J.04 Government Furnished Equipment.pdf
PDF 75 KB Posted
- Attached to
- Power Systems Installation Services Federal contract opportunity
- Solicitation number
- 6973GH-21-R-00088
About this file
This document provides details on government furnished equipment and a related federal contract opportunity for power systems installation services. The Federal Aviation Administration Power Services Group has a requirement for design and installation of power systems and ancillary power equipment. Equipment that may be provided includes switchboards, switchgear, panelboards, circuit breakers, transformers, engine generators from 15kW to 1.5MW, automatic transfer switches, uninterruptible power supplies from 10kVA to 825kVA, and direct current backup systems. Providers for this equipment include Schneider Electric, Square D, Kohler, L-3 Communications, and Eaton Electric. Lead times for large equipment range from 4 to 12 months. Interested parties should review the full solicitation and submit Phase I proposals to stefanie.wiles@faa.gov by March 10, 2021 at 2:00PM Central Time for consideration under solicitation number 6973GH-21-R-00088.
View the file
Other files for this federal contract opportunity
Show all 39
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment J.04
POWER SERVICES GROUP GOVERNMENT FURNISHED EQUIPMENT (GFE)
In support of the requirements of the Statement of Work and contract, below is a sample list of equipment that may be provided as GFE:
ELECTRICAL POWER DISTRIBUTION EQUIPMENT (EDE)
Vendor: Schneider Electric/Square D
Equipment: Switchboards, Switchgear, Panel boards, Circuit Breakers, Transformers, and Monitoring
Software and Hardware
Lead-time: Large Switchboards 4-5 months, Panel boards 1-3 months, Transformers 1-3 months
Switchgear 6-9 months
ENGINE GENERATOR (EG)
Vendor: Kohler
Equipment: Propane engine generators 20 kW to 100 kW
Diesel engine generators 15 kW to 1.5 MW
Automatic Transfer Switches, Load Banks, Day Tanks/Sub-Base Tanks and Mufflers
Voltages 480, 208, 240 three phase, 240 single phase
Lead-Time: 6-months
STATIC AUTOMATIC TRANSFER SWITCH (STS)
Vendor: L-3 Communications
Equipment: 480 volt, 200 amp to 600 amp
208 volt, 3 or 4-pole, 150 amp to 600 amp
Lead-Time: 158 - 365 days
UNINTERRUPTIBLE POWER SUPPLY (UPS)
Vendor: Eaton Electric
Equipment: 480 volt 30 KVA to 825 KVA
208 volt 10 KVA to 160 kVA
Battery strings, battery monitors, and bypass panels.
Lead-Time: small to medium UPSs and associated equipment 12-weeks
DIRECT CURRENT BACK-UP SYSTEM (DC BUS)
Vendor: Oceus
Equipment: 24 volt DC BUS, UXTM, ERMS, batteries, battery rack and strings
Lead-Time: 60-90 days
Note: Some equipment may have longer lead times than listed above.