This document is an attachment to a subcontract (Subcontract 692857) related to the federal contract opportunity for the LBNF Argon Receiving System (Solicitation Number LBNF-357714-JD).

The scope of this subcontract includes engineering, manufacturing, delivery, installation, and acceptance testing of an argon receiving system at the Sanford Underground Research Facility (SURF) in Lead, South Dakota. The system will serve as the entry point for liquid argon to be used in the Deep Underground Neutrino Experiment (DUNE) detectors, which will require a total of 70,000 tons of liquid argon. The subcontract covers two dedicated truck offloading stations, two 50 m3 liquid argon storage tanks, equipment to discharge and vaporize the argon, as well as all interconnecting piping and controls. The subcontractor will also install two additional 50 m3 tanks provided by the government. The subcontract may involve either temporary or permanent installation of the tanks, depending on the most cost-effective solution. The subcontractor is required to furnish all labor, engineering services, equipment, and materials to deliver the system in accordance with the Statement of Work.

View the file

Other files

File Type Posted
J-2 2025 INSURANCE REQUIREMENTS FOR FRA SUBCONTRACTED WORK AT SURF Risk category 3 (Rev 01.pdf PDF
Amendment 06--RFP LBNF-357714-JD.pdf PDF
J-1 FFDG General Terms and Conditions for Subcontracts Combining Supplies and Services Performed at SURF (01.2025).pdf PDF
Amendment 05--RFP LBNF-357714-JD.pdf PDF
Amendment 04--RFP LBNF-357714-JD.pdf PDF
S-FD-S-801.10.IFC.10.01.pdf PDF
S-FD-S-401.10.IFC.10.01.pdf PDF
S-FD-C-401.08.IFC.08.01.pdf PDF
S-FD-S-701.08.IFC.08.01.pdf PDF
QA - Appendix 1 - ARF Layout with labels.png PNG image
S-FD-A-103.09.IFC.09.01.pdf PDF
S-FD-A-104.09.IFC.09.01.pdf PDF
S-FD-S-002.09.IFC.09.01.pdf PDF
Amendment 03--RFP LBNF-357714-JD-Approved.pdf PDF
S-FD-C-402.05.IFC.05.01.pdf PDF
Amendment 02--RFP LBNF-357714-JD.pdf PDF
F10028336.02_Receiving_Facilities._Storage_Ar_Dewars_1_and_2.pdf PDF
Amendment 01--RFP LBNF-357714-JD.pdf PDF
F10028336.04_Receiving_Facilities._Gas_Analyzers_.pdf PDF
F10028336.01_Receiving_Facilities._Track_Connections.pdf PDF
F10028336.03_Receiving_Facilities._Storage_Ar_Dewars_3_and_4.pdf PDF
RFP LBNF-357714-JD 09-13-2024 final.pdf PDF
J-1 FRA General Terms and Conditions for Subcontracts Combining Supplies and Services Performed at SURF (03.2024).pdf PDF
J-4 Statement of Work - Argon Receiving 07-16-2024.pdf PDF
J-4 - ARF - Appendix C - Tanks from CERN - Datasheet.pdf PDF
J-2 INSURANCE REQUIREMENTS FOR FRA SUBCONTRACTED WORK AT SURF Risk category 3 (Rev 8.2024).pdf PDF
J-4 - SOW Appendix A - Instructions for Downloading.docx DOCX document
J-4 - ARF - Appendix B - Argon Receiving Facilities Interface Matrix.xlsx XLSX spreadsheet
J-5 - Exhibit A 7020 For Supply and Services SURF-ARF.pdf PDF
J-7 Section 013300 Submittals 02-14-2024.pdf PDF
J-8 - Section 014100 Cryo Quality Requirements_02-16-2024.pdf PDF
PUR-466_Proposal Certifications.pdf PDF
SMALL BUSINESS SUBCONTRACTING PLAN template Far 52.219-9.docx DOCX document
FRA Safety Questionnaire (Rev. 08-17)_URV.pdf PDF
J-6 - Section 010010 General Requirements Installation Feb 2024.pdf PDF
J-13 Project Schedule - ARF 07-18-2024.pdf PDF
Mandatory Site Visit Registration Questionnaire_ARF_Sept 2024.docx DOCX document
SARC_Subcontractor Annual RepsCerts Rev 3.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment J-3 Subcontract 692857

File details come from the government source that posted it. Updated .