This document is an Amendment to Solicitation Amendment No. 01 for RFP LBNF-357714-JD, issued by the Department of Energy's Fermi National Accelerator Laboratory. The Amendment provides answers to questions and attaches new technical files related to the solicitation for the LBNF Argon Receiving System.
The key details are:
- The solicitation is for the engineering, manufacture, delivery, installation, and acceptance testing of an Argon Receiving System at the Sanford Underground Research Facility (SURF) in Lead, South Dakota. The system will serve as the point of entry for argon to the larger LBNF/DUNE systems, including offloading, testing, temporary storage, and vaporization of the liquid argon for transfer underground.
- The solicitation includes two dedicated truck offloading stations, two 50 m3 liquid argon storage tanks, and associated piping and equipment. The Subcontractor shall also install two additional 50 m3 tanks provided by the government.
- Proposal due date is November 12, 2024.
- The Amendment provides P&ID drawings and responds to questions regarding instrumentation lists and valve types in the reference 3D model.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT TO SOLICITATION
AMENDMENT NO.
DATE OF AMENDMENT:
October 14, 2024
SOLICITATION NO.
RFP LBNF-357714-JD
DATE ISSUED:
September 17, 2024
PROJECT NO.
N/A
PROPOSAL DUE DATE:
November 12, 2024
TITLE OF PROJECT:
LONG-BASELINE NEUTRINO FACILITY ARGON RECEIVING
Offerors must acknowledge this Addendum prior to the hour and date set forth in the solicitation by one of the following methods:
1. By completing the Subcontractor Annual Representations and Certifications (SARC), or
2. By separate fax, letter, or email.
If by virtue of this Addendum you desire to change a proposal already submitted, such change may be made by email, provided such email clearly references the Solicitation number and this Amendment number and is received prior to the proposal due date.
Amendment No. 1 is issued to answer questions and to provide new technical files as follows:
Question No. 1: We would like to inquire whether there is a P&ID available that clearly delineates the scope boundaries for comparison with the specifications.
Answer No. 1: Yes, P&ID are currently available and provided with this Amendment. Please download the following four (4) attached files:
F10028336.01_Receiving Facilities_Track_Connections.pdf F10028336.02_Receiving Facilties_Storage_Ar_Dewars_1_and_2.pdf F10028336.03_Receiving Facilties_Storage_Ar_Dewars_3_and_4.pdf F10028336.04_Receiving Facilties_Gas Analyzers_pdf
Question No. 2: Could you please confirm if there is a supplementary instrumentation list included?
Answer No. 2: We do not have instrumentation list. However the P&IDs depict everything we anticipate (the final design is by the Subcontractor, so this could change as well)
Question No. 3: Regarding the 3D model provided, there are only a few ball valves included, Given their uncommon and potentially hazardous use in cryogenic applications, I would like to confirm, are these valves intended solely for illustrative purposes?
Answer No. 3: The 3D model is only a reference design – the valves there are for illustrative purposed only.
All other provisions remain unchanged.
Fermi Research Alliance, LLC P.O. Box 500 Batavia, IL 60510 M.S 123
Jeremy Duncan LBNF Procurement Specialist
(865) 300-0443
File details come from the government source that posted it. Updated .