S-FD-A-103.09.IFC.09.01.pdf
PDF 759 KB Posted
- Attached to
- LBNF Argon Receiving System
- Solicitation number
- LBNF-357714-JD
About this file
This is an architectural plan drawing showing the cryogen equipment layout for the Long-Baseline Neutrino Facility (LBNF) Surface Building at Fermilab. The drawing (S-FD-A-103) details the placement of key cryogenic components including fill stations, dewars, pumps, vaporizers, and a purity check building in relation to the existing Ross Warehouse.
The plan indicates specific dimensions and infrastructure elements including concrete equipment pads, pipe bollards, below-grade covered trenches for piping, and electrical components like transformers and luminaires. Notable features include heat-traced downspouts and gutters, gravel surfacing, and a design-build purity check building with performance requirements referenced on drawing A-104. The overall layout spans approximately 65' x 50' and includes detailed notes regarding symbols, equipment schedules, dimensions, and drainage specifications. The drawing was issued for construction on November 10, 2023 by TSP, Inc. and Arup USA Inc. for the Fermilab LBNF project.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fill Station Fill Station
Dewar Dewar
P u m p
P u m p
Dewar Dewar
Vaporizer
Vaporizer
OUTLINE OF BELOW GRADE
PIPE IN COVERED TRENCH,
REF MECH, REF CIVIL
EXISTING ROSS
WAREHOUSE
V
IF
V
IF
PURITY CHECK BUILDING,
DESIGN-BUILD,
SEE A-104 FOR
PERFORMANCE
REQUIREMENTS
TRANSFORMER,
REFER TO ELECTRICAL
CONCRETE EQUIPMENT
PAD, REF. STRUCTURAL,
REF. CIVIL
PIPE BOLLARDS, REF.
STRUCTURAL & CIVIL, TYPICAL
A-2011
GRAVEL, TYPICAL, REF. CIVIL
POST MOUNTED LUMINAIRE,
TYPICAL, REF. ELECTRICAL
EQUIPMENT AND DEVICES,
REF. ELEC.
/8
10' - 1" 15' - 1" 14' - 11 3/4" 14' - 11 3/4" 9' - 10 1/2"
4' - 4"
DOWNSPOUT WITH HEAT
TRACE, REF ELEC
NEW GUTTER WITH HEAT TRACE
AT EXISTING BUILDING
DOWNSPOUT WITH HEAT
TRACE, REF ELEC; RUN
DUCT AT AN ANGLE TO
OUTLET AT THE NORTH END
OF THE PAD
A-518
E1
E1
E3E3
E5E5
E1E1
65' - 0"
EXISTING WALL MOUNTED LUMINAIRE,
TYPICAL, REF.ELECTRICAL
WORK AT EXISTING ROSS WAREHOUSE IS
LIMITED TO GUTTERS, DOWNSPOUTS WITH
HEAT TRACE, SNOWGUARDS, AND WALL
MOUNTED LUMINAIRES
/4
/6
"POST MOUNTED LUMINAIRE,
TYPICAL, REF. ELECTRICAL
E2E2
CRYOGEN PLAN NOTES
1. REFER TO SHEET A-000 FOR SYMBOLS &
ABBREVIATIONS.
2. REFER TO SHEET A-601 FOR OFOI EQUIPMENT
SCHEDULE, PROVIDED FOR CONVENIENCE.
3. DIMENSIONS ARE TO EXTERIOR FACE OF
BUILDING & CLEAR BETWEEN EQUIPMENT,
UNLESS NOTED OTHERWISE.
4. ROOF DRAINAGE SLOPES SHOWN ARE
APPROXIMATE. REFER TO CIVIL FOR SITE
DRAINAGE INFORMATION.
5. ELECTRICAL AND MECHANICAL EQUIPMENT IS
NOTED FOR REFERENCE. SEE ELECTRICAL
AND MECHANICAL DRAWINGS AND
SPECIFICATIONS FOR MORE INFORMATION.
BRADLEY RYAN
MITZELFELT
R
EG
IS
T
E R
ED
P ROF E S S I ONA L
AR
C H
IT
E
C T
REG. NO.
S
O
U TH D A KO
T
A
15208
DATE:
TSP, Inc.
600 Kansas City St.
Rapid City, SD 57701 phone: (605) 343-6102 fax: (605) 343-7159 www.teamtsp.com
Arup USA Inc
77 Water Street, New York NY 10005, T 212 896 3000 www.arup.com
DRAWING NO.
SCALE:
REV.
REVISIONS
DESIGNED
DRAWN
CHECKED
DESCRIPTIONDATEREV.
Fermilab Long-Baseline Neutrino Facility
11/10/2023
SURFACE
ARCHITECTURAL
/1 /2
/9
/2
:0 :3
P
M L T
S P
R e v it L o c a l\ L
B N
F C ry o g e n S u rf a c e B u ild in g v o s te rl o o k a te a m ts p .c o m
.r v t
1015-1-6J S-FD-A-103
LBNF - FSCF - BSI
BRM
AH
SD DKa
CRYOGEN EQUIPMENT - PLANSDKa
TSP
SCALE: 1/8" = 1'-0"
CRYOGEN EQUIPMENT
PLAN
1 07/27/18 30% FD SUBMISSION
8 05/21/21 ISSUED FOR CONSTRUCTION - BSI HEADFRAME HEATERS
7 11/20/20 100% FD UPDATE
2 11/16/18 60% FD SUBMISSION
3 02/22/19 90% FD SUBMISSION
4 05/03/19 100% FD SUBMISSION
5 08/21/20 90% DRAFT FD UPDATE
6 10/01/20 90% FD UPDATE
9 03/17/23 ADDENDUM 3
10 11/10/23 ISSUED FOR CONSTRUCTION
AS NOTED
https://kiewit.teambinder.com/TeamBinderADFS/PROJNO103544/BlueBeamIntegration/Documents/S-FD-A-518_ROSS HEADFRAME AND WAREHOUSE -DETAILS.pdf https://kiewit.teambinder.com/TeamBinderADFS/PROJNO103544/BlueBeamIntegration/Documents/S-FD-A-518_ROSS HEADFRAME AND WAREHOUSE -DETAILS.pdf https://kiewit.teambinder.com/TeamBinderADFS/PROJNO103544/BlueBeamIntegration/Documents/S-FD-A-201_CRYOGEN EQUIPMENT -ELEVATIONS.pdf
File details come from the government source that posted it. Updated .