Amendment 01--RFP LBNF-357714-JD.pdf

PDF 97 KB Posted

Attached to
LBNF Argon Receiving System
Solicitation number
LBNF-357714-JD
Issued by

About this file

This document is an Amendment to Solicitation Amendment No. 01 for RFP LBNF-357714-JD, issued by the Department of Energy's Fermi National Accelerator Laboratory. The Amendment provides answers to questions and attaches new technical files related to the solicitation for the LBNF Argon Receiving System.

The key details are:

  • The solicitation is for the engineering, manufacture, delivery, installation, and acceptance testing of an Argon Receiving System at the Sanford Underground Research Facility (SURF) in Lead, South Dakota. The system will serve as the point of entry for argon to the larger LBNF/DUNE systems, including offloading, testing, temporary storage, and vaporization of the liquid argon for transfer underground.
  • The solicitation includes two dedicated truck offloading stations, two 50 m3 liquid argon storage tanks, and associated piping and equipment. The Subcontractor shall also install two additional 50 m3 tanks provided by the government.
  • Proposal due date is November 12, 2024.
  • The Amendment provides P&ID drawings and responds to questions regarding instrumentation lists and valve types in the reference 3D model.

View the file

Other files

File Type Posted
J-2 2025 INSURANCE REQUIREMENTS FOR FRA SUBCONTRACTED WORK AT SURF Risk category 3 (Rev 01.pdf PDF
Amendment 06--RFP LBNF-357714-JD.pdf PDF
J-1 FFDG General Terms and Conditions for Subcontracts Combining Supplies and Services Performed at SURF (01.2025).pdf PDF
Amendment 05--RFP LBNF-357714-JD.pdf PDF
Amendment 04--RFP LBNF-357714-JD.pdf PDF
S-FD-S-801.10.IFC.10.01.pdf PDF
S-FD-S-401.10.IFC.10.01.pdf PDF
S-FD-C-401.08.IFC.08.01.pdf PDF
QA - Appendix 1 - ARF Layout with labels.png PNG image
S-FD-A-103.09.IFC.09.01.pdf PDF
S-FD-A-104.09.IFC.09.01.pdf PDF
S-FD-S-002.09.IFC.09.01.pdf PDF
S-FD-S-701.08.IFC.08.01.pdf PDF
Amendment 03--RFP LBNF-357714-JD-Approved.pdf PDF
S-FD-C-402.05.IFC.05.01.pdf PDF
Amendment 02--RFP LBNF-357714-JD.pdf PDF
F10028336.02_Receiving_Facilities._Storage_Ar_Dewars_1_and_2.pdf PDF
F10028336.01_Receiving_Facilities._Track_Connections.pdf PDF
F10028336.04_Receiving_Facilities._Gas_Analyzers_.pdf PDF
F10028336.03_Receiving_Facilities._Storage_Ar_Dewars_3_and_4.pdf PDF
RFP LBNF-357714-JD 09-13-2024 final.pdf PDF
J-1 FRA General Terms and Conditions for Subcontracts Combining Supplies and Services Performed at SURF (03.2024).pdf PDF
J-4 Statement of Work - Argon Receiving 07-16-2024.pdf PDF
J-4 - ARF - Appendix C - Tanks from CERN - Datasheet.pdf PDF
J-8 - Section 014100 Cryo Quality Requirements_02-16-2024.pdf PDF
PUR-466_Proposal Certifications.pdf PDF
SMALL BUSINESS SUBCONTRACTING PLAN template Far 52.219-9.docx DOCX document
FRA Safety Questionnaire (Rev. 08-17)_URV.pdf PDF
J-2 INSURANCE REQUIREMENTS FOR FRA SUBCONTRACTED WORK AT SURF Risk category 3 (Rev 8.2024).pdf PDF
J-3 SDSTA Risk Transfer Protocols with Exhibits Final.pdf PDF
J-4 - SOW Appendix A - Instructions for Downloading.docx DOCX document
J-4 - ARF - Appendix B - Argon Receiving Facilities Interface Matrix.xlsx XLSX spreadsheet
J-5 - Exhibit A 7020 For Supply and Services SURF-ARF.pdf PDF
J-7 Section 013300 Submittals 02-14-2024.pdf PDF
J-6 - Section 010010 General Requirements Installation Feb 2024.pdf PDF
J-13 Project Schedule - ARF 07-18-2024.pdf PDF
Mandatory Site Visit Registration Questionnaire_ARF_Sept 2024.docx DOCX document
SARC_Subcontractor Annual RepsCerts Rev 3.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT TO SOLICITATION

AMENDMENT NO.

DATE OF AMENDMENT:

October 14, 2024

SOLICITATION NO.

RFP LBNF-357714-JD

DATE ISSUED:

September 17, 2024

PROJECT NO.

N/A

PROPOSAL DUE DATE:

November 12, 2024

TITLE OF PROJECT:

LONG-BASELINE NEUTRINO FACILITY ARGON RECEIVING

Offerors must acknowledge this Addendum prior to the hour and date set forth in the solicitation by one of the following methods:

1. By completing the Subcontractor Annual Representations and Certifications (SARC), or

2. By separate fax, letter, or email.

If by virtue of this Addendum you desire to change a proposal already submitted, such change may be made by email, provided such email clearly references the Solicitation number and this Amendment number and is received prior to the proposal due date.

Amendment No. 1 is issued to answer questions and to provide new technical files as follows:

Question No. 1: We would like to inquire whether there is a P&ID available that clearly delineates the scope boundaries for comparison with the specifications.

Answer No. 1: Yes, P&ID are currently available and provided with this Amendment. Please download the following four (4) attached files:

F10028336.01_Receiving Facilities_Track_Connections.pdf F10028336.02_Receiving Facilties_Storage_Ar_Dewars_1_and_2.pdf F10028336.03_Receiving Facilties_Storage_Ar_Dewars_3_and_4.pdf F10028336.04_Receiving Facilties_Gas Analyzers_pdf

Question No. 2: Could you please confirm if there is a supplementary instrumentation list included?

Answer No. 2: We do not have instrumentation list. However the P&IDs depict everything we anticipate (the final design is by the Subcontractor, so this could change as well)

Question No. 3: Regarding the 3D model provided, there are only a few ball valves included, Given their uncommon and potentially hazardous use in cryogenic applications, I would like to confirm, are these valves intended solely for illustrative purposes?

Answer No. 3: The 3D model is only a reference design – the valves there are for illustrative purposed only.

All other provisions remain unchanged.

Fermi Research Alliance, LLC P.O. Box 500 Batavia, IL 60510 M.S 123

Jeremy Duncan LBNF Procurement Specialist

(865) 300-0443

File details come from the government source that posted it. Updated .