AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment 002 Pre-Proposal Inquiries
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 10-Feb-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N33191-15-R-0802
X 9B. DATED (SEE ITEM 11)
13-Jan-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
10-Feb-2015
CODE
NAVFAC EUROPE AFRICA SOUTHWEST ASIA
PSC 817 BOX 51
FPO AE 09622-0051
N33191 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N33191-15-R-0802
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
AMENDMENT 002
AMENDMENT 002 is issued to incorporate the following changes and answer PPI questions:
Please submit you PPI form in a word format only, not .pdf.
PPI Question:
FUEL CELLS On Dwg, EP 602 we read that the Fuel Cell shall be 400 KW/472 KVA.
Specification Section 48 18 13.0050 Paragraph 1.6.3 “Design and Performance Requirements” reads:
Design and Performance Requirements
Power at Plant Rating, kW 300
Output Voltage, Volts 380
Frequency, Hz 50
Please clarify the different requirement.
Government Response: The required fuel cell rating is 400kW/472kVA, 380V, 50 HZ.
Donald Sellers, 02.09.15
PPI Question:
Section 48 18 13.00 50 – ELECTRICAL POWER GERNATION FUEL CELLS
The producer asked us questions that we indicated below:
1. Are you aware that they included two inconsistent performance specifications? Paragraph
1.6.3 describes a product similar to our DFC300 with 300 K W output, but paragraph 2.3.4 describes a unit like UTC/Clearedge/Doosan 400 KW system.
2. Does the customer really want load following (which is mentioned in the section 2.3.4?
3. The mixed country standards could e a problem, since our DFC250 or 400 units are not
CSA-FC1 certified, but they do meet European CE standards.
4. Does the customer really need an absolute NO-BREAK POWER? To disconnect from the grid takes usually some microseconds. If this would be to long for the powered equipment we would have to add advanced switches and probably an additional transformer.
5. Do we really have to operate on natural gas and anaerobic digester gas (means we’ll blend the gas?)
6. Please clarify Thanks
Government Response:
1. Fuel cell shall be rated for 400KW
2. Provide load following capability as specified.
3. The unit must meet cited European and CE standards. Meeting CSA-FC1 is not required.
4. Paragraph 2.3.1 requires transition to grid-independent operation in less than 10 seconds during utility grid outages.
5. Unit shall operate on natural gas only. Anaerobic digester gas operation is not required or desired.
PPI Question: As the host country (Italy) belongs to the European Union, you may know that all the Member States are in the Common European Market, so all the countries shall have the fair opportunity to compete for this efforts. Being said that, instead of the SOA Certification, which is only for italian companies, we would like to request the Navy to include the possibility of including in lieu of the SOA Certification, an equivalent document, issued by a competent authority of any member country of the European Union. A third competent party shall certify -
IN ENGLISH- that the document is equivalent to the Italian SOA classifications required in this bid, just as we have been addressed to do in other projects within the US Department of Defense.
Additionally, we can include the Italian classifications through a Letter of Commitment with a
Designated Subcontractor. Thank you
Government Response: Please refer to pages 11 and 12 of the RFP. The Government has to follow these requirements and the host nation requirements.
PPI Question: We would like to verify that we can submit documents in A4 format.
Government Response: Yes this is possible.
PPI Question: In the RFP, section 1.2. PRE-PROPOSAL CONFERENCE AND SITE VISIT
(page 8 of 50) it is stated that "Conference will start promptly at 1300 and those not in attendance will not be allowed to participate."
Do you mean that if the Offeror did not attend the Pre-proposal Conference and Site Visit, then it won't be allowed to submit a Bid Proposal? Or maybe the meaning is that if the Offeror does not arrive on time at 1300 it won't be allowed neither to participate in the Pre-proposal Conference and Site Visit? Since we could not attend the Pre-proposal Conference and Site Visit we would like to clarify the meaning of the sentence.
Thank you
Government Response: Your firm can still submit a proposal, even though they did not attend the site visit. What it meant was that if the offeror did not arrive on time they would not be allowed to attend.
B. ALL OTHER ITEMS:
All other terms and conditions remain unchanged.
PLEASE REMEMBER TO ACKNOWLEDGE THIS AMENDMENT ON YOUR BID
SCHEDULE
(End of Summary of Changes)