENDMENT ON YOUR BID
SCHEDULE
(End of Summary of Changes)